1、.PMP考试用到的公式Budgeted Cost of Work Scheduled = BCWS = Planned Value = PVBudgeted Cost of Work Performed = BCWP = Earned Value = EVActual Cost of Work Performed = ACWP = Actual Cost = ACBudget at Completion = BACEstimate at Completion = EACEstimate to Complete = ETCVariance at Completion = VACVariance

2、= Plan - ActualCost Variance CV = BCWP - ACWP = EV - ACSchedule Variance SV = BCWP - BCWS = EV - PVCost Performance Index CPI = BCWP / ACWP = EV / ACSchedule Performance Index SPI = BCWP / BCWS = EV / PVEstimate at Completion EAC = BAC / CPIEstimate to Completion ETC = EAC - ACWPVariance at Completi

3、on VAC = BAC - EACQ U A L I T Y - CoQ = ( ( Review Efforts + Test Efforts + Training Efforts + Rework Efforts + Efforts of Prevention) / Total Efforts) x 100 % PERT = O + 4ML + P - 6 MEAN -> Average MODE -> The “most found” number RANGE -> Largest - Smallest Measure. MEDIUM -> No in the

4、middle or avg. of 2 middle Nos STD. DEV. OF TASK = P - O _ 6 TASK VAR. = (P O) 2 = Std. Dev 2 _ 6 _ CP STD. DEV. = ² + ² + ² SIGMA 1 = 68.26 2 = 95.46 3 = 99.73 6 = 99.99 Channels of Communication - COMM = (N2 - N) / 2 = (N x (N 1) / 2 P R O J E C T S E L E C T I O N - PV = F V . - (1

5、+r) FV = PV x (1+r) NPV = S ( PV + PV + PV + PV ) - - - - (1+r) (1+r) (1+r) (1+r) Cash Flow = Cash Inflow Cash Outflow Discounted Cash Flow = CF x Discount Factor ARR = S Cash Flow / No. of Years ROI = (ARR / Investment) * 100 % BCR = Benefits / Cost Exp. Value = Probability % x Consequence $ Class

6、of Estimates - Definitive +5% Capital Cost +10-15% Appropriation +15-25% Feasibility +25-35% Order of Magnitude > +35% Contract Incentives - Savings = Target Cost Actual Cost Bonus = Savings x Percentage Contract Cost = Bonus + Fees Total Cost = Actual Cost + Contract Cost E A R N E D V A L U E A

7、 N A L Y S I S - PV (Present Value) = BCWS (Budgeted Cost of Work Schedule) EV (Earned Value) = BCWP (Budgeted Cost of Work Performed) AC (Actual Cost) = ACWP (Actual Cost of Work Performed) CV = EV AC CPI = EV / AC (efficiency) SV = EV PV SPI = EV / PV ETC = BAC EV or (BAC EV) / CPI EAC = AC + ETC

8、EAC = BAC / CPI VAC = BAC EAC % COMPLETE = EV / BAC x 100 % SPENT = AC / BAC x 100 CV% = CV / EV x 100 SV% = SV / PV x 100 EASY REFERENCE TO PROJECT MANAGEMENT COST EQUATIONSTheProjects Budget:PV:Planned Value (PreviouslyCalled BCWS:Budgeted Cost of WorkScheduled)Theplanned value is the project budg

9、etthat is part portion of the approvedcost estimate that is planned to be spenton the activity during a givenperiod.TheProjects Actual Cost:AC:Actual Cost (PreviouslyCalled ACWP:Actual Cost of WorkPerformed)The actual cost that is thetotal of direct and indirect costs incurred in accomplishing work

10、on theactivity during the given period.TheProjects Earned Value:EV:Earned Value (Previouslyand Interchangeably Called BCWP:Budgeted Cost of Work Performed)EV is the method for measuring projectperformance.§Itcomparesthe amount of work planned with what was actually accomplishedtodetermine if co

11、st and schedule performance is as planned.§Theearned value, previously and interchangeably called the Budgeted Cost ofWork Performed (BCWP), is a percentage of the total budget equal to thework actually performed.CostVariance:CV:Cost VarianceCV is any difference from the estimatedcost of an act

12、ivity and the actual cost of that activity.In earnedvalue analysis, CV = EV ACScheduleVariance:SV:Schedule VarianceSV is any difference from the between thescheduled completion of an activity and the actual completion of thatactivity.In earnedvalue analysis, SV = EV - PVCostPerformance Index:CPI:Cos

13、t Performance IndexCPI is the ratio of budget cost to actualcosts.In earned value analysis, CPI =(EV/AC)CumulativeCPI = (sum of all individual EV budgets / sum of all individual ACs)SchedulePerformance Index:SPI:Schedule Performance IndexThe SPI is used in some application areasto forecast the proje

14、ct completion date.SPI = (EV/PV)(Sourcefor above equations:PMBOKã, Section 10.3.2.4, Publishedby the Project Management Institute (PMI), 2000 edition)Valuable Hints NOT Written in Project Management BooksAbout Costs (Ormore succinctly “How to know youre in trouble”)When EVis used in a cost variance equation, it always goes first:CV = EV AC(ValuableHint:

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论