November2026

ElectricPower&NaturalGasPractice

SolvingBritain’senergybottle-necks:The£78billion-a-year

opportunityforcleaner,moreafordablepower

CompaniesthataddressthetoughestbottlenecksinBritain’spowersystemcouldcapturepartofa£78billion-a-yearopportunitywhilehelpingdelivercleaner,moreaffordable,andmorereliablepower.

Britain’senergytransitionismovingfromambitiontoexecution.Thepowersystemmustexpandandmoderniseatanunprecedentedpacewhilekeepingbillsaffordableandsupplyreliable.For

businessesacrosstheenergyvaluechain,theopportunityincreasinglyliesinsolvingthebottlenecksthatdeterminehowquicklynewcapacitycanbebuilt,connected,andused.

IntheOctober2026Budget,theUKgovernmentsetoutitsprioritiesformakingenergymore

affordablebyensuringnewcleangenerationdeliversvalueforconsumersandcanconnecttothe

grid,reducingexposuretointernationalgasprices,anddeliveringcheaper,fastergridconnections.1Deliveringontheseprioritieswhilemaintainingreliabilitywillrequireasubstantialshiftinhowthe

systemisbuiltandoperated.

Thechallengeisalreadyvisible.Largeindustrialusersfaceelectricitypricesofabout£0.27per

kilowatt-hour(kWh),morethan60percentabovetheInternationalEnergyAgency(IEA)median

ofabout£0.17/kWh.2Atthesametime,

demandissettogrowatroughly3percentayear

,drivenin

partbydatacentresandelectricvehicle(EV)adoption.3Gasstillsetsthewholesaleelectricityprice

around60percentofthetime,leavingbillsexposedtoglobalgaspriceshocks.4Britainstartsfromapositionofhighreliability,buttheApril2025Iberianblackoutisastarkreminderthat

systemsbuiltfor

adifferenterastrugglewiththesupplypluralismandvolatility

thatcomewithincreasinglycomplex

5

powersystems.

Ouranalysissuggeststhatmeetingthischallengewillrequireadifferentmodelforplanning,building,andoperatingtheelectricitysystem,notsimplyincrementalexpansion.Weestimatethat,by

2030,businessesthatcanhelpremovecriticalbottleneckscouldunlockabout£78billionayearincommercialopportunity—fromdevelopersandnetworkoperatorstotechnologyprovidersandflexibilityservices.

Thecommercialandconsumercasesarecloselyaligned.Thesamebottlenecksthatconstrain

businessvaluealsoaddtooverallsystemcosts,whichaffecthouseholdandindustrybills.

Transmissionconstraintsareoneexample:TheNationalAuditOfficereportsthatconstraintcoststotalled£1.9billionin2025–26andcouldreach£7.8billionby2030withoutconcertedactiontoaccelerategridupgrades.6

Thisarticlemapsthatopportunityacrosssixvaluepoolsandidentifieswhatitwilltaketocaptureit

(seesidebar“Methodology”).Theprizeisnotonlyvalueforenergybusinessesbutalsoacleaner,moreaffordable,andreliablepowersystemthatsupportsBritain’swidereconomicgrowth.

1“Budget2026:Breathingspacefortoday,hopeforthefuture,”HMTreasuryandTheRtHonJohnHealeyMP,UKGovernment,28October2026.

2Statisticaldataset,“Internationalnon-domesticenergyprices,”DepartmentforEnergySecurityandNetZero,UKGovernment,accessed14August2026.

3GlobalEnergyPerspective2026,McKinsey,30September2026.ContinuedMomentumscenario.Thereportidentifiesdatacentresasthefastest-growingloadsegmentinOECDpowermarketsandprojectsa19percentCAGRindatacentreelectricitydemandthrough

2030.

4

Midstreamgassystem:Updatetothemarket,DepartmentforEnergySecurityandNetZero,UKGovernment,30June2025.

5“GridincidentinSpainandPortugalon28April2025:ICSinvestigationexpertpanelfinalreport,”ENTSO-E,20March2026;InformenoconfidencialdelComitédeAnálisis28-A(Non-confidentialreportofthe28-Aanalysiscommittee),ComitédeAnálisis28-A(Spain’sMinistryfortheEcologicalTransitionandtheDemographicChallenge),16June2025;“Thehardstuff2025:Takingstockofprogressonthephysicalchallengesoftheenergytransition,”McKinseyGlobalInstitute,6November2025.

6

Upgradingtheelectricitytransmissionnetwork,NationalAuditOffice,11September2026.

2SolvingBritain’senergybottlenecks:The£78billion-a-yearopportunityforcleaner,moreaffordablepower

SolvingBritain’senergybottlenecks:The£78billion-a-yearopportunityforcleaner,moreaffordablepower3

Methodology

Valuepoolfiguresrepresentestimatedannualaddressablerevenuein2030(nominal£,adjusted

for2percentinflation).Thesearedirectionalestimatessubjecttopolicy,market,anddelivery

uncertainties;actualoutcomeswillvarywithbuildrates,commodityprices,andregulatorydecisions.Thesefiguresrepresentpotentialcommercialrevenues,notestimatesofconsumersavingsor

additionaleconomicoutput.

Renewablesencompassgenerationrevenuefrommerchant,contractsfordifference(CfDs),and

powerpurchaseagreements(PPAs).Gridincludesregulatedreturns(transmissionanddistribution),interconnectors,andindependentdistributionnetworkoperators(IDNOs).Equipment,engineering,andconstructioncoverstheshareofannualcapitalexpenditureattributabletoengineering,

procurement,andconstruction(EPC)andoriginalequipmentmanufacturers(OEMs)acrossallpools.Thisoverlapswithrenewablesandgridcapitalexpenditurebydesign,reflectingthedistinctmarginopportunityfordeliveryplayers.

Sixvaluepools:Howtocapturethevalueineach

SixvaluepoolsofferopportunitiesforBritain’senergyleadersto2030(exhibit).Eachofthese

valuepoolsrequiresitsownstrategytocapturevalueandcarriesitsownstrategicrisks,whilenew

technologiesofferopportunitiestodevelopastrongpositionforvaluecreationoverthenextdecade.

1.Renewables:Makingprojectsbankableatscale

Britain’srenewablesbaseisexpanding.AllocationRound7clearedarecord14.7gigawatts(GW),

underscoringthescaleofthebuild-out.7Asthepipelinegrows,whatmattersmostforconsumersand

energycompaniesisdeliveringprojectsthatarecost-competitive,financeable,andabletoconnect

tothegrid.Thechallengeisincreasinglyshiftingfromsecuringdevelopmentrightsto

delivering

bankableprojects

inanenvironmentofhigherfinancingcosts,four-yearequipmentleadtimes,andgridconstraintsthatcanmateriallyaffectreturns.Ørsted’sdecisiontopausetheHornsea4offshorewind

projectinthefaceofrisingsupplychaincosts,interestrates,andschedulerisksillustrateshowquicklyprojecteconomicscandeteriorate,evenforexperienceddevelopers.

8

Developersthatindustrialisetheend-to-endvaluechainwilllikelybetheonesthatsustainmargins.

Thisincludesearliersuppliercommitments,disciplinedriskallocationwithengineering,procurement,

andconstruction(EPC)partners,anddeliverymodelsthatreduceinterfaceriskbeforebidsare

submitted.Co-locatingrenewableswithutility-scalebatteriescouldfurtherimprovebankabilityby

enablinggeneratorstorespondtomarketsignals,earnflexibilityrevenues,andreducecurtailment.TherecentlylaunchedReformedNationalPricingprogrammereinforcestheimportanceofstorageand

system-awaresitinginreducingoverallsystemcosts.9ProjectssuchasRES’sLarksGreenandRWE’sco-locatedsolarandstoragedevelopmentinDevonillustratethemodelemerginginpractice.

10

7ContractsfordifferenceallocationRound7aresults,DepartmentforEnergySecurityandNetZero,UKGovernment,10February2026;EnergyUKexplains:AllocationRound7offshorewindresults,EnergyUK,14January2026.

8үrstedtodiscontinuetheHornsea4offshorewindprojectinitscurrentform,ӯrsted,7May2025.

9

ReformedNationalPricing(RNP):Deliveryplan,DepartmentforEnergySecurityandNetZero,UKGovernment,21April2026.

10“RESawardedassetmanagementcontractforUK’sfirsttransmission-connectedco-locatedsolarandstoragefacility,”RES,16December2024;“RWEactivatesfirstUKsolarfarmwithco-locatedstorage,”pvEurope,8July2025.

4SolvingBritain’senergybottlenecks:The£78billion-a-yearopportunityforcleaner,moreaffordablepower

Exhibit1

Thescarceassetineachvaluepooliswheretheopportunitylies.

Valuepool

2030value,£billion

Thescarceasset

Whoisbestplacedtocapturevalue?

Strategicrisk

Renewables

16.5

Bankabledeliveryandgrid-aware

siting

Developersthatindustrialise

end-to-endandembedsysteminteractionintoeconomics

Developerswithouttherightcommercialmodelsandsiteswithoutcolocationpotentialmayfacemarginpressure

Grid

15.8

Connectionspeed

andstandardiseddeliverycapacity

T&D¹operatorsandIDNOs²

thattranslateprojectpipelinesintorapid,repeatableexecution

Organisationsstillscalingupfrombespoke

project-by-projectdeliverymodels

Gas

5.8

ReliableoptionalityGeneratorsthatoptimise

availability,ramping,andancillaryservice

participation

Assetswherethe

economicsofmaintainingreadinesshavenotyet

adaptedtolowerutilisation

Flexibility

3.5

Optimisation

capabilityacross

volatilerevenuestreams

Playerswithproprietarytradingandcross-marketdispatch

Storageownersstillbuildingtradingcapabilityrisk

becomingtollingcounter-partiesasmarketsmature

Behind-the-meter/o仟-grid

5.5

Time-to-power

forlargeloads

ProvidersthatcandeliverTierIII³reliabilityin12–24months,bypassinggrid

queues

Operatorsthathavenotyetintegratedpowerintosite-selectionanddesigndecisions

Equipment,

engineering,

andconstruction

31.0

Repeatableconstructioncapacity

Equipment,engineering,and

constructionfirmsthatproduc-tisesubstations,BESS,⁴and

gridreinforcementpackages

Firmswhosedelivery

modelshavenotyetshiftedfrombespoketorepeatableexecution

Newtechnologies—Thesewillcomeinpost-2030

1Transmissionanddistribution.

2Independentdistributionnetworkoperators.

3TierIIIreliabilitymeansthatfacilitiescanundergoplannedmaintenancewithoutinterruptingoperations.

4Batteryenergystoragesystems.

Source:CfD2025Regulations;NationalGridFutureEnergyScenarios;NESOMarketReports;OfgemRIIOreports;McKinseyGlobalEnergyPerspective2026

McKinsey&Company

Behindthemeter,newservicemodelsarealsoloweringupfrontbarriersforbusinessesandhouseholds.Solar-as-a-serviceproviderscanfinance,install,andmaintainon-sitesolarinreturnforafixedprice

perkilowatt-hour,whileSunsavehasintroducedresidentialsolar-andbatterysubscriptionsandE.ONispilotinganenergyasaservice(EaaS)propositioncombiningEVcharging,heatpumps,andhomeenergymanagement.

11

Digitalplatformsarekeytomakingthesemodelsviableatscale

,allowing

providerstomonitorandoptimisedistributedassetsinrealtime,aggregatethemintovirtualpowerplants(VPPs),andparticipateinflexibilitymarkets.

11“Cleanenergythatdoesn’tcosttheearth,”Sunsave,accessedAugust2026;“Unlockyourgreenhome:E.ONNextGenHome,anenergyasaservicerevolution,”E.ONNext,28July2025.

SolvingBritain’senergybottlenecks:The£78billion-a-yearopportunityforcleaner,moreaffordablepower5

2.Grids:Faster,morecost-effectiveconnections

Approximately£70billionoftransmissioninvestmentwillbeneededbetween2025and2031to

connectnewgenerationandstrengthensystemresilience.12Atthesametime,demand-sidepressurehasacceleratedsharply,withOfgemreportingthatconnectionapplicationsrosefrom41GWto125

GWinunderayear,withdatacentresaccountingforatleast80GW.13Networkcongestionisalreadyforcingcurtailment,withoffshorewindlosingroughly11.5percentofoutputsince2023.14Reducingnetworkconstraintsandacceleratingefficientconnectionscanhelploweroverallsystemcostswhilesupportinginvestmentandeconomicgrowth.

Thesystemisalreadyresponding.AcceleratedStrategicTransmissionInvestment(ASTI)isdrivingmajortransmissionprojects,andRIIO-3hasmovedthenetworkintoanewfive-yeardelivery

cycle.TheNationalEnergySystemOperator(NESO)hasreformeditsconnectionprocessandnow

prioritisesprojectsthatarereadyandalignedwithnationalenergytargets.Ofgemisdeveloping

measurestoaddressspeculativeconnectionapplications,whilethegovernmenthasconfirmedplanstoprioritisestrategicallyimportantelectricitydemand,includingdatacentres.15Mostrecently,theUKgovernmentannouncedtheestablishmentofGreatBritishGrid,anewpubliclyownedbodythatwillworkalongsideexistingnetworkoperatorstoacceleratenetworkinvestmentandconnections.16

However,planning,supplychain,andsystemaccessconstraintscouldstillslowdelivery.17The

September2026NationalPlanningPolicyFrameworkasksplan-makerstoconsidernetwork

capacityandinfrastructureneedsearlier,whileNESO’semergingStrategicSpatialEnergyPlanningisintendedtoprovideamorecoordinatedviewofwhatshouldbebuiltwhere.18Atthedistribution

level,thechallengeisanticipatingwhereelectrificationwillmaterialise.ED3andNESO’snewregionalplanningprocessesareintendedtohelpdistributionnetworkoperators(DNOs)investaheadof

demandwithoutoverbuilding.19

Withinthiscontext,operatorsthatshiftfrombespokeprojectstoprogramme-levelstandards,

modularsubstations,andportfolio-levelsupplychainmanagementcoulddeliverprojectsfasterandmorecost-effectively,helpingtoreduceoverallsystemcosts.Independentdistributionnetwork

operators(IDNOs)thatareabletomobilisecapitalandaccelerateconnectionscouldalsofinda

distinctopening.DigitaltechnologyandAIcanfurtherincreasenetworkproductivitybytriaging

applications,forecastingcongestion,identifyingscheduleslippage,andpredictingequipmentfailure.

12

Upgradingtheelectricitytransmissionnetwork,NationalAuditOffice,11September2026.TheNationalAuditOfficereportsOfgem’sestimateof£70billionoftransmissioninvestmentbetween2025and2031,constraintcostsof£1.9billionin2025–26,anda

potentialriseto£7.8billionby2030withoutconcertedaction.

13“Ofgemactstofreeupgridcapacitybytacklingspeculativedatacentreprojects,”Ofgem,29July2026.

14CallumMacIverandKeithBell,“Transmissionnetworkunavailability—thequietdrivingforcebehindrisingcurtailmentcostsinGreatBritain,”UKEnergyResearchCentre,16June2025.

15Acceleratingelectricitynetworkconnectionsforstrategicdemand:Governmentresponse,DepartmentforEnergySecurityandNetZero,UKGovernment,28October2026.

16

Acceleratedstrategictransmissioninvestmentguidanceandsubmissionrequirementsdocument,Ofgem,25August2023;

“Connectionsreform,”NESO,July2026;Networkpricecontrol2026to2031(RIIO-3)guidance,Ofgem,1April2026;“GreatBritish

Gridtospeedupconnectionsandcutbills,”DepartmentforEnergySecurityandNetZeroandGreatBritishEnergy,UKGovernment,29September2026.

17

EmmaLoxton,MichaelBirshan,TomBrinded,andAlexandraGill,“Impatientforinfrastructure?FourchangestoimproveUKprojectdelivery,”McKinsey,12March2026.

18

NationalPlanningPolicyFramework,Chapter10:Securingcleanenergyandwater(W1–4),MinistryofHousing,Communities,and

LocalGovernment,UKGovernment,29September2026;“StrategicSpatialEnergyPlanning(SSEP),”NESO,accessedAugust2026.19ED3sectorspecificmethodologydecision,Ofgem,21May2026;“transitionalRegionalEnergyStrategicPlan(tRESP),”NESO,

January2026.

6SolvingBritain’senergybottlenecks:The£78billion-a-yearopportunityforcleaner,moreaffordablepower

EarlyexamplesincludeUKPowerNetworks’EnvisionplatformandEATechnology’sVisNettools.

20

The

UKgovernment’sSeptember2026workonanAI-enabledcleanenergysystemreinforcesthedirectionoftravel;thecommercialtestiswhetherthesetoolsmeasurablyimprovethroughput,reliability,orcost.21

3.Gas:Operatingforsystemreliability

GasislikelytoremainimportanttoBritain’ssystemreliabilitybeyond2030,evenastheamountof

electricitygeneratedfromunabatedgasdeclines.Meetingdemandduringlongerperiodsoflowwindandsolaroutputwillrequireamixofresources,withdispatchablegasremainingimportantuntilenoughlow-carbonfirmandflexiblecapacityisavailable.NESOprojectsthatroughly35GWofunabatedgascapacitymaystillbeneededaround2030.22

Thischangestheeconomicsandoperatingmodelofgasgeneration.Plantsmayrunfewerhoursbut

becomemorevaluablewhenthesystemneedsreliable,fast-responsecapacity.Morefrequentstarts,stops,andrampingalsoincreaseoperationalcomplexityandthermalstress.Generatorswillthereforeneedtomaximiseavailabilityandresponsiveness,protectbankabilitythroughcapacity,balancing,andotherflexibilityrevenues,andselectivelyprepareassetsforlower-carbonoperation.

Thesameshifthasimplicationsforgastransmissionandimportinfrastructure.Asdomesticproduction

declinesandthesystembecomesmorevariable,theseassetswillneedtoremainreliableandflexible

enoughtomanageseasonalswingsandsupplyshocks,supportedbystrongeroptimisationandbalancingcapabilities.RIIO-GT3isnowinoperation,prioritisingreliability,efficiency,andresilience.23Selective

investmentinstorageandreadinessforhydrogenorcarboncapture,utilisation,andstorage(CCUS)couldpreservelonger-termoptionality.

4.Flexibility:Optimisingenergyuseandsystemcosts

AswindandsolarmakeupmoreofBritain’spowermix,flexibility—theabilitytoadjustsupplyordemandwhenthesystemneedsit—becomesincreasinglyimportant.Itisneededacrosstimescalesranging

frombalancingsupplyanddemandwithinthedaytocoveringlongerperiodsoflowrenewableoutput.Thesystemwillthereforeneedamixofstorage,demandresponse,interconnectors,anddispatchablegeneration.Britaincouldrequire40–50GWoflonger-durationflexiblecapacityby2030.24

Asflexibilitymarketsmature,however,simplyowninganassetisnotenough.Returnscanfallquicklyas

moreparticipantsenterindividualmarkets,andthesameassetcanearnverydifferentreturnsdependingonhoweffectivelyitisusedacrosswholesalepower,balancing,capacity,andlocalflexibilitymarkets.

Thechallengeforassetownersisthereforetocombinephysicalassetswithstrongtradinganddispatchcapabilities,eitherin-houseorthroughpartners.

Emergingcommercialmodelsshowhowthiscanwork.StateraEnergy’s300-megawatt(MW)project,

backedbyaStatkraftPPAwitharevenuefloor,illustrateshowrevenuecertaintyandoptimisationcan

supportinvestment.

25

Forlong-durationstorage,Ofgem’scap-and-floorschemehasprovisionallyselecteditsfirstprojects,providinggreaterconfidencethatmorecapital-intensiveassetscanattractinvestment.

26

20Casestudy(UK):Digitalisingenergysystemsfornetzero,Ofgem,29July2021;“PowerfulanalysisandinsightstohelpyoumonitorandmaintainyourLVnetworks,”EATechnology,accessedAugust2026.

21

VisionforanAI-enabledcleanenergysystem,DepartmentforEnergySecurityandNetZero,UKGovernment,8September2026.22CleanPower2030Annex1:Electricitydemandandsupplyanalysis,NESO,5November2024.

23

RIIO-3finaldeterminations—nationalgastransmission,Ofgem,4December2025.

24CleanPower2030ActionPlan,DepartmentforEnergySecurityandNetZero,UKGovernment,updated15April2025.

25“StateraPPAagreementtakesStatkraft’sthird-partyflexportfoliotoover2GW,”Statkraft,1December2023.

26“Ofgemboostslongdurationstoragetosecuremorehomegrownenergyforcustomers,”Ofgem,26June2026.

SolvingBritain’senergybottlenecks:The£78billion-a-yearopportunityforcleaner,moreaffordablepower7

Consumerandbusinessflexibilityisalsobecomingamoreestablishedpartofsystemoperation.TheJuly2026updatetotheCleanFlexibilityRoadmapreportsthatNESOmetitsfirstannualtargetof

170MWofnewindustrialandcommercialflexibilityandexpandedtheDemandFlexibilityServicetoincludeincreasesaswellasreductionsindemand.

27

OctopusEnergy’sKrakenplatformcoordinatesapproximately2GWinrealtime.

28

Scalingfurtherwilldependonsimplerpropositions,greater

automation,andclearerwaysforconsumersandbusinessestoparticipate.

5.Behindthemeter:Solvingthetime-to-powerchallenge

Fordatacentresandotherfast-growingloads,accesstopowerisbecomingacriticalconstraintongrowth.Gridconnectionscantakefivetotenyears,29whiledatacentrecapacitycontinuestogrowrapidlyacrossEurope.

30

Againstthatbackdrop,about50percentofdatacentreoperatorsexpecttousesomeformofbehind-the-meterpower.31

Theresponseisbroaderthanasimplechoicebetweenwaitingforthegridandgeneratingpoweronsite.Optionsincludeflexiblegridconnections,co-locationwithgenerationorstorage,demandresponse,andtemporaryorpermanenton-sitepower.AVKandLandmarkPowerHoldings,for

example,aredevelopingmicrogridsusinggasenginesandcarboncapture,32whileFloralEnergyiscombiningrenewables,thermalgeneration,andstoragewithdigitaloptimisation.33

Nosingletechnologyislikelytodominate.Forlargersites,on-sitegasgenerationmayprovideabridgeorback-upsolution,butitseconomicsneedtobeweighedagainstfuelandcarboncosts,theriskofassetsbecomingobsolete,andtheprospectofafuturegridconnection.Overtime,

technologiessuchasfuelcellsandsmallmodularreactorscouldprovidereliable,lower-carbonpower.

Theopportunityliesincombiningtechnologiestoreducetime-to-power.ProvidersthatcandeliverTierIII-gradereliability34in12to24monthsthroughamixofgridaccess,storage,generation,and

modularsolutionscouldcreatesignificanteconomicvalue.Foroperators,poweravailabilityisincreasinglyafactorinsiteselectionanddesignratherthansomethingaddressedafterasiteischosen.

Thereisalsoawidersystemtrade-off.Heavyrelianceonon-sitegenerationcanleavefeweruserssharingthefixedcostsofthegrid,whilerequiringstrategicprojectstowaitforafullgridconnectioncandelayinvestmentandgrowth.Inmanycases,thebestsolutionislikelytocombinegridand

on-siteresources,balancingspeed,reliability,cost,carbon,andtheabilitytoconnectmorefullytothegridovertime.

27“Cleanflexibilityroadmap:July2026update,”DepartmentforEnergySecurityandNetZero,UKGovernment,13July2026.

28“4.5millioncuppas?Scotspowertheworld’slargestvirtualpowerplant,”OctopusEnergy,11September2025.

29

ZacharySkidmore,“UKdatacenterfirmscouldbuildgaspowerplantstoexpediteprojects—report,”DataCentreDynamics,30April2025.

30“Datacentretake-upinEuropetoreachnewpeakin2025,”CBRE,27May2025.

31

32

33

34

McKinsey2026EMEAEPNGSurvey(double-blindsurveyofn=51datacentrerespondents),June2026.

PamelaLargue,“NewwaveofUKdatacentrestorunongasengineandCCSmicrogrid,”Enlit,17October2025.

F

,accessed30July2026.

TierIIIreliabilitymeansthatfacilitiescanundergoplannedmaintenancewithoutinterruptingoperations.“Tierclassificationsystem,”UptimeInstitute,accessedJuly2026.

8SolvingBritain’senergybottlenecks:The£78billion-a-yearopportunityforcleaner,moreaffordablepower

6.Equipment,engineering,andconstruction:Industrialisingdeliverytounlockanaffordabletransition

Britain’stransitiontocleaner,moreaffordablepowerdependsonavaluechainfarbeyondenergy

providers.Rawmaterials,manufacturedequipment,engineering,construction,andprojectdeliverycouldallbecomebottlenecks.Althoughmuchofthevalueinareassuchasturbines,solarpanels,batteries,andgridequipmentiscapturedoverseas,asignificantdomesticopportunityremainsinbuilding,retrofitting,andintegratingsubstations,batterystorage,gridreinforcement,generationassets,andnuclearprojects.

Theconstraintisincreasinglydeliverycapacityitself.Infrastructureexecutioncostshaverisenbyabout30percentrelativetoGDPpercapitasince2007,35andtheConstructionIndustryTrainingBoard(CITB)estimatesthattheUnitedKingdomwillneedmorethan206,000additionalskilledworkersbetween

2026and2030.36TheNationalAuditOfficeidentifiesplanning,supplychain,andsystemaccessrisks

assignificantthreatstodeliveringtherequiredtransmissionupgrades.37Powerprojectscompetefor

engineeringtalent,equipment,contractors,anddeliverycapabilitywithwater,roads,rail,anddigital

infrastructure.TheUKgovernment’sSeptember2026planningframeworkseekstoaddresspartofthischallengebybringingenergyandwaterinfrastructureneedsintodevelopmentplanningearlier.38

Becausecapitalcostsaffectfinalconsumercosts,deliveringinfrastructurefasterandmoreefficientlycanimprovetheaffordabilityofelectricity.Companiesthatcanturnrecurringprojectsintostandardisedproductscouldbebetterplacedtodeliveratscale.Standardisedoffshorewindplatforms,forexample,helpedreducelevelisedcostsbymorethan50percentovertenyears,39whileSizewellCexpectsabout20percentcostsavingsfromreplicatingtheHinkleyPointCdesign.40Similarapproachescouldapply

torepeatableassetssuchasbatterystoragepackagesandsubstations,reducingengineeringeffort,interfacerisk,anddeliverytime.

Ofcourse,noteveryprojectcanbestandardised.Complex,first-of-a-kinddevelopmentssuchasBalfourBeatty’s£833millionNetZeroTeessidecontractwillstillrequirebespokeengineeringanddelivery.

41

Theopportunityisthereforetostandardisewhatcanberepeatedwhilestrengtheningcontroloftheprojectsthatcannot.

Digitaltoolscansupportboth.Thepriorityisasingle,trustedviewofdesign,cost,schedule,andrisk

acrosstheprojectecosystem,supportedbycommondatastandardsanddisciplinedmanagement

routines.Integratedprojectcontrols,digitaltwins,andtargetedAI-enabledworkflowscanthenimprovevisibilityandspeedupdecisions.

Generativ

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论