1、Abstract City subway usually shallow buried tunnel, and the route to the bustling city lots, overlying buildings, dense, heavy traffic, so it is usually constructed by shield method to reduce the effect of ground.However in the process of excavation in hard rock, Boulder or long distance of soft har

2、d lot, still using shield method construction will accelerate the tool wear, reducing driving speed, frequent replacement of tools will enable the artificial cost and engineering cost rises ceaselessly, and the construction safety risk, the project impact.Therefore in such areas may be considered mi

3、ning method with shield method combining construction.Keywords:Shield; mining method; construction technology of combining.摘要 城市地铁通常为浅埋隧道,且穿越路线为城市繁华地段,上覆建筑物多、人口密集、交通繁忙,所以通常采用盾构法施工以减少对地面影响。然而在开挖过程中若遇到硬岩、孤石群或长距离上软下硬地段时,仍采用盾构法施工将会加速刀具磨损、降低掘进速度,频繁更换刀具将使人工成本及工程成本不断上升,且施工安全风险极大,对工程整体进度产生影响。故在此类地段可以考虑矿山法与盾

4、构法相结合进行施工。关键词:盾构法; 矿山法; 结合施工技。1 .Introduction Along with our country city track transportation tunnel engineering construction development, the engineering geological condition becomes more and more complex, simple shield method construction technology and construction technology of simple mining me

5、thod on the adaptation of formation increasing limitations.When the tunnel segments with uneven hardness and the difference is larger, if only using shield method construction, selection can also meet the cutting strength is low and soft soil excavation of high strength rock composite shield machine

6、 shield machine, not only the high cost, in hard rock excavation cost is high.And when the stratum uneven hardness difference in hard rock strength is high, the shield machine is very difficult to satisfy the requirements of both, will cause a series of problems and accidents.On the other hand, the

7、soft rock of mine construction, high cost of construction, long construction period, and the construction risk is difficult to control.Especially in city subway tunnel, the buildings on the ground and pipes, the tunnel construction process of ground subsidence and deformation of high control require

8、ments, when there is an accident, economic loss is estimated hard, social influence to bear.2. Principle and characteristic of subway tunnel construction2.1 Principle of Subway Tunnel Construction City subway usually shallow buried tunnel, and the route to the bustling city lots, overlying buildings

9、, dense, heavy traffic, so it is usually constructed by shield method to reduce the effect of ground, does not affect the city traffic, no pollution, no noise.2.2 Characteristic of Subway Tunnel ConstructionCity subway construction is one of the greatest features, is the project is located in flouri

10、shing region of the city, commerce, traffic is busy, many buildings on the ground.Therefore, in most cases, the city subway construction only by tunneling method. In city subway project, the construction time is the longest, the largest project is the construction cost of subway station construction

11、.Especially in city subway tunnel shield construction after introduction, due to shield construction speed, interval tunnel construction speed and construction of subway station speed asymmetry of the contradiction is highlighted particularly.3.Technological Process of Shield Tunnel Shield construct

12、ion is to shield the construction machinery on the ground below dark tunnel construction method. The shield is a can support the formation pressure and promote activities in the formation of steel tube structure.Steel cylinder is arranged at the front end of the support and excavation equipment, ste

13、el tube jacking installation has the desired jacks,Steel cylinder tail can be assembled prefabricated or cast lining ring.Each ring of a shield advance distance, at shield tail support of assembling a ring lining, and the lining ring to peripheral gap pressure injection of cement mortar, to prevent

14、tunnel and ground subsidence.The shield advance force by a lining ring bear.Shield construction before the construction of a shaft, in shaft mounted within the shield, shield excavation soil by access shaft out of the ground.Because of its resistance to circular formation of earth pressure and water

15、 pressure on lining is better, assembly is simple, can use the general component, easy to replace, so it is widely used.Shield method is mainly characterized in that: except for shaft construction, construction operations are in the ground, which does not affect the ground transportation, but also r

16、educe the residents in the vicinity of the noise and vibration;Shield tunneling, excavation, assembling the lining the main cycle of construction, easy management, construction personnel is relatively small; less quantity of earth;Crossing the river does not affect shipping; construction from the st

17、orms and other weather conditions; in poor geological conditions, high underground water level to the local construction deeply buried tunnel, shield method has higher technical and economic superiority.4.Technological Process of Mining Method Mining method originated in the1986 Beijing subway Fuxin

18、gmen reentrant line engineering, is the Chinese people to create their own suitable for China's national conditions of a tunnel construction method.Its outstanding advantage is not influence city traffic, no pollution, no noise, and is suitable for various sizes and cross section of tunnel.The p

19、rinciple is: use of soil layer in the excavation process in short time since the steady ability, take the appropriate support measures, rock or soil surface to form a close type thin wall supporting structure of slotted construction method, is mainly applied to the clay, sand, the sand and gravel la

20、yer and geological.As a result of shallow tunneling method in eliminating many approval, demolition, excavation and other procedures, this is construction unit commonly adopted.5. Combination of Two Technological ProcessConstruction scheme design for a range using mining excavation,anchor shotcrete

21、lining, composite construction method.Firstly, using the tunnel primary support, and then use a shield segment air is pushed through the tunnel by mining method,Air push by the shield segments form mining method tunnel two lining, two lining and primary support between the pore with grain size of le

22、ss than 10mm gravel ( stone ) filled, and then filling the spaces between the gravel, and ultimately by the grout and segments constitute the mining method tunnel two lining.6. Conclusion Therefore, take the mining method and the shield method of combination construction, which not only solves the s

23、hield method in hard rock section tunneling difficult problem, but also avoid the mining method in soft rock section construction risks.At the same time, because the city subway tunnel construction is often restricted to the construction site, the mining method and the shield method construction of

24、shield in combination, has been applied to the mine tunnel air pushed past approaches, hard rock section ends without setting a shield machine, hanging out and then starting work well, can effectively reduce the construction site requirements, greatly facilitate the construction organization.The min

25、ing method and the construction technology of shield method combination, can shorten the construction period, reduces the engineering cost, and reduce the construction difficulty and the construction risk, can play two kinds of method the advantages and benefits.Bibliography1 铁建设2005160号,客运专线铁路桥涵工程施

26、工质量验收暂行标准S2 TB10415-2003,铁路桥涵工程施工质量验收标准s3 GB50007-2002,建筑地基基础设计规范S4 JGJ79-2002,建筑地基处理技术规范s5 李闻铁路客运专线预制梁场存梁台座设计研究J铁道标准设计,2009(S1)6 李 昂建筑地基处理技术及地基基础工程标准规范实施手册M北京:金版电子出版公司,20031引言 随着我国城市轨道交通隧道工程建设的发展,面临的工程地质条件越来越复杂,单纯盾构法施工工艺及单纯矿山法施工工艺对适应地层的局限性越来越突出:当隧道各区段软硬不均且差异较大时,若单纯采用盾构法施工,需选用能同时满足掘削强度很低的软土和掘削高强度岩石的

27、复合式盾构机,不但盾构机造价高昂,在硬岩中掘进成本也较高;且当地层软硬不均差异过大硬岩强度过高时,盾构机很难同时满足两者要求,将导致一系列工程难题和事故。另一方面,单纯采用矿山施工,软岩段建设成本高、工期长,且施工风险难以控制。特别是城市地铁隧道,地面建筑及管线密集,对隧道施工过程中的地面沉降和变形控制要求高,一旦发生安全事故,经济损失难以估量,社会影响难以承受。2地铁施工的原则和技术特点2.1地铁施工的原则 城市地铁通常为浅埋隧道,且穿越路线为城市繁华地段,上覆建筑物多、人口密集、交通繁忙,所以通常采用盾构法施工以减少对地面影响,不影响城市交通,无污染、无噪声。2.2地铁施工的特点城市地铁施

28、工的一个最大特点,就是工程位于城市繁华地区,商业、交通繁忙,地面建筑物众多。故在大多数情况下,城市地铁施工只能采用暗挖法施工。在城市地铁工程中,施工时间最长,施工费用最大的工程即为地铁车站工程。特别是城市地铁区间隧道引进盾构法施工后,因盾构法施工速度快,区间隧道施工速度与地铁车站施工速度快慢不对称的矛盾尤为突出。3盾构法施工特点盾构法施工是以盾构这种施工机械在地面以下暗挖隧道的一种施工方法。盾构是一个既可以支承地层压力又可以在地层中推进的活动钢筒结构。钢筒的前端设置有支撑和开挖土体的装置,钢筒的中段安装有顶进所需的千斤顶;钢筒的尾部可以拼装预制或现浇隧道衬砌环。盾构每推进一环距离,就在盾尾支护下拼装(或

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论