1、 110110米米箱箱梁梁张张拉拉控控制制应应力力及及油油表表读读数数千斤顶型号规格:400t千斤顶编号:12060501油泵编号:压力表编号:33744压力表型号规格:060MPa压力荷载关系公式:y=0.0135X-0.9456梁板位置钢束号钢绞线根数控制张拉力(KN)施工张拉力 (KN)油表读数(MPa)全桥边腹板N115280510%280.52.8420%5616.6350%1402.517.99100%280536.92N215280510%280.52.8420%5616.6350%1402.517.99100%280536.92N315280510%280.52.8420%56
2、16.6350%1402.517.99100%280536.92中腹板N115280510%280.52.8420%5616.6350%1402.517.99100%280536.92N215280510%280.52.8420%5616.6350%1402.517.99100%280536.92N315280510%280.52.8420%5616.6350%1402.517.99100%280536.92边腹板N115280510%280.52.8420%5616.6350%1402.517.99100%280536.92N215280510%280.52.8420%5616.6350%1
3、402.517.99100%280536.92N315280510%280.52.8420%5616.6350%1402.517.99100%280536.92全桥面板N415277510%277.52.8020%5556.5550%1387.517.79100%277536.52N515277510%277.52.8020%5556.5550%1387.517.79100%277536.52跨中底板N612222010%2222.0520%4445.0550%111014.04100%222029.02跨中底板N6122220 110110米米箱箱梁梁张张拉拉控控制制应应力力及及油油表表读读
4、数数千斤顶型号规格:400t千斤顶编号:12060502油泵编号:压力表编号:33787压力表型号规格:060MPa压力荷载关系公式:y=0.0132X-0.3869梁板位置钢束号钢绞线根数控制张拉力(KN)施工张拉力 (KN)油表读数(MPa)全桥边腹板N115280510%280.53.3220%5617.0250%1402.518.13100%280536.64N215280510%280.53.3220%5617.0250%1402.518.13100%280536.64N315280510%280.53.3220%5617.0250%1402.518.13100%280536.64中
5、腹板N115280510%280.53.3220%5617.0250%1402.518.13100%280536.64N215280510%280.53.3220%5617.0250%1402.518.13100%280536.64N315280510%280.53.3220%5617.0250%1402.518.13100%280536.64边腹板N115280510%280.53.3220%5617.0250%1402.518.13100%280536.64N215280510%280.53.3220%5617.0250%1402.518.13100%280536.64N315280510
6、%280.53.3220%5617.0250%1402.518.13100%280536.64全桥面板N415277510%277.53.2820%5556.9450%1387.517.93100%277536.24N515277510%277.53.2820%5556.9450%1387.517.93100%277536.24跨中底板N612222010%2222.5420%4445.4750%111014.27100%222028.92跨中底板N6122220 110米箱梁预应力张拉计算(N1)本合同段预应力混凝土结构采用j15.20高强度低松驰钢绞线,钢绞线的标准强度为fpk=1860
7、MPa ,N1-N3锚下控制应力为con=0.723 fpk=1345 MPa,N4-N6锚下控制应力为 con=1330 MPa,截面积为139mm2,Ep=192(根据钢绞线实验数据取平均值)。张拉采用双向张拉,千斤顶到锚具工作长度按60cm计。单束预应力筋的张拉力P =0.723 fpkAg/1000=0.7231860139/1000=187KN 孔道采用PE塑料波纹管成型,=0.15,K=0.0015 计算公式: PP=P(1-e(kx+)/(kx+) L=PPL/APEP箱梁N1钢绞线伸长量计算(N1-钢束15束)分段X(m)(rad)Kx+e-(Kx+)起点力(KN)终点力(KN
8、)平均力(KN)L(m)单端伸长L(m)P2804.325工作端0.600.0009000.9991004052804.3252804.332804.330.0042031250.3366AP2085L14.7660800.0071490.9928763742804.332784.352794.320.033268322EP192L20.474520.0474520.0078300.9922009912784.352762.632773.480.003287545K0.0015L310.612240.0524970.0237930.976487912762.632697.682730.030.
9、0723713430.15L40.467170.1777390.0273620.9730093332697.682624.872661.110.003105487L59.5671800.0143510.9857517112624.872587.472606.120.062283241L61.226970.1226970.0202450.9799585492587.472535.612561.450.007850775L72.5660800.0038490.9961582782535.612525.872530.740.016222196L80.364180.1635670.0250810.97
10、52306032525.872463.302494.460.002269261L97.1467200.0107200.9893371752463.302437.042450.150.043741301L102.272980.2272980.0375040.9631904012437.042347.332391.900.013581012L1112.88340.0637320.0288850.9715282812347.332280.502313.750.074462989L120.854982工作端N1钢束单端延伸量L=193.9mm,图纸设计伸长量:?mm 施工时前10%张拉伸长量不准确,初
11、始伸长量含将钢绞线拉直的长度,实际施工时按0-10%张拉力量测伸长量L110%,按10%-20%张拉力量测伸长量L210-20%,计算伸长量(0-10%张拉力)L1,10%=L2*(10-20%);控制10%20%、20%100%的伸长量,伸长量偏差不超过6%,否则应分析原因或重新张拉。 110米箱梁预应力张拉计算(N2)本合同段预应力混凝土结构采用j15.20高强度低松驰钢绞线,钢绞线的标准强度为fpk=1860 MPa ,N1-N3锚下控制应力为con=0.723 fpk=1345 MPa,N4-N6锚下控制应力为 con=1330 MPa,截面积为139mm2,Ep=192(根据钢绞线实
12、验数据取平均值)。张拉采用双向张拉,千斤顶到锚具工作长度按60cm计。单束预应力筋的张拉力P =0.723 fpkAg/1000=0.7231860139/1000=187KN 孔道采用PE塑料波纹管成型,=0.15,K=0.001 5 计算公式: PP=P(1-e(kx+)/(kx+) L=PPL/APEP箱梁N2钢绞线伸长量计算(N2-钢束15束)分段X(m)(rad)Kx+e-(Kx+)起点力(KN)终点力(KN)平均力(KN)L(m)单端伸长L(m)P2804.325工作端0.600.0009000.9991004052804.3252804.332804.330.0042031250
13、.3550AP2085L17.3038500.0109560.9891040212804.332773.772789.020.050885736EP192L20.410680.0410680.0067760.9932466872773.772755.042764.390.002835933K0.0015L37.234530.0357880.0162200.9839108412755.042710.712732.810.0493870520.15L41.591610.1591610.0262620.9740802712710.712640.452675.430.01063708L59.71441
14、00.0145720.9855340372640.452602.252621.310.063610195L61.086170.1086170.0179220.9822378352602.252556.032579.070.006997682L74.673200.0070100.9930147112556.032538.182547.090.02973391L81.563180.1563180.0257920.9745373142538.182473.552505.720.009784415L97.2335800.0108500.9892082832473.552446.852460.180.0
15、44454157L102.153870.2153870.0355390.9650852352446.852361.422403.890.012933796L1111.940760.0590690.0267710.973583692361.422299.042330.090.069502125L1255.50584工作端N2钢束单端延伸量L=187.5mm,图纸设计伸长量:?mm 施工时前10%张拉伸长量不准确,初始伸长量含将钢绞线拉直的长度,实际施工时按0-10%张拉力量测伸长量L110%,按10%-20%张拉力量测伸长量L210-20%,计算伸长量(0-10%张拉力)L1,10%=L2*(1
16、0-20%);控制10%20%、20%100%的伸长量,伸长量偏差不超过6%,否则应分析原因或重新张拉。 110米箱梁预应力张拉计算(N3)本合同段预应力混凝土结构采用j15.20高强度低松驰钢绞线,钢绞线的标准强度为fpk=1860 MPa ,N1-N3锚下控制应力为con=0.723 fpk=1345 MPa,N4-N6锚下控制应力为 con=1330 MPa,截面积为139mm2,Ep=192(根据钢绞线实验数据取平均值)。张拉采用双向张拉,千斤顶到锚具工作长度按60cm计。单束预应力筋的张拉力P =0.723 fpkAg/1000=0.7231860139/1000=187KN 孔道采
17、用PE塑料波纹管成型,=0.15,K=0.001 5 计算公式: PP=P(1-e(kx+)/(kx+) L=PPL/APEP箱梁N3钢绞线伸长量计算(N3-钢束15束)分段X(m)(rad)Kx+e-(Kx+)起点力(KN)终点力(KN)平均力(KN)L(m)单端伸长L(m)P2804.325工作端0.600.0009000.9991004052804.3252804.332804.330.0042031250.3563AP2085L18.7740700.0131610.9869251242804.332767.662785.950.061061489EP192L20.492030.0492
18、030.0081180.9919143712767.662745.282756.450.003387935K0.0015L34.761270.0235530.0106750.9893819192745.282716.132730.680.0324777770.15L41.453720.1453720.0239860.9762990072716.132651.762683.810.009745991L59.8200100.0147300.9853779412651.762612.982632.320.064571895L60.994030.0994430.0164070.983726375261
19、2.982570.462591.660.006435327L76.7530100.0101300.9899216162570.462544.552557.480.043142277L81.495940.1495940.0246830.9756191252544.552482.512513.410.009392248L97.316300.0109740.989085552482.512455.422468.940.045122706L102.039880.2039880.0336580.9669021092455.422374.152414.560.012303672L1110.995790.0
20、543940.0246530.9756486132374.152316.342345.120.064414707L12工作端N3钢束单端延伸量L=180.9mm,图纸设计伸长量:?mm 施工时前10%张拉伸长量不准确,初始伸长量含将钢绞线拉直的长度,实际施工时按0-10%张拉力量测伸长量L110%,按10%-20%张拉力量测伸长量L210-20%,计算伸长量(0-10%张拉力)L1,10%=L2*(10-20%);控制10%20%、20%100%的伸长量,伸长量偏差不超过6%,否则应分析原因或重新张拉。 110米箱梁预应力张拉计算(N4=N5)本合同段预应力混凝土结构采用j15.20高强度低松
21、驰钢绞线,钢绞线的标准强度为fpk=1860 MPa ,N1-N3锚下控制应力为con=0.723 fpk=1345 MPa,N4-N6锚下控制应力为 con=1330 MPa,截面积为139mm2,Ep=192(根据钢绞线实验数据取平均值)。张拉采用双向张拉,千斤顶到锚具工作长度按60cm计。单束预应力筋的张拉力P =conAg/1000=1330139/1000=185KN 孔道采用PE塑料波纹管成型,=0.15,K=0.001 5 计算公式: PP=P(1-e(kx+)/(kx+) L=PPL/APEP箱梁N4钢绞线伸长量计算(N4、N5-钢束15束)分段X(m)(rad)Kx+e-(K
22、x+)起点力(KN)终点力(KN)平均力(KN)L(m)整段长L(m)P2773.05工作端0.600.0009000.9991004052773.052773.052773.050.004156250.2822AP2085L11.6740500.0025110.9974920752773.052766.102769.570.011581736EP192L21.722750.1722750.0284250.9719748252766.102688.582727.150.011736112K0.0015L317.1364900.0257050.9746228192688.582620.35265
23、4.310.1136231950.15L4工作端N4、N5钢束整段延伸量L=286.5mm,图纸设计伸长量:?mm 施工时前10%张拉伸长量不准确,初始伸长量含将钢绞线拉直的长度,实际施工时按0-10%张拉力量测伸长量L110%,按10%-20%张拉力量测伸长量L210-20%,计算伸长量(0-10%张拉力)L1,10%=L2*(10-20%);控制10%20%、20%100%的伸长量,伸长量偏差不超过6%,否则应分析原因或重新张拉。 110米箱梁预应力张拉计算(N6)本合同段预应力混凝土结构采用j15.20高强度低松驰钢绞线,钢绞线的标准强度为fpk=1860 MPa ,N1-N3锚下控制应力为con=0.723 fpk=1345 MPa,N4-N6锚下控制应力为 con=1330 MPa,截面积为139mm2,Ep=192(根据钢绞线实验数据取平均值)。张拉采用双向张拉,千斤顶到锚具工作长度按60cm
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2026年设备监理师之设备工程监理基础及相关知识题库与答案
- 2026年临床执业医师资格考试综合试题及答案
- 回复投诉处理结果回复函8篇范本
- 2026年二级造价师土建实务真题(附解析)
- 2026年(其他类)职业病诊断医师考试老师题库及答案(广东汕尾)
- 2026年1月19日巫山事业单位考试A类《职业能力倾向测验》试题(考生回忆版)
- (2026)市政施工员考试题库及参考答案
- 智慧教育平台互动性提升与创新教育融合解决方案
- 工程师项目进度绩效表
- 慢性失眠中医诊疗共识重点2026
- 修订一单一库质量手册和程序文件参考文件
- 空调器装配工班组考核水平考核试卷含答案
- 2026年农商行面试题及答案
- 2026年呼和浩特市政府采购评审专家考试真题含答案
- 2026年加油站员工上岗考试题库及答案
- 更换消火栓的施工方案(3篇)
- 虚拟电厂运营速成
- 以目标为导向的大学英语模块化教学
- 2026春每日一练小纸条数学人教版小升初
- 雨课堂学堂在线学堂云《航空电机与电器(中国人民解放军海军航空)》单元测试考核答案
- 中药材有机种植生产技术手册
评论
0/150
提交评论