1、外文文献:Project Cost Control: The Way it WorksBy R. Max WidemanIn a recent consulting assignment we realized that there was some lack of understanding of the whole system of project cost control, how it is setup and applied. So we decided to write up a description of how it works. Project cost control
2、is not that difficult to follow in theory.First you establish a set of reference baselines. Then, as work progresses, you monitor the work, analyze the findings, forecast the end results and compare those with the reference baselines. If the end results are not satisfactory then you make adjustments
3、 as necessary to the work in progress, and repeat the cycle at suitable intervals. If the end results get really out of line with the baseline plan, you may have to change the plan. More likely, there will be (or have been) scope changes that change the reference baselines which means that every tim
4、e that happens you have to change the baseline plan anyway.But project cost control is a lot more difficult to do in practice, as is evidenced by the number of projects that fail to contain costs. It also involves a significant amount of work, as we shall see, and we might as well start at the begin
5、ning. So let us follow the thread of project cost control through the entire project life span.And, while we are at it, we will take the opportunity to point out the proper places for several significant documents. These include the Business Case, the Request for (a capital) Appropriation (for execu
6、tion), Work Packages and the Work Breakdown Structure, the Project Charter (or Brief), the Project Budget or Cost Plan, Earned Value and the Cost Baseline. All of these contribute to the organizations ability to effectively control project costs.FootnoteI am indebted to my friend Quentin Fleming, th
7、e guru of Earned Value, for checking and correcting my work on this topic.The Business Case and Application for (execution) FundingIt is important to note that project cost control is most effective when the executive management responsible has a good understanding of how projects should unfold thro
8、ugh the project life span. This means that they exercise their responsibilities at the key decision points between the major phases. They must also recognize the importance of project risk management for identifying and planning to head off at least the most obvious potential risk events.In the proj
9、ects Concept PhaseEvery project starts with someone identifying an opportunity or need. That is usually someone of importance or influence, if the project is to proceed, and that person often becomes the projects sponsor.To determine the suitability of the potential project, most organizations call
10、for the preparation of a Business Case and its Order of Magnitude cost to justify the value of the project so that it can be compared with all the other competing projects. This effort is conducted in the Concept Phase of the project and is done as a part of the organizations management of the entir
11、e project portfolio.The cost of the work of preparing the Business Case is usually covered by corporate management overhead, but it may be carried forward as an accounting cost to the eventual project. No doubt because this will provide a tax benefit to the organization. The problem is, how do you t
12、hen account for all the projects that are not so carried forwardIf the Business case has sufficient merit, approval will be given to proceed to a Development and Definition phase.In the projects Development or Definition PhaseThe objective of the Development Phase is to establish a good understandin
13、g of the work involved to produce the required product, estimate the cost and seek capital funding for the actual execution of the project.In a formalized setting, especially where big projects are involved, this application for funding is often referred to as a Request for (a capital) Appropriation
14、 (RFA) or Capital Appropriation Request (CAR).This requires the collection of more detailed requirements and data to establish what workneeds to be done to produce the required product or deliverable. From this information, a plan is prepared in sufficient detail to give adequate confidence in a dol
15、lar figure to be included in the request.In a less formalized setting, everyone just tries to muddle through.Work Packages and the WBSThe Project Management Plan, Project Brief or Project CharterIf the deliverable consists of a number of different elements, these are identified and assembled into Wo
16、rk Packages (WPs) and presented in the form of a Work Breakdown Structure (WBS).Each WP involves a set of activities, the work that is planned and scheduled as a part of the Project Management Plan. Note, however, that the planning will still be at a relatively high level, and more detailed planning
17、 will be necessary during execution if the project is given the go ahead.This Project Management Plan, by the way, should become the bible for the execution phase of the project and is sometimes referred to as the Project Brief or the Project Charter.The cost of doing the various activities is then
18、estimated and these estimated costs are aggregated to determine the estimated cost of the WP. This approach is known as detailed estimating or bottom up estimating. There are other approaches to estimating that well come to in a minute. Either way, the result is an estimated cost of the total work o
19、f the project.Note: that project risk management planning is an important part of this exercise. This should examine the projects assumptions and environmental conditions to identify any weaknesses in the plan thus far, and identify those potential risk events that warrant attention for mitigation.
20、This might take the form of specific contingency planning, and/or the setting aside of prudent funding reserves.Request for capitalConverting the estimateHowever, an estimate of the work alone is not sufficient for a capital request. To arrive at a capital request some conversion is necessary, for e
21、xample, by adding prudent allowances such as overheads, a contingency allowance to cover normal project risks and management reserves to cover unknowns and possible scope changes.In addition, it may be necessary to convert the estimating data into a financial accounting format that satisfies the cor
22、porate or sponsors format for purposes of comparison with other projects and consequent funding approval.In practice all the data for the type of bottom up approach just described may not be available.In this case alternative estimating approaches are adopted that provide various degrees of reliabil
23、ity in a top down fashion. For example:Order of Magnitude estimate a ball park estimate, usually reserved for the concept phase onlyAnalogous estimate an estimate based on previous similar projectsParametric estimate an estimate based on statistical relationships in historical data Whichever approac
24、h is adopted, hopefully the sum thus arrived at will be approved in full and proves to be satisfactory! This is the trigger to start the Execution Phase of the project Note: Some managements will approve some lesser sum in the mistaken belief that this will help everyone to sharpen their pencils and
25、 work smarter for the benefit of the organization. This is a mistaken belief because management has failed to understand the nature of uncertainty and risk in project work. Consequently, the effect is more likely to result in corner cutting with an adverse effect on product quality, or reduced produ
26、ct scope or functionality. This often leads to a game in which estimates are inflated so that management can adjust them downwards. But to be fair, management is also well aware that if money is over allocated, it will get spent anyway. The smart thing for managements to do is to set aside contingen
27、t reserve funds, varying with the riskiness of the project, and keepthat money under careful control.Ownership of approved capitalIf senior management approves the RFA as presented,t he sum in question becomes the responsibility of the designated project sponsor. However, if the approved capital req
28、uest includes allowances such as a Management Reserve, this may or may not be passed on to the projects sponsor, depending on the policies of the organization.For the approved RFA, the project sponsor will, in turn, further delegate expenditure authority to the projects project manager and will like
29、ly not include any of the allowances. An exception might be the contingency allowances to cover the normal variations in work performance.The net sum thus arrived at constitutes the project managers Approved Project Budget. Note: If management does not approve the RFA, you should not consider this a
30、 project failure. Either the goals, objectives, justification and planning need rethinking to increase the value of the projects deliverables, or senior management simply has higher priorities elsewhere for the available resources and funding.The Projects Execution PhaseThe project managers Project
31、Budget responsibilityOnce this Approved Project Budget is released to the project manager, a reverse process must take place to convert it into a working control document. That is, the money available must be divided amongst the various WBS WPs that, by the way, have probably by now been upgraded! T
32、his results in a project execution Control Budget or Project Baseline Budget, or simply, the Project Budget. In some areas of project management application it is referred to as a Project Cost Plan.On a large project where different corporate production divisions are involved, there may be a further
33、 intermediate step of creating Control Accounts for the separate divisions, so that each division subdivides their allocated money into their own WBS WPs.Observe that, since the total Project Budget received formal approval from Executive Management, you, as project manager, must likewise seek and o
34、btain from Executive Management, via the projects sponsor, formal approval for any changes to the total project budget. Often this is only justified and accepted on the basis of a requested Product Scope Change.In such a case the projects sponsor will either draw down on the management reserve in hi
35、s or her possession, or submit a supplementary RFA to upper management.Now that we have the Project Budget money allocated to Work Packages we can further distribute it amongst the various activities of each WP so that we know how much money we have as a Baseline cost for each activity.This provides
36、 us with the base of reference for the cost control function. Of course, depending on the circumstances the same thing may be done at the WP level but the ability to control is then at a higher and coarser level.Use of the Earned Value techniqueIf we have the necessary details another control tool t
37、hat we can adopt for monitoring ongoing work is the Earned Value (EV) technique. This is a considerable art and science that you must learn about from texts dedicated to the subject.But essentially, you take the costs of the schedule activities and plot them as a cumulative total on the appropriate
38、time base. Again you can do this at the activity level, WP level or the whole project level. The lower the level the more control information you have available but the more work you get involved in.The Cost BaselineThis planned reference S-curve is sometimes referred to as the Cost Baseline, typica
39、lly in EV parlance. That is, it is the Budgeted Cost of Work Scheduled (BCWS), or more simply the Planned Value (PV).Observe that you need to modify this Cost Baseline every time there is an approved scope change that has cost and/or schedule implications and consequently changes the projects Approv
40、ed Project Budget.Now, as the work progresses, you can plot the Actual Cost of Work Performed (ACWP or simply Actual Cost - AC).You can plot other things as well, see diagram referred to above, and if you dont like what you see then you need to take Corrective Action.CommentaryThis whole process is
41、a cyclic, situational operation and is probably the source of the term cycle in the popularly misnamed project life cycle.As an aside, the Earned Value pundits offer various other techniques within the EV process designed to aid in forecasting the final result, that is, the Estimate At Completion (E
42、AC). EAC is what you should really be interested in because it is the only constant in a moving project. Therefore, these extended EV techniques must be considered in the same realm of accuracy as top-down estimating. They are useful, but only if you recognize the limitations and know what you are d
43、oing!But, as we said at the beginning, it is a lot more difficult to do in practice and involves a significant amount of work. But, lets face it, thats what project managers are hired for, right 中文译文:项目成本控制:它的工作方式R.马克斯怀德曼我们在最近的咨询任务中意识到,对于整个项目成本控制体系是如何设置和应用 的这个问题,我们仍有一些缺乏了解。因此,我们决定写出它是如何工作的说明。从 理论上讲,
44、项目成本控制并不难。首先,建立一套参考基准。然后,按照工作的进展,监察工作,分析结果显示, 预测最终结果并与参考基线作比较。如果最终结果不令人满意,那么你要对正在进行 中的必要的工作进行调整,并在适当的时间间隔内重复循环。如果最终结果已经与基 线计划脱节,你可能不得不改变计划。更有可能的是,将会有(或已经)变化的范围 改变参考基线,这意味着,每一次范围发生变化,无论如何你都必须改变基线计划。但是通过项目数量未能控制成本,证明在实践中,项目成本控制是很难真正实施 的。我们将看到,它还涉及到相当数量的工作,因此,我们不妨在一开始就启动它, 通过整个项目的线程寿命来进行工程造价控制。同时,我们将借此
45、机会指出几个显着的适当的地方文件。 这些措施包括商业案例,(资本)请求拨款(执行),工作包和工作分解结构,项目章程(或摘要),项目预算或成本计划,获得的价值和成本基准。所有这些都有助于提高该组织有效地控制项 目成本的能力。脚注我要感谢我的朋友,大师昆汀弗莱明,检查和纠正我关于这一主题的工作。(执行)资助的商业案例和应用重要的是要注意,当负责的执行管理者对项目应如何通过项目寿命展开这个问题 有很好的理解时,项目的成本控制是最有效的。这意味着,他们在主要阶段的关键决 策点之间行使自己的责任。他们还必须认识到,至少对最明显的潜在危险事件,用于 查明和规划掌管关闭的项目风险管理的的重要性。在项目的概念
46、阶段每一个项目都由确定的机会或需要的人开始。 通常是有一定重要性或影响力的人, 如果该项目继续进行,这个人往往成为该项目的赞助者。为了确定潜在项目的适用性,大多数组织呼吁编制“商业案例”和“量级”的成 本,以证明该项目的价值,使其可以与所有其他项目竞争。企业的商业案例的准备工作成本通常包括管理开销,但它可结转为最终项目的会 计成本。毫无疑问,因为这将为该组织提供一个税务利益。问题是,你如何再占有所 有不结转项目?如果有足够的商业案例的优点,赞助者将继续发展和定义阶段。在该项目的发展或定义阶段在开发阶段的目标是建立一种涉及到生产所需的产品,估计成本,并为该项目的 实际执行寻求资本资金的良好的工作
47、的认识。在正式的设置, 尤其是在涉及大项目中, 这个拨款申请通常简称为 (大写)(RFA) 拨款或资本拨款请求( CAR)。这需要更详细的要求和数据的收集,建立什么工作需要来完成生产所需的产品或 “交付”。从这个信息来看,一个准备足够的细节计划在一美元的数字请求上给予足 够的信心。在一个不太正式的设置中,每个人都只是试图蒙混过关工作包和 WBS项目管理计划,项目简介或项目宪章 如果可交付的成果由一些不同元素组成,这些都是确定和组装工作包( WPS),并 在工作分解结构( WBS)的形式提交。每个的 WP涉及的一系列活动,计划和计划的一部分作为“工作”项目管理计划。但是请注意,如果该项目在执行过
48、程中前进,将该规划水平变得更高,更详细,将是 必要的。该项目管理计划的方式,应该成为该项目“圣经”的执行阶段,同时它有时被称 为“项目简介”或“项目宪章”。然后估计各种活动的成本,这些估计费用汇总以确定的 WP的估计成本。这种方法 作为“详细估算”或“自下而上估算”而为人知晓。还有其他的方法来估算,我们将 在一分钟内到达。无论哪种方式,结果都是该项目的总工作的估计费用。 注:该项目的风险管理规划,是这次演习的一个重要组成部分。这应该检查该项目的 假设和环境条件,以确定该计划中的任何弱点,到目前为止,并找出值得注意缓解这 些潜在的风险事件。这可能采取具体的应急计划的形式和 / 或预审慎的资金储备
49、。 资本要求 转换的估计然而,单独的工作的一个估计是没有足够资本要求的。为到达一定的资本要求, 一些转换是必要的,例如,通过加入审慎津贴如开销,一个应急的津贴,以弥补包括 未知和可能的范围变化的正常的项目风险和管理储备。此外,财务会计格式转换成估算数据可能是必要的,以满足有目的的企业或赞助 商的形式与其他项目比较和随之而来的拨款。刚才所描述的方法中, 所有的数据类型为 “自下而上” ,在实践中可能无法使用。 在这种情况下,替代的估算方法是在时尚中通过提供不同程度的“自上而下”的可靠 性。例如:订购数量级的估计 - “球公园”估计,通常只为概念预留类似的估计 - 根据以前类似项目的预算 参数估计 - 基于对历史数据的统计关系估计 无论采用哪种方法,这种希望总和能被全面批准和证明是令人满意的!这是启动 该项目的执行阶段。注:有些管理层将批准错误地认为,大家以“提升他们的铅笔”和
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 初中道德与法治八年级上册第四单元4.1“涉险滩”与“啃硬骨头”教学设计
- 高中语文必修上册《赤壁赋》第二课时沉浸式思辨教学设计
- 2025新《安全生产法》培训考试试卷及答案
- 2026年深圳市资本运营集团有限公司人员招聘笔试备考试题及详细答案解析
- 高二地理选择性必修1 板块构造学说与全球地貌格局教学设计
- 2025长鑫存储新员工入职在线考核试题及答案
- 2025中国红十字会救护员培训理论考试试题及答案
- 2026年南通市烟草专卖局人员招聘参考题库及详细答案解析
- 2026年西安铁路局人员招聘笔试模拟试题及详细答案解析
- 小学四年级劳动教案 精美小布艺创意设计与缝制教学
- 2026年安全教育授课教师培训试题
- 劳务公司上墙管理制度
- 中国历史简史课件
- 25春国家开放大学《园艺植物栽培学总论》形考任务1-3+实验实习参考答案
- 燃气维保合同协议
- 工程科学的创新之道-研究生科研能力的培养与提升
- 医用高等数学智慧树知到答案2024年南方医科大学
- 中田健身加盟合同范本
- 人自然社会浙江绿谷
- 风控(大数据时代下的信贷风险管理和实践)
- 【平衡计分卡(BSC)】经典培训讲义课件
评论
0/150
提交评论