




已阅读5页,还剩4页未读, 继续免费阅读
版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领
文档简介
电缆敷设施工方案Construction Scheme for Cable Layout1编制说明及依据1.1编制说明为保证电缆线路安装工程的施工质量,使电缆敷设得以顺利进行,特编写此方案。此方案适用于10KV及以下塑料绝缘电力电缆、控制电缆线路的敷设施工。12、编制依据承包合同或协议。施工图及其它设计文件。电气装置安装工程电缆线路施工及验收规范GB5016992电气装置安装工程电气设备交接试验标准GB5016992建筑电气安装工程质量检验评定标准GB503032002。石、公司质量保证手册、质量体系程序及其支撑性文件。2、工程概况工程名称、范围、地点、规模、特点、主要技术要求、工期要求等。主要实物工作量以设计院的图纸及现场实际情况计算3、施工程序和施工方法Construction Procedure and Construction Method:3.l、施工程序Construction Procedure电缆出库工具准备电缆电气绝缘检查直沟电缆挖沟桥架配管不合格品标识隔离铺设施工用设备安装电缆铺设隐蔽工程检查隐蔽工程记录电缆铺设记录电缆沟回填桥架盖板安装电缆头制作绝缘检查受电交付使用Identifying and separating unsatisfactory productsTools for sending cable out of warehouseElectric insulation check for cableExcavating trench for direct burying and pipingCheck concealed worksCable layoutLayout equipment installationConcealed recordLayout recordBackfilling trench,Installing cover plateMaking cable ends,Check insulation Running and handover32、施工方法和质量要求Construction Method and Quality Requirements (1) 电缆出库Sending cable out of warehousea、电缆出库应根据施工图认真核对需出库电缆的规格、型号、数量是否符合设计要求,且应标示清楚。电缆盘外观完整无损,合格证等产品文件齐全。While sending cable out of warehouse, check its specification, type, quantity carefully to verify whether comply with design or not and identify clearly. Appearance of cable drum is perfect and no damage, certificate and other product files are full. 对由多根电缆缠绕在同一个盘上的电缆盘,应记录其内外层电缆的长度和缠绕次序,以利于合理安排敷设。For the same cable drum twisted by multi-cables, to facilitate to direct properly layout, the length of inner and outer layer cable and twisted order should be recorded.b、电缆出库运输过程中,采用机械吊装和运输,严禁将电缆盘直接由车上推下,同时电缆盘不应平放运输和贮存。 During the course of sending cable out of warehouse, follow mechanical hoisting and delivery. No pushing cable drum from truck directly. Meanwhile, cable drum shall not be placed, delivered or stored horizontally.短距离的运输可采用滚动电缆盘的方法。但必须顺着电缆盘上的箭头指示或缠紧方向滚动。 For short-distance transportation, rolling cable drum is available. However, rolling direction must be consistent with that of arrow indication on drum or cable winding. c、 电缆出库后应集中分类存放,尽可能存放在开始敷设电缆处的附近。盘间留有通道,存放处不得积水。 After sending cable out of warehouse, store them collectedly and classifiably. Place them as near of the place, where begin to layout cable, as possible. Keep access among cable drums, and no accumulated water at depositing site. (2) 电缆敷设前建筑工程应具备的条件:Prior to layout, civil works shall possess the following terms:a、电缆沟、隧道、竖井、人孔等处的地坪及抹面工作结束。Completion of grade and mortar for cable trench, tunnel, well, manhole.b、电缆夹层、电缆沟、桥架内的施工临时设施模板、建筑废料已清理干净。施工用道路畅通盖板齐全,电缆沟排水畅通,电缆夹层门窗安装完毕。Temporary boards and waste materials, used for cable interlayer, trench, and tray, have been completely removed. Cover-plates for access road are all ready, and trench drainage is free. Doors and windows on cable interlayer have been installed. (3)电缆敷设前电气专业应具备的条件:a、 电缆的起点及终点设备已安装完毕,位号标识准确清楚。Having mounted plants at place of cables starting point and end. And their Tag Numbers are identified corrected and clearly.b、 电缆敷设表编制完毕,表册中应标明每根电缆使用的电缆盘号,敷设的先后次序,Having compiled list of cable layout, in which Drum No. applied by each cable and layout order should be indicated.c、 敷设次序应是先远距离,后近距离。根据设计和电缆的实际情况,合理安排,避免浪费和接头。Layout order is from distant to close. According to design and cables real condition, assign reasonably and avoid waste and joint.d技术交底和安全技术交底已做完,并存记录卡。Having finished technical talk and safety technical talk, and preserved record card.e当电缆沿桥架敷设时,若没有人行通道应事先沿全长搭设脚手架,绑扎牢固。While layout cable along tray, if nonexistence of sidewalk, set up scaffolding and band tightly along the whole tray in advance.f 辅助材料供货到位,如电缆扎带、电缆标牌、电缆标志桩等。Accessory materials, such as cable tie, cable brand and column, are ready.电缆的电气绝缘已检查,试验项目包括下列内容:Electric insulation inspection for cable has performed. Including the following test items.测量绝缘电阻,即测量各电缆线芯对地或对金属屏蔽层和线芯间的绝缘电阻。Measuring insulation resistance.Insulation resistance of each core versus earth, versus metallic shield other core shall be measured.直流耐压试验及泄露电流测量(其试验要求见GB5015091)DC voltage-withstand test and leakage current measurement. Test requirement refer to GB50150-91)a、 敷设电缆使用的电线滑车(滚轮),牵引设备已安装到位,电缆滑车每3米1个,以电缆不拖地为原则。大规模敷设电缆时,事先应准备好广播器材,对讲机、半导体、喊话器等。 Pulley or roller and draught equipment used for cable layout have been installed. Set a pulley every 3 meters. The principal is that cable should not touch ground. When layout cable in force, prepare for broadcast appliances ahead such as talk about, radio, speaker.b、针对敷设电缆时的具体情况,技术人员和施工负责人应编制出劳动力分布图,指明每个关键部位的负责电工及所需人数,责任到人,在技术交底时予以公布。According to local specific condition, prior to layout, technician and construction header should compile labor distribution chart, point out responsible electrician and necessary number of employee at important place to ensure everyone see his own duty. Above items shall be declared when executing technical talk. (4)、桥架内电缆敷设Layout cable inside tray.a安装质量要求 Installation quality requirements: 电缆的最小弯曲半径应符合GB50168一92的规定,即:The minimum bending radius should conform to Norm of GB50168-92.多芯控制电缆 10D聚氯乙烯绝缘电力电缆 10D聚氯乙烯绝缘电力电线多芯 15D交联聚乙烯绝缘电力电线单芯 20D注D为电缆外径。Multi-core control cable 10DPVC insulated power cable 10DPVC insulated multi-core power cable 15DLinking PVC insulated one-core power cable 20DNote: D is outer diameter.电缆的固定要求:桥架上垂直敷设每隔2m处,水平敷设的电缆首末两端及转弯、电缆接头两端处应加以固定, Requirements for fastening cable:Fix cable every 2 meters when laying cable vertically. For horizontal layout cable, fixing it at the beginning and end, two sides of corner and joint.交流系统的单芯电缆应使固定夹具不构成闭合磁络,且按正三角形排列,每隔1m用绑带扎牢。For AC one-core cable, fixing it with special clamp not to form closed magnetic loop and arraying it in form of pure triangle. Banding tightly every 1 meter.桥架上交流三芯电力电线不宜超过2层控制电缆不宜超过三层。AC multi-core power cable should be not beyond 2 layers, and control cable no more than 3 layers.电缆的排列:高低压电力电缆、强电弱电控制电缆应按顺序分层配置,高压与低压增加隔板。Arraying order of cable: Place high and lower voltage power cable, intensive and faint control cable in layer and in sequence. Add partition between high and lower voltage power cable.b、敷设方法 Layout method: 电缆应从电缆盘上部引出,同时检查是否有套扣现象,将写好的电缆编号交专人负责贴在电缆首末端。Pulling cable from the upper direction of drum. Meanwhile, checking whether existence of cable-wring or not. Make special employee to stick prepared cable number on both ends of cable. 桥架上所有电缆全部敷设完毕,即时安装盖板,达到防护的目的。After completion of all cable layout inside tray, installing covers timely to protect.(5)、地埋电缆的敷设方法及质量要求Layout method and quality requirements for buried cable under ground:a、质量要求:Quality Requirements:电缆上表面距地坪面不小于07m。0.7m is the least distance from the upper side of cable to grade.电缆上边及下边应复以100mm的软土或沙层,并盖上红砖或混凝土板。Fill 100mm thickness soft earth or fine sand around cable up and down, and cover red brick or concrete plate. 电缆之间、电缆与其它管道、道路、建筑物等之间平行和交叉时的最小净距应符合GB5016892的表543的要求。When existing parallel or crossing between cable and cable, cable and other pipes, roads, or architectures, the minimum distance should conform to Table of 5.4.3 in GB50168-92.严禁将电缆平行敷设于管道的上方或下方。No laying cable over and under pipes in parallel过路保护管伸出道路路基两边各2m伸出排水沟0.5m。While protection pipe spreading road base, 2m should be left each side of base and 0.5m is required while spreading drainage直埋电缆在直线段每隔50100m处或电缆接头处、转弯处、进人建筑物处应设置明显的标桩。. Setting identical columns for direct buried cable at the straight line each 50-100m, at joint or swerving place and at entrance to architecture. 电缆的弯曲电缆应符合要求。Cable bending should conform to requirementb、敷设方法 Layout method:估工估料:大型的电缆敷设应做这项工作,在详细研究工程设计书后,到现场勘察线路地形并了解情况,然后制订出技术措施和安全措施,并核对设计用料是否正确,根据工程情况决定敷设方式,是采用人工敷设,还是采用机械化敷设。Estimate works quantity and necessary materials: It is required to lay large-sized cables. After studying design documents for engineering detailed, go to local field to explore lines landform and learn real environment. And then, write out technical and safety measures and check whether design materials are correct or not. According to engineering condition, decide layout method: by manpower layout or machine layout材料、工具准备:敷设电缆所需的机具设备,如卷扬机、钢丝网套、千斤顶、滑轮以及铁锹等都应需要事先备好。电缆及保护盖板等材料,最好按施工计划日期直接发运到施工现场,以节约人工费用。Prepare for materials and tools: Machines and tools needed for laying cable should be all ready in advance, such as hoist, steel-wire net, jack, rolling wheel and shovel. To economize lab our cost, we had better to deliver directly cable and cover plate to site in reference to construction plan date.对外联系工作:敷设电缆线路影响到农田、园林、公共道路、市区交通等情况应事先与农村政府、园林部门、铁路局、交通队等联系,办妥有关手续后方可施工。决定电缆中间接头的位置。当电缆线络较长有中间接头的情况下,要事先选择合适的接头位置,因中间接头故障率较电缆本体为多,因此要考虑检修问题,故不要将位置选择在道路交叉口,或与其它地下管线交叉的地方。在设计的电缆线络上开挖试探样洞,其主要目的是调查土壤及地下管线布置情况,深度1m。In order to study soil and distribution of underground pipelines, excavate exploring sample holes, 1m in depth, along the designed cable line.放样:根据设计图和土层调查情况,用石灰粉画出挖土范围Performing sample:On the basis of design drawings and soil terms, drawing out excavation region with lime powder敷设过路保护管,可采用不开挖路面的顶管方法,如果有困难应按路宽分半施工,必要时夜间施工。. When laying protective pipe through road, pushing pipe with jack is available instead of excavating ground. If it is difficult to construct, doing it on base of half of road width. If necessary, constructing at night.挖土:施工地点周围应设置警告标志,挖出的泥土应放置在沟边03m以外,电缆沟的挖掘还必须保证电缆敷设后的弯曲半径不小于规定值,宽度、深度按设计要求开挖。Excavating:Placing warning symbols around construction location. Excavated soil should be piled and more than 0.3m is required away trenchs edge. In addition, excavation must ensure bending radius of cable is no less than regulated value. Width and depth for excavation should conform to design.敷设电缆准备工作。敷设前应整理土沟,将沟内石子或其他杂物清除,然后在沟中放置滑轮,每3m一个,转角处加放转角滑轮,保护电缆的盖板沿开挖的电缆沟分放好。同时将电缆推滚到所需位置架设好。Preparation for direct buried cable layout:Before layout, clean inner stones or other waste things up and mend trench, then place pulley into trench every 3m, and add corner pulley at the corner. Set cover plate along excavated cable trench, roll cable drum to proper location and put it onto rack.当敷设大截面和较长电缆时可采用卷扬机等机械化方法(长沙及武汉电缆附件厂有成套设备)敷设。敷设时拖拽电缆可用特制的钢丝网套套在电缆端头上。机械化敷设电缆有以下要求:While laying large cross sectional area and longer cable, following mechanization method such as hoist is available (Changsha and Wuhan cable accessory factory possess sets of equipments). Dragging cable with special making steel wire net tied at the beginning of cable. Note the following requirements when adopting mechanization method:电缆最大牵引强度(N/mm2)牵引方法牵引头钢丝网套受力部位铜芯铝芯铅套铅套塑料护套允许牵引强度704010407 Max. Draught Stress of Cable (N/mm2)Draught MethodDraught EndSteel Wire Net and SheathPressurized sectionCopper coreAluminumcoreLead SheathLeadSheathPlastic SheathAllowable stress degree704010407另外,速度不宜超过15m/min,应在牵引头或钢丝网套与牵引钢缆之间装设防捻器。 Whats more, layout speed should not surpass 15 m/min., splice-proof shall be set between draught head or steel wire net and draught cable.施放电缆时无论在任何情况下,都不能让电缆在地上拖拉,电缆到位后,可逐段将电缆提起,移去滑轮,并将电缆放在沟底,在电缆需做中间头的地方,要留有余度,在敷设过程要统一指挥,互通信息。When laying cable, no dragging cable along ground in no case. After cable reach its position, lift it step by step, remove pulley, and then put it at the bottom of trench. Leave spare length at the place of middle joint.电缆敷设完毕,请甲方及监理验收隐蔽工程,技术人员做好敷设记录。然后回填,应分层夯实,安装电缆标桩。In one word, during
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 入职安全生产知识培训课件
- 2025年煤炭清洁利用产业政策与市场策略研究报告
- 健康教育专项知识培训会课件
- 高中复读费管理办法
- 江西省高级导游等级考试(导游综合知识)在线自测试题库及答案(2025年)
- 个案工作的基本技巧详解
- 记者站管理办法央视
- 综合办文件管理办法
- 超市资源位管理办法
- 企业燃气安全培训模板课件
- 陕西省农村宅基地管理办法
- 门诊手术分级管理办法
- 中国武术课件
- 2025-2030中国便携式篮球架行业市场发展趋势与前景展望战略研究报告
- 核心素养背景下项目式学习在初中美术教学中的设计与应用
- 北京版英语1-6年级单词表
- 陕旅版小学六年级上册全册英语教案
- 中国美容仪器市场调研及发展策略研究报告2025-2028版
- 海洋工程装备概述
- 烈士陵园改扩建项目可行性研究报告(完整版)
- 《劳动争议处理实务教程》课件(1)章节
评论
0/150
提交评论