PMP考试官方样题_第1页
PMP考试官方样题_第2页
PMP考试官方样题_第3页
已阅读5页,还剩45页未读 继续免费阅读

下载本文档

版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领

文档简介

1、样题二考前须知1. PMP课堂模拟题是团队针对PMP知识点提炼出来。2. 本套模拟题共有200道单项选择题,测试时间为3个小时,闭卷答题!正确率 要求答对140题70%或以上。正式考试为4个小时3. 本套模拟题尽可能地覆盖PMP考试的题型,请学员们集中精力在4个小时内完 成,到达全真的模拟效果4模拟考试过程中,调整思维,揣摩考题的意图;考试结束后,认真总结。5. 解题策略:TKS策略T topic 真正读懂题目K key迅速抓住考点Ssource准确找到出处C choice果断做出选择6. PMP课堂模拟题,版权归清晖所有,未经清晖许可,不得复制或抄袭。7. 对试题或参考答案如有疑问:把试题整

2、理好发给您的教务班主任,班主任会把您的疑问转给讲师为您解答。清晖傅老师解答:E-mail:contractor installs the last product and receives payment. The project manager discovers flaws in the installation and requests that the contractor complete the repairs at no cost. Which of the following arguments should the contractor use to refuse the p

3、roject manager 's requestA. contractual closure was approvedB. installation was improperly performed by the project teamC. contractor 's quality policy does not allow for this situationD. financial closure was approved1. 承包商安装最新产品并接收付款。工程经理发现安装有缺陷,并要求承包商免费完成修 理。承包商应使用以下哪一个论据,拒绝工程经理的请求A. 合同收尾

4、已批准B. 工程团队执行的安装不当C. 供给商的质量政策不允许发生这种情况D. 财务收尾已批准business analyst collects requirements for a new project. Stakeholders are from different departments and have various requirements. The project budget is limited and can only deliver half of the requirementsA. Facilitated workshopsB. Focus groupsC. Gro

5、up decision making techniquesD. Group creativity techniques2. 业务分析员为一个新工程收集需求。干系人来自不同部门并且需求也各不相同。工程预 算有限只能交付一半需求。为确保应包含那些需求,业务分析员应使用以下哪一项A. 引导式讨论会B. 焦点小组C. 群体决策技术D. 群体创新技术a quality assurance audit, a project manager receives a formal change request proposing a modification to a component drawing. wh

6、ich of the following plans should the project manager review firstA. Project management planB. Change management planC. Configuration management planD. Quality management plan3. 在质量保证审计之后,工程经理收到一份正式的变更请求,提出修订一封部件图纸。项 目经理先查看以下那一份方案A. 工程管理方案B. 变更管理方案C. 配置管理方案D. 质量管理方案increase trust and improve interpe

7、rsonal relationships, the project manager of virtual team schedules an off-site building activity. However, due to a scheduling conflict, a key team member cannot attend the activity.To avoid this conflict, what should the project manager have reviewedA. Project staff assignmentB. Resource calendarC

8、. Project scheduleD. Project organization chart4. 为提高信任度和改善人际关系, 一个虚拟团队的工程经理安排了一次非现场团队的建设 活动。然而,由于进度冲突,一名关键团队成员不能参加活动。为防止这个冲突,工程经理应已经审查那些内容A. 工程人员配备B. 资源日历C. 工程进度D. 工程组织图project manager negotiates contract terms with an external vendor that will provide additional resources to complete a critical pr

9、oject task. To minimize project risk, what type of contract should the project manager selectA. Cost-reimbursableB. Firm-fixed-priceC. Fixed-price-incentive-feeD. Time and material5. 工程经理与将提供额外资源完成关键工程任务的外部供给商协商合同条款。 为了减少项 目风险,工程经理应选择什么合同类型A. 本钱补偿合同B. 固定总价合同C. 总价加鼓励费用合同D. 工料合同project team completes

10、a project to transition from an old database to a new database. Regarding lessons learned, what should the project manager do nextA. Present to the sponsor at the stakeholder closeout meetingB. Present to the client to ensure agreementC. Ensure information is stored in a project fileD. Ensure inform

11、ation is stored in a corporate knowledge base6. 工程团队完成了一个从就数据库转变到新数据库的工程。在经验教训方面,工程经理下 一步该怎么做A. 在干系人收尾会议上提交给发起人B. 提交给客户确保协议C. 确保信息储存在一份工程文件中D. 确保信息储存在公司知识库中the project executio n phase, a project man ager lear ns that the customer'sorga ni zatio n could beacquired by ano ther orga ni zati on. Wh

12、at should the project man ager do nextA. Revisit the project charterB. Perform a risk reassessme ntC. Ask for the project sponsor 'guidaneeD. Discuss the issue with stakeholders7. 在工程执行阶段,工程经理了解到客户所在组织可能被另一个组织收购。工程经理下一步该怎么做A. 查看工程章程B. 执行风险再评估C. 寻求工程发起人的知道D. 与干系人讨论这个问题should the effectiveness of

13、a project 'quality control activities be determinedA. Evaluate the quality assura nee pla n aga inst market ben chmarksB. Impleme nt a quality audit strategyC. Con duct a quality audit of the deliverablesD. Evaluate the cost of quality8. 应如何确定工程质量控制活动的有效性A. 对照市场标杆评估质量保证方案B. 实施质量审计谋略C. 对可交付成果实施质量

14、审计D. 评估质量本钱a project kick-off meet ing, the chief executive officer(CEO) requests cha nges that will impact the project scope. How should the project man ager resp ondA. Advise the ceo that the project team will estimate the impact of the cha nge requestB. Inform the CEO that the scope cannot implem

15、e nt the cha nge because the project scope isfin alizedC. Accept the cha nges accord ing to CEO'requestD. Con sider the CEO's cha nge duri ng the project executi on phase-9. 在工程启动大会上,首席执行官( CEO提出的变更将会影响工程范围。工程经理应如何响应。A. 通知CEO工程团队将调查所建议变更的影响B. 通知CEQ范围已最终确定,无法变更C. 按CEO请求,接受变更D.在工程实施阶段考虑 CEO的变更

16、task has the correct assig nment in the RACI chart序TaskTeam member#1Team member#2Team member#3Team member#4Team member#51Unit testRAICA2Integration testIACAR3System testIRCIA4User acceptanceRACIAA. Task 1B. Task 2C. Task 3D. Task 410.那一个任务在 RACI图中的分配正确序任务团队成员#1团队成员#2团队成员#3团队成员#4团队成员#51单位测试RAICA2集成测试

17、IACAR3系统测试IRCIA4用户验收测 试RACIAA.任务1B.任务2C.任务3D.任务4the end test part 4, the project man ager reviews a con trol chart. What does the chart in dicateA. Quality is in line with expectati onsB. Quality expectatio ns are not achievableC. Quality has not improved since the begi nning of the testsD. Quality

18、is not in line with expectations11. 在测试零件4结束时,工程经理查看了控制图。这个控制图会说明说明A. 质量符合预期B. 质量预期不可实现C. 自从测试开始起,质量未得到改善D. 质量与预期不符a project 'implementation, several providers participate in the project. The project manager meets with stakeholders, exter nal con sulta nts, and subject matter experts to defi ne

19、the project scope.The project man ager should in clude which items as part of the project scope stateme ntA. Requireme nts traceability matrix, risk register, stakeholder register, activity listB. Con stra in ts, schedule, assumpti ons and work breakdow n structureC. Scope descripti on, accepta nee

20、criteria, con stra ints and deliverableD. Tech nical referen ce, excepti ons, deliverable and scope baseli ne12. 在工程实施期间,多名供给商参与工程。工程经理与工程干系人、外部参谋和主题专家 一起开会定义工程范围。工程经理应该将那些项内容包含作为工程范围说明书的组成局部A. 需求跟踪矩阵、风险登记册、干系人登记册和活动清单B. 制约因素、进度方案、假设和工作基准结构C. 范围说明、验收标准、制约因素和可交付成果D. 技术参考、例外情况、可交付成果和范围基准project team i

21、n stalls a new operati ng system. Before impleme ntatio n, the team tests the system on a smaller, isolated network and discovers some issues. After finding solutions to these issues, the team still encounters implementation issues. However, the number and severity of issues are greatly reducedWhich

22、 of the following does the project team useA. Transferring riskB. Mitigating riskC. Accepting riskD. Avoiding risk13. 工程团队安装一个新的操作系统。实施之前,该团队在一个较小独立的网络中测试该系 统,并发现一些问题。发现这些问题的解决方案之后,团队仍然碰到实际问题。然后, 问题数量和严重程度大大降低。工程团队使用的是以下哪一项A. 转移风险B. 减轻风险C. 接受风险D. 躲避风险new project manager takes over a project in the e

23、xecution phase. The project manager learns that the customer did not provide the correct product requirementsThe project manager should apply activities from which of the following plansA. Scope management planB. Change management planC. Configuration management planD. Requirements management plan14

24、. 新工程经理接管了一个处于执行阶段的工程。 工程经理了解到客户没有提供正确的产品 需求。工程经理应采用下面哪一项方案中的活动A. 范围管理方案B. 变更管理方案C. 配置管理方案D. 需求管理方案bicycle company releases a new line of baskets with a five-year warranty. The material withstands extreme weather conditions. The product is well received by customers and is considered top of the line

25、 the design is basic with no additional features Which of the following describes this productA. High grade, high qualityB. Low grade, low qualityC. High grade, low qualityD. Low grade, high quality15. 一家自行车公司发布了一款拥有五年质保期的新车蓝系列。材料能抵御极端天气条件。 产品广受用户接受,且视为是系列中的顶级产品。产品只有根本设计,无额外功能。以下哪一项为哪一项该产品的描述A.高档、高质

26、B.低档、低质C.高档、低质D.低档、高质project contains several stakeholders, 50 team members, a number of job sites, and stakeholders and project team member may review a lot of information and documents anytime during the project period, what communication method the project manager should use to solve the informat

27、ion requirement of projectA. Interactive communicationB. Push communicationC. Pull communicationD. Send-receive16. 一个工程包含多名干系人, 50 名团队成员, 多个工作现场, 以及干系人和团队成员可能 需要在工程过程中任何时间查看的大量信息文件。假设要解决工程的信息需求,工程经理 应使用哪一个沟通方式A. 交互式沟通B. 推式沟通C. 拉式沟通D. 发送 -接收project manager wants to develop a resource breakdown struct

28、ure(RBS) for a new project. A team member states that the team already developed an RBS for similar, existing project. What should the project manager do nextA. Compare the existing project 'sRBS to the organization 's standard templateB. Use the existing project 'sRBS to save timeC. Cre

29、ate a new RBS using the organization 's standard templateD. Use the applicable categories of the existing project 'sRBS17. 工程经理希望为一个新工程制定资源分解结构( RBS。一名团队成员称该团队已经为 一个类似现有工程制定了 RBS.工程经理下一步该怎么做A. 将现有工程的RBS与组织的标准模板进行比照B. 使用现有工程的 RBS节约时间C. 使用组织的标准模板创立一份新的 RBSD. 使用现有工程RBS的适用类别project manager disco

30、vers that a key team member will leave the organization in two weeks.The team member works on tasks that are on the critical pathWhat should the project manager do firstA. Evaluate the impact of losing this memberB. Verify if can change the scopeC. Update work breakdown structureD. Change the projec

31、t team member18. 工程经理发现一名关键团队成员将在两周内离开组织。该名团队成员正在为处于关键路径上的任务工作。工程经理首先应该做什么A. 确定该名团队成员的影响B. 核实是否能够变更范围C. 更新工作分解结构D. 更换团队成员company 's president asks a project manager to implement a new financial system. What technique should the project manager use to obtain a high-level project scopeA. Perform a

32、 make-or-buy analysisB. Meet with the director of information technology to conduct an analysisC. Define requirement with the company 's finance experts and business ownersD. Collect requirements from financial application vendors19. 公司总监要求工程经理实施一个新的财务系统。 工程经理应使用什么技术获得高层次项 目范围A. 开展自制或外购分析B. 与信息技

33、术总监开会开展一项分析C. 与公司的财务专家和企业所有者定义需求D. 收集财务应用程序供给商的需求negotiation with resource manager, project manager develops the project management plan. In the kick off meeting, resource manager says the resource only can be available in the late state of project period, what should the project manager do nextA. A

34、dd the resource risk into risk registerB. Record the change, review and update the project management planC. Communicate the resource availability delay and manage the stakeholder participation levelsD. Do not take any action, since the issue has been discussed in the kick off meeting20. 在于资源经理协商之后,

35、工程经理制定工程管理方案。在工程启动大会上,资源经理称 一名资源在进度方案后期才可用。工程经理下一步该怎么做A. 在风险登记册中添加该资源风险B. 记录该变更,并审查和更新工程管理方案C. 在资源可用性中沟通该延迟,并管理干系人的参与水平D. 不采取其他行动,因为该问题已在工程启动大会上讨论过了conflict among some project member may delay the project, what should the project manager do nextA. Solve the conflict in advance in privateB. Delay the

36、 conflict, and evaluate if it will impact the project in futureC. Report the conflict to function managerD. View the human resource management plan and take the corrective action21. 一些团队成员的内部冲突可能延迟工程,工程经理下一步该怎么做A. 提前并私下解决冲突B. 延迟冲突,评估其是否将会在后期影响工程C. 将冲突上报给职能经理D. 查看人力资源管理方案并采取纠正措施project is near comple

37、tion and another US$120,000 is needed to finish the project. Even though US$1 million has already been spent on the project, the project sponsor requires the project manager to stop the project for various circumstancesIn this case the actual costs are:A. Direct costs for the projectB. Part of the p

38、roject 's contingency reserveC. Indirect costs for the projectD. Sunk costs not taken into account for this decision22. 工程接近完工,但另需 120,000 美元来完成该工程。虽然该工程已经花费 100 万美元, 处于各种情况,工程发起人要求工程经理停止该工程。在这种情况下,实际本钱为:A. 工程的直接本钱B. 工程应急储藏的一局部C. 工程的间接本钱D. 该决定不考虑漂浮本钱storm damages a data center, causing a delay t

39、o the project. as a result of this unexpected event, what should the project manager do nextA. Use management reserve funds to generate a workaroundB. Delay the project and wait for management 's directionsC. Update the schedule and advise the project sponsorD. Meet with the project team to disc

40、uss the immediate response23. 一场风暴损坏了数据中心,导致工程延迟。由于这是一个意外事件,工程经理下一步该 怎么做A. 使用管理储藏金来生成一个权变措施B. 延迟工程,并且等待管理层的只是C. 更新进度,并且通知工程发起人D. 与工程团队开会讨论直接的应对措施project manager works on a US$3 million project which involves two suppliers. The project manager creates a statement of work(SOW) for each supplierWhich o

41、f the following needs SOWA. Risk management planB. Project charterC. Procurement management planD. Supplier scope statement24. 工程经理正在管理价值 300 万美元,涉及两个供给商的工程。工程经理为每名供给商创 建了一份工作说明书( SOW) .以下哪一项需要 SOW 的信息A. 风险管理方案B. 工程章程C. 采购管理方案D. 供给商范围说明书project management plan is distributed to all key stakeholders.

42、 However, the project sponsor and the customer have comments and want to make some changes Who should receive this feedback and take the appropriate actionsA. Change control boardB. Project sponsorC. Project managerD. Project team25. 已将工程管理方案分发给所有关键干系人。然而,工程发起人和客户有意见,并希望做 一些改良。谁应负责收取该反响并采取适当的行动A. 变更

43、控制委员会B. 工程发起人C. 工程经理D. 工程团队unexpected risk occurs during a project. After analyzing risk, the project manager finds that mitigating the risk to make the project success, but will increase the project cost What should the project manager do nextA. Get the approval from top management to increase the

44、project budgetB. Arrange a project meeting to discuss the reason why the risk wasn 't included in the risk registerC. Get the approval of top management to use contingency reserve to mitigate the riskD. Arrange a project meeting to discuss how to push project according to the plan26. 工程期间发生了意外风险

45、。分析风险之后,工程经理发现为了让工程成功有必要减轻风 险,但是会增加工程本钱。工程经理下一步该怎么做A. 获得高级管理层的批准,增加工程资金B. 安排一次经济工程团队会议,讨论该风险未包含进风险登记册的原因C. 获得高级管理层的批准,使用应急储藏减轻风险D. 与工程团队安排一次会议,讨论推进工程的方案estimating an activity cost, the team members estimate US$5,000 to hire a consultant for the next year, divided as follows:US$4,500 - Consultant fee

46、US$200 Tn flation allowa nee for next yearUS$300 - Buffer for un foreseen costsWhat should the projeet manager do nextA. Estimate US$4,700B. Estimate US$5,000 with an explanationC. Estimate US$5,000 and update the cost baselineD. Estimate US$4,80027. 估算一项活动本钱时,团队成员估算下一年要花费 5000 美元聘用一名参谋,划分如下 4500 美元

47、 -参谋费200 美元 -下一年的通货膨胀余量300 美元 -不可预见本钱的缓冲 工程经理接下来应该怎么做A. 估算 4700 美元B. 估算 5000 美元,并附加说明C. 估算 5000 美元,并更新本钱基准D. 估算 4800 美元project is planned for four days with an allocated budget of US$4,000. The project manager allocated a resource for US$1,000 per day to complete the work in the scheduled time. At t

48、he end of the second day, the amount of work performed is evaluated at US$1,600. If the productivity rate of the resource remains the same, when is the project expected to be completedA. 6th dayB. 5th dayC. 4th dayD. 3rd day28. 工程预算工期为四天, 分配的预算为 4000美元。工程经理按每天 1000 美元分配一项资 源以按方案时间完成工作。在第二天结束时,所执行的工作

49、量预估金额为 1600 美元。 如果资源的生产率保持相同,工程预计将于何时完成A. 第 6 天B. 第 5 天C. 第 4 天D. 第 3 天identifying a risk with the company 's standard template for contract statements of work(SOW), the steering committee decides to use a special SOW template for all project contraction which of the following should the committ

50、ee the special SOW templateA. Primary contractor agreementB. Change order to the project management planC. Procurement management planD. Risk management plan29. 识别到使用公司合同工作说明书(SOW)标准模板存在风险之后,指导委员会决定为所有工程合同使用一种特殊SOW目标。委员会应在以下那一项保持特殊SOW模板A. 主承包商协议B. 对工程管理方案的变更单C. 采购管理方案D. 风险管理方案a weekly project review

51、 meeting, the project manager discusses various type project risks Which of the following risk quantification techniques should be usedA. Probability distributionsB. Expert judgmentC. Data quality assessmentD. Risk urgency assessment30. 在每周工程审查会议上,工程经理讨论了不同类型的工程风险。应使用以下那一项风险 量化工具A. 概率分布B. 专家判断C. 数据质

52、量评估D. 风险紧迫性评估guarantee their next project delivery, two project teams require the same critical resource within the same timeframe. What should the project manager do firstA. Inform the customer that the delivery will be delayedB. Advise the resource to work overtime to complete both activitiesC. Re

53、view the human resource management plan and contact a preferred consulting firmD. Arrange a joint problem-solving session with the two team leaders to identify possible actions31. 为保证下一次工程交付,两个工程团队在相同的时间范围内需要相同的关键资源。工程 经理首先应该做什么A. 通知客户将延迟交付B. 通知资源加班工作完成两项活动C. 审查人力资源管理方案并联系一家首选参谋公司D. 与两名团队领导安排一次联合问题解

54、决会议,确定可能的行动project manager determines which risks have the greatest impact on the project and plans to use a sensitivity analysis model. The project manager is in which of the following processesA. Identify risksB. Perform quantitative risk analysisC. Control risksD. Perform qualitative risk analysi

55、s32. 工程经理确定了哪些风险对工程产生的影响最大,并方案使用敏感性分析模型。工程经 理目前处于以下哪一个过程A. 识别风险B. 实施定量风险C. 风险控制D. 实施定性风险分析a project 's closing phase, a project manager presents the last project deliverable and run the acceptance criteria. However, before accepting the project, the customer wants to add extra functionalityWhat

56、should the project manager do nextA. Agree to include the requirementB. Update the project management plan according to the new requestC. Review the impact of the change and start the change management processD. Reject any changes since the project is in the closing phase33. 在工程收尾阶段,工程经理提交了最后一个工程可交付

57、成果,并运行验收标准。但是, 在验收工程之前,客户希望增加额外功能。A.B.C.D.同意包含该需求按照新的请求更新工程管理方案审查变更影响,并开始变更管理过程 因为工程处于收尾阶段,拒绝任何变更the project 's execution phase, a key executive reports that a portion of the project will be given to a new external vendor for development. The new vendor provides their additional requirements which cause a potential delay in the delivery scheduleW

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论