1、Translation:Construction Contract  Party A:  (Developer)Party B:  (Contractor)This contract is signed by the two Parties Party A and Party B according to the Contract Law of the Peoples

2、 Republic of China, the Contraction law of the Peoples Republic of China , and other relevant national laws and regulations, as well as the specific nature of this project. On the basis of honest

3、y and credit, equality, voluntariness, party A and party B have reached consensus through negotiations and signed this contract. 1. Project Introduction  1.1Name of Project: 1.2Location of Project: From to .1.3Scope and content of the project:&#

4、160; .1.4The design of construction drawings: .2. Nature of Contracting: Contract for labor and materials .3. Construction period This project will take 20 days after the receive of the beginning notice from Party A (including reception time after completion),and including the beginni

5、ng date and completion date.4. Quality of Project Quality of Project: qualified .5. Contract Amount5.1Contract Amount: be RMB 400,000 Yuan tentatively (The actual settlement shall prevail).5.2Adjustment of contract amount: .6. Final Audit of

6、0;the project6.1The condition and steps for Party A pay the project funds to Party B:Party A agrees to pay Party B for RMB150,000Yuan three days after the beginning of the project,the balance will be paid 97% after the qualified completion, and 3% warranty guarantee fee will be paid one years if the

7、re is no quality problem.6.2Mode of payment: .6.3Party B shall submit to Party A equivalent invoice before Party As each period payment, otherwise, Party A can refuse to pay until the receiving of the Party Bs invoice.6.4The invoice provided by Party B should be valid. Any falls invoice pr

8、ovided by Party B which are found by relevant office, the Party B should not only provide the valid invoice to Party A, but also bear the responsible caused by the invalid invoice.7. Variation of design and visa 7.1During the process of the project, any contract list, t

9、echnology checking list ( not include the variation, addition, substitution, and reduction on the drawings and project fee) concerning about this project shall only be regarded as effective with the confirmation of the representative Party A in writing. 7.2 An

10、y variation notice list, technology checking list, contract list, technology checking list ( include the drawings design) concerning about this project shall only be regarded as effective with the confirmation of the seal of Party A. 7.3In the event of Party B fail

11、s to complete the project according to the drawing variation, Party B shall pay to Party Aas penalty for the breach.Party B will also bear the responsible and the reworking fee caused by the continued work

12、ing regardless of the new design. 7.4Party B shall take full responsibility for any loss caused by delaying for more than  days applying for extension vise from Party A days after the receiving of changed design. 8. Acceptanc

13、e and Final Audit of the project8.1 Acceptance of the project8.1.1This project should meet the national quality acceptance standards and should be accepted at the first inspection after comp

14、letion. The Quality Acceptance Criteria of Construction of nation must be regarded as the acceptance standards for the project. Party B shall inform Party A in writing of all kinds

15、 of inspection and acceptance  within 3 days.Party A shall arrange inspection and acceptance within  3  working days after receiving the notification.8.1.2Party B shall be responsi

16、ble for the re-inspection cost, and the project period shall not be extended.8.2 Final Audit of the projectIf the result of re-inspection has passed acceptance standards, Party

17、0;B shall submit the audit report and materials to Party A for verification within 7 days. (the materials include ).9. Obligations of Party A and Party B9.1. Obligations of Party A: 9.1.1.Party A appoints   as the on-site representative to super

18、vise the fulfillment of contract obligations, to oversee the quality control and check the project progress, and to handle issues such as acceptance and variations and withdraw the

19、 representative at any time.9.1.2. Days before beginning of the project, Party A shall provide Party B .9.1.3. Party A shall confirm the variation and suggestion days after providing to design drawings and scheme to Party B. 9.1.4.Party A shall be responsible for coordinating the relationship with t

20、he engining. 9.2. Obligations of Party B.Party B appoints WangZhirong as the on-site representative of Party B to take charge of fulfilling the contract obligations. The on-site representative

21、60;of Party B shall organize the construction according to contract requirements so that the project can be completed according to the quality and quantity requirements and

22、60;on a timely manner.Party B shall observe safety policies of on-site management by the state and Guangxi , Nanning government authorities and shall independently and fully assumes responsible for the loss caused by violatio

23、n. 9.2.3Party B shall observe policies of on-site management by the state and local government authorities as well as Party A's rules and regulations; Party B shall c

24、ompensate for the losses to any facilities, equipment or pipelines both inside and outside of the construction yard caused by party B. 9.2.4.During construction, Party B 

25、should make such adjustment to the construction plan and the progress schedule per Party A's instruction and change-orders.9.2.5. Party B should transfer the construction site within days after the qua

26、lified completion. 10.Agreement on SafetyParty B must strictly adhere to the Safety and Technical Standards of Construction and Infrastructure Installation and regulation of China, Guangxi Zhuang Autonomous Region,

27、Nanning Safety Standards  and other relevant regulations and standards.the construction spot should meet all standards  of the People's Republic of China. And bearing the safety fees which are not caus

28、ed by party A.11.The concerning material supply 11.1. Party A or Party B should be responsible for the material ,equipments,which should meet the qualified design request with qualification guarantee books.11.2. Any material,equipment which is bought by the Party B, if not agree with the quality req

29、uest or specification contain difference,should forbid any usage.the Party B should rebuy the equipment and bear the responsibility to make sure no delay on the project.if Party B refuses to change the materials, Party A has the right to terminate the contract and asks for loss from Party B.11.3 Any

30、 material,equipment which is bought by the Party A, if not agree with the quality request or specification contain difference,should forbid any usage.the Party A should rebuy the equipment and bear the responsibility to make sure no delay on the project.12. Warranty12.1.Warranty scope: as state in t

31、he contract.12.2.Warranty period: 1 year after the qualified completion.12.3During the warranty period, Party B shall fix within 2 days after receiving the notice from Party A. In the event of Party B fails to fix the defects on a timely manner, Part

32、y A has the right to hire a third Party to do the repair, and any costs incurred shall be burdened by Party B.12.4. Mode of notices: phone, fax, e-mail, and so on.12.4.1 in the way of call the phone or faxing: Party B s TEL: ,Fax: . These contact ways will be regarded as the evidence of wa

33、rranty notice to Party B after the calling and faxing.12.4.2.in the way of posting: Party B s address: . These contact ways will be regarded as the evidence of warranty notice to Party B after e-mailing.12.4.3. in the way of e-mailing: Party B s e-mail: . These contact ways will be regarde

34、d as the evidence of warranty notice to Party B after e-mailing.12.4.4. The fees of noticing Party B will be borne by Party B.12.5. Project quality retention fee(tip: the blue words will be suite for under the condition of withing the Project quality retention fee)12.5.1Project quality retentio

35、n fee: , which will be deduce from the project funds of Party B.12.5.2 After the expire date, Party A will return the rest of the quality retention fees without interest to Party B. This will be applied by Party B within ten days after the completion of qualified project.13. Liabilities for

36、0;Breach13.1.In the event of Party A fails to make payment according to the payment terms, Party A should pay a late fee to Party B;  Daily rate of the

37、0;late fee is  % of the   payment. If the delay of the payment is caused by Party A and is delayed for more than   days, then Party B can termina

38、te this contract.13.2In the event of Party B fails to complete the project according to the construction period in the contract, Party B shall pay % of the total

39、0;contract amount for each day overdue as penalty for the breach. Daily rate of the late fee is  % of the  payment.13.3.Party A can terminate this contract and&

40、#160;Party B shall take full responsibility for any loss caused by this when one of these condition takes place.13.3.1 Overdue over days.13.3.2Party B  transfers the contract and any part of the&

41、#160;contract and its corresponding to any third party without Party A's consent in writing. 13.3.3.Be ordered to shut down by the administrative organ caused by Party B over days.13.3.4.Safety and quality accidents.13.3.5.

42、60;The materials provided by Party B differs from the QA certificate and the Report of Quality Assurance Test. And Party B can not make change on these material.13.4.Party B should make sala

43、ry/wages payment to all construction staffs in time on a monthly basis, and will be fully responsible for any liabilities caused by any loss or damage to Party 

44、A as a result of Party B's failure to pay salaries and wages according to the requirements. In the event of migrant workers create a disturbance on group site, Party A's premises, office space

45、, Party B should paid penal sum Yuan each time. 13.5.In the event any Party shall fail to complete the work in time owing to reasons that the contractor shall be held liable, the Party shall pay a penalty for RMB Yuan, and bear all be loss of the other Party.13.6. penal sums and other penalty fees that Party B should to Party A , Party A can take out the same amount of money directly from the project fees. (including quality reten

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论