版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领
文档简介
1、外文翻译原文:measurement of transmission line parameters from scada data g. l. kusic and d. l. garrison abstract-transmission line equivalent circuit parameters are often 25% to 30% in error compared to values measured by the scada system. these errors cause the economic dispatch to be wrong, and lead to
2、increased costs or incorrect billing. the parameter errors also affect contingency analysis, short circuit analysis, distance relaying, machine stability calculations, transmission planning, and state estimator analysis. an economic example is used to demonstrate the affect of transmission line erro
3、rs. scada measurements from several utilities are used to compute the real world value of the transmission line parameters. state estimation with the estimated parameters is compared to the computations using the theoretical values. index termsscada measurements, state estimation, transmission line
4、parameter estimation i. introduction utilities in most instances use theoretical values for line parameters calculated from ideal line geometry such as height of conductor above flat, constant resistance earth. earth resistivity is variable with terrain. conductor sag effects are impossible to estim
5、ate over hilly terrain. usually shield wires are grounded at each tower instead of floating over the entire line length. line resistance varies with current, the ambient temperature and wind effects. an outage is required to measure the line charging equivalent capacitance, only if one-sided excitat
6、ion does not cause too much voltage rise on the open-circuit end. construction of new parallel lines with mutual coupling, affects old database values. the series reactance of a transmission line is rarely measured, so the value used is for an ideally transposed line. lines are not transposed becaus
7、e of the added construction cost to mechanically alter positions of the conductors with respect to the support poles every 1/3 the distance. with all of these variations from ideal conditions, and few real measurements, utilities often have as much as 25% to 30% error in their database parameters co
8、mpared to the real world values. utilities use mw and mvar metering for revenue. transmission line losses are usually less than 3% of the total generation. however, line parameters from a theoretical database are used to calculate loss coefficients, or determine the incremental loss factors, in orde
9、r to set the dispatch point for generators (output power). if accurate values of line parameters re-allocate the generator powers, and reduce transmission losses by 0.1%, this translates into immense energy savings over years of operating the power system. for example, at 0.1% savings, a large utili
10、ty transmitting 10000 gwh annually, 0.6 load factor, fuel at $20/mbtu and 10.5 mil rate, may save $11 million per year for bulk power in the eastern u.s. monitoring the state of the power system is a major security function of the computer system used at the central control center (dispatch center)
11、of utilities. voltages and power flow on lines and buses in the control area of the power system are monitored on the order of every 2 seconds. if the measured data are beyond safe operating tolerance limits, the alarms generated must be cleared by the dispatcher through switching line compensators
12、such as capacitor banks and shunt reactors, adjusting variable tap transformers, or transferring generator output, etc. so that dispatcher action can be based on reliable and complete information, measurements of voltages and power flow are processed by a state estimator which detects faulty measure
13、ment transducers (bad data) and fills in lost measurements when remote terminal units (rtus) have interrupted signals. state estimator calculations are based upon theoretical values for transmission line parameters. errors in the analytical values for transmission line parameters limit the state est
14、imators capability to detect bad data, and make it ineffective as a monitoring tool. with transmission line errors, the normalized residuals are larger than they should be. at least one utility adjusts its line parameter database to match the real world transmission lines in order to improve the sta
15、te calculated. ii. an economic example consider the 5 bus transmission network shown in figure 1, where the cost of generation is bid as shown for 4 busses. the total load is 669 mw and located at busses b,c, and d. the transmission line flows as calculated for loss-less lines 1 is shown in figure 1
16、. the flow on transmission line xed = .0297 is limited to 240 mw. the other transmission line reactances are xab = .0281, xbc = .0108, xcd = .0297 xad = .0303, xae = .0064 and are loss-less. the open arrows in figure 1 indicate injected power, and the black fill arrows indicate load at the bus in fi
17、gure 1, of all the locational marginal price (lmp) bids for generation, the 600 mw $10/mwh at bus e is completely utilized before the 69 mw at bus a is employed. the transmission line flows that result from this dispatch are shown on the figure. the total operating cost is $6966/h. fig. 1 economic d
18、ispatch for 669 mw load to utilize the lowest cost of available generation as the load on the system uniformly increases to 300 mw at busses b,c, and d, the lmp dispatch would attempt to use all the 210 mw of inexpensive power ( 110mw$14/mwh and 100 mw$15/mwh) at bus a before 90 mw of the $30/mwh po
19、wer at bus d is used. the total cost would be $11,740/h. however, when 210 mw is dispatched at bus a, this results in 243 mw of flow on line e-d to violate the constraint. as a result, only 166 mw of the inexpensive power at bus a is utilized and 124 mw at bus d is required. total operation cost inc
20、reases to $12,100/h because of the constraint. the dispatch is shown in figure 1a. if the transmission line e-d has a real world reactance of xed = 1.25*.0297, or in other words has a measured 25% more reactance than the database, the dispatch for 900 mw load utilizes all the low cost power because
21、the power flow does not violate the e-d line constraint. the transmission line power flows for this case are shown on figure 2. the total cost of the dispatch is $11,740/h. the example shown in figure 1 was employed by an eastern usa power pool to demonstrate constraints in line flow. figure 2 shows
22、 that power flows computed with correct line parameters are significantly different, to the point where large economic differences are present. corrections are rarely made to transmission line parameters in order to match measured line flows because sources of measurement error are unknown. in a uti
23、lity it also difficult to change parameters in the database because so many different groups within the utility, e.g., planning, relaying, security, etc., must change their values or settings of field equipment. iii. estimation of transmission line parameters for short to medium length, compared to
24、a 60 hz wavelength, 3-phase transmission lines are modeled by pi-equivalents calculated from ideal geometry and operated under balanced phase conditions. the voltage magnitudes at the line terminations are an average of the phase measurements, usually obtained with 1% to 2% accuracy step-down transf
25、ormer measurements. fig. 1a economic dispatch for 900 mw load limited by constraint on line e-d the real and reactive power flow for the pi-equivalent is a sum of flows on the 3 phases and obtained as an instantaneous product of 1% to 2% accurate current measurements with the voltage measurements. n
26、eglecting the small contributions of a/d converters at the transducers and computer numerical word length, the overall accuracy of power flow measurements also is on the order of 1% to 2%. figure 2 economic dispatch for 900 mw load with xed =1.25*.0297 transmission line reactance (no line constraint
27、s violated) the eastern power pool used for figure 1and 1a provided a scada snapshot of power flow and voltage measurements for the 3-bus network shown in figure 3. data of the snapshot is presented in figure 4. notice more real power comes out of line l1 than goes into it (s1 and s2), but this anom
28、aly is due to measurement tolerance as the real power difference is 2% of the absolute value. snapshot is state estimator terminology for an almost synchronized set of measurements because a short time interval (milliseconds) exists from the initial measurement to the final measurement for a slowly
29、changing load/generation. fig. 3 scada measurement points on a 3 bus network fig. 4 scada measurements for figure 3 a state estimation computation smoothes the data, detects bad transducers, and calculates the best estimate of the voltage and phase angle at busses of the network, i.e., the state of
30、the network. the calculated state is a weighted least squares estimate best fit to the measurements using database values for the pi-equivalent transmission line parameters, r+jx for the series p.u. impedance elements jy/2 for the shunt p.u. susceptance at both ends of the line. analytical methods e
31、xist to estimate transmission line parameters from snapshots in conjunction with the state estimator. the first such method appeared soon after the start of state estimation 2. many contributions were made around 1990 of which 3, 4 are typical, new techniques continue to evolve 5. a recent summary i
32、s reference 6. the data snapshot of figure 4 was used to estimate the transmission line parameters of figure 3 by a method of propagating residual errors of state estimation related to 5 and finding the worst fit line. the results of the parameter estimation with this method are presented in figure
33、5. only 2 transmission lines of the figure 3 network could be estimated before residual errors swamped out further detection. lines bc and ab show 25% errors in line charging susceptance compared to the database. there is a 50% error in the estimated line resistance of line bc compared to the databa
34、se value, which may be due to an operating temperature difference. fig. 5 results of transmission line parameter estimation for network of figure 3 with scada data of figure 4 the estimated values for line charging susceptance of transmission lines bc and ab affect reactive compensation in their vic
35、inity. the 50% difference in resistance of line bc may affect the transmission loss coefficients in the vicinity. power flow calculations with s1 to s6 data of figure 4 show that power flow on the network lines is much closer to measured values using the estimated parameters than with the database v
36、alues. iv. verification of the parameter estimation method it is difficult to prove that estimated transmission line parameters are true to the real world values. analytical cases using power flow computations from standard ieee 5 bus, 14 bus cases, etc., then corrupting the line parameters and flow
37、s by random noise, have been used in order to obtain test the algorithm. however, this analytical process does not match real world data. a real world case to verify the parameter estimation algorithm is as follows. parameters for transformers are perhaps the best known of large power handling eleme
38、nts because of measurements performed by the manufacturer. the 3 parallel transformers and a 4th series transformer shown in figure 6a, had the scada snapshot measurements shown in figure 6b. fig. 6a parallel and series transformers fig. 6b scada measured flows for the parallel and series transforme
39、rs the parameter estimation program applied to the data of figure 6b resulted in the values shown in figure 7. there is exact agreement of estimated and database reactance for transformer ta bk 63, and some difference in resistance. the estimated parameters for ta bk 62 match the database values for
40、 ta bk 60, and the estimated values for ta bk 60 match the database values for ta bk 62. these two analysis discrepancies were resolved when the utility discovered ta bk 62 and ta bk 60 had their field instrumentation wires switched at the remote-terminal unit (rtu). a more extensive verification of
41、 the parameter estimation method was obtained in very closely controlled laboratory test bed experiments conducted at nasa glenn research center 7. these tests, performed on both radial and loop networks, considered a transmission line fault to be any change in the transmission line test bed value c
42、ompared to the pre-test or calibrated database value. in the laboratory tests, discrete physical resistors were added as series or line-to-ground components in the test bed, and the parameter estimation program was required to detect the altered line from a data snapshot. the tests found the deliber
43、ate error introduced in a transmission line 100% of the time over wide ranges of network operating conditions. the tests demonstrated the limit of the transmission line parameter estimation program is the capability to estimate lines with residuals above the threshold of noise due to measurement and
44、 other transmission line errors in the network.for the power system case shown in figures 3, 4, and 5, only 2 of 3 transmission lines could be estimated. for the transformer case in figures 6a, 6b, and figure 7, only 3 of 4 transformers could be parameter estimated before the algorithm became limite
45、d by noise. fig. 7 database and parameter estimations for a transformer group ( ta bk 62 and ta bk 60 switched in the field) v. a large network test case the 19 bus, 42 line, 2 transformer network shown in figure 8 had a scada snapshot of only transmission line flows and voltages with which to perfo
46、rm the parameter estimation. in the figure, the bus numbers are in circles. often 2 or 4 transmission lines are in parallel from bus-to-bus. the scada data snapshot for figure 8 consisted of 170 measurements of line flows plus voltages. a portion of the scada data is presented in figure 9. the 170 s
47、cada measurements were used to compute the state estimate from the state estimator residuals, the worst fit of estimated parameters to database values was for the transmission line between bus #8 and #16, followed by the parallel lines between bus #6 and bus #8, etc., in the order presented in figur
48、e 9. values of estimated transmission line parameters are presented in figure 10 for lines that could be estimated before noise limited figure 8 test network of 19 busses fig. 9 scada data for part of figure 8(p.u., 100 mva base) fig. 10 estimated line parameters for 9 lines from the 19 bus network
49、(figure 8) a comparison of figure 10 estimated parameters against the figure 9 database values shows 50% to 400% differences in line charging. estimated resistance compared to database resistance varies from close agreement to 300% difference. the lines between bus #15 and bus #6 show 300% differenc
50、e in reactances estimated compared to database. these are significant differences. by matching line termination p,q,v in a one line, two bus power flow, the calculation shows estimated lines are a closer fit to scada flows. a state estimator computation for the 19 bus topology of figure 8 with datab
51、ase line parameters had 50 points of normalized residuals .00005 but =.0003, and no points higher. the same snapshot with estimated transmission line parameters had only 28 points in this same range. this is a much closer fit of calculations to measurements. vi. concluding remarks the parameter esti
52、mation method was verified by several field tests, simple computations, and in laboratory experiments. physical checks, such as scada measurements on open-end excitation of transmission lines, should be used by utilities to measure line capacitance when a line is restored to service. scada-based est
53、imates are more accurate than theoretical database parameters. the property of parameter estimation, as eventually limited by noise in measurements and other transmission line errors, forces the algorithm to be applied to only 15 to 30 bus portions of larger networks. analysis is performed until the
54、 algorithm becomes limited, then the test area is moved to a new portion of the larger network. vii. references 1 wood, a.j., and wollenberg, b.f. “power generation, operation, and control”, text, j. wiley, 1996, isbn 0-47158699-4 2 debs, a., “parameter estimation for power systems in the steady-sta
55、te”, ieee trans. power, vol.19, #6, dec. 1974 3 wu, f.f., “detection of topology errors by state estimation”, ieee pes winter meeting, 1988 4 liu, w-h.,e., wu, f.f., and lun, s-m, “ observability analysis and bad data processing for state estimation with equality constraints”, ieee trans. pow. sys.,
56、 vol.pwrs-3, may 1988 5 liu, w-h.,e., wu, f.f., and lun, s-m., “estimation of parameter errors from measurement residuals in state estimation”, trans. pow. sys., vol. 7, no. 1, feb 1992 6 zarco, p. and exposito, a.g., “power system parameter estimation : a survey”, ieee trans. pow. sys., vol 15, no.
57、1, feb,2000 7 kusic, g.l., “experimental tests on power system monitoring and fault detection”, report to nasa glenn research center from power systems consultants, inc, dec 24, 2002 dr. george kusic, m 1953, received his bsee (1957), msee (1964), and ph.dee (1968) from carnegie-mellon university. s
58、ince he received his doctorate, he has been a faculty member of the department of electrical engineering at the university of pittsburgh. his areas of interest are the power field and electronics. dr. kusic has numerous ieee publications in the power field and is the author of a textbook, “computer-aided power system analysis”, by prentiss-hall. in 1981 dr. kusic founded power systems consultants to provide electrical engineering consulting to various firms, utilities, and governmental agencies. among the firms clients are westinghouse electric, ibm, c
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2026年企业员工招聘渠道监控策略方案
- 2026年园艺技术(植物养护)试题及答案
- 2026年初中历史真题试卷预测试卷
- 导数英语试题及答案
- 医院违规收费自查自纠报告
- 防雷检测合同(范本)
- 六年级下册数学北师大含答案 常见的量
- 自考管理学原理试卷及答案详情
- 浙江温州市瑞安市2025-2026学年人教版六年级下学期期末考试数学试题(含答案)
- 关于丰田喷漆的试题及对应答案
- DBJ51T188-2022预拌流态固化土工程应用技术标准
- 十年(2016-2025)高考英语真题分类汇编:专题22 语法填空(全国)(解析版)
- 2025至2030中国智能无人船行业市场发展分析及竞争态势与产业运行态势及投资规划深度研究报告
- 2025年淮南市潘集区公开招聘社区“两委”后备干部10名备考考试题库附答案解析
- 太空探索与航天科技:初中物理科普教学教案
- 豁免源管理办法
- 《建筑施工技术》课件
- 《淀粉样变心肌病》课件
- 急诊常见中毒的急救与护理
- 医院培训课件:《静脉留置针的应用及维护》
- 烷烃的说课稿
评论
0/150
提交评论