V. Construction Site Coordination Management1. Construction General Layout Plan CoordinationBased on construction deployment and milestone delivery requirements in various phases, General Contractor is in charge of formulating overall plan for general layout plan and deliver technical disclosure to subcontractors for carrying out dynamic management.General contractor is responsible for dispatching road, temporary storage yard, fixed storage yard within construction site unitedly.The subcontractor shall submit “temporary access road or storage yard application sheet to General contractor as per production requirements at each stage for approval by procedures.The subcontractor shall submit “Use of existing fixed storage yard application sheet” (Sheet 7-2) to General Contractor Production Coordination Department as per production requirements at each stage for approval.The subcontractors are responsible for standardized management and maintenance of public facilities, surrounding roads within fixed storage yard or temporary site they used, as well as to cater for General Contractors standardized management requirements.2. Temporary Water and Power Supply CoordinationGeneral Contractor is in charge of overall planning and implementation for temporary water and power supply deployment and deliver technical disclosure to subcontractors.The subcontractors are in charge of configuring full-time temporary water and power supply managerial personnel, who should submit to General Contractor “Subcontracting use power general schedule” within stipulated period, as well as to sign “ Temporary water and power use management agreement” with General Contractor within one week.The subcontractor shall submit “Use of temporary power supply application” to General Contractor Production Coordination Department as per production requirements at each stage for approval.The subcontractors are in charge of safety management of temporary water and power use and accept daily inspection from General Contractor, as well as rectify the discovered problems during inspection and make reply immediately.3. Temporary Facilities CoordinationGeneral Contractor is in charge of overall planning and implementation for temporary facilities, formulating usage allocation scheme and deliver technical disclosure to subcontractors.The subcontractor shall submit “Use of temporary facilities (office, living) application sheet” to General Contractor Production Coordination Department as per production requirements at each stage for approval.The subcontractors are in charge of maintain and manage temporary facilities use and accept daily inspection from General Contractor, as well as rectify the discovered problems during inspection and make reply immediately.The subcontractors are in charge of applying overall acceptance and handover to General Contractor after temporary facilities usage completed.4. Material and Equipment Mobilization and Demobilization Coordination The subcontractors shall submit detailed material, equipment mobilization application schedule in accordance with General Contractors construction progress to confirm material, equipment name, specification, model and mobilization time.The subcontractors are in charge of material mobilization and demobilization, who shall prepare documents which include, but not limited to, material type, transportation mode, quality assurance, etc. as well as submit “Material/equipment mobilization and demobilization application sheet” to General Contractor Production Coordination Department for approval.The subcontractors are in charge of abide by General Contractors site material and equipment management system, pile up mobilized material and equipment in good order, accept daily inspection from General Contractor, as well as rectify the discovered problems during inspection and make reply immediately.5. Vertical Transportation CoordinationGeneral Contractor is in charge of overall planning and implementation for vertical transportation equipment, formulating project vertical transportation scheme and deliver technical disclosure to subcontractors.The subcontractors shall submit “ Subcontract vertical transportation equipment use schedule sheet” to General Contractor for approval.The subcontractor shall submit “Use of vertical transportation application sheet” to General Contractor Production Coordination Department every day as per daily construction demand for approval.General Contractor is in charge of planning all subcontractors vertical transportation equipment use situation as a whole and formulating and public “Daily use distribution sheet of vertical transportation equipment” , as well as coordinate and resolve emergent problems among subcontractors for using vertical transportation equipment.The subcontractors are in charge of configure full-time staff to manage vertical transportation within subcontractors and cooperate General Contractor to coordinate and resolve emergent problems among subcontractors for using vertical transportation equipment.General Contractor is in charge of arranging vertical transportation equipments keep and maintenance, attachment, jacking time reasonably and give to publicity timely.6. Public Operation Platform CoordinationGeneral Contractor is in charge of formulating overall plan for public operation platform and deliver technical disclosure to subcontractors in accordance with contract organization or entrust subcontractors to erect, dismantle and maintain public operation platform.The subcontractor shall submit “Dismantle of public operation platform application sheet” to General Contractor Production Coordination Department for approval due to the need of altering, dismantling platform, dismantle shall be conducted only after obtained the approval, which could be used only after inspection and acceptance of dismantling and alteration.General Contractor is in charge of supervising public operation platforms use condition, handling misuse timely.7. Public Security Protection CoordinationGeneral Contractor is in charge of unifying public security standard in accordance with contract organization or entrust subcontractors to fit with public security protection facilities, as well as deliver technical disclosure to subcontractors.General Contractor is in charge of public security protection and supervision within public area, the subcontractors are responsible for security protection and supervision within working face.The subcontractor shall submit “Dismantle of public security protection application sheet” to General Contractor Production Coordination Department for approval due to the need of altering, dismantling safety protection, dismantle shall be conducted only after obtained the approval, which could be used only after inspection and acceptance of dismantling and alteration.General Contractor is in charge of managing security protection in construction site as a whole, as well as execute supervision and acceptance works for safety protection dismantling and alteration.8. Site Elevation Axis CoordinationGeneral Contractor is responsible for preparing overall survey control scheme, establishing Level 1 plane and vertical control network, main axis, elevation control networks within site area, as well as make identification and carry out daily maintenance, meanwhile deliver control point and control axis disclosure to subcontractors, finish handover works.The subcontractors are in charge of configuring qualified surveyors, surveying instrument, calibrate survey instrument periodically and submit to General Contractor for register.The subcontractors are in charge of measuring pass, setting out, measurement testing, deformation monitoring, etc.9. Site Construction Interfaces CoordinationGeneral Contractor is in charge of organize subcontractors to identify all interfaces, form “Interface matrix table”, “Interface division schematic diagram”.The subcontractors are in charge of familiarizing with construction contract, in case of requiring other subcontractors cooperation matters, draft a list and submit General Contractor for register.General Contractor is in charge of formulating subcontractors working face transfer plan as per progress programme, as well as organize related parties to transfer working faces as scheduled.As receiver of working faces, the subcontractors are in charge of preparing critical areas transfer list, under General Contractors management, make three tier transfer check and form check record.As receiver of working faces, the subcontractors are in charge of completing the remained works and rectifying the defected works to achieve transfer requirements as scheduled pursuant to “Key areas working face transfer list” requirements provided by the receiver.VI. Public Resources Management1. Management Key Points at Each StageManagement ProcessManagement Key PointsPlane management(1) Layout planning and deployment(2) Site and road approval(3) Daily management of traffic organization and civilized construction Temporary water, power supply management(1) Planning and total quantity control for temporary water and power supply(2) Management agreement signing for temporary water and power supply(3) Temporary water and power supply approval(4) Management responsibility division and daily maintenanceTemporary facilities management(1) Implementation of temporary facilities planning and deployment pursuant to contract type(2) Approval and acceptance of temporarily used land and facilities(3) Daily supervision of temporary facilities(4) Transfer and counter transfer of temporary facilitiesVertical transportation equipment management(1) Planning and daily maintenance of vertical transportation equipment(2) Supervision of subcontractors vertical transportation equipment usage plan(3) Daily approval and display to public for vertical transportation equipment(4) Daily supervision and statistical analysis for vertical transportation equipment usePublic operation platform management(1) Public operation platform planning and deployment(2) Daily supervision and coordination for public operation platform use(3) Approval of public operation platform dismantle and alter Public security protection management(1) Prepare unified standard and deployment for public security protection(2) Public security protection dismantle and alter approval and acceptance(3) Public security protection transfer, acceptance and counter transfer(4) Daily maintenance and supervision for public security protectionSurvey management(1) Preparation and implementation of general survey control scheme(2) Transfer and daily maintenance of controlling point and axis.(3) Supervision and management for subcontractors survey execution, survey result, personnel and equipment. 2. Plane ManagementBased on construction deployment and milestone delivery requirements in various phases, to organize general layout plans overall planning, deployment and deliver disclosure to subcontractors for carrying out dynamic management to ensure its effectiveness.3. Temporary water, power supply managementTo be responsible for overall planning construction site temporary water, power supply arrangement, implement or entrust implementation according to contract requirements and deliver disclosure to subcontractors.4. Temporary facilities managementMake Overall planning for temporary facilities and implement according to contract requirements, establish use schedule and deliver disclosure to subcontractors, who are in charge of use normally and maintain periodically.5. Vertical transportation equipment managementDesign and Technical Department are responsible for make overall planning and deployment of vertical transportation equipment, construction and coordination team are in charge of delivering disclosure to subcontractors, as well as install, dismantle, maintain vertical transportation equipment as per contract organization or entrust implementation.6. Public operation platform managementDesign and Technical Department are responsible for make overall planning and deployment of public operation platform, construction and coordination team are in charge of delivering disclosure to subcontractors, as well as install, dismantle, maintain public operation platform as per contract organization or entrust implementation.7. Public security protection managementTo unify public security protection standard, organize or entrust implementation of public security protection facilities and delivering disclosure to subcontractors, the subcontractors are in charge of erecting or maintain self-working faces safety protection.8. Survey ManagementTo transfer plane height measurement control point to the employer and do re-measurement for control point, to prepare general survey control scheme and establish level 1 plane and height control networks within site, the subcontractors shall complete their own surveying works and be responsible for surveying results.To set up main axis, elevation control networks within site, as well as make identification and daily maintenance, deliver disclosure to subcontractors in respect of control points and control axis within site and complete handover works. To inspect and check subcontractors surveyors, surveying instrument and survey scheme.To urge subcontractors to establish survey instrument management list (Table9-2);to supervise subcontractors to calibrate survey instrument periodically and submit to General Contractor for register.To review subcontractors surveying result and organize subcontractors to resolve surveying tolerance timely to form surveying result as a whole.To supervise subcontractors to complete survey pass, setting out, measurement detection, deformation monitoring, etc., supervise subcontractors to make identification and maintenance of their surveying axis, elevation control points.VII.Interface Management1. Construction Procedure Interface ManagementTo organize subcontractors to prepare “Key parts construction procedures list” as per “Interface matrix table”, “Interface division schematic diagram” submitted by detailed design team.To be responsible for prepare implementation schedule for key parts construction procedure process and urge subcontractors to organize construction as scheduled.To organize subcontractors to hand over working procedure, as for defected works discovered in handing over process, record timely and supervise involved party to rectify as scheduled.After related parties rectification completed, record in writing and signature on “Key parts construction procedure flow chart”.2. Construction Working Face ManagementTo prepare subcontractors working face transfer schedule according to progress plan, to arrange working face transfer as a whole and minimize professional subcontractors in sole working face, as well as minimize site conflict and contradiction.Building Department is responsible for coordinating professional subcontractors within sole working face.To organize subcontractors to prepare key parts working face transfer list for providing basis for three tier joint inspection.To organize all related subcontractors and supervisors to inspect jointly for site works to ensure all interfaces works could transfer as scheduled.To urge transfer subcontractor implement rectification plan as per “Working face three-level transfer checking list”, to handle formal transfer formalities.VIII. Coordination and Cooperation Measures for the Employer and Designer1. Coordination and Cooperation Measures with the EmployerServiceContentsStrengthening communication and mutual understanding with the employer To consult the employer for related suggestions on project construction subject to the employers construction intention, for questions proposed by the employer, which shall be replied and handled in a timely manner, to improve our work uninterruptedly.Be a good assistant and adviser for the employerTo develop our companys technology advantage into full play subject to the employers construction intention, take into consideration of problems from the perspective of projects usage function, design reasonability, construction reliability and to give reasonable suggestions. In accordance with contract requirements, organize construction scientifically and reasonably, coordination and management of project uniformly, as well as to solve various troubles appeared in performance of the works to let the employer trust. To develop project regular meeting system and strengthen communication to solve quality, progress rate problems, as well as to set up site management team to strengthen correlation with local authorities and solve possible disturbance of local residents problems timely. As for sectional acceptance, in case of obtaining support from Project Management Bureau, which is beneficial for future work construction.Service for final userTo carry out concept of “with final user as guidance, life cycle management” as required by the employer. In the light of coordination plan, to coordinate with final user representative and listen to opinions and suggestions what they have for performing goal directed in-depth design prior to detailed design involved with final users usage function.Collection service for process informationIn the course of information transfer, key information tend to be lost, which will result in various troubles appeared for final users usage. Adoption of information management technology in cooperation with the employer can effectively transfer important information, as well as provide service for whole life cycle of buildings.2. Coordination Management Measures with DesignerWe hereby commit that: to completely ensure

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

最新文档

评论

0/150

提交评论