ExecutiveBriefing

PREVENTINGMULTIMILLION

DOLLARDATACENTRELOSSESTHROUGHREPORTING

Thisreportassessestheimpactsofdelaysindatacentreconstructiononoperationalfinancialmetrics,budgetandinternalrateofreturn,andexaminestheroleofeffectivereportinginensuringon-timedelivery.

JonasTopp-Mugglestone,Consultant|jonas.topp-mugglestone@|March2025

PREVENTINGMULTIMILLIONDOLLARDATACENTRELOSSESTHROUGHREPORTING|MARCH2025

©STLPartnersEXECUTIVEBRIEFING2

Foreword

Methodology

Thisreportpresentsinsightsfromarecentresearchprogramme,inwhichweconductedin-depthinterviewswith14professionalsinthedatacentreindustry-fromprojectmanagerstoC-levelexecutives.Theobjectivewastouncoverthecriticalchallengesandpainpointsshapingdatacentreconstructionandprojectmanagementprocesses.

Intervieweeprofiles

Editorialindependence

ThisreporthasbeenpreparedbyindependentconsultingandresearchcompanySTLPartnersandwascommissionedbyForesightWorks.

STLPartnersmaintainsstricteditorialindependence.Mentionsorallusionstocompaniesorproductsinthisdocumentareintendedasillustrationsofmarketevolutionandarenotincludedasendorsementsorproduct/servicerecommendations.

PREVENTINGMULTIMILLIONDOLLARDATACENTRELOSSESTHROUGHREPORTING|MARCH2025

©STLPartnersEXECUTIVEBRIEFING3

Thetruecostofdelaysindatacentreconstruction

Globaldatacentredemandissurging,withcapacityprojectedtogrowata17%compoundannualgrowthrate(CAGR)between2025and2030,reaching100GWby2030

1.

Deliveringthiscapacityisincreasinglychallengingduetorisingconstructioncomplexity,supplychaindisruptionsandtighteningregulatoryframeworks.Inthisenvironment,preventingdelaysiscriticaltosafeguardingfinancialreturnsondatacentreprojects,yetthegrowingscaleandcomplexityofprojectsmakeon-timedeliveryharderthanevertoachieve.

AccordingtoSTLPartners’research,foreverymonthofdelayinthecompletionofadatacentre,thedeveloperincursUSD14.2millionoflostrevenue,costoverrunsandcontractualpenalties.Athree-monthdelaycanresultinanindicativeinternalrateofreturn(IRR)decreasefrom17.1%to12.6%acrossaten-yeartimeframe.Thisisbeforefactoringinindirectcostssuchasthestrainedstakeholderrelationshipsandthereputationalimpacts.

Customersofdatacentredevelopers,particularlyhyperscalersandotheranchortenants(e.g.,largeenterprises),operateontightschedules.Thismeansthatanydisruptioninfacilityavailabilitycanpushthesecustomerstowardcompetitors.Atthesametime,capital,equipmentandlabourcostsaccumulaterapidly,increasingthedevelopers’financialburdenfromevenminoroverrunsandlimitingtheavailabilityoftheconstructionteamtoworkonnewprojectsinthepipeline.

Toaddressthesechallenges,datacentredevelopersmust:

•Planfordisruption:Useproactivescenarioplanningandstronggovernancetomaketheprojectplanasresilientasthesiteitself.

•Implementstandardised,real-timereporting:Equipconstructionmanagerswithliveinsightstoaddressrisksearly.Integratedreportingenablestimelyescalation,reducingoverrunsand

improvingcontrol.

•Proactivelymanagerisks:Defineandcommunicateaclearriskmatrix,escalationpathandretrospectiveprocesstoenablerapidissueresolutionandcontinuousprocessimprovement.

•Deploysmartertools:Adoptdigitalsolutions,integratingadvancedtechsuchasAI,andprioritiseinteroperabilitytoenhancedeliveryefficiency.

1Source:

CitiResearch

PREVENTINGMULTIMILLIONDOLLARDATACENTRELOSSESTHROUGHREPORTING|MARCH2025

©STLPartnersEXECUTIVEBRIEFING4

Tableofcontents

Foreword 2

Methodology 2

Intervieweeprofiles 2

Editorialindependence 2

Thetruecostofdelaysindatacentreconstruction 3

Countingthepriceofdelay 5

OverallimpactonIRR 8

Beyondthebalancesheet:Theindirectcostsofdatacentredelays 8

Successthroughcontrol:Howeffectiveprojectmanagementandreportingeliminatedelays 10

Corereportingchallengesindatacentreconstruction 11

Complexstakeholdermanagement:Thecoordinationbottleneck 11

Thedataintegritychallenge:Inconsistentreportingandtheburdenofmanualvalidation 12

Theresourceconstraintschallenge:Labourshortagesandsupplychainuncertainty 13

Theregulatoryandregionalcomplexitychallenge:Navigatingcompliance,certificationand

culturalbarriers 14

Optimisingreportingandriskmanagement:Bestpracticestopreventdelays 15

Planfordisruption:Expecttheunexpected 15

Standardisecustomisablegovernance:Createclearreportingandcommunicationstructures.16

Proactiveriskmanagement:Identify,trackandmitigateearly 17

Smartertools:Usetechnologytoenhancevisibilityanddecision-making 17

Conclusion 19

PREVENTINGMULTIMILLIONDOLLARDATACENTRELOSSESTHROUGHREPORTING|MARCH2025

©STLPartnersEXECUTIVEBRIEFING5

Countingthepriceofdelay

Thisreportexploresthetruecostofdelaysindatacentreconstruction,gatheringdatafrominterviewswith14datacentredevelopmentprofessionals,plussecondarysources,andexaminesbothdirectfinancialimplicationsandindirectconsequencesofdelays.Moreimportantly,itoutlinespracticalstrategiestomitigatetheserisks,focusingonstructuredgovernance,proactiveriskmanagementandadvancedreportingframeworkstominimiseunforeseenissues,accelerateissueresolutionandensureon-timedelivery.

Figure1:Thetruecostofaone-monthdelayofanindicativedatacentreproject

Source:STLPartners,estimationcalculatedfromindustryinterviewscompletedinJanuary2025

OurresearchshowsthateverymonthofdelayinthecompletiondateofadatacentreconstructionprojectcoststhedeveloperanestimatedUSD14.2million,assumingtheygoontooperatethefacilitypost-completion.

Asshownin

Figure1,

thisestimationcoverslostrevenue,labourcostoverrunsandservice-levelagreement(SLA)fines-itislikelyaconservativeestimateasnoconsiderationisgiventoadditionalcosts,suchasconstructionequipment,equipmentstorageandcostofcapital.Thiscalculationassumesasingle-tenant60MWdatacentrefacilityintheUS.

Breakdownofeachcomponentofthisestimationisasfollows:

PREVENTINGMULTIMILLIONDOLLARDATACENTRELOSSESTHROUGHREPORTING|MARCH2025

©STLPartnersEXECUTIVEBRIEFING6

Revenueloss

Themostimmediateandquantifiableimpactcomesfromdelayedrevenuerealisation.Revenuelossindatacentreconstructionoccurswhendelayspreventthefacilityfrombecomingoperationalandgeneratingincomeasplanned.Customercontractscanstartfromkeymilestonedates,rangingfromprebuildforhyperscalersthroughtoshellandcorehandoverforlargecolocationcustomers,meaningdelaysrepresentpermanentlostrevenuethatcanneverberecovered,impactingtheproject’sreturnoninvestment(ROI)andlong-termfinancialviability.IntheUS,wheretypicalleaseratesfordatacentrespacehoveraroundUSD180/kWpermonthinkeyareas,a60MWfacilityfacesrevenuelossesofUSD10.8millionfromeverymonththatthecompletionisdelayed(assumingsingle-tenantarchitecturewithimmediatesiteutilisationof100%)

.2

Labourcostoverruns

Constructiondelaysleadtosignificantlabourcostoverruns,ascontractors,projectmanagersandengineersmustremainengagedbeyondschedule-thoughifthedelayiscontractor-driven,theymaybearthesecosts.Manycontractsrequireminimumlabourcommitments,forcingpaymentevenifworkstalls.Separately,datacentretechniciansandsalesteamshiredtorunthesiteandmanagecustomersmuststillbepaidfromtheplannedstartdate.Fora60MWfacility,withanassumptionof300workingcontractorsonsitealongsideprojectmanagementoverhead,workingata50%marginabovewages,thiscomestoamonthlyrunrateofUSD1,947,000.Inaddition,60datacentretechnicianswillbeonstandbyforgoinglive,conformingtoindustrystandardsofroughlyoneon-sitetechnicianperMWoffacilitycapacity,atatotalofUSD255,000permonth.ThesecombinedcostscanreachUSD2.2millionpermonth

.3

Afurtherchallengeariseswithseasonallabouravailability,asdelayscanalsodisruptworkforceavailability,potentiallyfurtherextendingprojecttimelines.Manyskilledworkersinvolvedindatacentreconstructionoperateonshort-termcontracts,movingbetweenprojects.Ifadelaypushespasttheiravailabilitywindow,theymayleaveforotherjobs,depletingthelabourpoolatacriticalphase.Thisforcesprojectmanagerstoscrambleforreplacements,oftenleadingtolabourshortages,slowerexecutionandlossofspecialisedexpertise.Theresultingdelayscanfurthermisalignschedules,causingadditionalattritionandescalatingtheriskofprolongedoverruns.

SLAfines

DatacentredevelopersfrequentlysignSLAswithcustomers,committingtostrictprojectdeliverytimelinesthatensureinfrastructureisavailablewhenpromised.Theseagreementsareespeciallyrigidforhyperscaletenantswhichoperateonpreciseexpansionschedulesandrelyonnewfacilitiestosupporttheirgrowingcustomerbases.SLAfinesdirectlyerodeprojectmarginsandsomeagreementshaveescalatingpenalties,makingextendeddelaysexponentiallycostlier.FinescommonlystartataroundUSD100,000perweekforenterprisetenantsandoftenexceedUSD300,000perweekforhyperscaletenants(USD1.2millionpermonth)

.4

2Source:

Statista

3Source:

USBureauofLaborStatistics-OccupationalEmploymentandWageStatistics

4Source:STLPartnersindependentresearch

PREVENTINGMULTIMILLIONDOLLARDATACENTRELOSSESTHROUGHREPORTING|MARCH2025

©STLPartnersEXECUTIVEBRIEFING7

Thefinancialimpactofdelaysextendsfarbeyondthesethreeimmediatelyquantifiablecosts,withalongtailofdirectcostswhichcanspiralintheeventofprolongeddelays.Theseinclude:

Costofcapital

Large-scaledatacentreprojectsaretypicallyfinancedwith30-40%equityand60-70%debt

,5

balancingriskandcapitalefficiency.Debtfinancingcommonlyusesrepaymentschedulesalignedtorevenuegenerationdates.Whendelaysoccur,organisationsincurunexpectedinterestpaymentsservicingthisloan,addingunplannedexpensesinastrainoncashflow.Thiscannecessitaterefinancingoralteringtermswhichincursbothanoverheadintherenegotiationaswellastightercontractualterms,suchashigherinterestratesoradditionalfees.Fora60MWfacility,thedebtburdencanbeupwardsofUSD360million,meaningthatevenservicingtheinterestforanadditionalmonthbeforeprincipalrepaymentstartscoststheprojectaroundUSD1.8million,dependingonfinancingterms(ourcalculationassumesa6%interestrate).Additionally,theprocurementofkeyequipmentmayneedtobetimedtocapitaliseonfavourableexchangerates,especiallyinmarketssubjecttocurrencyvolatility.Therefore,forCFOsandfinancedirectors,delaysresultinacomplexbalancingactofmanagingcashflow,renegotiatingtermsandmitigatingfinancialrisk,allwhileensuringthatstrategicobjectivesaremet.

Equipmentstorage

Equipmentstoragecostscanbecomeasignificantconcernacrossaproject’slifecycle,inparticularinthelead-uptokeyprojectmilestonessuchasthebuildingbecomingweathertight.Sensitivecomponents,suchasswitchesandservers,requirecontrolledenvironmentsfortemperature,humidityandairquality,tominimisedegradationandoptimisecomponentperformanceandlifespan.Thismeanstheirinstallationishighlydependentonheating,ventilationandairconditioning(HVAC)andadjacentinstallations.Giventhecurrentextendeddeliveryleadtimesforthistypeofhardware,constructiondelayscancreateaneedtotemporarilystoretheseitemsinspecificconditions,atshortnotice.Beyondtheimmediatecosts,prolongedstoragewilllikelyimpactthevaluederivedversusthedepreciationprofileoftheasset.Inextremecases,suchdelayscanleadtonewcomponentmodelsbeingreleasedbetweenprocurementandinstallationwhichcanimpactcustomerspecificationsandleadtoduplicationandredundancy.

Constructionequipment

Anotheroften-overlookedconsequenceistheextendedcostofleasedorrentedconstructionequipment,suchascranes,scaffoldingandheavymachinery.Manyoftheseassetsarecontractedonfixedrentalterms,meaningdelayspushtheseexpensesbeyondtheoriginallybudgetedperiod.Unlikelabourcosts,whichmaybescaledinslowperiods,rentalfeesaccumulateregardlessofusageandcanevenescalateincertaindelayscenarios.

5Source:

NortonRoseFulbright

PREVENTINGMULTIMILLIONDOLLARDATACENTRELOSSESTHROUGHREPORTING|MARCH2025

©STLPartnersEXECUTIVEBRIEFING8

“Privateequity-backedprojectsare

incrediblysensitivetotime.Theyneedto

becompletedwithintheirinvestment

window,andanydelayscausearipple

effectonexpectedreturns.”

Corporatedevelopmentdirector-UKdata

centreoperator

OverallimpactonIRR

Fordatacentrebuildssponsoredbyprivateequity(PE)andotherinstitutionalinvestors,maintainingahealthyIRRisthekeytoasuccessfulproject.However,justthreemonthsofdelaycanreducethisfigureforourindicative60MWsitefrom17.1%to12.6%,withasix-monthdelaycuttingthisfiguredrasticallytojust8.8%,thankstoacombinationoflostrevenue,costoverrunsandfinancingadjustments.

Figure2:DatacentredeliverydelayscandecimateIRR

Delaylength(months)

0

1

2

3

4

5

6

IRR

17.1%

15.5%

14.0%

12.6%

11.3%

10.0%

8.8%

Source:STLPartners

Beyondthebalancesheet:Theindirectcostsofdatacentredelays

Whilethedirectfinancialimpactofdelays,suchasrevenueloss,costoverrunsandSLAfinesalonearesubstantial,theindirectcostsareoftensignificantlydamagingaswell.Thesehiddencostsextend

PREVENTINGMULTIMILLIONDOLLARDATACENTRELOSSESTHROUGHREPORTING|MARCH2025

©STLPartnersEXECUTIVEBRIEFING9

beyondfinancialstatements,affectingcustomerrelationships,marketreputationandlong-termcompetitiveadvantage.Unlikedirectcostswhichcanbequantified,understoodandmitigated,indirectcostscanbesweptunderthecarpetasknownunknownsnotimpactingtheshort-termgoalsofaspecificindividual.However,theycanhavebroaderstrategicimplicationsthatmaytakeyearstofullymaterialise.

Reputationaldamage:Thelong-termtrustdeficit

Inthehigh-stakesworldofdatacentreconstruction,reliabilityandcredibilityareessential.Delaysnotonlycausefinancialstrainbutalsoerodetrustamongcustomers,partnersandinvestors.Justonedelayedprojectandsitehandovercanactasasignalforprospectivecustomers,impactingtheirdatacentredeveloperscoringacrossmetricssuchasscheduleadherenceandcostefficiency,thus

“Yourreputationsurvivesonthelastdata

centreyoubuild,sotheremustbegreat

caretakeninmakingsurethatyouare

tryingtoriskmitigateallthewaythrough.”

Chiefinvestmentofficer-UKdatacentre

operator

impactingtheirlikelihoodofsuccesswithfuturebids.Reputationisbuiltgraduallybutbrokeninstantly,especiallywithinthesmall-butgrowing-circlesofthedatacentreindustrywherevendorscoringsystemsplayacrucialroleindeterminingfuturecontractawards.Incompetitivemarkets,thislossofcredibilitycanbejustasdamagingasfinancialpenalties,asitinfluenceswhetheranoperatorisconsideredforfutureprojectsandexpansions,withahypothetical10%reductioninwinprobabilityofthenextcontractworthuptoUSD1millionperMW

6

inweightedpipelinereduction.

Competitivepositioning:Losingmarketsharetofastercompetitors

Supplyconstraintsandlongleadtimesmeanthatcompaniesthatcandeliverprojectsontimegainasignificantcompetitiveadvantage.Thisisexacerbatedforoperatorsseekingtoexpandintonewregions,wheredelaysinmarketentryduetoconstructionholdupscaneliminatefirst-moveradvantage

“Delaysinourbuildaffectcustomerspace

allocationglobally,causingdisruptions

acrossregions.”

Seniorconstructionmanager-

Hyperscaler(APAC)99

andmateriallyimpactcompetitiveadvantageoveramulti-yeartimehorizon.Thisisespeciallyrelevantinmarketswithlimitedpoweravailability,wherebeingfirsttosecuregridaccessandpermittingapprovalscanlockoutcompetitors-withdelaysextendinguptofiveyearsforgridconnections

.7

6

7

AssumingtotalconstructioncostsofUSD10millionperMW.Source:

D

Source:

DatacenterDynamics

PREVENTINGMULTIMILLIONDOLLARDATACENTRELOSSESTHROUGHREPORTING|MARCH2025

©STLPartnersEXECUTIVEBRIEFING10

Successthroughcontrol:Howeffectiveprojectmanagementandreportingeliminatedelays

Datacentreconstructionisinherentlycomplex,requiringthecoordinationofmultiplecontractors,regulatorybodies,equipmentsuppliersandinvestors—allunderunforgivingdeadlinesandhighfinancialstakes.Whiledelaysareofteninevitableduetounforeseenissuessuchassupplychaindisruptions,regulatorybottlenecksandlabourshortages,theirultimateimpactcanbesignificantlyreducedthroughproactiveprojectmanagementandrobustreportingpractices.

ThekeyprincipleatplayhereisMurphy’slaw:“Anythingthatcangowrong,willgowrong”.Whileunexpectedissueswillalwaysariseinlarge-scaleprojects,thedifferencebetweenamanageabledelayandacatastrophicoverrunishowquicklyandeffectivelyteamscandetect,assessandrespondtoemergingrisks,issuesanddependencies.

Reportingisnottheonlywaytomitigateagainstdelay,butitisthemostcost-effective,holisticandscalablesolution.Whileothermethodssuchasdynamic

“Delaysareinevitable,butbetterplanning

andreportingcanmitigatemostofthem.

Wecan’tpreventeveryissue,butifyou

anticipaterisksearly,youhaveachanceto

adjustbeforetheycauserealdamage.”

Constructionmanager-Hyperscaler(APAC)

workforcemobilisation,earlyprocurementoflong-leaditemsandprefabrication/modularconstructionhelppreventdelays,eachhaslimitations.Dynamicworkforcemobilisationsecureslabourbutonlywithpre-approvedcontractors,earlyprocurementreducessupplyrisksbutdemandsupfrontcapital,whileprefabrication/modularconstructionacceleratestimelinesbutdependsondesignstandardisationandsupplychainstability.Thus,thoughthesestrategiesimproveresilience,onlystructuredreportingensuresreal-timevisibilityandrapidresponse—allowingteamstoactbeforeminorissuesbecomemajordelays.

Thebiggestchallengeindatacentreconstructionisthelagbetweenissuesarisingandmanagementidentifyingthem.Delaysworsenwhenpoorreporting,inconsistentdataandsiloedcommunicationkeepproblemshiddenforweeks.Effectivereportingandprojectmanagementclosethisgap,ensuringearlyriskdetection,data-drivendecisionsandfasteraction.Beyonditsoperationalbenefits,reportinggivesprojectmanagersaseatattheC-leveltable,enablingthemtodrivehigh-stakesdecisionsandproactiveriskmitigation-inasectorwheredelayscostmillions,thosewhocontroltheinformationflowcontrolprojectsuccess.

Effectivereportingisthefoundationofsuccessfuldatacentreconstructionasitistheonlywaytoenabletimelymitigationofrisksastheyariseandfacilitatedeliveryontimeandonbudget.

PREVENTINGMULTIMILLIONDOLLARDATACENTRELOSSESTHROUGHREPORTING|MARCH2025

©STLPartnersEXECUTIVEBRIEFING11

Corereportingchallengesindatacentreconstruction

Whiletheimportanceofeffectivereportingindatacentreconstructionisclear,achievingitisfarfromstraightforward.Complexstakeholderdynamics,inconsistentdataintegrity,resourceconstraintsandregionalcompliancerequirementscreatesignificantobstaclestotimelyandaccuratereporting.Thesechallengesnotonlyhinderreal-timevisibilitybutalsoincreasetheriskofdelays,misalignmentandreactivedecision-making.Successindatacentreconstructionultimatelyhingesonadeepunderstandingofthesecorechallengesandthestrategicmeasuresneededtoovercomethem.

Complexstakeholdermanagement:Thecoordinationbottleneck

Datacentreconstructionprojectsinvolveacomplexreportinghierarchy,includingC-levelexecutives,projectowners,contractors,suppliers,regulatorsandendcustomers,eachrequiringadifferentlevelofdetailandreportingfrequency.Eachofthesegroupsneedsvariouslevelsofdetailanddatapresentation,makingeffectiveinformationflowasignificantchallenge.Withoutstandardisedandrigorousreportingprocesses,projectteamsstruggletogainvisibilityofcriticalpathupdates,aligndependenciesandidentifyrisksinrealtime,leadingtoinefficientdeliveryconstrainedbydelaysinissuedetection,escalationandresponse.

Oneofthemostpersistentissuesisreportingcadencemisalignment,inwhichdailysiteupdates,weeklyflashreportsandmonthlyexecutivebriefingsareproducedindifferentformatsfordifferentaudiences.Thisfragmentedapproachoftenresultsinprojectmanagersspendingexcessivetimereconcilinginconsistenciesacrossreports,manuallycompilingdatafrommultiplesources,andensuringthatupdatesarecoherentandactionable.Misalignmentinreportingstructuresoftenleadstoconflictinginterpretationsofprojectprogress,causingdelaysindecision-makingand,insomecases,erodingtrustbetweenteams.

Giventheincreasinglyglobalnatureofthedatacentreboom,cross-bordercoordinationintroducesanadditionallayerofcomplexity,requiringteamstocoordinateacrossmultipletimezones,languagesandregulatoryframeworks.Forexample,arecentdatacentreprojectintheDemocraticRepublicoftheCongofacedchallengeswhenlocalcontractorsonlyspokeFrench,whilereportingwasrequiredtobeinEnglish-addinganadditionallevelofcomplexityincoordinationandensuringtheaccuracyofmessaging.Furthermore,inconsistentterminologyandregionaldiscrepanciesincompliancerequirementscanleadtosignificantdelaysifreportingstructuresarenotdesignedtoseamlesslyintegrateglobalstandardsalongsidelocalrequirements.Differencesincertificationsandregulations

PREVENTINGMULTIMILLIONDOLLARDATACENTRELOSSESTHROUGHREPORTING|MARCH2025

©STLPartnersEXECUTIVEBRIEFING12

acrossregionscancomplicatetheuseoffullystandardisedtooling,requiringadditionalmanual

adjustmentsbeforeexecutivereportscanbesent.

“It’spossibletoendupinasituationwhere

Thiscoordinationisamajortimedrainmultipleindependentcontractorscreatea

forprojectmanagerswhospendupto‘blameculture’requiringconstantmediation.

50%oftheirtimemanagingcontractorsProjectoversightbecomesmoreabout

andaligningreports.Thishighdisputeresolutionthanaboutactuallykeeping

administrativeburdenleaveslittletheprojectontrack”.

bandwidthforstrategicproblem-solving,

riskmitigationandforward-lookingPlanningprofessional-Datacentre

constructioncompany

planning—shiftingprojectoversightfromapreventivetoareactivemodel.

Thedataintegritychallenge:Inconsistentreportingandtheburdenofmanualvalidation

Accurateandtimelydataisessentialforeffectivedecision-makingandriskmitigationindatacentreconstruction.However,disparitiesindataquality,lackofstandardisationandfragmenteddigitaltoolscreatesignificantchallengesinmaintainingdataintegrityandprojectvisibility.

Apersistentissueisthemanualreconciliationofmetricsfromexternalcontractors.Forexample,progresstrackingmaybereportedaspercentagecompletion,milestone-basedphasesorrawlabourhours,whilefinancialdatacanvarybetweenlumpsumcostsanditemisedinvoices,makingdirectcomparisonsdifficult.Thislackofstandardisationrequiressignificantadministrativeefforttoreconcilediscrepancies,slowingdowntheprocessofcompilingaccurateprogressupdatesandshiftingreportingfurtherawayfrombeingreal-timeandactionable.Withoutaunifiedreportingstructureandglossary,inconsistenciescancreateconfusionandleavedecision-makerswithimperfectinformationfromwhichtomakecrucialprojectdecisions.

Thefragmentednatureofreportingtoolsenhancestheseissuesofreconciliation.Manyteamsjugglethreetofourdifferentplatforms(suchasProcore,MicrosoftProjectandAutodeskBIM360)withoutseamlessintegrationbetweendesign,scheduling,budg

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论