1、.method statement for pipe jacking1. construction of pitsthe jacking pit with a dimension of 6mx5 clear opening with depth of 250mm below invert level of the steel pipe.the floor will be leveled by 100mm thick concrete blinding fixing tow i beams(1.5mx15cm) in the center of the pit for fixing jackin
2、g frame.2. installation of jacking frameafter the construction of drive, the jacking rig will be lowered into the pit and adjust to the control line and level. the rig will be used on this contract consist of two number of hydraulic cylinders with a capacity of 150 ton each to give a total jacking f
3、orce of 300 tons. the rig will have guided rails, pushing plate and base plate to hydraulic power back with control unit. the hydraulic system will run through a diesel engine installed the top of the pit.the rig will installed to the correct line and level and check by the consultant in respect to
4、level and alignment.3. thrust wallconstructing a concrete block behind the base plate of the rig to a dimension of 2x1.5x0.5m will be provided to take and distribute the jacking load.4. pipe jacking operationa steel shield is used at the front of the pipe to accommodate the.miner and to allow for st
5、eering of the pipe jack. the soil within the shield is manually excavated and loaded into a wheel skip for transport to the pit bottom. the miner does not dig outside the shield (both in front and radically) and the front, or cutting edge, of the shield is always kept buried in the face, so stabilit
6、y is maintained. the shield is thus used to trim the excavation to the size of the pipe thus minimizing the potential for settlement of the ground above the pipe jack.in the pit bottom, the skip is hoisted to the surface, emptied and returned to the used to loosen it prior to digging. the exact diam
7、eter of shield will be selected to suit the pushing pipes.as excavation continues, the shield is jacking forward using two hydraulic jacks thrusting from the back wall. when the shield is buried, the jacks are retracted and the first sleeve pipe lowered on to the rails. this in then pushed up to the
8、 shield and excavation can then continue. when the sleeve pipe is pushed home, the hydraulic jacks are retracted and the services (lighting& ventilation) disconnected. the next sleeve pipe is lowered on to the rails and the services reconnected and the cycle repeated until the shield is pushed into
9、the receiving pit and the pipeline pushed into final position.5. maintaining line and levelin order to maintain the correct line and level, a graduated target plate.is located within the shield. the site engineer notes the position of the visible sport on the target, this initial position is used as
10、 reference value to locate the relative position of the shield at all times during the drive. at each push, the site engineer monitors the position reference value with the help of level instrument and theodalite, thus giving a shield position (high or low, right or left) relative to the design posi
11、tion. based on this information, the operator manipulates a correct course.extending or retracting a combination of steering rams causing the front of the shield to articulate in the required direction carries out the steering. as the pipe follows the shield, the correct line and level will be maint
12、ained. at all times, the amount steering applied is kept to minimum.6. fixing carrier pipesafter completion of the pipe jacking , we check the line and level for the steel pipe and we take the exact line and level for the carrier pipe with the help of survey instruments.a 3 steel anglebar fixed by w
13、elding in the correct bottom level of the carrier pipe, then 3mm thick flat bar half moon claps will fixed through wielding in the correct line after that we put neoprene rubber 3mm thick in the clamp to avoid the scratches of the carrier pipes.then we start laying the carrier pipe one by one and fi
14、x the clamps.through nuts and bolts. after fixing the nuts and bolts we make angle support in between the top of the clamp and top of the pipe. then we fix the other pipe in the same manner. the same procedure will continues up to the requirement.7. groutingupon completion of pipe jacking we make 4
15、2 holes like ventilationin every meter, it helps the concrete fill the gap between the steel pipeand ground. then we fixed six inch grouting pipe vertically one meterheight in the top of the pipe both end jacking and receiving. one sidewillkeep ventilation and the otherside forconnection andtheconcr
16、ete pump.afterthat we lay the carrier pipe inthe correct line and levelthencheck with the consultant and make the test required fromtheconsultant then we close the both end between steel and carrier pipe by m/s plate welding or masonry, the gap between steel sleeve and ground in the both end we clos
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2026中南大学非事业编制工作人员招聘13人笔试模拟试题及答案解析
- 2026广西南宁市青秀区凤岭北路中学教师招聘笔试备考试题及答案解析
- 2026年四川省攀枝花市高职单招职业适应性测试考试题库有答案详细解析
- 2026重庆荣昌区招聘社区工作者后备人选454人笔试备考题库及答案解析
- 2026粤海控股集团所属粤西供水、科达水电公司招聘4人笔试模拟试题及答案解析
- 2026中兴通讯实习生招聘考试备考题库及答案解析
- 2025-2026学年西藏西藏达孜县达标名校初三下学期寒假验收考试英语试题含解析
- 2026届广东省番禺区六校教育教联合体初三下学期第三次质量考评英语试题含解析
- 安阳市安阳一中学2026年初三下学期第五次模拟语文试题含解析
- 河南省郑州一中市级名校2025-2026学年初三三模(最后一卷)英语试题试卷含解析
- 《植物生产与环境》考试复习题及答案
- 2024-2030年中国AG玻璃市场供需形势与未来经营效益分析研究报告
- 克服囤积癖(认知行为自助手册)
- 入股协议合同完整版
- 基于县域大数据分析的学生心理自助微课程的开发研究课题申报评审书
- 2024年南昌市交通投资集团有限公司招聘笔试参考题库附带答案详解
- 2024杭州钱塘新区建设投资集团有限公司招聘笔试参考题库附带答案详解
- 新教科版四年级下册科学全册精编教案教学设计(新课标版)
- 2023年南京信息职业技术学院单招考试数学试题及答案解析
- 招聘专员培训课件
- 主题班会清明祭英烈
评论
0/150
提交评论