1、本期规模size of1X25MW发电机组projectPowergenerating setof 1X25MW泰水泥TS4&6 水泥生产绦 热发电项目Waste heat power generating project for Thailand cement TS4&6 cement production line专业specialty电气electric电气单体调试方案ITest program for single electric equipment河南省安装集团有限责任公司中试所Central Testing Institute of HeNan Province Installa

2、tion Group Co., Ltd7月July编写Wrote by年 year月 month日day审核Checked by年 year月 month日day批准Approved by年 year月 month日day目 录catalog1、编制依据basis to write this program2、电气调试施工前的准备 preparations for electric test3、调试试验作业内容job contents for test4、安全注意事项 safety issues1、编制依据basis to write this program1.1、电气装置安装工程电气设备交

3、接试验标准GB50150standards for electric equipment transferring to test for electric equipmentinstallation project GB501501.2、继电器保护校验规程regulations of protection and test for relay1.3、电气指示仪表检验规程test regulations for electric indication instruments1.4、火力发电厂基本建设工程及竣工验收工程1996年版Acceptance regulations of startup

4、 and finishing of power plant constructionproject(version of 1996)1.5、继电保护及电网安全自动装置检验条例test rules for relay protection and grid safety automatics1.6、设备生产厂家的技术标准及设备调试大纲Test outlines of equipment and technological standards of manufacturer1.7、工程电气施工图纸Construction drawings of electric project2、电气调试施工前的

5、准备 preparations before electric test2.1、主管该项目的技术负责人应参加本工程的图纸会审、提出合理化建议。Technicians in charge of this project should participate in united checking for drawings of the project, and put forward rational advices。2.2、对本工程的新设备、新技术提前准备详细资料、并写出专项调试方案。Prepare detailed documents in advance for new equipment

6、and new technology in this project and write special test programs。2.3、按设计院设计的原理接线图对一次、二次接线、微机、继电保护装置进行全面的了 解,对特殊保护装置等应有专项调试方案。Understand thoroughly the primary wiring、 the secondary wiring、 computer and relay protector referring to principal wiring diagram designed by design institutes。 Special tes

7、t program should be there for particular protector etc。2.4、熟悉了解全厂大容量及重要设备的性能、技术数椐、试验方法、保护整定值、以 确保试验结果的正确性。Know well the performance、 technological data、 test methods and setting values of protection of important equipment with big capacity of plant to ensure correctness of test results。2.5、根据本厂设备选型收

8、集各厂家的技术资料、对施工人员进行安全、技术交底、确保 施工质量及施工工艺。Collect technological data of all manufacturers according to equipment model selection of the plant, make technology and safety introduction to construction persons to ensure quality and techniques of construction。2.6、提出电气调试项目、标准,根据现场的工程进度编制调试进度计划表。Make out item

9、s and standards of electric test, work out test progress schedule according project construction progress on site。3、调试试验作业内容test job content3.1 电力变压器:power transformers3 1.1 测量绕组连同套管的直流电阻:measure DC resistance of windings and casings采用直阻速测微欧姆计或双臂电桥,测量应在各分接头的所有位置上进行,各相测得值 的相互差值应小于平均值的2%,线间测得值的相互差值应小于

10、平均值的1%。The measurement will be taken with quick microhm meter of direct resistance or double bridges in all branch connectors, the mutual difference of all measurement results of all phases should be less than 2% of average values, the mutual difference of all measurement results of all phase-to-pha

11、se resistance should be less than 1% of average values,3 1.2 检查所有分接头的变压比:check voltage ratio of all branch connectors检查采用变压比电桥,其变压比的允许误差在额定分接头位置时为0.5%。Use voltage ratio bridge for checking, the tolerance of voltage ratio should be 0.5% in rated branch connectors。3 1.3 检查变压器的三相结线组别:check windings of

12、three phases wiring of transformer与检查变压比同时进行,必须与设计要求及铭牌上的标记和外壳上的符号相符。This job and checking of voltage ratio will be done synchronously, the results must be in accordance with designing requirements、 marks in nameplates and symbols in outside shell。3 1.4测量绕组连同套管及铁芯的绝缘电阻与吸收比:Measure insulation resista

13、nce and absorption ratio of windings casings and iron cores。采用2500/500V兆欧表进行测量,绝缘电阻值不应低于产品出厂试验值的70%。Use megohmmeter of 2500/500V for measurement, the insulation resistance values should not be less than 70% of experimental values of production delivery。3 1.5 绕组连同套管的交流耐压:AC voltage endurance of windi

14、ngs and casing本项试验应根据被试变压器绝缘介质要求相应进行。高压绕组短接接入试验变压器高压 侧,低压绕组短接接地。低压绕组短接接入试验变压器高压侧,高压绕组短接接地。试验符 合规范要求。This test will be carried out according to requirements of insulation media of transformers to be tested High voltage winding will be short connected to high voltage side of transformers to be tested,

15、 low voltage winding will be short connected to earth。low voltage winding will be short connected to high voltage side of transformers to be tested, high voltage winding will be short connected to earth。 The test must meet requirements of regulations。3 1.6在额定电压下对变压器的冲击合闸试验 :impact test on transforme

16、r in rated voltage在额定电压下对变压器的冲击合闸试验,应进行5次,每次间隔时间宜为5min,应无异常 现象;冲击合闸宜在变压器高压侧进行;对中性点接地的电力系统,试验时变压器中性点必须 接地,无电流差动保护的干式变压器可冲击3次。Impact test on transformer in rated voltage will be done in five times, the interval should be 5 minutes, there should be no something abnormal; the test should be done on high

17、 voltage side of transformer。For the electric system of neutral point being grounded, the neutral point of transformer must be grounded when test was done; for the dry transformer without current differential protection, the test can be done for three times。3 1.8检查变压器的相位必须与电网相位一致。Check the phases of

18、 transformer, they must be in accordance with grid phases 3.2 互感器(6.6/0.4KV) mutual inductor3 2.1 测量绕组的绝缘电阻:measure insulation resistance of winding采用2500V兆欧表测量一次绕组对二次绕组及外壳、各二次绕组间及其对外壳的绝缘 电阻,与产品出厂试验值比较,应无明显差别。Use megohmmeter to measure insulation resistances between primary winding and secondary winding、 primary wind

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论