建筑工程安全 宜昌东站天桥专项安全施工方案(改)目录11工程简介1工程特点1参建单位2检测机构323文件依据3采用的技术标准、规范334钢结构吊装施工进度计划4劳动力、机械配备及材料计划4第4章 施工工艺技术7钢结构安装准备7组织指挥系统12主要吊装机械选择13钢箱梁吊装20第5章安全文明施工措施23组织保障及文明施工23安全措施24应急救援预案26吊装安全操作规程32检查监控33附录:临时支架受力计算书351工程简介二楼站台与汽车客运站,方便来往乘客安全行走。工程特点该天桥为全钢箱梁和两部钢楼梯构造,采用钢结构形式。箱梁全长11价起吊,进行高空对接。单件箱梁最重27.73t,单件最长16m,截面为6.4m×1.7m3.6m×1.7m(0.9m)装安全是重点也是难点。构件清单如下:序号构件名称构件编号构件重量(kg)长(mm)宽(mm)高(mm)1天桥钢箱梁QL1—12238111500330017002天桥钢箱梁QL1—22585015000330017003天桥钢箱梁QL1—32773613500330017004天桥钢箱梁QL2—11942011500314017005天桥钢箱梁QL2—22009015000314017006天桥钢箱梁QL2—32288311300314017007天桥钢箱梁QL3—12366414000360017008天桥钢箱梁QL3—22480414500360017009天桥钢箱梁QL3—323634140003600170010天桥钢箱梁QL3—416805100003600170011天桥钢箱梁QL4—124800159703600900~170012天桥钢楼梯GT—120025218692400/13天桥钢楼梯GT—216507218942400/施工平面布置:有关规定,施工作业面部署如下:参建单位监理单位:武汉威仕工程监理有限公司勘测单位:湖北建科建设工程有限公司施工单位:中国机械工业第二建设工程有限公司检测机构检验单位:湖北省建筑工程质量监督检验测试中心2文件依据中国市政工程中南设计研究总院有限公司的设计图纸;国家现行的施工规范和标准;图纸会审记录以及钢结构深化图纸等;我公司本项目投标时的施工组织设计;我公司承担类似工程的建设经验。采用的技术标准、规范国家、行业及地方的相关现行标准《建筑施工起重吊装安全技术规范》JGJ276-2012《建筑工程施工质量验收统一标准》GB50300-2013《钢结构工程施工质量验收规范》GB50205-2001《碳素结构钢》GB/T700-2006《热轧钢板和钢带的尺寸、外形、重量及允许偏差》GB709-2006《优质碳素结构钢热轧厚钢板和宽钢带》GB711-2008《钢结构检测评定及加固技术规范》YB9257-96《钢焊缝手工超声波探伤方法和探伤结果分级》GB11345-89《建筑钢结构焊接规程》JGJ81-2002《手工电焊焊接接头的基本形式与尺寸》GB985-88《工程测量规范》GB50026-2007《建筑防腐蚀工程施工及验收规范》GB50212-2002《建筑防腐蚀工程质量检验评定标准》GB50224-2010《涂装前钢材表面锈蚀等级和除锈等级》GB8923-88《建筑施工安全检查标准》JGJ59-2011《高空作业机械安全规则》JGJ5099-98《建筑机械使用安全技术规程》JGJ33-2012《施工现场临时用电安全技术规范》JGJ46-2005《建筑施工高处作业安全技术规范》JGJ80-91《起重机械安全规程》GB6067-2010《起重机试验规范和程序》GB/T5905-2011《建设工程项目管理规范》GB/T50326—2006《建设施工安全检查标准》JGJ59—2011建设部建质[2009]87号文件《危险性较大的分部分项工程安全管理办法》3钢结构吊装施工进度计划劳动力、机械配备及材料计划劳动力计划进行劳动力的选择时应考虑以下因素:高劳动力的综合素质。动力得以充分利用。的施工队伍。本工程现场安装部分劳动力投入计划如下:工种人数工种人数焊工4电工1起重工3测量工3高空作业5司索指挥3合计19施工机械设备计划主要机械设备表主要施工机械序号机械或设备名称型号/规格数量施工部位备注1汽车吊QY1301所有吊装任务2汽车吊QY251配重吊装3货运车17.5m4货运所有构件钢结构安装机具序号名称规格型号单位数量1交流电焊机BX1-300台22CO2350台43角向磨光机φ150台24经纬仪J2台15水平仪S1台16链条葫芦5T条27爬梯10m具28千斤顶5t把69氧气乙炔/套24钢结构安装准备现场施工工艺装条件1.2(1)1.2(1)架 随意更改。参加起重吊装的人员应经过严格培训,取得培训合格证后,方可上岗。应确保其完好,符合安全要求。起重设备需经过相关部门检验。起重设备通行的道路应平整坚实。划定施工车辆进场线路,保证车辆能够自由进出。确保吊车作业场地无限制,比如:附近建筑、电线管路等。绑扎所用的吊索、卡环等的规格应按计算确定。起吊前,应对起重机钢丝绳及连接部位和锁具设备进行检查。检查抗震支座的标高和纵、横定位轴线;确认箱梁的分段几何尺寸和分段重量;绑扎钢丝绳、高空用操作栏杆、生命线和操作平台、爬梯;确认高空拼装支架的基础强度达到承重条件,复核临时支架的标高;充分考虑构件卸货、吊运中的一切空中障碍;路况;吊装前,箱梁支座及以下工程必须经过检查验收合格;吊车行进路线、吊点位置的地基基础确保符合吊装条件;每一机位均应试吊,没有问题的情况下进行正式吊装作业。临时支架的制作和搭设4接。所有安装工程结束后拆除临时支架。支架布置位置如图: 临时支架的制作:采用D219钢管长度确定支架的高度,水平梁用H340*250*8*14的H型钢,支点部位增加10mm厚加强板。钢箱梁的标高D219临时支架的搭设:临时支架搭设在两段钢箱梁之间。搭设前按图在现场的4m×1m×0.5mC30M14*100HHD219H钢梁上。临时支架受力验算(附支架受力计算书)28选用符合载重要求。施工车辆进场路线图吊装顺序、吊点及区域分布吊装顺序说明:根据现场情况,1#桩不能满足承重条件,每单件箱梁成契合QL4-1(5),QL3-4(6)。顺序如下:QL3-2~QL3-3~QL3-1~QL2-3~QL1-3~QL2-2~QL1-2~QL2-1~QL1-1~QL4-1~QL3-4吊点布置重心要在两端吊耳的中点的连线所在的垂直面上,误差不超过10mm,以避免箱梁24mm。交通疏导钢箱梁白天不能封路吊装,只能晚上使用探照路灯在夜里12点至凌晨6点中进行。吊装施工时必须单侧临时封闭,严禁车辆穿行。封闭范围见下图:组织指挥系统施工员现场组织系统框架图施工员安全员安全员项目管理制度🖂后,应根据工程计划具体抓五个环节:即质量、安全、工期、理制度。主要吊装机械选择汽车吊选择米,采用130t吊车起吊,其工作性能如下表:130工作半径(m)主臂长度(m)12.612.616.620.624.528.532.531201113.510710292495948881694.58682756657976706251666666255494075656554944.538848.54847444038.594241.540.54036.532.5103736.535.535.533.530.5⃗1229.12828.927.826.21424.822.723.522.522.51618.319.418.4191815.815.815.216.8抗倾覆验算27.73t⃗可知⃗KGMG+KQMQ+KWMW≥0KG—自重加权系数⃗1⃗KQ—起升荷载加权系数⃗1.15RKW—风动载加权系数⃗1⃗MG、MQ、MW为汽车吊自重、起升荷载、风动荷载对倾覆边的力矩,N·m汽车吊工作时受力简图如下G—汽车吊自重(加配重),130t⃗Q—起升物重量,考虑单机抬吊,取27.73t⃗W—风动载⃗20%考虑⃗a—8m,故a取4m⃗R—12m⃗KGMG+KQMQ+KWMW=1×G×a-1.15×Q×(R-a)-1×W×h=1×1300000×4-1.15×277300×(12-4)-1×277300×0.2×10=2094240N·m>0稳定力矩=KGMGKGMG=1×G×a=1300×4=4200KN·m倾覆力矩=KQMQ+KWMW=1.15×Q×(R-a)+1×W×h=1.15×27.73×(12-4)+0.2×27.73×10=310.576KN·m;稳定系数=稳定力矩/倾覆力矩=4200/310.576=13.52>1.5满足规范要求。下⃗根据∑MA=0⃗可得⃗0.5q(L+L’)2+P(L+L’)=RB·LRB=[0.5q(L+L’)2+P⃗L+L’]/L=[0.5*600/(12+4.86)*(12+4.86)2+74*(12+4.86)]/12=525.47KNRA=q(L+L’)+P-RB=600/(12+4.86)*(12+4.86)+74-525.47=148KNB每个支腿下加垫两层枕木两层枕木长度方2630×30cm,单根长度2.0m120cm×120cm×2cm心垂直。则地基承载力:P=N/A=262.735/(2*2)=65Kpa现场路基和吊车作业点均为分层碾压后的砖渣路基,fa=150kpa,远大于65KPa,故能满足施工要求。根据上述验算,130t吊车能满足使用要求。钢丝绳计算钢丝绳选用计算公式:1、钢丝破断拉力总和=公称抗拉强度(Mpa)×钢丝总断面积(mm²)2、钢丝破断拉力=钢丝破断拉力总和×换算系数3、钢丝绳安全载重力=钢丝绳破断拉力÷安全载重系数钢丝绳的选用计算根据箱梁分段起吊重量284⃗34mm(6*19)钢丝绳进行吊装作业。计算简图如下::[Fg]=aFg/K注:[Fg]钢丝绳容许拉力(KN)Fg,a0.82K6(无绕曲时)则:[Fg]=(0.82*606)/6=496.92/6=82.82KN/9.8N=8.45t本项目钢箱梁吊装选中⃗34mm(6*19),共4个吊点吊装,则:8.45t*4=33.8t根据钢丝绳与钢箱梁夹角为60°33.8*sin60°=33.8*0.866=29.27t>28t卸扣计算7t,DD-11/8,9.5t>7t,满足要求。4.3.4.临时吊耳设计与复核Q23522mm36mm,板孔局部采用16mm双面加强板补强,临时板式吊耳与钢箱梁顶板连接采用双破口全溶透焊接,破口角度为50°,按单个临时板式吊耳能承受7t荷载进行受力验算,板式吊耳大样图如下图所示:(1)单个吊耳板孔强度验算板孔壁承压应力=1.1*8*9800*(100²+36²)/(38+16*2)*40*(100²-36²)=39.97MPa<[fv]=50MPa满足要求。单个吊耳板焊缝强度验算当吊耳受拉伸作用,吊耳板采用双面坡口满焊时,可按对接焊缝校核,即:满足要求。耳的安全验算满足要求。钢箱梁吊装4.4.1.钢箱梁的吊装要点吊完成后方可正式起吊。钢箱梁的轴线、标高控制侧壁板反线到面板来确定,标高测量点如图划定。钢箱梁安装调校钢箱梁就位时,把钢箱梁放到临时支架的调节短管上,用水平仪和经准仪调要求后用定位钢板定位,定位后吊车松钩,吊下一件钢箱梁。如图:钢箱梁间的临时固定2mm。如图:其他钢箱梁安装方法同上。钢楼梯安装方法与钢箱梁方法相同.钢箱梁焊接当焊缝码口完成后,施焊前,清理完焊道后,用陶瓷垫片在焊缝坡口的反面粘贴。单面焊接双面成型。防止钢箱梁变形和应力集中。焊缝质量要求:按国家规范执行。临时支架的拆除载和拆除由天桥桥墩中部向两端进行。如图:5组织保障及文明施工吊装安全管理网络安全所有在安
起责任重责任
安安全全安全,所有参与项目施工 工。必须严格执行安全政策。项目经理责任项目经理是本项目安全生产第一责任人,对本项目安全生产负总的领导责任。贯彻执行公司安全生产规章制度,并执行业主的有关安全管理规定。负责组织项目部所有员工进入施工现场前安全教育。负责组织项目部每季度和每个月的安全生产检查工作。负责本项目的安全文明施工及其周围的环境保护工作。安全员责任理规定,制订项目的安全标准(规定)。保持与医疗部门、急救部门的联络,掌握有关信息(电话、地址等)。通过教育和培训项目的每位员工,以推动项目的安全工作。对现场的工作条件和工作行为进行经常性的监督检查。行检查指导。有责任保证项目的救助系统的完善。安全措施根据现场施工条件进行分析,在施工过程中具有以下危险情况:吊车倾覆高处坠落机械伤害触电伤人物体打击危险源预防措施1、挖掘机、吊车、混凝土泵车必须严格按照操作规程进行操作。臂、泵管收回原位。3、挖掘机、吊车、混凝土泵车操作期间各监控人员必须到位。4、加强作业人员岗前培训工作,增强作业人员的安全意识。56、严格执行各个岗位安全操作规程,执行项目部的各项规章制度。7、加强起重设备的检查维护,坚决杜绝带病作业。8、严格遵守起重机“十不吊”术操作证后,方可从事指挥。信号清晰明确。11、起重司机人员严格按照作业细则作业。12、在大风(超过六级)、大雨、大雾等恶劣天气下严禁作业。预防高空坠落事故的安全技术措施制事故能安全要求,从而为预防、控制高处坠落事故发生。脏病、和思想情绪低落人员要停止高处作业;严禁酒后从事高处作业。高处跳上跳下。业。同时安全带的质量必须达到以使用安全要求,并要做到高挂低用。木电杆的根部是否腐烂。严禁在石棉瓦,刨花板、三合板顶棚上行走。加以排除,使之达到安全要求,从而控制高处坠落事故发生。预防机械伤害的安全技术措施1、机械设备要安装固定牢靠。2、增设机械安全防护装置和断电保护装置。3、对机械设备要定期保养、维修,保持良好运行状态4、经常进行安全检查和调试,消除机械设备的不安因素。5、操作人员要按规定操作,严禁违章作业。预防触电的安全技术措施1、加强劳动保护用品的使用管理和用电知识的宣传教育。2、建筑物或脚手架与户外高压线距离太近的,应按规范增设保护网。电气设备。换和维修。一闸一漏配置。6、根据不同的施工环境正确选择和使用安全电压。7、电动机械设备按规定接地接零。8、手持电动工具应增设漏电保护装置。9、施工现场应按规范要求高度搭建机械设备,并安装相应的防雷装置。预防物体打击的安全技术措施志和搭设围网。2、安全防护用品要保证质量,及时调换、更新。3、经常检查地锚埋设的牢固程度和揽风绳的使用情况。4、严格按照吊装技术操作规程作业。56、清理脚手架上堆放的材料,做到不超重、不超高、不乱堆乱放。安全防护措施1、安全防护和保证措施1全意识薄弱。因此要求现场安全措施高。2墙围挡,非施工人员不得进入施工现场。324施工人员在操作平台上施工时应系好安全带,确保作业人员安全。5全带挂在生命线上,确保施工人员安全。应急救援预案本预案针对可能发生的伤亡事故作出应急准备和响应。火警:119公安:110医疗:120交通:122应急救援机构项目部成🖂事故应急救援指挥领导小组,组长由项目经理担任,副组长由设置相应的应急救援指挥部。应急救援机构职责负责制定事故预防工作相关部门人员的应急救援工作职责。材料物资等资源的调配。进行有针对性的应急救援应变演习,有计划区分任务,明确责任。,🖂即报告公司相关主管部门并及时采取救援工作,尽快控制险情蔓延,必要时,报告当地部门,取得政府部门的帮助。应急救援工作程序🖂即向组长汇报,由组长🖂即上报公司,必要时,汇报当地有关部门,以取得政府部门的帮助。尽快控制险情蔓延,并配合、协助事故的处理调查工作。人指挥安排。事故发生时,应急救援小组🖂即组织营救受害人员,组织撤离或者率,减少事故的损失。事故发生后迅速控制危险源,对事故造成的危害进行监测、测定事因,查明人员伤亡情况,协助上级部门对事故调查。事故报告的真实性和时效性。应急救援装备水管、消防水池、防毒面具、应急药箱、担架、抽水机及切割机等。应急救缓药品凉油或驱风油、三角巾、急救包。服药品:人丹、十滴水、保济丸或藿香正气丸、一般退烧药品。应急救援措施行处理。发生物体打击事故,应马上组织抢救伤者脱离危险现场,以免再发生损伤。进行抢救治疗。搬运。疗。污染较重的伤口,可简单清除伤口表面异物,剪除伤口周围的毛发,但切料覆盖包扎创口。在运送伤员到医院就医时,昏迷伤员应侧卧位或仰卧偏头,以防止呕重,造成或加重脊髓损伤。高空坠落急救措施中的硬物。对禁止一个抬肩一个抬腿的搬法,以免发生或加重截瘫。搬运。疗。12发现脊椎受伤者,创伤处用消毒的纱布或清洁布等覆盖伤口,用绷带或腿或单肩背运。处上下关节为原则,可就地取材,用木板、竹片等。复合伤要求平仰卧位,保持呼吸道畅通,解开衣领扣。1h明上止血带时间。骨折和脑脊液漏患者切忌作填塞,以免导致颅内感染。红汞,然后盖上消毒纱布,用绷带较紧地包扎。加压包扎止血法:用纱布、棉花等做成软垫,放在伤口上再加包扎,来增强压力而达到止血。止血带止血法:选择弹性好的橡皮管、橡皮带或三角巾、毛巾、带状1/21/3每隔25-40min放松一次,每次放松0.5-1min。②动用最快的交通工具或其他措施,及时把伤者送往邻近医院抢救,运送(3)坍塌事故急救措施险队伍,迅速组建、调集抢险及救护队伍。发现事故预兆后,🖂即停止作业,迅速组织人员撤离作业场所。应急救迅速疏散影响范围内的所有人员。分析事故坍塌的影响范围,迅速组织疏散无关人员撤离事故现场,并组织人员建🖂警戒区域,不让无关人员进入事故影响范围。当发生坍塌事故后,最早发现者或目击者应🖂即大声呼救,并根据情况可🖂即采取正确方法施救,向项目部有关人员报告或报警。项目部应急小组应迅速判断事故发展状态和现场情况,采取正确方法施救。在救护过程中要防止坍塌再伤人,扩大伤害范围,必要时要先对危险的地方采取一定的防护措施。急救人员按照有关救护知识,🖂即抢救出来的伤员,在等待医生救治或急救等。当现场不具备抢救条件时,应🖂即向社会求救。触电事故急救措施者二次触电或抢救者触电。隔离电源方法:①断开电源开头;②使用绝缘物(如干燥的竹枝、木枝)隔离或挑开电源或带电体;路。抢救方法:①口对口、口对鼻人工呼吸法:(停止呼吸者)(如木板、干燥的泥地等)的地方。B、一只手捏紧鼻孔,另一只手掰开嘴巴(如果掰不开嘴巴,可用口对鼻人工呼吸法贴鼻吹气)。D、救护人换气时放松触电者的嘴和鼻,让其自然呼吸。②胸外心脏挤压法(心脏跳动停止者)A、解开触电者的衣服,让其仰卧在地上或硬板上。B、救护人员骑跪在其腰部两侧,两手相送,手掌根部放在心口稍高一点的地方,即放在胸骨下三分之一至三分之一处。C、掌根用力垂直向下挤压,压出心脏里面的血液。对成人应压陷3-4cm,60D、挤压后,掌根迅速全部放松,让其胸部自动复原,血又充满心脏,放松时掌根不必完全离开胸膛。同时交替进行。上出现身体僵冷或尸斑,经医生作出无法救治的诊断后方可停止抢救。火灾事故急救措施现场的电源。地方;一边向当地公安消防部门报警,同时向公司应急救援指挥部报告。🖂救人重于救火的原则,救人是火场上的首要任务。棉被、毯子浸水后盖在身上,防止灼伤。抱或抬出火场。当抢救的正常通道被隔断时,应利用安全绳、梯等将人救出。贵重设备及物品等,并把疏散出来的物资集中存放到安全地点,指定专人看管,查明有关情况,及时向指挥部报告。吊装安全操作规程作业中必须严格按操作规程进行工作。有关安全操作规程如下:1、起重工必须经过有关部门考试合格后,发给特殊工种安全操作证,才能独🖂安全防护用品。2、必须熟悉所用起重机械及工具的基本性能,作业前应认真检查使用的设备或工具是否良好,不完好的设备不能投入使用。3、严禁使用已报废的起重机具(起重器具及各种绳索)。4、根据物体的重量、体积、大小、形状及种类,采用适当的起重吊运方法。吊起吊。搬运大型物体必须有明确标志(白天挂红旗,晚上悬红灯)。5、在起吊各种物件前应进行试吊,确认可靠后方可正式吊运。6、使用桅杆或三脚架起吊重物时,应绑扎牢固,杆脚固定牢靠。三脚架的杆距60°,不得斜吊。7、使用千斤顶时,必须上下垫牢,随起随垫,随落随抽垫木。8、使用滚杠搬运物件时,滚杠两端不宜超出工件地面过长,摆放滚杠人员不准显标志;危险区域内禁止人员通过及停留。9、吊运重物时,尽可能不要使重物离地面太高;在任何情况下都禁止将吊运的吊在空中。应选择适当的位置及随物护送的线路。),吊运🖂即停止操作进行检查,绝不能有侥幸心理。严禁站在重物倾斜的一方。120°。垫,以防损坏或割断吊绳。动件滑下伤人。物要保持物体平稳,避免互相碰撞。物压在电气线路和管道上面,或堵塞通道;物体堆放应整齐平稳。车辆上时,要观察重心是否平稳,确认松绑后不至倾倒方可松绑卸物。撞;操作时指挥要统一,动作要协调。情况下都不得让他人代替挂钩重物。工作岗位。械时应与司机密切配合,并严格执行起重作业“十不吊”规定。23、在离地面两米以上的高处作业时,应执行高空作业的安全操作规程。并注意保管。检查监控检查,所有安全检查记录必须形成书面材料。吊装检查重点部位:是否严格按载荷表的规定,禁止超载,禁止超过额定力矩。操纵中不准猛力推拉操纵杆,开始起升前,检查离合器杆是否处于断开位置上。自由降落作业只能在下降吊钩时或所吊载荷小于许用荷的30%时使用,禁止在自由下落中紧急制动,是否执行。在下降货物时是否锁住鼓轮。在起重作业时要是否鸣号警告。在起重作业范围内除信号员外是否有其他人进入。两台起重机共同起吊一货物时,是否有专人统一指挥,两台起重机性能、速度是否相同,各自分担的载荷值,是否小于一台起重机的额定总起量的80%;其重物的重量是否超过两机起重总和的75%。回转作业时,是否紧急停转,导致吊物剧烈摆动发生危险。回转中操作司机是否注意机上有人或后边有无障碍危险。不回转时是否将回转制动锁住。起重臂收放臂杆时是否带载收臂杆。主吊臂杆的臂角是否小于本起重机说明书规定的最小角度,否则整机将倾覆。定固定好,制动回转台,同时考虑空中有无可碰撞的障碍物。、是否按规定顺序收回支腿并固定好。吊机在承受六级大风或大暴雨后必须进行全面检查。监测点布设:在钢桥两端及中部各设一监测点。附录:临时支架受力计算书************PK11.EXE*****************1、设计主要依据:《建筑结构荷载规范》(GB50009-2012);《建筑抗震设计规范》(GB50011-2010);(GB50017-2003);2、结果输出总信息结构类型:单层钢结构厂房结构重要性系数:1.008柱数:13梁数:1支座约束数:27风荷载计算信息:不计算风荷载钢材:Q235恒载作用下柱的轴向变形:考虑:1.20基础计算信息:不计算基础梁刚度增大系数:1.00:0.85钢柱计算长度系数计算方法:有侧移:0.800钢结构受拉柱容许长细比:300钢结构受压柱容许长细比:200:l/400钢梁(活)容许挠跨比:l/500柱顶容许水平位移/柱高:l/500窄行输出全部内容节点坐标XYXYXY(1)1.501.50(2)0.003.00(3)3.003.00(4)1.504.50(5)0.006.00(6)3.006.00(7)0.000.00(8)3.000.00柱关联号柱号节点Ⅰ节点Ⅱ柱号节点Ⅰ节点Ⅱ柱号节点Ⅰ节点Ⅱ(1)72(2)83(3)81(4)71(5)12(6)23(7)13(8)34(9)24(10)25(11)45(12)36(13)46梁关联号梁号节点Ⅰ节点Ⅱ梁号节点Ⅰ节点Ⅱ梁号节点Ⅰ节点Ⅱ(1)56----柱上下节点偏心----节点号柱偏心值节点号柱偏心值节点号柱偏心值节点号柱偏心值(1)0.00(2)0.00(3)0.00(4)0.00(5)0.00(6)0.00(7)0.00(8)0.00----标准截面信息----(1)17,219,6.0,5I(3)33,L63x4,等边角钢截面LII(6)31,I32a,普通工字钢截面I(7)39,HN300X150,H----柱布置截面号,铰接信息,截面布置角度-----面号信息置角度面号信息置角度(1)130(2)130(3)330(4)330(5)330(6)330(7)330(8)330(9)330(10)130(11)330(12)130(13)330----梁布置截面号,铰接信息,截面布置角度-----面号信息置角度面号信息置角度(1)5302、标准截面特性10.109500.109500.22793E-040.22793E-040.40150E-0220.000000.000000.00000E+000.00000E+000.00000E+0030.017000.017000.19030E-060.19030E-060.49800E-0340.050000.100000.23690E-040.15790E-050.35550E-0250.058000.125000.50170E-040.28040E-050.48510E-0260.000000.000000.00000E+000.00000E+000.00000E+0070.075000.150000.68290E-040.50720E-050.46780E-02ixiyW1xW2xW1yW2y10.75346E-010.75346E-010.20816E-030.20816E-030.20816E-030.20816E-0320.00000E+000.00000E+000.00000E+000.00000E+000.00000E+000.00000E+0030.19548E-010.19548E-010.11220E-040.41300E-050.11220E-040.41300E-0540.81600E-010.21100E-010.23690E-030.23690E-030.31600E-040.31600E-0450.10170E+000.24000E-010.40140E-030.40140E-030.48400E-040.48400E-0460.00000E+000.00000E+000.00000E+000.00000E+000.00000E+000.00000E+0070.12080E+000.32900E-010.45530E-030.45530E-030.67600E-040.67600E-04恒荷载计算...节点荷载:节点号弯矩垂直力水平力0柱荷载:柱号荷载类型荷载值荷载参数1荷载参数20112212470.000.50470.002.50----恒荷载标准值作用计算结果-------柱内力---柱号MNVMNV10.0071.030.000.00-69.890.0020.0071.030.000.00-69.890.0030.003.35-0.040.00-3.28-0.0440.003.350.040.00-3.280.0450.003.21-0.040.00-3.14-0.0460.00-4.490.070.004.490.0770.003.210.040.00-3.140.0480.003.22-0.040.00-3.15-0.0490.003.220.040.00-3.140.04100.0069.720.000.00-68.590.00110.003.08-0.040.00-3.00-0.04120.0069.720.000.00-68.590.00130.003.070.040.00-3.000.04---梁内力---MNVMNV10.00-2.1570.690.002.1570.69---恒荷载作用下的节点位移(mm)---节点号.XY10.00.12-0.10.330.10.340.00.450.00.560.00.5活荷载计算...节点荷载:节点号弯矩垂直力水平力0柱荷载:柱号荷载类型荷载值荷载参数1荷载参数2011220---活荷载标准值作用下的节点位移(mm)---节点号.XY10.00.020.00.030.00.040.00.050.00.060.00.0荷载效应组合计算...-----荷载效应组合及强度、稳定、配筋计算------1=17;布置角度=0;计算长度:Lx=3.00,Ly=3.00;长细比:λx=39.8,λy=39.8构件长度=3.00;计算长度系数:Ux=1.00Uy=1.00截面参数:D=219T=6构件钢号:Q235GB50017-2003柱下端柱上端10.0085.230.000.00-83.870.0020.0071.030.000.00-69.890.0030.0085.230.000.00-83.870.0040.0071.030.000.00-69.890.0050.0085.230.000.00-83.870.0060.0071.030.000.00-69.890.0070.0095.890.000.00-94.360.0080.0085.230.000.00-83.870.0090.0071.030.000.00-69.890.00100.0095.890.000.00-94.360.00110.0085.230.000.00-83.870.00120.0071.030.000.00-69.890.00130.0095.890.000.00-94.360.00140.0085.230.000.00-83.870.00150.0071.030.000.00-69.890.00160.0095.890.000.00-94.360.00170.0085.230.000.00-83.870.00180.0071.030.000.00-69.890.00190.0085.230.000.00-83.870.00200.0071.030.000.00-69.890.00210.0085.230.000.00-83.870.00220.0071.030.000.00-69.890.00230.0085.230.000.00-83.870.00240.0071.030.000.00-69.890.00250.0085.230.000.00-83.870.00260.0071.030.000.00-69.890.00270.0085.230.000.00-83.870.00280.0071.030.000.00-69.890.00290.0085.230.000.00-83.870.00300.0071.030.000.00-69.890.00310.0085.230.000.00-83.870.00320.0071.030.000.00-69.890.00330.0085.230.000.00-83.870.00340.0071.030.000.00-69.890.00350.0085.230.000.00-83.870.00360.0071.030.000.00-69.890.00370.0085.230.000.00-83.870.00380.0071.030.000.00-69.890.00390.0085.230.000.00-83.870.00400.0071.030.000.00-69.890.00410.0085.230.000.00-83.870.00420.0071.030.000.00-69.890.00430.0085.230.000.00-83.870.00440.0071.030.000.00-69.890.00450.0085.230.000.00-83.870.00460.0071.030.000.00-69.890.00470.0085.230.000.00-83.870.00480.0071.030.000.00-69.890.00强度计算最大应力对应组合号:7,M=0.00,N=95.89,M=0.00,N=-94.36(N/mm*mm)=28.10强度计算最大应力比=0.131(N/mm*mm)=26.55平面内稳定计算最大应力比=0.124(N/mm*mm)=26.55平面外稳定计算最大应力比=0.124腹板容许高厚比计算对应组合号:1,M=0.00,N=85.23,M=0.00,N=-83.87[D/T]=100.00强度计算最大应力<f=215.00<f=215.00<f=215.00D/T=36.50<[D/T]=100.00λ=40.≤[λ]=200λ=40.≤[λ]=200构件重量(Kg)=94.55-2=17;布置角度=0;计算长度:Lx=3.00,Ly=3.00;长细比:λx=39.8,λy=39.8构件长度=3.00;计算长度系数:Ux=1.00Uy=1.00截面参数:D=219T=6构件钢号:Q235GB50017-2003柱下端柱上端10.0085.230.000.00-83.870.0020.0071.030.000.00-69.890.0030.0085.230.000.00-83.870.0040.0071.030.000.00-69.890.0050.0085.230.000.00-83.870.0060.0071.030.000.00-69.890.0070.0095.890.000.00-94.360.0080.0085.230.000.00-83.870.0090.0071.030.000.00-69.890.00100.0095.890.000.00-94.360.00110.0085.230.000.00-83.870.00120.0071.030.000.00-69.890.00130.0095.890.000.00-94.360.00140.0085.230.000.00-83.870.00150.0071.030.000.00-69.890.00160.0095.890.000.00-94.360.00170.0085.230.000.00-83.870.00180.0071.030.000.00-69.890.00190.0085.230.000.00-83.870.00200.0071.030.000.00-69.890.00210.0085.230.000.00-83.870.00220.0071.030.000.00-69.890.00230.0085.230.000.00-83.870.00240.0071.030.000.00-69.890.00250.0085.230.000.00-83.870.00260.0071.030.000.00-69.890.00270.0085.230.000.00-83.870.00280.0071.030.000.00-69.890.00290.0085.230.000.00-83.870.00300.0071.030.000.00-69.890.00310.0085.230.000.00-83.870.00320.0071.030.000.00-69.890.00330.0085.230.000.00-83.870.00340.0071.030.000.00-69.890.00350.0085.230.000.00-83.870.00360.0071.030.000.00-69.890.00370.0085.230.000.00-83.870.00380.0071.030.000.00-69.890.00390.0085.230.000.00-83.870.00400.0071.030.000.00-69.890.00410.0085.230.000.00-83.870.00420.0071.030.000.00-69.890.00430.0085.230.000.00-83.870.00440.0071.030.000.00-69.890.00450.0085.230.000.00-83.870.00460.0071.030.000.00-69.890.00470.0085.230.000.00-83.870.00480.0071.030.000.00-69.890.00强度计算最大应力对应组合号:7,M=0.00,N=95.89,M=0.00,N=-94.36(N/mm*mm)=28.10强度计算最大应力比=0.131(N/mm*mm)=26.55平面内稳定计算最大应力比=0.124(N/mm*mm)=26.55平面外稳定计算最大应力比=0.124腹板容许高厚比计算对应组合号:1,M=0.00,N=85.23,M=0.00,N=-83.87[D/T]=100.00强度计算最大应力<f=215.00<f=215.00<f=215.00D/T=36.50<[D/T]=100.00λ=40.≤[λ]=200λ=40.≤[λ]=200构件重量(Kg)=94.55-3=33;布置角度=0;计算长度:Lx=2.12,Ly=2.12;长细比:λx=168.4,λy=108.5构件长度=2.12;计算长度系数:Ux=1.00Uy=1.00抗震等级:不考虑抗震截面参数:L63x4热轧等边角钢构件钢号:Q235GB50017-2003柱下端柱上端10.004.02-0.040.00-3.94-0.0420.003.35-0.040.00-3.28-0.0430.004.02-0.040.00-3.94-0.0440.003.35-0.040.00-3.28-0.0450.004.02-0.040.00-3.94-0.0460.003.35-0.040.00-3.28-0.0470.004.53-0.050.00-4.43-0.0580.004.02-0.040.00-3.94-0.0490.003.35-0.040.00-3.28-0.04100.004.53-0.050.00-4.43-0.05110.004.02-0.040.00-3.94-0.04120.003.35-0.040.00-3.28-0.04130.004.53-0.050.00-4.43-0.05140.004.02-0.040.00-3.94-0.04150.003.35-0.040.00-3.28-0.04160.004.53-0.050.00-4.43-0.05170.004.02-0.040.00-3.94-0.04180.003.35-0.040.00-3.28-0.04190.004.02-0.040.00-3.94-0.04200.003.35-0.040.00-3.28-0.04210.004.02-0.040.00-3.94-0.04220.003.35-0.040.00-3.28-0.04230.004.02-0.040.00-3.94-0.04240.003.35-0.040.00-3.28-0.04250.004.02-0.040.00-3.94-0.04260.003.35-0.040.00-3.28-0.04270.004.02-0.040.00-3.94-0.04280.003.35-0.040.00-3.28-0.04290.004.02-0.040.00-3.94-0.04300.003.35-0.040.00-3.28-0.04310.004.02-0.040.00-3.94-0.04320.003.35-0.040.00-3.28-0.04330.004.02-0.040.00-3.94-0.04340.003.35-0.040.00-3.28-0.04350.004.02-0.040.00-3.94-0.04360.003.35-0.040.00-3.28-0.04370.004.02-0.040.00-3.94-0.04380.003.35-0.040.00-3.28-0.04390.004.02-0.040.00-3.94-0.04400.003.35-0.040.00-3.28-0.04410.004.02-0.040.00-3.94-0.04420.003.35-0.040.00-3.28-0.04430.004.02-0.040.00-3.94-0.04440.003.35-0.040.00-3.28-0.04450.004.02-0.040.00-3.94-0.04460.003.35-0.040.00-3.28-0.04470.004.02-0.040.00-3.94-0.04480.003.35-0.040.00-3.28-0.04强度计算最大应力对应组合号:7,M=0.00,N=4.53,M=0.00,N=-4.43(N/mm*mm)=12.58强度计算最大应力比=0.058(N/mm*mm)=42.17平面内稳定计算最大应力比=0.196(N/mm*mm)=21.24平面外稳定计算最大应力比=0.099强度计算最大应力<f=215.00平面内稳定计算最大应力<f=215.00平面外稳定计算最大应力<f=215.00λ=168.≤[λ]=200λ=109.≤[λ]=200构件重量(Kg)=8.29-4=33;布置角度=0;计算长度:Lx=2.12,Ly=2.12;长细比:λx=168.4,λy=108.5构件长度=2.12;计算长度系数:Ux=1.00Uy=1.00抗震等级:不考虑抗震截面参数:L63x4热轧等边角钢构件钢号:Q235GB50017-2003柱下端柱上端10.004.020.040.00-3.940.0420.003.350.040.00-3.280.0430.004.020.040.00-3.940.0440.003.350.040.00-3.280.0450.004.020.040.00-3.940.0460.003.350.040.00-3.280.0470.004.520.050.00-4.430.0580.004.020.040.00-3.940.0490.003.350.040.00-3.280.04100.004.520.050.00-4.430.05110.004.020.040.00-3.940.04120.003.350.040.00-3.280.04130.004.520.050.00-4.430.05140.004.020.040.00-3.940.04150.003.350.040.00-3.280.04160.004.520.050.00-4.430.05170.004.020.040.00-3.940.04180.003.350.040.00-3.280.04190.004.020.040.00-3.940.04200.003.350.040.00-3.280.04210.004.020.040.00-3.940.04220.003.350.040.00-3.280.04230.004.020.040.00-3.940.04240.003.350.040.00-3.280.04250.004.020.040.00-3.940.04260.003.350.040.00-3.280.04270.004.020.040.00-3.940.04280.003.350.040.00-3.280.04290.004.020.040.00-3.940.04300.003.350.040.00-3.280.04310.004.020.040.00-3.940.04320.003.350.040.00-3.280.04330.004.020.040.00-3.940.04340.003.350.040.00-3.280.04350.004.020.040.00-3.940.04360.003.350.040.00-3.280.04370.004.020.040.00-3.940.04380.003.350.040.00-3.280.04390.004.020.040.00-3.940.04400.003.350.040.00-3.280.04410.004.020.040.00-3.940.04420.003.350.040.00-3.280.04430.004.020.040.00-3.940.04440.003.350.040.00-3.280.04450.004.020.040.00-3.940.04460.003.350.040.00-3.280.04470.004.020.040.00-3.940.04480.003.350.040.00-3.280.04强度计算最大应力对应组合号:7,M=0.00,N=4.52,M=0.00,N=-4.43(N/mm*mm)=12.58强度计算最大应力比=0.058(N/mm*mm)=42.16平面内稳定计算最大应力比=0.196(N/mm*mm)=21.24平面外稳定计算最大应力比=0.099强度计算最大应力<f=215.00平面内稳定计算最大应力<f=215.00平面外稳定计算最大应力<f=215.00λ=168.≤[λ]=200λ=109.≤[λ]=200构件重量(Kg)=8.29-5=33;布置角度=0;计算长度:Lx=2.12,Ly=2.12;长细比:λx=168.4,λy=108.5构件长度=2.12;计算长度系数:Ux=1.00Uy=1.00抗震等级:不考虑抗震截面参数:L63x4热轧等边角钢构件钢号:Q235GB50017-2003柱下端柱上端10.003.85-0.040.00-3.77-0.0420.003.21-0.040.00-3.14-0.0430.003.85-0.040.00-3.77-0.0440.003.21-0.040.00-3.14-0.0450.003.85-0.040.00-3.77-0.0460.003.21-0.040.00-3.14-0.0470.004.34-0.050.00-4.24-0.0580.003.85-0.040.00-3.77-0.0490.003.21-0.040.00-3.14-0.04100.004.34-0.050.00-4.24-0.05110.003.85-0.040.00-3.77-0.04120.003.21-0.040.00-3.14-0.04130.004.34-0.050.00-4.24-0.05140.003.85-0.040.00-3.77-0.04150.003.21-0.040.00-3.14-0.04160.004.34-0.050.00-4.24-0.05170.003.85-0.040.00-3.77-0.04180.003.21-0.040.00-3.14-0.04190.003.85-0.040.00-3.77-0.04200.003.21-0.040.00-3.14-0.04210.003.85-0.040.00-3.77-0.04220.003.21-0.040.00-3.14-0.04230.003.85-0.040.00-3.77-0.04240.003.21-0.040.00-3.14-0.04250.003.85-0.040.00-3.77-0.04260.003.21-0.040.00-3.14-0.04270.003.85-0.040.00-3.77-0.04280.003.21-0.040.00-3.14-0.04290.003.85-0.040.00-3.77-0.04300.003.21-0.040.00-3.14-0.04310.003.85-0.040.00-3.77-0.04320.003.21-0.040.00-3.14-0.04330.003.85-0.040.00-3.77-0.04340.003.21-0.040.00-3.14-0.04350.003.85-0.040.00-3.77-0.04360.003.21-0.040.00-3.14-0.04370.003.85-0.040.00-3.77-0.04380.003.21-0.040.00-3.14-0.04390.003.85-0.040.00-3.77-0.04400.003.21-0.040.00-3.14-0.04410.003.85-0.040.00-3.77-0.04420.003.21-0.040.00-3.14-0.04430.003.85-0.040.00-3.77-0.04440.003.21-0.040.00-3.14-0.04450.003.85-0.040.00-3.77-0.04460.003.21-0.040.00-3.14-0.04470.003.85-0.040.00-3.77-0.04480.003.21-0.040.00-3.14-0.04强度计算最大应力对应组合号:7,M=0.00,N=4.34,M=0.00,N=-4.24(N/mm*mm)=12.05强度计算最大应力比=0.056(N/mm*mm)=40.40平面内稳定计算最大应力比=0.188(N/mm*mm)=20.35平面外稳定计算最大应力比=0.095强度计算最大应力<f=215.00平面内稳定计算最大应力<f=215.00平面外稳定计算最大应力<f=215.00λ=168.≤[λ]=200λ=109.≤[λ]=200构件重量(Kg)=8.29-6=33;布置角度=0;计算长度:Lx=3.00,Ly=3.00;长细比:λx=238.1,λy=153.5构件长度=3.00;计算长度系数:Ux=1.00Uy=1.00抗震等级:不考虑抗震截面参数:L63x4热轧等边角钢构件钢号:Q235GB50017-2003柱下端柱上端10.00-5.390.080.005.390.0820.00-4.490.070.004.490.0730.00-5.390.080.005.390.0840.00-4.490.070.004.490.0750.00-5.390.080.005.390.0860.00-4.490.070.004.490.0770.00-6.070.090.006.070.0980.00-5.390.080.005.390.0890.00-4.490.070.004.490.07100.00-6.070.090.006.070.09110.00-5.390.080.005.390.08120.00-4.490.070.004.490.07130.00-6.070.090.006.070.09140.00-5.390.080.005.390.08150.00-4.490.070.004.490.07160.00-6.070.090.006.070.09170.00-5.390.080.005.390.08180.00-4.490.070.004.490.07190.00-5.390.080.005.390.08200.00-4.490.070.004.490.07210.00-5.390.080.005.390.08220.00-4.490.070.004.490.07230.00-5.390.080.005.390.08240.00-4.490.070.004.490.07250.00-5.390.080.005.390.08260.00-4.490.070.004.490.07270.00-5.390.080.005.390.08280.00-4.490.070.004.490.07290.00-5.390.080.005.390.08300.00-4.490.070.004.490.07310.00-5.390.080.005.390.08320.00-4.490.070.004.490.07330.00-5.390.080.005.390.08340.00-4.490.070.004.490.07350.00-5.390.080.005.390.08360.00-4.490.070.004.490.07370.00-5.390.080.005.390.08380.00-4.490.070.004.490.07390.00-5.390.080.005.390.08400.00-4.490.070.004.490.07410.00-5.390.080.005.390.08420.00-4.490.070.004.490.07430.00-5.390.080.005.390.08440.00-4.490.070.004.490.07450.00-5.390.080.005.390.08460.00-4.490.070.004.490.07470.00-5.390.080.005.390.08480.00-4.490.070.004.490.07强度计算最大应力对应组合号:7,M=0.00,N=-6.07,M=0.00,N=6.07(N/mm*mm)=16.86强度计算最大应力比=0.078强度计算最大应力<f=215.00λ=238.≤[λ]=300λ=153.≤[λ]=300构件重量(Kg)=11.73-7=33;布置角度=0;计算长度:Lx=2.12,Ly=2.12;长细比:λx=168.4,λy=108.5构件长度=2.12;计算长度系数:Ux=1.00Uy=1.00抗震等级:不考虑抗震截面参数:L63x4热轧等边角钢构件钢号:Q235GB50017-2003柱下端柱上端10.003.850.040.00-3.770.0420.003.210.040.00-3.140.0430.003.850.040.00-3.770.0440.003.210.040.00-3.140.0450.003.850.040.00-3.770.0460.003.210.040.00-3.140.0470.004.330.050.00-4.240.0580.003.850.040.00-3.770.0490.003.210.040.00-3.140.04100.004.330.050.00-4.240.05110.003.850.040.00-3.770.04120.003.210.040.00-3.140.04130.004.330.050.00-4.240.05140.003.850.040.00-3.770.04150.003.210.040.00-3.140.04160.004.330.050.00-4.240.05170.003.850.040.00-3.770.04180.003.210.040.00-3.140.04190.003.850.040.00-3.770.04200.003.210.040.00-3.140.04210.003.850.040.00-3.770.04220.003.210.040.00-3.140.04230.003.850.040.00-3.770.04240.003.210.040.00-3.140.04250.003.850.040.00-3.770.04260.003.210.040.00-3.140.04270.003.850.040.00-3.770.04280.003.210.040.00-3.140.04290.003.850.040.00-3.770.04300.003.210.040.00-3.140.04310.003.850.040.00-3.770.04320.003.210.040.00-3.140.04330.003.850.040.00-3.770.04340.003.210.040.00-3.140.04350.003.850.040.00-3.770.04360.003.210.040.00-3.140.04370.003.850.040.00-3.770.04380.003.210.040.00-3.140.04390.003.850.040.00-3.770.04400.003.210.040.00-3.140.04410.003.850.040.00-3.770.04420.003.210.040.00-3.140.04430.003.850.040.00-3.770.04440.003.210.040.00-3.140.04450.003.850.040.00-3.770.04460.003.210.040.00-3.140.04470.003.850.040.00-3.770.04480.003.210.040.00-3.140.04强度计算最大应力对应组合号:7,M=0.00,N=4.33,M=0.00,N=-4.24(N/mm*mm)=12.05强度计算最大应力比=0.056(N/mm*mm)=40.39平面内稳定计算最大应力比=0.188(N/mm*mm)=20.35平面外稳定计算最大应力比=0.095强度计算最大应力<f=215.00平面内稳定计算最大应力<f=215.00平面外稳定计算最大应力<f=215.00λ=168.≤[λ]=200λ=109.≤[λ]=200构件重量(Kg)=8.29-8=33;布置角度=0;计算长度:Lx=2.12,Ly=2.12;长细比:λx=168.4,λy=108.5构件长度=2.12;计算长度系数:Ux=1.00Uy=1.00抗震等级:不考虑抗震截面参数:L63x4热轧等边角钢构件钢号:Q235GB50017-2003柱下端柱上端10.003.86-0.040.00-3.77-0.0420.003.22-0.040.00-3.15-0.0430.003.86-0.040.00-3.77-0.0440.003.22-0.040.00-3.15-0.0450.003.86-0.040.00-3.77-0.0460.003.22-0.040.00-3.15-0.0470.004.34-0.050.00-4.25-0.0580.003.86-0.040.00-3.77-0.0490.003.22-0.040.00-3.15-0.04100.004.34-0.050.00-4.25-0.05110.003.86-0.040.00-3.77-0.04120.003.22-0.040.00-3.15-0.04130.004.34-0.050.00-4.25-0.05140.003.86-0.040.00-3.77-0.04150.003.22-0.040.00-3.15-0.04160.004.34-0.050.00-4.25-0.05170.003.86-0.040.00-3.77-0.04180.003.22-0.040.00-3.15-0.04190.003.86-0.040.00-3.77-0.04200.003.22-0.040.00-3.15-0.04210.003.86-0.040.00-3.77-0.04220.003.22-0.040.00-3.15-0.04230.003.86-0.040.00-3.77-0.04240.003.22-0.040.00-3.15-0.04250.003.86-0.040.00-3.77-0.04260.003.22-0.040.00-3.15-0.04270.003.86-0.040.00-3.77-0.04280.003.22-0.040.00-3.15-0.04290.003.86-0.040.00-3.77-0.04300.003.22-0.040.00-3.15-0.04310.003.86-0.040.00-3.77-0.04320.003.22-0.040.00-3.15-0.04330.003.86-0.040.00-3.77-0.04340.003.22-0.040.00-3.15-0.04350.003.86-0.040.00-3.77-0.04360.003.22-0.040.00-3.15-0.04370.003.86-0.040.00-3.77-0.04380.003.22-0.040.00-3.15-0.04390.003.86-0.040.00-3.77-0.04400.003.22-0.040.00-3.15-0.04410.003.86-0.040.00-3.77-0.04420.003.22-0.040.00-3.15-0.04430.003.86-0.040.00-3.77-0.04440.003.22-0.040.00-3.15-0.04450.003.86-0.040.00-3.77-0.04460.003.22-0.040.00-3.15-0.04470.003.86-0.040.00-3.77-0.04480.003.22-0.040.00-3.15-0.04强度计算最大应力对应组合号:7,M=0.00,N=4.34,M=0.00,N=-4.25(N/mm*mm)=12.07强度计算最大应力比=0.056(N/mm*mm)=40.45平面内稳定计算最大应力比=0.188(N/mm*mm)=20.38平面外稳定计算最大应力比=0.095强度计算最大应力<f=215.00平面内稳定计算最大应力<f=215.00平面外稳定计算最大应力<f=215.00λ=168.≤[λ]=200λ=109.≤[λ]=200构件重量(Kg)=8.29-9=33;布置角度=0;计算长度:Lx=2.12,Ly=2.12;长细比:λx=168.4,λy=108.5构件长度=2.12;计算长度系数:Ux=1.00Uy=1.00抗震等级:不考虑抗震截面参数:L63x4热轧等边角钢构件钢号:Q235GB50017-2003柱下端柱上端10.003.860.040.00-3.770.0420.003.220.040.00-3.140.0430.003.860.040.00-3.770.0440.003.220.040.00-3.140.0450.003.860.040.00-3.770.0460.003.220.040.00-3.140.0470.004.340.050.00-4.250.0580.003.860.040.00-3.770.0490.003.220.040.00-3.140.04100.004.340.050.00-4.250.05110.003.860.040.00-3.770.04120.003.220.040.00-3.140.04130.004.340.050.00-4.250.05140.003.860.040.00-3.770.04150.003.220.040.00-3.140.04160.004.340.050.00-4.250.05170.003.860.040.00-3.770.04180.003.220.040.00-3.140.04190.003.860.040.00-3.770.04200.003.220.040.00-3.140.04210.003.860.040.00-3.770.04220.003.220.040.00-3.140.04230.003.860.040.00-3.770.04240.003.220.040.00-3.140.04250.003.860.040.00-3.770.04260.003.220.040.00-3.140.04270.003.860.040.00-3.770.04280.003.220.040.00-3.140.04290.003.860.040.00-3.770.04300.003.220.040.00-3.140.04310.003.860.040.00-3.770.04320.003.220.040.00-3.140.04330.003.860.040.00-3.770.04340.003.220.040.00-3.140.04350.003.860.040.00-3.770.04360.003.220.040.00-3.140.04370.003.860.040.00-3.770.04380.003.220.040.00-3.140.04390.003.860.040.00-3.770.04400.003.220.040.00-3.140.04410.003.860.040.00-3.770.04420.003.220.040.00-3.140.04430.003.860.040.00-3.770.04440.003.220.040.00-3.140.04450.003.860.040.00-3.770.04460.003.220.040.00-3.140.04470.003.860.040.00-3.770.04480.003.220.040.00-3.140.04强度计算最大应力对应组合号:7,M=0.00,N=4.34,M=0.00,N=-4.25(
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 出租场所安全管理制度
- 地下自动车行地道施工方案
- 卫生院新冠消毒实施方案
- 搭建平台运营方案
- 社群建设策划方案范文
- 拼接屏安装施工组织设计方案
- 海洋工程深潜施工方案
- 城市涵洞改造方案范本
- 小学二年级数学下册应用题专项练习题(每日一练共11份)
- 小学劳动四年级上册《标识牌大揭秘》教学设计
- 2026医院不合理收费行为自查自纠报告
- YY/T 1997-2026体外诊断试剂临床试验生物样本管理要求
- Unit 6 Crossing Cultures(大单元教学设计)英语新教材人教版八年级下册
- GB/Z 177.4-2026人工智能终端智能化分级第4部分:微型计算机
- 2026年甘肃省酒泉市初二学业水平地理生物会考真题试卷+解析及答案
- 2026安宁疗护患者人文关怀专家共识(2025版)
- 2026低空经济产业园区规划设计方案
- 2026年上海市浦东新区社区工作者招聘笔试参考试题及答案解析
- 2025年四川省初二地生会考考试题库(附含答案)
- 2026年区划系统版行政区划调整与城市规划知识试题
- 2026届江苏省扬州市中考四模数学试题含解析
评论
0/150
提交评论