1、施工组织设计是为保证工期、质量及平安、本钱及文明工地条件编制出有针对性 的施工组织方案,以指导施工顺利地完本钱工程工程的建设,大力推广应用新技术、 新材料,限制工程的本钱,最大化的缩短工期,创立优质工程为目的.本文以六盘水银行办公大楼施工工程为实例并结合实际情况对工程的各分局部 项工程施工方案进行了详细设计.通过工程量清单的计算、设计施工方案部署、设计 施工现场平面布置图、部署施工技术举措、设计横道图和网络图,对施工进度方案进 行分析、施工机械设备配备情况、工期保证举措、工程质量保证举措、平安及文明施 工举措、施工现场治理举措等因素对工程从开工准备到竣工验收全过程进行了系统的 进度规划设计,以
2、保证工程开工后施工能高效、 有序、平安、文明、科学合理的进行. 关键词:施工组织设计; 施工方案;进度规划AbstractConstruction design can be defined as a targeted construction plan compiled for insuring the construction period, quality, safety, cost and civilized site condition. It intends to smooth the accomplishment of construction projects, vigorou
3、sly promoted the application of new technology and new materials, control the cost of construction, maximize the contraction of construction period and create high quality projects.This report will analyze steps of a construction design item by item and combine with actual situation analysis by usin
4、g the construction project of Liupanshui Bank office block as an example in point. That is it will show the effect of a whole systematic process of schedule planning and designing from pre start up phasesto project final acceptanceto insure the orderly performance of project construction with high e
5、ffectiveness, safety, civilization and scientific rationality, through the construction deployment, the layout plan of construction site, the construction plan, the construction technology and measures, the analysis of the construction schedule planning by using bar chart and network diagram, the al
6、location situation of machine equipment, the period assurance measures, the quality assurance measures, the safe and civilized construction measures as well as the management measures of construction site.Key words: Construction Design, Construction Plan, Schedule Planning绪论 11编制说明及编制依据 21.1 编制说明 21
7、.2 编制依据 22工程概况 32.1 地理位置 32.2 工程设计概况 33工程量的计算 43.1 建筑面积 43.2 土石方工程 43.3 桩根底工程 43.4 标准层砌筑工程 53.5 标准层柱、梁工程量 63.6 楼梯工程量 123.7 门窗工程量 133.8 屋顶钢架及行标工程 153.9 化粪池及室外环境工程 163.10 装饰工程 194施工总体部署 214.1 施工工程经理部组织机构的选择及机构系统图 214.2 工程经理部设置 224.3 工程治理人员简介 224.4 工程治理人员责任 225各种资源需要量方案及施工准备 255.1 劳动力的配置 255.2 主要施工机械的配
8、备 265.3 主要周转材料需要方案 275.4 材料、机具、设备供给保证的应急举措 286施工技术及施工举措 296.1 施工条件及施工阶段的划分 296.2 运输机械的选择 296.3 测量放线 296.4 外架搭设 316.5 模板工程施工 316.6 钢筋工程施工 326.7 框架碎工程施工 336.8 砌体工程施工 356.9 屋面工程施工 366.10 装饰、装修工程施工 376.11 楼地面及重点部位施工 407工程工程进度安排及保证举措 427.1 工期目标 427.2 保证工期的主要举措 428施工总平面布置 448.1 施工现场临时道路 448.2 施工临时给、排水 448
9、.3 施工用电 458.4 生产临时设施的布置 468.5 生活临时设施的布置 479质量治理体系和保证举措 489.1 主要材料及设备的采购和保管 489.2 施工过程质量限制 499.3 检验和试验 509.4 纠正和预防举措 5010平安保证举措 5111冬雨季施工 5411.1 冬季施工 5411.2 雨季施工 5411.3 雨季避雷 5512环境保护及文明施工治理举措 5613降低本钱举措 59结论 60致谢 61参考文献 62附录 63绪论六盘水银行办公大楼工程施工组织设计是对拟建该工程施工的全过程实行科学 治理的重要手段.通过该施工组织设计的编制,可以全面考虑该拟建工程的各种具体
10、 施工条件,扬长避短地拟定合理的施工方案,确定该施工顺序、施工方法、劳动组织 和技术经济的组织举措,并合理地统筹安排拟定施工进度方案, 且保证拟建工程按期 投产或交忖使用;也为该拟建工程的设计方案在经济上的合理性,在技术上的科学性 和在实施工程上的可能性进行论证提供依据; 还为建设单位甲方编制根本建设方案和 施工企业编制施工方案提供依据. 施工企业乙方可以提前掌握人力、 材料和机具使用 上的先后顺序,并全面安排资源的供给与消耗;可以合理地确定该施工方案的临时设 施的数量、规模和用途,以及临时设施、材料和机具在该施工场地上的布置方案.施工组织设计是规划和指导工程投标、 承包合同签订、施工准备及施
11、工全过程的 全局性技术,是对施工活动实行科学治理的重要手段, 具有战术安排和战略部署的双 重作用.可以保证施工过程能有序的进行.施工组织设计是组织工程施工总的指导性文件, 应该在正式开工前编制及审批完 成并且应根据业主的工期要求进行编制, 制定合理的施工进度方案,这样就能调好项 目的设计与施工、技术与经济、各施工阶段和施工过程之间的关系, 就能采用科学的 治理方法,有效使用人力、物力,安排好时间、空间,以到达耗工少,工期短、质量 高和造价低的最优效果,全面的完成施工任务.本施工组织设计是依据设计院设计的施工图和中华人民共和国建设部公布的各 种有关建筑结构设计标准及现行建筑工程施工验收标准和操作
12、规程,以及国家颁发的工程质量、文明施工及平安生产的有关规定及要求编制的.所需的主要标准、标准、 规程包括:?建筑工程设计文件编制深度规定?(2022年版)、?工程建设标准强制性 条文房屋建筑局部?(2022年版)、?建筑设计防火标准?(GB50016-2022)、?民用 建筑设计通那么?(GB50352-2022)、?钢管脚手架扣件?(JGJ22-55)、?外墙外保温工 程技术规程?(JGJ144-2022、J408-2022)等.本施工组织设计主要内容包括工程概况、施工部署、施工工期及保证举措、主要工程施工方法、主要治理举措等几个方面.施工组织是以科学编制一个工程设施或群 体的施工组织设计为
13、研究对象,结合具体施工对象,编制出指导施工的施工组织设计, 合理的使用人力、物力、空间和时间,着眼于各工种工程施工中关键工序的安排,使 之有组织有秩序的施工.通过它可以全面考虑拟建工程的各种具体施工条件,拟定合理的施工方案,确定施工顺序、施工方法和技术经济的组织设计, 合理的安排拟定施 工进度方案.1编制说明及编制依据1.1 编制说明本投标施工组织设计严格根据工程招标范围和招标文件对施工组织设计的要 求进行编制.在人员、机械、材料调配、质量要求、进度安排等方面统一部署的原那么 下,由土建、安装二大专业组成.根据本工程设计特点、功能要求,本着对业主资金合理利用,对工程质量的高 度责任感,我们的编
14、制原那么是“经济、合理、优质、高效.本投标施工组织设计的编制,受到了我公司的高度重视和大力支持,公司将参 加过类似工程施工的有关负责人召集在一起,形成方案编制专题小组,采用“比照优 化、博采众长的编制思路,力求本方案重点突出,针对性、可操作性强.本投标施工组织设计根据业主招标文件的要求分以下两个局部编制.第一局部为土 0.00以下及以上土建工程.第二局部为安装工程.1.2 编制依据六盘水银行办公大楼工程(以下简称本工程)招标文件.遵义市建筑设计研究院设计的本工程招标设计图纸.我公司的技术、机械设备装备情况及治理制度.国家和行业现行的施工及验收标准?硅结构工程施工及验收标准?(GB50204-0
15、2)?地面与楼地面工程施工及验收标准?(GB50209-02)?屋面工程施工及验收标准?(GB50204-03)?建筑装饰工程施工及验收标准?(JGJ73-01)?地基与根底工程施工及验收标准?(GBJ202-03)?砖石工程施工及验收标准?(GBJ203-03)?木结构工程施工及验收标准?(GBJ206-05)?施工现场临时用电平安技术标准?(JGJ46-01)?建筑施工平安检查标准?(JGJ59-05)?建筑施工高处作业平安技术标准?(JGJ80-04)?建筑工程质量检验评定标准?(GBJ301-05)地方和企业现行的施工工艺和工法?高层建筑泵送碎施工工法?(GJGF07-06?竖向电渣压
16、力焊施工工法?(Q/CJZ(TG 004-01)等.工程概况东华理工大学毕业设计论文2工程概况2.1 地理位置本工程位于六盘水市钟山中路和水西南路交汇处.北距钟山大道约10m东距水西南路约5.7m,南距中行宿舍约18.5m,西侧紧邻红华家电商场.2.2 工程设计概况建筑概况本工程由群楼和塔楼两局部组成.建筑总高49.35米,共11层,其中土 0.00以下为一层.地下一层为通风、回风、集水坑等,营业一层,以上为办公楼.顶上两层 为会议室和培训室.其上为钢筋混凝土地板根底.上部结构为框架结构.总建筑面积 为5964平方米.其中地下室面积为330平方米.整个工程设有水、电、消防、暖通、 营业大厅、办
17、公室等配套设施.是一栋配套设施齐全的办公建筑物.结构概况本工程为框架结构,工程平安等级为二级场地土类别为二场区,六度抗震设防, 地基根底为大直径机械成孔桩,根据上部结构荷载及地质资料根底J1,J2,J4采用冲孔 灌注桩,根底J3采用钻孔灌注桩.孔深均在9米以上,最深到达41.7米,平均深度约18 米.持力层为较完整白云质灰岩;取地基承载力特征值fa=5010kpa.采用冲孔时,应严 格根据"JGJ94-94"标准第6.3.10-6.3.17施工明确成桩质量,村底沉渣厚度不于等于 50mm施工中应妥善处理泥浆.施工放线时,孔桩中央应与柱中央重合,施工时应采 取挖孔中适合的施工
18、平安及排水举措开挖过程中如遇特殊情况应通知有关人员的情 况处理.桩身每隔2000增设14加劲箍一道.地质资料中已注明参考桩长,该桩长是 以钻探点进入中风化完整基岩500的实际长度结算桩长接到承台底的实际长度计.桩 顶嵌入承台100,承台底面钢筋保护层为70mm桩根底施工完后应进行桩的有效检测, 桩质量合格前方可进入下步工序施工.地梁采用 C30&现浇纵筋采用双面搭接焊应满 足Ld>10dma界条t50,地梁底作b+200宽C10昆凝土垫层厚100.框架柱钢筋伸入承台内 600弯起a=902000.地梁配筋根据?03G101-1?图集绘制,施工时严格根据,四级 抗震等级构造详图施工
19、.碎:根底垫层C10;根底、根底底板、地下室侧墙、框架梁、板,框架柱,楼梯 及其它现浇构件均采用C30砌体:本工程外墙及楼梯四周墙为240厚,采用轻质砖.走道两边墙为240厚,采 用轻质砖.房间内墙为240厚,采用轻质板.电梯墙为240厚,采用页岩砖.所有墙隔 声系数为50HPA地下室墙体防潮做法见建施图,地面采用 20厚1: 2水泥砂浆,加3% 防水剂.钢筋混凝土墙、柱与砌体连结处应有钢筋拉结,碎保护层厚度:根底底板100mm;地下室外墙外侧,地下室顶板顶侧,现浇梁柱 30mm;剪力墙地下室外墙内侧、现浇梯板、楼板 20mm.3工程量的计算3.1建筑面积地下建筑面积为23.9*16.7-3.
20、6*2.6-3.6*2.5-6.8*7.4=330 m2底层建筑面积为30.8*23.7+15.5*24.6-5.5*9.9*0.5=1084 m22-11层建筑面积为30.8*16.7-3.6*3.5*2-3.6*4.2*2-1.8*2.2*0.5*2=455 m2总面积:1084+455*10+330=5964 m23.2 土石方工程量平整场地工程量计算:协整场地=S +2L#+16L# =30.8+7.6+24.6+15.5+30.8+23.7+9.2+12=154.2 m8n 场地=1084+2*154+16=1408 m23.3 桩根底工程量本工程平安等级为二级场地土类别为二场区地震
21、烈度6度.承台埋深1.3m,承台高0.7m,桩顶伸入承台100mml冈筋保护层取70mm根据上部结构荷载及地质资料 根底J1,J2,J4采用冲孔灌注桩,根底J3采用钻孔灌注桩.设计长度均为14m直径分别为1m,0.8m,1.5m,1.3m.桩身长度混凝土强度是 C2Q桩进入基岩0.5m.钻土孔混凝土工程量混泥土工程量V=桩设计断面积* (设计桩长+0.25m) *桩数J-1 8 个 :(14+0.25) * 兀 *0.5*0.5*8=89.49m 3J-2 1 个:(14+0.25) * 兀 *0.4*0.4*1=7.16 m 3J-3 19 个:(14+0.25) * Tt*0.65*0.6
22、5*19=359.19m 3J-4 3 个 :(14+0.25) * Tt*0.75*0.75*3=75.51m 3总计 89.49+7.16+359.19+75.51=531.35m 3钻岩孔混凝土工程量J-1 8 个 :0.5* 九 *0.5*0.5*8=3.14 m 3J-2 1 个:0.5* 九 *0.4*0.4*1=0.25 m 3J-3 19 个:0.5* 九 *0.65*0.65*19=12.6 m 3J-4 3 个 :0.5* 九 *0.75*0.75*3=2.65 m 3总计 3.14+0.25+12.6+2.65=18.64 m 3泥浆外运531.35+18.6=549.9
23、9 m 3钢筋钢筋工程量=钢筋截面积*钢筋密度*钢筋长度*根数*桩数J-1 8 个:主筋 18mm G=0.009*0.009*3.14*7.85*14*8*8=1341.7kg箍筋 12mm G=0.006*0.006*3.14*7.85*5.6*10*8=397.54kgJ-2 1 个:主筋 18mm G=0.009*0.009*3.14*7.85*14*8*1=167.7kg箍筋 12mm G=0.006*0.006*3.14*7.85*5.6*10*1=49.69kgJ-3 19 个:主筋 18mm G=0.009*0.009*3.14*7.85*14*8*19=3186.3kg箍筋
24、12mm G=0.006*0.006*3.14*7.85*5.6*10*19=944.16kgJ-4 3 个:主筋 18mm G=0.009*0.009*3.14*7.85*14*8*3=503.1kg箍筋 12mm G=0.006*0.006*3.14*7.85*5.6*10*3=149.07kg总计=1341.7+397.54+167.7+49.69+3186.3+944.16+503.1+149.07=6739.26kg3.4 标准层四层砌筑工程量墙身工程量按实体积以立方米计算V二墙长*墙高-三嵌入墙身门窗洞口面积*墙厚-三嵌入墙身的混泥土构件体积 标准层砌体第四层表1门窗统计表门窗名称
25、代号洞口尺寸mm数量单傕回积itf合计面积itf塑钢推拉窗C11800X180043.2412.96塑钢推拉窗C21500X180032.78.1塑钢推拉窗C31200X180042.168.64塑钢推拉窗C4900X180011.621.62塑钢推拉窗C5700X180021.262.52塑钢推拉窗C617000X3100152.652.65续表1门窗名称代号洞口尺寸mm数量单傕回积itf合计面积itf镶板门M2900X210051.899.45乙级防火门M31400X210012.942.94电梯门M51100X210022.314.62全板夹板门M6800X210031.685.04丙级
26、防火门M7700X180021.262.52Fn 窗=12.96+8.1+8.64+1.62+2.52+52.6+9.45+2.94+4.62+5.04+2.52=111.01m2外墙中央线: 心=(30.8+2.4+1.8+1.5+2.4+2.4+0.9+1.5+2.0) *2=91.4内墙净长线: L争=(6.8+2.4+7.5 ) *5+ (2.4+0.9 ) *6-0.12*22=100.66 m外墙高H外=3.3m内墙高H内=2.6m内外墙工程量=(91.4*3.3+100.66*2.6-111.01) *0.24=108.56m33.5 标准层(四层)柱、梁工程量3.5.1 柱表2
27、柱截面尺寸及个数柱截卸尺寸mm数量KZ1650*6504KZ3650*65010KZ4650*65012KZ5D7504KZ6650*6504KZ8700*7004KZ9650*6504KZ10600*6002柱-混凝土柱的混凝土工程量=三柱截面面积*柱的高度*根数V1 =0.65*0.65*3.3*4=5.58 m3V3=0.65*0.65*3.3*10=13.9 m 3V4 =0.65*0.65*3.3*12=16.7 m 3V5 =0.375*0.375*3.14*3.3*4=5.83 m3V6 =0.65*0.65*3.3*4=5.58 m 3V8 =0.7*0.7*3.3*4=6.4
28、7 m 3V9 =0.65*0.65*3.3*4=5.58 m 3V10 =0.6*0.6*3.3*2=2.38 m 3总计:12 V=5.58+13.9+16.7+5.83+5.58+6.47+5.58+2.38=62.02 m 3柱-模板柱的模板工程量= 柱截面周长*柱的高度*根数S1 =0.65*3.3*4*4=34.32m283 =0.65*3.3*10*4=85.8m2S4 =0.65*3.3*12*4=102.96m285 =0.75*3.14*3.3*4=31.09m2S6 =0.65*3.3*4*4=34.32m288=0.7*3.3*4*4=36.96m2S9 =0.65*3
29、.3*4*4=34.32m2S0=0.6*3.3*2*4=15.84m2总计:S=34.32+85.8+102.96+31.09+34.32+36.96+34.32+15.84=375.61 m2柱-钢筋钢筋工程量=钢筋截面积*钢筋密度*钢筋长度*根数*柱数纵筋长度= 层高-该层 max Hn/6、hc、500 + 上一层 max Hn/6、hc、500L=3.3-max2.6/6,650,500+ max2.6/6,650,500=3.3 mG1 =0.011*0.011*3.14*7.85* 3.3*12*4=472.4kgL3 =3.3-max2.6/6,650,500+ max2.6/
30、6,650,500 =3.3 mG3 =0.011*0.011*3.14*7.85* 3.3*12*10=1181.08 kgL4 =3.3-max2.6/6,650,500+ max2.6/6,650,500 =3.3 mG4 =0.011*0.011*3.14*7.85* 3.3*12*12=1417.3 kgL5 =3.3-max2.6/6,750,500+ max2.6/6,750,500 =3.3 mG5 =0.011*0.011*3.14*7.85* 3.3*12*4=472.4 kgL6 =3.3-max2.6/6,650,500+ max2.6/6,650,500 =3.3 m
31、G6 =0.011*0.011*3.14*7.85* 3.3*12*4=472.4 kgL8 =3.3-max2.6/6,700,500+ max2.6/6,700,500 =3.3 mG8 =0.011*0.011*3.14*7.85* 3.3*12*4=472.4 kgL9 =3.3-max2.6/6,650,500+ max2.6/6,650,500 =3.3 mG9 =0.011*0.011*3.14*7.85* 3.3*12*4=472.4 kgL10 =3.3-max2.6/6,600,500+ max2.6/6,600,500 =3.3 mG10 =0.011*0.011*3.1
32、4*7.85* 3.3*12*2=236.22 kg总计:G=472.4*5+1181.08+1417.3+236.22=5196.6 kg3.5.2 梁梁-混凝土梁的混凝土工程量=三梁截面面积*梁的长度*根数表3梁截面尺寸及长度和体积梁代号及截卸面积mm梁的长度m梁的体积m3KL1 300*600(3.3-0.3 ) *1=30.3*0.6*3=0.54KL2 300*450(3.3-0.3 ) *1=30.3*0.45*3=0.405KL3 300*450(5.7-0.3)*1=5.40.3*0.45*5.4=0.729KL4 300*650(9.2-0.3*2 ) *1=8.60.3*0
33、.65*8.6=1.68KL5 300*450(16.7-0.3*3)*1=15.80.3*0.45*15.8=2.1KL6 300*500(16.7-0.3*4)*1=15.50.3*0.5*15.5=2.33KL7 300*500(3.3-0.3 ) *1=30.3*0.5*3=0.45KL8 300*500(16.7-0.3*4)*1=15.50.3*0.5*15.5=2.33KL9 300*450(7.5-0.3*2)*1=6.90.3*0.45*6.9=0.93KL10 300*600(12.5-0.3*3)*1=11.60.3*0.6*11.6=2.1KL11 300*450(8.
34、1-0.3)*1=7.80.3*0.45*7.8=1.1KL12 300*450(3.5-0.3 ) *1=3.20.3*0.45*3.2=0.43KL13 300*450(3.3-0.3*2)*1=2.70.3*0.45*2.7=0.36KL14 300*450(3.3-0.3*2)*1=2.70.3*0.45*2.7=0.36KL15 300*700(17-0.3*4)*1=15.80.3*0.7*15.8=3.32KL16 300*450(5.7-0.3)*1=5.40.3*0.45*5.4=0.73KL17 300*450(5.7-0.3)*1=5.40.3*0.45*5.4=0.73
35、KL18 300*600(6.9-0.3)*1=6.60.3*0.6*6.6=1.2KL19 300*650(3.6-0.3)*1=3.30.3*0.65*3.3=0.65KL20 300*500(30.8-0.3*7)*1=28.70.3*0.5*28.7=4.3KL21 300*450(30.8-0.3*7)*1=28.70.3*0.45*28.7=3.87KL22 300*450(3.6-0.3 ) *1=3.30.3*0.45*3.3=0.459续表3梁代号及截面尺寸梁的长度梁的体积KL23 300*500(3.6-0.3 ) *1=3.30.3*0.5*3.3=0.5KL24 300
36、*450(23.6-0.3*7 ) *1=21.50.3*0.45*21.5=2.9LL1 250*4502.4*2=4.80.25*0.45*4.8=0.54LL2 250*4003.3*1=3.30.25*0.4*3.3=0.33LL3 300*5006.8*1=6.80.3*0.5*6.8=1.02LL4 250*4002.2*1=2.20.25*0.4*2.2=0.22LL5 300*4504.7*3=14.10.3*0.45*14.1=1.9LL6 300*4502.35*1=2.350.3*0.45*2.35=0.32LL7 300*4505.7*1=5.70.3*0.45*5.7
37、=0.77LL8 250*4003.3*1=3.30.25*0.4*3.3=0.33总计:V=0.54+0.405+0.729+1.68+2.1+2.33+0.45+2.33+0.93+2.1+1.16+0.43+0.36+0.36+3.32+0.73+0.73+1.2+0.65+4.3+3.87+0.45+0.5+2.9+0.54+0.33+1.02+0.22+1.9+ 0.32+0.77+0.33=40.42 m 3梁-模板梁模板工程量=(梁底宽+梁侧高*2) *梁长*根数Skl1= (0.3+0.6*2 ) *3*1=4.5 m2Skl2= (0.3+0.45*2 ) *3*1=3.6
38、.SKL3= (0.3+0.45*2 ) *5.4*1=6.48 m2Skl4= (0.3+0.65*2 ) *8.6*1=13.76 m2SKL5= (0.3+0.45*2 ) *15.8*1=18.96 m2Skl6= (0.3+0.5*2 ) *15.5*1=20.15 m2Skl7= (0.3+0.5*2 ) *3*1=3.9 m2Skl8= (0.3+0.5*2 ) *15.5*1=20.15 m210Skl9= (0.3+0.45*2 ) *6.9*1=8.28 m2Skl10= (0.3+0.6*2 ) *11.6*1=17.4 m2Sklii= (0.3+0.45*2 ) *7
39、.8*1=9.36 m2Skl12= (0.3+0.45*2 ) *3.2*1=3.84 m2Skl13= (0.3+0.45*2 ) *2.7*1=3.24 m2Skl14= (0.3+0.45*2 ) *2.7*1=3.24 m2Skl15= (0.3+0.7*2 ) *15.8*1=26.86 m2SKL16= (0.3+0.45*2 ) *5.4*1=6.48 m2Skl17= (0.3+0.45*2 ) *5.4*1=6.48 m2Skl18= (0.3+0.6*2 ) *6.6*1=9.9 m2SkL19= (0.3+0.65*2 ) *3.3*1=5.28 m2Skl20= (0
40、.3+0.5*2 ) *28.7*1=37.31 m2Skl21= (0.3+0.45*2 ) *28.7*1=34.44 m2Skl22= (0.3+0.45*2 ) *3.3*1=3.96 m2Skl23= (0.3+0.5*2 ) *3.3*1=4.29 m2SKL24= (0.3+0.45*2 ) *21.5*1=25.8 m2Sll1= (0.25+0.45*2 ) *2.4*2=5.52 m2Sll2= (0.25+0.4*2 ) *3.3*1=3.47 m2SLL3= (0.3+0.5*2 ) *6.8*1=8.84 m2SLL4= (0.25+0.4*2 ) *2.2*1=2.
41、31 m2SLL5= (0.3+0.45*2 ) *4.7*3=16.92 m2Sll6= (0.3+0.45*2 ) *2.35*1=2.82 m211SLL7= (0.3+0.45*2 ) *5.7*1=6.84 m2SLL8= (0.25+0.4*2 ) *3.3*1=3.47 m2总计:S=3.47+6.84+3.96+4.29+25.8+5.52+3.47+8.84+2.31+16.92+2.82+4.5+3.6+6.48 +13.76+18.96+20.15+3.9+20.15+8.28+17.4+9.36+3.84+3.24+3.24+26.86+6.48+6.4 8+9.9+5
42、.28+37.31+34.44 =347.85 m2 梁-钢筋 钢筋总长=(各跨长之和或净长-2*保护层厚度+锚固)*根数 a.贯穿筋 4 22 总长=3500*4=14 m b.底筋 8 18 总长=3380*8=27 m c.箍筋 42 6 总长=1460*75=109.5 m d.贯穿筋与底筋 6 18 总长=7580*6=45.48 m e.钢筋用量汇总 6: 109.6*0.222=24.333 Kg 18: (45.48+27)*1.999=144.89 Kg 22: 14*2.999=41.98 Kg总计:24.33+144.89+41.98=211.2 Kg3.6 楼梯工程量当
43、楼梯井宽度小于200mm寸楼梯工程量=楼梯间净宽* (休息平台宽+ 踏步宽*步数)* (楼层数-1 )标准层(四层)水磨石楼梯工程量 =(1.64+2.52+1.64-0.12 ) * (3.3-0.12*2 )=14.26m2踏步工程量=踏步长*踏步宽*步数S= (1.55-0.12 ) *0.3*10=4.29 m2台阶(包括踏步及最上一步踏步口外延300mm整体面层按水平投影面积以平方米计算.台阶花岗石板贴面工程量=4* (0.3+0.15 ) *10=18 m2123.7 门窗工程量SM1A =3.3*5.1*2=33.66SM1 =7.4*5.1*1=37.74 m2SM2 =0.9
44、*2.1*71=134.19 m2SM3 =1.4*2.1*25=73.5m2Sm 4 =1.4*2.4*6=20.16m2Sm5 =1.1*2.1*22=50.82 m2SM 6=0.8*2.1*36=60.48 m2SM7 =0.7*1.8*21=26.46 m2Sm 8 =1.4*2.1*2=5.88 m2Sm10 =0.9*2.1*3=5.67 m2Sm12 =1.4*2.1*3=8.82 m2Sm9 =0.7*2.1*1=1.47 m2SM11=2*2.1*1=4.2 m2门编p名称洞口尺寸mm数量一层二层三层四-八层九层十层屋顶合计M1地弹门7400*510011M1A地弹门330
45、0*510022M2镶板门900*21003510483271M3乙级防火门1400*2100212105425M4塑钢门1400*24001216M5电梯门1100*2100222102222M6全本夹板门800*2100533153336M7丙级防火门700*1800222102221M8防盗门1400*210022M9推拉门700*210011M10防盗门900*210033M11防盗门2000*210011M12镶板门1400*210033表4门统计表m2S总=37.74+33.66+134.19+73.5+20.16+50.82+60.48+26.46+5.88+1.47+5.67+
46、4.2+8.82=463.05 m213窗8cl=1.8*1.8*24=77.76m2Sc3 =1.2*1.8*38=82.08 m2SC5 =0.7*1.8*26=32.76 m2SC2 =1.5*1.8*19=51.3 m2Sc4=0.9*1.8*14=22.68 m2SC6=17*3.1*6=316.2 m2SC7 =1.8*2.4*20=86.4 m2SC8 =1.5*2.4*10=36 m2SC9 =1.2*2.4*4=11.52 m2SC10 =1.38*10.73*1=14.81m214表5窗统计表编p名称洞口尺寸mm数量一层二层三层四-八层九层十层屋顶合计C1塑钢推拉窗1800
47、*180042024C2塑钢推拉窗1500*1800315119C3塑钢推拉窗12004塑钢推拉窗900*1800331511214C5塑钢推拉窗700*1800442102226C6塑钢推拉窗17000*3100156C7塑钢推拉窗1800*2400574420C8塑钢推拉窗1500*2400133310C9塑钢推拉窗1200*240011114C10刚 化 大 玻 窗1380*1073011C116400*1073011C122820*1703011C131950*1703033C147000*1703011C155700*1703011C167400*46001
48、1C175700*1703011C187400*460011C193300*460022C203000*415011C21塑钢推拉窗17000*37011C22塑钢推拉窗17000*4900118cli=6.1*10.73*1=68.67 m2Sci3 =1.95*17.03*3=99.63 m2SC15 =5.7*17.03*1=97.07 m2SC17 =5.7*17.03*1=97.07 m2Sc19 =3.3*4.6*2=30.36 m2SC21 =17*3.7*1=62.9 m2SC12 =2.82*17.03*1=48.25m2SC14 =7.0*17.03*1=119.21m2S
49、C16 =7.4*4.6*1=34.04 m2SC18 =7.4*4.6*1=34.04 m2Sc20 =3.0*4.15*1=12.45m2SC22 =17*4.9*1=83.3 m2S总.=77.76+51.3+82.08+22.68+32.76+316.2+86.4+36+11.52+14.81+68.67+48.25+99.63+119.21+97.07+34.04+97.07+34.04+30.36+12.45+62.9+83.3=1518.5 m23.8 屋顶钢架及行标工程量40丝铝塑板4 nlm厚幕墙侧边及女儿墙顶口 = (45.45-11.45 ) X 0.7 X 2+17.2
50、4X 1.05=65.70 m2钢架外包铝塑板=40X (0.3+0.7 ) X2X3+14X (0.6+0.7 ) X 2X 3 + (0.3+0.6 )X2X (4.8+6.02) X3X 2+ (1.5+0.6 ) X 2X 10.8=511.42m2行标=(1.5+0.6 ) X 2X10.8=45.36 m2总计=45.36+511.42+65.70=598.28 m2屋顶钢架基座基座 C20碎=1.85X 1.75 X0.3 X3=2.91 m2钢筋1620瞅层双向=(1.85-0.03) X (1.75-0.03)+0.2+1 X6X 1.58=165.63 m2=(1.75-0
51、.03)X (1.85-0.03)+0.2+1 X6X 1.58=164.69 m212 mm厚钢板=3X1.85 X 1.75=9.71 m23.9 化粪池及室外环境工程量厅P分项工程名称单位工程数 量计算式153.9.1化粪池a挖掘机挖土方装 车259.73挖掘机挖土方m374.56(10.92+0.61 ) X ( 4.68+0.61 ) 1 1.22+0.52X 1.22 3+3=74.56挖掘机挖湿土 x1.15系数m3185.17(10.92+1.14)义(4.68+1.14)义2.28+0.5 2X2.283+3义 1.15=185.17b人工挖基坑三、四 内土深4米深内 20米
52、内运m321.71湿土m321.71(4.68+0.2 ) X (10.92+0.2 ) X 0.4+0.52X0.4 3+3=21.71c人工20米内取三、 四类土夯填放坡 基坑周边m3146.78(259.73+21.71 ) - ( 3.48 义 9.72 义3.4+7.3+3.93+8.42=146.78d挖掘机装车,自卸汽车外运土方8KMm3259.73人工装车,自卸汽 车外运土方8KMm321.71e100 mm管径污水 泵抽污水台班20fM10水泥砂浆砌体m344.17(3.9-0.5-0.6 ) X 0.5 X ( 3.48+9.72 ) X2+0.37 X 3.48 X 2X2.8=44.17g现浇C25ffi筋混凝 土板
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 江西省抚州市乐安县重点达标名校2025年初三阶段性测试(五)数学试题试卷含解析
- 上海杉达学院《国际经济学》2023-2024学年第二学期期末试卷
- 2025年网络营销专业技能考试试题及答案
- 2025年信息系统项目管理师资格考试试题及答案
- 台州市临海市2025年数学三下期末综合测试模拟试题含解析
- 上海民远职业技术学院《唐诗选读》2023-2024学年第二学期期末试卷
- 未来医疗行业发展趋势与相关护理考试试题及答案
- 泰山护理职业学院《水利工程专业导论》2023-2024学年第二学期期末试卷
- 吉林省长春市朝阳区2024-2025学年联考第一次诊断性考试化学试题含解析
- 江苏省常州市武进区礼嘉中学2024-2025学年高三4月高考二模英语试题含解析
- 2025年港口国企笔试题库及答案
- 儿童发展问题的咨询与辅导-案例1-5-国开-参考资料
- 《中小学综合实践活动课程指导纲要》教育部2022版
- 太上碧落洞天慈航灵感度世宝忏
- 国家标准硬度转换表参考模板
- 轮胎式装载机检测报告(共5页)
- 弯矩二次分配法excel表-(1)
- 半导体分立器件制造公司绩效制度范文
- 铁板神数详细取数法(共16页)
- 粉煤灰漂珠粉项目可行性研究报告写作范文
- 弧焊(3)电弧焊焊条
评论
0/150
提交评论