1、地面砖、花岗岩铺贴施工方案ConstructionSchemeofFloortileandGranitetileInstallation一、准备工作Preparations1 .弹水平线,确定室内地石专完成面土0.00标高。Thehorizontalline,makesureindoorfloortilefinishsurfaceelevationof+/-0.00.2 .水电管线已安装完毕。Waterandelectricitylinealreadydeployed.二、准备材料Preparationofmaterials1. 425水泥及中砂,白水泥。425cementandmediums

2、andandwhitecement.2. 800*800*25花岗岩,600*600*25花岗岩,600*600*12地石专。800*800*25granite,600*600*25granite,600*600*12floortile.二、施工方法:constructionprocedure1、工艺流程constructionprocess材料准备一弹楼地面面层标高控制线-基层处理一弹线找中我方一铺贴基准控制标筋-铺贴面层一铺贴踢脚板-养护与成品保护PreparematerialsBombthegroundfloorsurfaceelevationcontrollineBasetreatme

3、ntBomblineLayupthebenchmarkcontrolstandardscreedlayupsurfacecourseLayupthebaseboard&Maintenanceandprotectionforthefinalproduct2、铺贴顺序:Tileinstallationorder(1)、大面积施工时,应用分段顺序铺贴。Largeareaconstruction,segmentedorderpaving(2)、对于整个楼层,要先铺贴独立房间,再铺贴通道或走廊。Fortheentirebuilding,firsttileseparaterooms,thenpas

4、sgewaysorcorridors.(3)、对于一般房间采用退步法先由房间中部向两侧铺贴。对于有独立柱的大厅,要先铺贴柱间部分,然后再向两边展开。ForGeneralrooms,useregressionmethodbylayingupfromthecentraltobothsides.Forthegreathallwithindependentcolumn,firsttilecolumnsection,thenexpandtobothsides.(4)、所有房间先铺贴整块板材,非整块板材最后铺贴。地面铺贴完后再铺贴踢脚板。Alltheroomsfirstlypavedwithblockpl

5、ate,ortileatlast.Skirtingboardtiledaftertheground.3、铺贴方法:Tileinstallationmethod(1)、以提前做好的标筋为基准,首排板材两边挂线,首排铺贴好后可单边挂线。Baseedonmarkingscreedmadebefore,thefirstrowplatehanglineonbothsides,afterthefirstrawistiled,itcanbehanglineononeside.(3)、结合层与板材面层应分段同时铺砌。先进行试铺,将干硬性水泥砂浆摊铺到铺贴部位刮平,其厚度要适宜,然后将板材平铺到干硬性水泥砂浆上

6、(干硬程度以手捏成团,落地即散为宜),用橡皮锤用力敲击板面,使摊铺的干硬性水泥砂浆结合层密实,并且使板材表面低于地面标高控制线2-5mmCombinedcourseandplatesurfacecourseshouldbetiledatthesametime.Firsttriallaying,flattherigidcementmortartothepavingpart,anditsthicknessshouldbeappropriated.Thentiletheplanktodry,rigidcementmorta(Advisabledegreeofdryiscanbekneadedtoge

7、ther,andscatteredwhendroppedonland).Usearubbermallethardstriketheboardtomakethepavingdryrigidcementmortarlayercombinationisclose-grained,andmakethesurface2-5mmbelowthegroundelevationcontrolsheet.(4)、试铺合适后,将板材揭起,在密实的干硬性水泥砂浆结合层上撒布一层干水泥面并用喷壶淋水一遍,或浇一层水泥浆作粘结,然后将板材再原位置再次安放。Afterappropriatetrialpaving,lift

8、uptheplate.Spreadalayerofdrycementtothedry,rigidclose-grainedcementmortar,andwetitoncebythewateringcan,orwateralayerofcementpasteformudbonding,thenputtheplatebackattheposition.再次安放时,板材四角要同时下落,放稳后用橡皮锤敲击板面使其平整并与结合层能紧密年粘接牢固,板材表面与地面标高控制线吻合便完成一块板材铺贴,再依次铺贴下一块。Whenplacedagain,fourcornersoftheplankshouldbed

9、roppedatthesametime.Afterlayeddownsteadily,usearubberhammertostrikeittomakeitflatandbondedfirmlywiththecombinedcourse.Theplankpavingisdonewhentheplanksurfaceiscoincidedwiththeelevationofthegroundcontrol,thenpavethenextone.铺贴时要随时找平找直,做到四角平整,纵横缝隙对齐。Whenpaving,besurethatitisflatandstraight.Makesurethef

10、ourcornersflat,andverticalandhorizontalcrackaligned.三、质量要求Qualityrequirements1、大理石,花岗石Marble,granite1.1 主控项目Dominantitem(1)面层与下一层应结合牢固无空鼓。Surfacecourseshouldbecombinedfirmlywiththenextone,withoutanygaps.(2)四角平整,纵横缝隙对齐、无色差。Fourcornersflat,verticalandhorizontalcrackaligned,colorlessdifference.1.2 一般项目

11、Generalitem(1)大理石,花岗石面层的表面应洁净,平整,无磨痕,且应图案清晰,色泽一致,接缝均匀,周边顺直,镶嵌正确,板块无裂、掉角、缺棱等缺陷。ThesurfaceofMarbleandgraniteshouldbeclean,flat,nogrindingmark,andclearpattern,consistentcolor,junctureuniform,straightsurrounding,rightMosaic,plateswithoutbrokencorners,nocrackdefectssuchaslackofedges.(2)踢脚线表面洁净,高度一致,结合牢固,

12、出墙厚度一致。Thesurfaceofthebaseboardshouldbeclean,andconsistentinheight,firmlycombined,andwithconsistentwallthickness.(3)楼梯踏步和台阶板块的缝隙宽度应一致,齿角整齐,楼层阶段相邻踏步,高度差不应大于10mmThestairtreadandstepplateshouldbeconsistentingapwidth,andtidytoothangles.Thefloorstageshouldbeadjacenttothetread,angtheheightdifferenceshould

13、benomorethan10mm.(4)大理石和花岗石面层的允许偏差应符合:Thedeviationofmarbleandgranitesurfacelayershouldbeallowedtomeet:、表面平整度:1.2mm、缝格平直:1.2mm接缝高低差:0.8mm踢脚线上口平直:1.2mm板块间隙宽度:1.2mmSurfaceevenness:1.2mmSeamcasestraight1.2mmJunctureheightdifference!)Skirtinglineflatside:1.2mmPlategapwidth:1.2mm2、地面砖Floortile主控项目:Dominan

14、titem(1)面层与下一层的结合(粘结)应牢固,无空鼓。Surfacecourseshouldbecombinedfirmlywiththenextone,withoutanygaps.(2)四角平整,纵横缝隙对齐,无色差Fourcornersflat,verticalandhorizontalcrackaligned,colorlessdifference.一般项目:Generalitem(1)砖面层的表面应洁净,图案清晰,色泽一致,接缝平整,深浅一致,周边顺直,板块无裂纹,掉角和缺损等缺陷。Thesurfaceofbricklayershouldbeclean,flat,nogrindi

15、ngmark,andclearpattern,consistentcolor,junctureuniform,straightsurrounding,rightMosaic,plateswithoutbrokencorners,nocrackdefectssuchaslackofedges.(2)面层邻接处的镶边用料及尺寸应符合设计要求,边角整齐,光滑。Theedgematerialsanddimensionsofsurfacecourseadjacentsideshouldmeetthedesignrequirement,withtidycornersandsmooth.(3)地板石专间隙宽

16、度:1.2以内mm。Floorbrickgapwidth:lessthan1.2mm.(4)踢脚线表面应洁净,高度一致,结合牢固,离墙厚度一致。Thesurfaceofthebaseboardshouldbeclean,andconsistentinheight,firmlycombined,andwithconsistentwallthickness.(5)面层表面的坡度应符合设计要求,不倒流水,无积水,与地漏,管道结合处应严密牢固无渗漏。Theslopeofsurfacecourseshouldmeetthedesignrequirement,oninverseflow,nonostagn

17、antwater.Thejunctionwithfloordrain,andpipeshouldbecloselysolidwithnoleakage.五、成品保护Maintenanceandprotectionforthefinalproduct1,铺好的地面3天后方可上人。Thepavedgroundcanbelanded3dayslater.新铺的房间应临时进行封闭,操作人员和检查人员进入房间踩踏时,要轻踏在一块木板上。Thenewpavedroomshouldbeclosedtemporarily,whenoperatorsandinspectorsenterrooms,pleasesteponapieceofwoodlightly.地面完工后,房

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论