UnitedNationsDevelopmentProgramme
WhitePaper
MainstreamingFinancial
AggregationforDistributedRenewableEnergy
January2024
◆
Copyright©2024.Allrightsreserved.
OneUnitedNationsPlaza,NewYork,NY10017,USA
Disclaimer:Theviewsexpressedinthispublicationarethoseoftheauthor(s)anddonotnecessarilyrepresentthoseoftheUnitedNations,includingUNDP,orthe
UNMemberStates.
Coverphoto:UNDP/KarinSchermbrucker
Suggestedcitation:UNDP(2024).WhitePaper:
MainstreamingFinancialAggregationforDistributedRenewableEnergy,NewYork.
Acknowledgements
ThedevelopmentofthispaperwasfundedbytheGEF,ledbytheUNDPandpreparedbyexpertsfromTFE.
TheUNDPtaskteamresponsiblefortheproductionofthisreportwascomposedofEduardoAppleyardandMateoSalomon.
TheTFEteamthatwrotethispaperincludesAndréTroost,Dr.SamDubyandKumbiraiMakanza.
Thispaperbenefitedgreatlyfromtheinsightsfrom:AlexWanumeandChrisKanani(WinchEnergy),EricdeMoudt(AfricanFrontierCapital),ChristopherAidunandToukamNgoufanke(PersistentEnergy)andAnshulPatel(Bboxx).
WhitePaper:MainstreamingFinancialAggregationforDistributedRenewableEnergy
UNDP
UNDPistheleadingUnitedNationsorganizationfightingtoendtheinjusticeofpoverty,inequality,andclimatechange.Workingwithourbroad
networkofexpertsandpartnersin170countries,wehelpnationsbuildintegrated,lastingsolutions
forpeopleandtheplanet.
Learnmoreat
orfollow
@UNDP
TheClimateAggregationPlatform(CAP)
TheClimateAggregationPlatformisaGlobal
EnvironmentFacility(GEF)fundedflagshipinitiativeofUNDP,whichseekstosupportthestructuring
anddeploymentofinnovativebusinessmodelsandfinancialmechanismstoaccelerateenergyaccessandajustenergytransition.
TheCAPseekstoadvanceandraiseawarenessforinnovativesolutionstomarketbarriersforfinancialaggregationinthesmall-scale,low-carbonenergysector–withthegoaltoincreaseaccesstolow-costfinancingforcleanenergyinemergingmarkets.
Learnmoreat:
/climate
-
aggregation-platform
GEF
TheGlobalEnvironmentFacility(GEF)isafamilyoffundsdedicatedtoconfrontingbiodiversityloss,
climatechange,pollution,andstrainsonlandandoceanhealth.Itsgrants,blendedfinancing,andpolicysupporthelpdevelopingcountriesaddresstheirbiggestenvironmentalprioritiesandadheretointernationalenvironmentalconventions.Overthepastthreedecades,theGEFhasprovided
morethan$23billionandmobilized$129billioninco-financingformorethan5,000nationalandregionalprojects.
Page2|ClimateAggregationPlatform|WhitePaper|MainstreamingFinancialAggregationforDRE
Introduction
4
Contents
12DT2ee1frminiISnntghreoDedRtusEcftfoioinrnaDtnoRcEtieafrlimnagasnghcereieagtlsaatgiognregation656
2.1.1Considerationsaffectingtermsheetdesign6
2.2Keycomponentsofdrefinancialaggregationtermsheets8
2.2.1Operationsandserviceagreement8
2.2.2Datasharingagreement9
2.2.3Purchaseandsaleagreement9
2.2.4Loanagreement10
3.CasestudiesofpastandpresentDREfinancialaggregation
facilitiesandtransactions11
3.1Bboxxdistributedenergyassetreceivables$500,000pilotin
Kenya(2015)11
3.1.1Transactionstructure12
3.1.2Lookingtothefuture12
3.2WinchEnergy:$16millionmini-gridportfoliofinance(2021)13
3.2.1Transactionstructure13
3.2.2Lookingtothefuture13
3.3BrighterlifeKenya2:landmarkoff-balancesheetfacility(2022)14
3.3.1Transactionstructure14
3.3.2Lookingtothefuture15
4.DFIsandconcessionalfundsinvolvementinDREfinancial
aggregation17
Conclusion1
9
Page3|ClimateAggregationPlatform|WhitePaper|MainstreamingFinancialAggregationforDRE
Photo:UNDP/LouisFourmentin
Introduction
Lastyearmarkedthehalfwaypointtowardsthe2030deadline
forachievingtheSustainableDevelopmentGoals(SDGs).WhileconsiderableprogresshasbeenmadetowardstheSDG7
targetsoncleanandaffordableenergy,inparticularinrelation
toenergyaccess(7.1),675millionpeopleremainwithoutaccesstoelectricityandafurther2.3billionhavenoaccesstoclean
cookingsolutions.1Basedonthecurrentpaceofprogress,effortsmustbesignificantlyrampeduptoachievetheSDGtargetsby
2030.What’smore,althoughcleanenergyisacrucialelement
ofmostNDCs,moreambitioustargetsareneededtokeepus
belowthe1.5°Cthreshold.2WeneedtogreatlyenhancethelevelofpublicandprivateinvestmentinsolutionssuchasDistributedRenewableEnergy,toadvancesustainabledevelopmentand
deliverthegoalsoftheParisAgreement.Toachievethis,new
approachesareneededtode-riskinvestmentsandcrowdinnewsourcesofcapital.
Financialaggregation,definedinthecontextofthispaperastheaggregationofDistributedRenewableEnergy(DRE)receivables,holdsgreatpromiseinreducingthemismatchbetweenDRE
fundingneedsandinvestorrequirementsandinturnincreasingcapitaldeploymentinthesector.Whendesignedcorrectlyanddeployedinsuitablemarkets,theseinstrumentscanofferfasterandmoreaffordableaccesstocapital.
However,financialaggregationinstruments,inparticularoff-
balancesheetonesarecomplex,expensivetosetup(asmuchasUS$2millioninsomeinstances3)andinvolvemanylengthyprocesses–Itcantakeuptotwoyearstocloseatransaction.Theirsuccessfulimplementationdependsonafavourable
enablingenvironmentandtheexistenceofasufficientlylargepipelineofDREassetsoftherightcharacteristicsandquality.Atthemoment,onlyahandfulofmarketplayerscanmeetsuchconditionsorareabletoabsorb,ontheirown,theticketsizesrequiredbyinvestorstojustifysuchanundertaking.Therefore,untilveryrecently,therewerefewexamplesoftransactions
trulyshowcasingthepotentialoffinancialaggregationintheDREsector.
Furthermore,arecurrentmessagethroughouttheextensiveconsultationsthattookplaceinthecontextoftheClimate
AggregationPlatformandthedevelopmentofits
‘Financial
AggregationforDistributedRenewableEnergy’reportsseries
istheneedtoelucidatefinancialaggregationtransactions
throughreal-lifeexamples.Morespecifically,whilethere
hasbeenpioneeringworkdonebyleadingDREcompanies,
arrangers,andinvestorstoclosesuchtransactions,thisworkistypicallydoneinsiloes.Asaresult,thereislimitedknowledgedisseminationonhowtostructureandclosesuchtransactions.
Thiswhitepaperservesasaninitialattempttoshedlightonthemainingredientsinvolvedinclosingcost-effectiveandscalableDREfinancialaggregationtransactionsandshareinsights
andlessonsfromreal-lifeexamples.Thepaperseekstoequipinvestors,DREcompaniesandtransactionarrangersinterestedinfinancialaggregationwithknowledgethatcanhelpthem
1TrackingSDG7:TheEnergyProgressReport.2023(
Link
)
2InternationalRenewableEnergyAgency(IRENA).2023.(
Link
)
3Basedoninterviewsundertakeninthecontextofthispaper.
betterunderstandandnavigatethisprocess.Theintentionis
thatthiscanpavethewayforfurthermainstreamingoffinancialaggregationintheDREsectorandpointtoopportunitiesto
streamlineandreducethecostandtimerequiredforsuch
transactions(e.g.,throughthesharingofbestpracticesandthedevelopmentofstandardizedagreements).
ThepaperwasdevelopedinthecontextoftheClimate
AggregationPlatform(CAP),aGlobalEnvironmentFacility
(GEF)-fundedprojectimplementedbyUNDP,whichseeksto
promotethescale-upoffinancialaggregationforsmall-scale,low-carbonenergyassetsinemergingmarkets.Itbrings
togetherinsightsfromdetailedinterviewswithDREcompaniesandarrangersthatwereinvolvedinpasttransactions.
ThepaperopenswithabriefexplanationofDREfinancial
aggregationanditsdifferentmanifestations.Chapter2followswithadetaileddescriptionofDREfinancialaggregationterm
sheetsandaconcretecaseoutliningkeyconsiderations
affectingtheirdesign.Chapter3discussesthekeylessons
emanatingfromthreepioneeringDREfinancialaggregation
transactions,twoofwhichweredoneintheKenyanmarketandoneinUgandaandSierraLeone.Lastly,Chapter4touchesontheroleofconcessionalfundsinenablingfinancialaggregationintheDREsector.
Page4|ClimateAggregationPlatform|WhitePaper|MainstreamingFinancialAggregationforDRE
$
SpecialPurposeVehicle
Investors
Untilrecently,instancesofDREtransactionsinvolvingsuch
complexmechanismswererare.Infact,onlyahandfulofpureoff-balancesheettransactionshavebeenclosedintheDREsectorinsub-SaharanAfricatodateandthesehavemainly
beenintheOff-gridSolar(OGS)sector(See
Chapter3
).
Establishedplayersinthissectorarerelativelymatureandarelookingtoleveragethevalueoftheircustomerreceivables
toaccessdebttofundfurthergrowth.Incontrast,other
DREsectorsarestillatarelativelyearlygrowthstage.Moretraditionalfinancinginstrumentsarestillmostappropriateinthesesectorsatthisstage.
4UNDP-ClimateBondsInitiative(2022).LinkingGlobalFinancetoSmall-ScaleCleanEnergy;FinancialAggregationforDistributedRenewableEnergyinDevelopingCountries,NewYork.(
Link
)
1.DefiningDREfinancialaggregation
Small-scaleenergyassetscanbeaggregatedintoportfolios
toachievescaleandattractlargerinvestmentticketsizes4inaprocessdefinedasfinancialaggregation.Itcantaketheformofsecuritizationoffuturecashflows(accountsreceivables)
andtheaggregationoftheseintopoolingstructures,typicallySpecialPurposeVehicles(SPVs).Itcanalsotaketheform
ofaggregationofprojectsintoportfoliosforprojectfinance
purposes.Securitizationofreceivablesismorecommonly
performedinproduct-basedsectors,forexampleSolarHomeSystems(SHSs),whileprojectaggregationismorecommonlydeployedinproject-basedsectors,mainlymini-gridsand
captivepower.Financialaggregationinitspurestforminvolvescompletetransferalofthesecuritizedassetsintoanoff-balancesheetstructure,suchasanSPV,asFigure2indicates.This
meansthattheDREcompany,theoriginatoroftheassets,effectivelysellstheassetstotheSPV.
Intheory,thisprocessreducestheriskofthesecuritized
assetsforaninvestorandultimatelythecostofcapitalfortheoriginatorbyeffectivelyseparatingtherisksofsecuritized
assetsfromthatoftheoriginator.Separationofriskalsomeansthatifthecompanywhoinitiallysoldordevelopedtheasset
(theoriginator)failsandisliquidated,itwillhavenorecourseovertheassetsheldbytheSPV.
Successfulattemptshavebeenmadeinothermarkets,notablyKenya,toemployelementsofpureoff-balancesheetstructuresinwhatwetermquasioff-balancesheettransactions.In
theseinstances,originatorsselltheirsecuritizedassetstoa
limitedliabilitypartnership,whichtheyco-ownwithanentity
responsibleforarrangingthefacility.Theoriginator,asaresult,stillhasrecoursetotheassets.
Finally,amorecommonapproachduetotherelativelysmall
sizeofthemarket,hasbeentosecuritizeDREreceivables,
withoutaggregatingandtransferringthemtooff-balancesheetorquasioff-balancesheetstructures5.Theassetsremainfully
onthebalancesheetofthecompany.Whilenotaggregation
perse,thequantificationoffuturecashflowsimprovesthe
company’sinvestorpitchandcanbeusedaspartofthecollateralrequirementsforaloanorastheonlycollateralincaseswhere
moreprogressiveinvestorsareinvolved.Dealscanbesmallerastransactioncostsaresignificantlylowerthanoff-balancesheettransactions.Thispaper,however,focusesontransactionsthatinvolvesomedegreeofoff-balancesheetsecuritization.
5InthecontextoftheCAPFinancialInnovationChallenge,HypoportAfricahasworkedona
syntheticsecuritizationstructureforsolarhomesystemswherethelegalownershipofassetsismaintainedontheoriginator’sside,andnoseparatelegalentityisrequired.
OriginatorsellsDREassets:
•Projects(Mini-gridsorcaptivepower)
•Customerreceivables(OGS,mini-grids,
captivepowerorEVs)
Asset-backed
securities
OriginatoroftheDREAssets
$
Figure1:Basicdepictionofanoff-balancesheetsecuritizationtransaction
Source:Author’sowndiagram.
TolearnmoreaboutfinancialaggregationpleaseseeUNDP’sandtheClimateBondsInitiativereporton
“
LinkingGlobalFinancetoSmall-ScaleCleanEnergy
”.
Page5|ClimateAggregationPlatform|WhitePaper|MainstreamingFinancialAggregationforDRE
Assets
•Minigrids
•C&ISolar
•Electricvehicles•OGS
Legaland
regulatory
•Licensing
•Set-upand
runningexpenses•LocalSPVsviable/ required?
•Issuitablelocalcapitalavailable?•Taxsystem
Receivables
•Fixed(e.g.PPA)•Variable(e.g
PAYGO)
•Reportingandverification
systems
•Connectionorprojectlevelaggregation
Structure
•On/Offbalancesheet
•Debtorequitybased
•Tenureduration
•Discrete
Investmentsorrollingcapitalstructure
•Scalabilityandreplicability
Aggregationmechanisms
2.TermSheetsforDREfinancialaggregation
2.1Introduction
totermsheets
Althoughtheyaretypicallynon-binding,termsheetsserve
asthetemplateandbasisforthemoredetailedandlegally
bindingdocumentsthatspecifythetermsandconditionsof
aninvestmentorbusinesstransaction.Assuch,termsheets
needtocarefullydetailthemostimportantstructuralelements
ofaninvestment.Aggregationbasedtransactionshave
additionalcomplexityincomparisontothemorecommonand
straightforwardtransactions,andassociatedtermsheetsneedtoreflectthis.Theshapeanddesignofanaggregationmechanismwilldependonamyriadoffactorsincludingthetypesofassetstobeaggregatedandthelocationoftheseassets.Figure2
belowshowssomeofthekeyconsiderationsofanaggregationmechanismandtheelementsthataretypicallycoveredinthe
supportingtermsheets.Section2.1.1belowpresentsanexampleofhowthesedifferentconsiderationscanmanifestinpractice.
2.1.1Considerationsaffecting
termsheetdesign
Asanillustration,thissectiondissectsthekeycharacteristicsofanaggregationfacilitycurrentlybeingdevelopedbyTFEalongthecategoriesoutlinedinFigure2.
ThenewfacilityseekstoenableDREdeveloperstoconvert
theirmostsignificantasset(theirrightstofutureenergy
payments/revenues)intocashimmediately(insteadofslowlyoverthelifetimeofaproject)bysecuritizingtheserevenues.
Thefundusesdatastreamsfromcustomerrelationship
managementsystems,demographicdatabases,andGISlayerstocategorizeandclustercustomersbasedonfactorsincludingbutnotlimitedtoabsoluteexpectedrevenue,potentialupsideordownsiderisk,paymentrisk,businesstypeorgender.Thefundthenusesitsproprietaryalgorithmstoaccuratelyforecasttheexpectedrevenueofeachclusteroveragiventimeperiod.Followingtheforecasting,thefundseekstoringfencecash
flows,factortheexpectedreceivablesandofferlowinterest
loanstoDREbusinessesbasedonthestrengthoftheexpectedrevenueofstable,highvalueclustersofinterest.
ThekeycharacteristicsofthefundwhichwillhaveimplicationsfortermsheetdesignaredefinedbyTFEasfollows:
Assets
·Mini-gridandCommercialandIndustrial(C&I)receivables.
Theserefertoanyfuturecashflows.Inthecaseofmini-gridsfuturecashflowsaretypicallystructuredasflatfeespaidbycustomersatregularintervalsorvariableconsumption-basedpaymentsataspecifiedtariffstipulatedinthecustomer
contract.C&Icashflowsaretypicallystructuredsimilarly–
customerscanalsopayflatfeesatregularintervals,while
consumption-basedpaymentsareprovidedforinpower
purchaseagreements(PPAs).PPAscaneitherbestructuredona“takeorpay”basiswhereallenergygeneratedbythesystemmustbepaidforbythecustomeror,alternatively,onthebasisthatthecustomeronlypaysforwhattheyconsume.
DREsectorspecific
Thefundrefinancesexistingprojectsfromlicenseddevelopers;
·Thefundcanbecomefinanciallyprofitableataminimumsizeof$10million;
·Earlyinvestorsareimpactfocusedwithafocusontarget
sub-SaharanAfrican(SSA)countriesincludingNigeriawherethefacilityislaunchingfirst;
·ThefacilityhasreceivedextensiveadvicefromlocalcounselinNigeriatomakesurethatthemechanismiscompliantwithalllocalregulationsandistaxefficient;
·Thefacilityworkswithdeveloperswhoowntheassets.By
refinancingthereceivablesstreamsonly,noassetownershiptransferisrequired;
·Refinancingexistingassetsmeansthatthefacilityisless
exposedtotheavailabilityoflocalfinance.
DRESector
specific
•Businesslicensing•Transactionsize
•Investor
preferences
•Sectorregulations•Assetownershipstructure
•Workingcapital
availability
Geography
•Localstructure
•Hybrid
•Purely
international
•Riskmanagement
andmitigation
•Impactassessment
andreporting
•Dataandreporting
systems
•Longterm
sustainability
Figure2:Mainconsiderationswithpossiblepermutationstobecoveredintermsheets
Source:Author’sowndiagram.
Page6|ClimateAggregationPlatform|WhitePaper|MainstreamingFinancialAggregationforDRE
Receivables
·Every‘asset’underconsiderationforthefundmusthavea
reliabledatafeed.Thesecanbethevariablepaymentsfromindividualsmartmetersonamini-gridorfixed,performance-basedpaymentsfromaC&IPPA;
·Thefacilityusesdatastreamsfromindividualcustomersmartmeters,demographicdatabases,andGISlayerstocategorizeandclustercustomersbasedonfactorsincludingbutnot
limitedtoabsoluteexpectedrevenue,potentialupsideordownsiderisk,paymentrisk,businesstypeorgender;
·Thedataprovidestransparencyaswellasallreportingandthird-partyverificationfunctionality;
·Usingthisdata,thefacilityseekstotoaggregateand
refinanceindividualmini-gridcustomerconnectionsaswellasentireC&Iprojects.
Legalandregulatory
ForthespecificcontextofNigeria:
·LendingasaforeignentityinNigeriaispossible;
·TaxesonNigerianinvestments(loanproducts)aremoderate(e.g.,10percentwithholdingtaxinNigeria);
·ForeignentitieslendingtolocalcorporateentitiesdonotneedanSPVorotherspecificlicensestoconductsuchactivities;
·ForeigncurrencyinvestmentsintoNigeriaareexposed
tohighcurrencyrisksduetocurrencydepreciationand
conversion.Availabilityofforeigncurrencyisalsolimitedinthecountry;
·Nigeriaappliesforeignexchangecontrolsonthetransfersofforeigncurrencyandlocalcurrencyintoandoutofthecountry;
·Alocalbankaccountcanonlybeopenedwithalocal/residentSPV,butthefundcanalsouselocalintermediariesandescrowagentsforthepurposeofcollectingpaymentsinNaira;
·AforeigninvestorseekingtoinvestcapitalinNigeriaby
wayofdebtorequitycanbringintheinvestmentcapital
throughanauthorizeddealer(typically,alicensedNigeriancommercialbank);
·Acertificateofcapitalimportation(CCI)mustbeobtainedin
relationtothecapitalimportation.ThecertificateisalsousedtofacilitatethepurchaseofforeigncurrencyintheOfficialMarketwhenaninvestorseekstoexportorrepatriatetheirinvestment;
·CCIdoesnotguaranteethatthecertificateholderwillalwayshaveaccesstoforeigncurrency;
·TheCentralBankofNigeria(CBN)tendstoimpose,fromtimetotime,capitalcontrolstomanagethereserveofhardcurrencies;
·AlltypicalformsofsecurityorcreditenhancementarepossibleinNigeria(fixedcharges,floatingcharges,
guaranteesetc.);
·ThecostofregisteringsecurityattheCorporateAffairs
Commission(CAC)is0.35percentoftheamountsecuredbythecharge;
·Stampdutieswillalsoapplytotheloandocumentation.Therateofstampdutyis0.125percentforsecuredtransactionsand0.375percentforunsecuredloans;
·Keyenergyandrelatedregulationstobecompliedwithinclude:
(a)ElectricPowerSectorReformAct2005–ThisistheprincipallegislationforthepowersectorinNigeria;
(b)NERCRegulationsforMiniGrids2016–Thisregulationregulatesthedevelopmentandoperationsofmini-gridsinNigeria;
(c)NERCLicensingandOperatingFeesRegulations2010–Thisregulationprescribesthelicensingfeesandoperatingfeesthatshouldbepaidbylicenseesinthepowersector;
(d)EnvironmentalImpactAssessmentAct:Thislawstates
therequirementforanenvironmentalimpactassessmentforpowerprojects.
Geography
·Purelyinternational,whichmeansthatallstructurespertainingtothedealareoffshore.CapitalislentwithoutalocalentityorlocalSPV.
Structure
·DomiciledintheNetherlands;
·ADutchlimitedcompany(“NLBV”)wasselectedbecauseof:。Setupcostandtimeefficiency;
。Easeofoperation;
。Regulation;
。Limitedtaxleakage(taxefficienteconomy,yetstillfairtax);
。Reputationandfamiliarityamonginvestors.
·Mechanics:
。TheNLBVissuesdebtnotestoselectedinvestors;
。Notesincludeonetypeofclassorvariousclasses(e.g.
seniororjunior).Thisiscommonplaceinblendedfinance;
。NLBVinvestsintothefund(debtand/orequity);
。ThefundlendstoDREcompanies–EachborrowerhasauniqueloanagreementunderNigerianlaw.
·Assetsareaggregatedinfunding‘windows’withalimitedtenure.
Investmentsinthefundatlargecanbediscrete(attachedtoaspecificwindow)orrolling(recycledintosubsequentwindows).
Page7|ClimateAggregationPlatform|WhitePaper|MainstreamingFinancialAggregationforDRE
DRE
Financial
Aggregation
TermSheet
2.2KeycomponentsofDRE
financialaggregation
termsheets
DREfinancialaggregationtermsheetstypicallyhavefourcomponents:
serviceformatureDREsectorsonwhichtheservicelevel
agreementcanbemodelled,forexampletheMini-gridQualityAssuranceFramework(QAF).6
OperationsandserviceagreementsforDREfinancial
aggregationwilltypicallyrequireclausespertainingtothe
elementspresentedinTable1below.
Operations
andServiceAgreement
(QualityandperformanceexpectationsimposedupontheO&Mserviceprovider)
DataSharingAgreement
(DSA)
(Conditionsandprocessesfordatasharingbetweentheinvolvedentities)
PurchaseandSaleAgreement(PSA)
(Onlyforoff-balancesheettransactions:
Conditionsandprocessesofsaleof
DREassetsfromtheoriginatortothe
purchaser,typicallythefinancier)
LoanAgreement
(Allthecreditterms,includinginterestrates,repaymentscedules,andmore)
Figure3:OverviewofDREfinancial
aggregationtermsheetcomponents
Source:Author’sowndiagram.
2.2.1Operationsandserviceagreement
OperationsandServiceAgreementsareusuallyrequired
whenthepartythatacquiresorownstheDREassets(typicallytheSPVsetupbythetransactionarranger)doesnotwholly
(i)operateandmaintaintheassethardwareandsoftware
serviceor(ii)servicetheend-users.Inthisscenario,thepartywillcontractwhollyorpartiallytheoperations,maintenance
andservicingcomponentstotheoriginalassetownerand|oranyothercapablethirdparty.Thisentity,“theoperator”,is
responsibleforthedailyoperationandmaintenanceofthe
hardware,softwareandhumanresourcesrequiredtoprovidetheDREproductorservicetotheenduser.Thisarrangementiscommonwhentheoperationalcomponentisnotacore
capabilityoftheassetownerandcanbedonemoreeffectivelybyanotherentity.
Theoperationsandserviceagreementoutlinesthespecific
rolesandresponsibilitiesofthepartiesinvolved,thedurationoftheagreement,theremunerationstructureandlevelofservicerequired.Thelevelofservicerequiredvariesfromsectorto
sector.Therearewidelyrecognizedindustrystandardsof
KEYELEMENTTOINCLUDE
DESCRIPTION
Detailedscope
ofOperations
andMaintenance
(O&M)services
AlltaskstobeexecutedbytheO&M
provider(e.g.,ensuringhighquality
serviceuptime,uninterruptedoperation
ofcustomercomplaintssystems,etc.).
Outliningthe
performance
standardsto
beachieved
Qualitystandardspertainingtotechnical
performance(e.g.,voltagevariationsandsystemaverageinterruptionfrequencyindex(SAIFI)).
Detailingall
guaranteesand
warranties
Includesallguaranteespertainingtoservicelevelsaswellasproductwarrantieswhererelevant(off-gridsolarproductsinthe
caseofproduct-basedsectorsorancillaryproductssuchassmartmetersinservice-basedsectorssuchasmini-grids).
Detailingthe
insurancepolicy
(ifrequired)
Theseincludeinsurancepoliciesthatprotecteitherthefinancierortheproviderfrom
eventssuchasemployeeinjury,etc.
Detailingthe
limitationsand
liabilities
Referstothelimitati
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 护理服务:提升患者体验的秘诀
- 护理研究创新性评估的评估机制创新
- 西式厨师证初级实务题库及答案
- 工资转帐协议书
- 委托投资款协议书
- 2026年人教版科学三年级下册期中测试卷(含答案)
- 重力势能课件2025-2026学年高一下学期物理人教版必修第二册
- 2022年部编版八年级语文上册期中考试及答案【各版本】
- 直线与直线平行课件2025-2026学年高一下学期数学人教A版必修第二册
- 2026年小区雨水管网改造承包合同协议
- 2026版公司安全生产管理制度及文件汇编
- 2026年中国铁路各局集团招聘试题及答案解析
- 湖北省2026届高三(4月)调研模拟考试 英语答案
- 2026中国养老服务市场需求分析与商业模式研究报告
- 2026年丝绸博物馆陈列设计岗面试作品集准备
- 2026年八年级信息技术考试试题库(答案+解析)
- 中国酒精使用障碍防治指南(2025版)
- 新版人教版八年级下册数学全册教案(完整版)教学设计含教学反思
- 蓄热步进式加热炉设计说明书
- 质量保证体系架构图
- JJG 943-2011 总悬浮颗粒物采样器-(高清现行)
评论
0/150
提交评论