1、project lanco amarkantak thermal power station 2300 mw unit # 1 pathadi village, korba - 495667. chhattisgarh - india owner lanco amarkantak power private limited hyderabad - india principal contractor zelan projects private limited document no. : rev : 0 document title : india amarkantak power plan

2、t project construction engineering daterevisionprepared by reviewed by released by india amarkantak power plant project construction engineering rev:0 1 contents 1. basis of preparation and explanation.3 1.1basis of preparation .3 1.2 explanation of the preparation.4 2. description of the project.4

3、2.1 the scale of the project .4 2.2 project information.4 2.3 the main equipments .5 2.4 required construction time limit.11 3organization mechanism and its duty.12 3.1 organization mechanisms.12 3.2 management duty.12 4management of the project schedule.15 4.1 management process of progress plan.15

4、 5.technical management in construction.18 5.1 organization of technical management in construction.18 5.2 construction management .18 5.3 technology management .21 5.4 management of technical documents.25 6. management of quality in project.28 6.1 quality target.28 6.2 quality checking units .29 6.

5、3 quality management measures .29 6.4 quality checking project and procedures .32 6.4.1 quality checking works .32 6.4.2 quality checking procedures.32 6.5 plan of supervision and inspection for quality of turbine project.34 7. steam turbine engineering safety management.41 7.1 safety management met

6、hod.41 7.2 safety facilities.41 7.3 safety measures.42 7.3.1 site transportation.43 7.3.2 hoist and transportation.43 7.3.3 special seasons measures.43 7.4 civil construction.44 7.5 environment protection.45 8. manpower resource and machinery and tools allocation plan.46 8.1 manpower resource plan.4

7、6 8.2 training.46 9. finished product protection .47 9.1 equipment, material storage and stack .47 9.2 the protection in installation .47 10. main construction scheme and technical measures of the steam turbine.48 india amarkantak power plant project construction engineering rev:0 2 10.1 check and r

8、epair of equipment before erection.48 10.2 erection of the steam turbine body.51 10.3 construction scheme and measures of generator.58 10.4 the main machine oil circulation scheme and measures.67 10.5 high pressure installation technology measures.69 10.6 turbine auxiliary equipment and machinery in

9、stallation measures.70 11appendix: main construction scheme and work instruction list.73 11.1 construction scheme .73 11.2 work instruction.74 india amarkantak power plant project construction engineering rev:0 3 1. basis of preparation and explanation thermal power plant project of india 1200mw lan

10、co amarkantak takes zeland project pvt ltd as general contractor and dongfanf electric corporation the sub-contractors of the equipments. for construction, civil work and installation is taken charge of by construction sub- contractor, dec take charge of supervision and necessary technical instructi

11、on on construction. it aims at assuring quality of the project and completing the construction tasks provided in the contract of the project safely and orderly on time with high-efficiency to prepare construction engineering, which can be provided to dec for reference of organizing construction. acc

12、ording to the contract of the lanco amarkantak thermal power station 2300 mw unit # 1 thermal power plant and the construction technology and many-year supervision experience of our company, we prepare this construction engineering as one of the documents of installation, supervision and technology

13、instruction of erection plant project. 1.1 basis of preparation 1.1.1the contract of the india lanco amarkantak thermal power plant 1.1.2“technical specification of construction the second unit is put into operation after 6 months of unit 1. no.contentstart end 1site survey 2005-10-1 2main building,

14、 boiler and equipment foundation construction 2006-02-15 3civil and structure works2006-01-14 4boiler steel structure erection2006-07-01 5steam drum lifting2006-11-30 6turbine erection2007-02-01 turbine casing covering2007-06-30 7coal pulverizing system2007-01-30 8generator erection2007-430 9condens

15、er erection2006-122-123 10boiler hydraulic test2007-5-7 11boiler firing and steam blowing2007-10-1 12oil circulation2007-9-6 13turning gear 2007-10-22 14turbine rotor rolling2007-12-11 15synchronization2008-1-11 commercial operation2008-03-1 india amarkantak power plant project construction engineer

16、ing rev:0 9 16performance test2008-3-12008-6-1 no.itemsbeginning timecompletion time 1地质勘探及试验2005-10-01 2主厂房、锅炉及设备基础施工2006-01-15 3土建及结构工程2006-01-14 4锅炉钢架安装2006-07-01 5汽包起吊2006-11-30 6汽机安装2007-02-01 汽机扣盖2007-06-30 7煤粉制备系统2007-01-30 8发电机安装2007-04-30 9凝汽器安装2006-12-12 10锅炉水压试验2007-05-07 11锅炉点火吹管2007-10-

17、01 12油循环2007-09-06 13tg 盘车2007-10-22 14汽机冲转2007-12-11 15并网2008-01-11 商业运行2008-03-01 16性能试验2008-03-012008-06-01 india amarkantak power plant project construction engineering rev:0 10 3organization mechanism and its duty 3.1 organization mechanisms the owner of the project is lanco amarkantak power pr

18、ivate limited hyderabad india and zelan projects private limited as principal contractor roundly takes charge of design, equipments, construction, commissioning and operation, etc. chinadongfang electric corporation(dec) as sub-contractor takes charge of design, equipment manufacturing and supply, i

19、nstallation supervision and technical instructor of the project. construction organization mechanism is shown in fig. 1. 3.2 management duty 3.2.1 duty of zeland roundly take charge of design, equipments, construction, commissioning and operation, etc. 3.2.2 duty of dec takes charge of design, equip

20、ment manufacturing and supply, supervision of installation and necessary technical instruction of the project. 3.2.3 duty of erection supervisor and technical instructor provide reference documents of construction and technology and assure they are exact. prepare the project quality

21、inspection (5) making full use of machine and tools as well as field arrange work and rest time reasonably through organization and command to get a high use rate of machines and tools and field. 5.3 technology management flow chart of construction technology management can see figure 4: 5.3.1 prepa

22、ring unit erection organization scheme only when collecting the necessary documents and files on designs and equipments, can it prepare unit erection organization design according to actual situation. it should be the practical value of operability and guiding this project. and it should be carried

23、out only after decision of the related personnel and examining and approving program. 5.3.2 joint checkup of erection drawings specialized erection drawings of the unit are the principal basis for checking and accepting specialized india amarkantak power plant project construction engineering rev:0

24、20 erection joint checkup of construction drawings can be performed in various ways and it should solve the problems in design, equipments, erection, materials, production operation, the unit taking charge of joint check-up construction drawings should make a particular joint checkup newsreel and st

25、ored for future reference. 5.3.3 technical instruction of erection before erection, technical personnel should prepare erection scheme, measures and working instruction based on approved erection design files, drawings, manufacture documents, requirements of contract, regulations, criterion and insp

26、ection standard. technical introduction of erection is to make constructors understand project scale, characteristics, construction task, special operation methods, quality requirements and safety measures and make sure that the constructors know fairly well; take charge of the technical instruction

27、 respectively, the files that having been introduced on technology should not be altered at will in construction and if necessary, it must have the related alteration procedure and approval program, the personnel attending technical instruction of construction signs to ratify the instruction content

28、s. flow chart of technical introduction of construction sees figure 5. 5.3.4 design alteration and project contact list the approved design files are the principal basis for construction and the construction unit should construct it by drawings and ensure project quality, if find problems on design

29、or it will be altered due to construction party, only when it is applied for, or contacted and transacted signature procedure, can it be altered. project contact list should be formally put forward after it passes related examination and approval program by way of project contact channel. design alt

30、eration documents and project contact list must be reserved as accomplishing documents for future reference. india amarkantak power plant project construction engineering rev:0 21 begin prepare be familiar with construction drawings of project contract summary of drawing joint checkup general situat

31、ion of project, time limit management, quality management, resource management and construction scheme material plan, processing piece plan, machine and tool plan and equipment list construction process card, construction scheme, resource distribution, schedule requirement and quality requirement re

32、cords for technical introduction of construction inspect record and tracking report store information end inspect and accept construction supervision and technical guide technical introduction of construction working introduction of construction scheme modify and adjust working plan general design o

33、f construction organization modify and adjust drawing joint checkup auditing auditing auditing feed back opinions unqualified acceptable unqualified unqualified acceptable acceptable figure 4 flow chart for technical management of construction india amarkantak power plant project construction engine

34、ering rev:0 22 figure 5 flow chart for technical introduction of construction 5.3.5 preparing and releasing technical documents in erection technical documents of construction is a part of project accomplishing documents so it must reflect the construction process of the whole project clearly accord

35、ing to the facts and an important history archives for owners to know the situation of this project. technical documents of construction calls for original documents filled neatly, all of the technical record of construction and erection (including hidden project and measuring record) begin release

36、construction task, technican of construction group should attend erection scheme and working guide, available document and information introduction for erection drawings operation methods and quality and safety assurance measure design alteration and situation of using material for other purpose ins

37、pect acceptance requirements, quality standard and quality acceptance and assessment methods end india amarkantak power plant project construction engineering rev:0 23 the technical documents of construction should not be duplicate copy, the signature of the party must be signed by himself and it sh

38、ould be his whole name. providing of technical documents in construction will be settled through negotiation according to requirements of contract generally. technical and accomplishing documents of construction must transact formal signature procedure before handing over and taking over them. progr

39、am of preparing and releasing technical documents can see figure 6. 5.4 management of technical documents 5.4.1 range of technical documents it includes: drawings, engineering technical documents related to supplying and erection, standard, regulations and criterion for project, working introduction

40、, safety construction measures, contract, technical protocol and letters related to project. the aim of managing technical documents if to ensure using available files and documents and not losing them in project construction and handing over accomplishing documents completely. 5.4.2 document manage

41、ment drawing document management file management center should check and number the drawing documents after party a receives them and establish machine account, stamp mark of being controlled and manage it being controlled. file management center should deliver them according to stated range

42、 and establish machine account. after accomplishing project, file management center will take back all of the drawings delivered and then deal with and pigeonhole them uniformly. when file management center receives design alternation sheet provided by party a, check and number them, establish machi

43、ne account and put them into the corresponding drawing volumes. file management center delivers design alteration sheet according to delivery range and quantity of drawing and after that establish machine account. when receiving design alteration sheet, the departments using the drawings should stam

44、p alternation marks on the corresponding drawings. after accomplishing the project, file management center will take back alternation sheet (together with drawings) and then deal with them in concert, after that pigeonhole them according to india amarkantak power plant project construction engineeri

45、ng rev:0 24 requirements. the documents should be numbered uniformly according to regulation of party a, the searching catalog and code of all drawing documents will be put in computer. all documents should be pigeonholed according to code and classified on contents for convenient inquiry. india ama

46、rkantak power plant project construction engineering rev:0 25 begin prepare technical documents collate documents examine documents modify documents approve documents mark of documents submit and confirm documents release documents accept and register documents ends figure 6 programs for preparing a

47、nd releasing technical documents india amarkantak power plant project construction engineering rev:0 26 letter management all of the two-way technical letters related to project should be managed by file management center. when file management center receives a letter, number and register it

48、, stamp seal for incoming dispatches passing round for perusal and then send it to the manager in charge for reviewing. then copy it and deliver it to the related departments according to reviewing while pigeonhole the original letter through file management center. when posting a letter, the depart

49、ment to post a letter should send the letter to the leader in charge for examination and check and after approval and signature of the leader in charge, file management center should number, register, send and pigeonhole the letter. number letters according to requirements of party a uniformly, and

50、then put it in computer. management for accomplishing documents tidy up various engineering data, engineering documents, erection record, acceptance and assessment record, equipment defect treatment situation, material qualification and test report in form of unit project document appearing

51、in construction in form of unit project document package. then according to requirements of contract (or agreement with owner), accomplishing documents should be provided to owners according to requirements. 6. management of quality in project such project is examined and evaluated on quality in acc

52、ordance with recognized quality checking and evaluating standard for construction of thermal power engineering in power industry: volume of turbine, piping volume, welding engineering volume, processing and configuring volume, water processing volume, and hydrogen-making device volume. 6.1 quality t

53、arget the general target for installation quality of such project is: the excellence percentage of unit project is up to the standard and as required by the contract; the excellence percentage of individual project is up to the standard and as required by the contract; to ensure the quality in const

54、ruction, improve technology of construction and found first-class project. india amarkantak power plant project construction engineering rev:0 27 6.2 quality checking units the project uses three-grade checking and evaluating system as erection group deczeland. no.involved departmentgrade 1erection

55、groupgrade i 2decgrade ii 3zelandgrade iii 6.3 quality management measures 6.3.1 construction quality management measures practice a system: “no erection without examination of drawings, without work instruction, without description of technology”. before erection, examining the drawings, pr

56、eparing work instruction and describing erection technology. implement the system of quality checking and planning. according to monthly construction plan, prepare monthly acceptance plan on quality. the persons in charge of checking quality should be ready for acceptance in advance as requi

57、red by the plan. implement three-grade acceptance and management system, namely self-checking in installation department, cmec/sec inspection and mapna rechecking, and ipdc acceptance. the checking items and grades at different levels are divided as required by identification table of checki

58、ng and acceptance for quality in constructional project. establish and realize responsibility system for project quality, and investigate the responsibilities for possible problem of quality level by level. insist on such a quality management system as a regular meeting on quality ea

59、ch week in installation department, and a quality analysis meeting each month in quality monitoring department. hold site analysis meeting immediately if there is any quality problem found; and reflect the irregular quality check results held by owner and monitoring department. as for the pr

60、oject passing grade iii acceptance, after it is conformed by grade ii acceptance in completion of the project, the constructional unit should regulate materials in time, mapna should notice gnce to check for acceptance. correct and reflect the proposed problems and requirement in time. india amarkan

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论