下载本文档
版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领
文档简介
1、.Method Statement for Pipe Jacking1. Construction of PitsThe jacking pit with a dimension of 6mx5 clear opening with depth of 250mm below invert level of the steel pipe.The floor will be leveled by 100mm thick concrete blinding fixing tow I beams(1.5mx15cm) in the center of the pit for fixing jackin
2、g frame.2. Installation of Jacking FrameAfter the construction of drive, the jacking rig will be lowered into the pit and adjust to the control line and level. The rig will be used on this contract consist of two number of hydraulic cylinders with a capacity of 150 ton each to give a total jacking f
3、orce of 300 tons. The rig will have guided rails, pushing plate and base plate to hydraulic power back with control unit. The hydraulic system will run through a diesel engine installed the top of the pit.The rig will installed to the correct line and level and check by the consultant in respect to
4、level and alignment.3. Thrust WallConstructing a concrete block behind the base plate of the rig to a dimension of 2x1.5x0.5m will be provided to take and distribute the jacking load.4. Pipe Jacking OperationA steel shield is used at the front of the pipe to accommodate the.miner and to allow for st
5、eering of the pipe jack. The soil within the shield is manually excavated and loaded into a wheel skip for transport to the pit bottom. The miner does not dig outside the shield (both in front and radically) and the front, or cutting edge, of the shield is always kept buried in the face, so stabilit
6、y is maintained. The shield is thus used to trim the excavation to the size of the pipe thus minimizing the potential for settlement of the ground above the pipe jack.In the pit bottom, the skip is hoisted to the surface, emptied and returned to the used to loosen it prior to digging. The exact diam
7、eter of shield will be selected to suit the pushing pipes.As excavation continues, the shield is jacking forward using two hydraulic jacks thrusting from the back wall. When the shield is buried, the jacks are retracted and the first sleeve pipe lowered on to the rails. This in then pushed up to the
8、 shield and excavation can then continue. When the sleeve pipe is pushed home, the hydraulic jacks are retracted and the services (lighting& ventilation) disconnected. The next sleeve pipe is lowered on to the rails and the services reconnected and the cycle repeated until the shield is pushed into
9、the receiving pit and the pipeline pushed into final position.5. Maintaining Line and LevelIn order to maintain the correct line and level, a graduated target plate.is located within the shield. The site engineer notes the position of the visible sport on the target, this initial position is used as
10、 reference value to locate the relative position of the shield at all times during the drive. At each push, the site engineer monitors the position reference value with the help of level instrument and theodalite, thus giving a shield position (high or low, right or left) relative to the design posi
11、tion. Based on this information, the operator manipulates a correct course.Extending or retracting a combination of steering rams causing the front of the shield to articulate in the required direction carries out the steering. As the pipe follows the shield, the correct line and level will be maint
12、ained. At all times, the amount steering applied is kept to minimum.6. Fixing Carrier PipesAfter completion of the pipe jacking , we check the line and level for the steel pipe and we take the exact line and level for the carrier pipe with the help of survey instruments.A 3 steel anglebar fixed by w
13、elding in the correct bottom level of the carrier pipe, then 3mm thick flat bar half moon claps will fixed through wielding in the correct line after that we put neoprene rubber 3mm thick in the clamp to avoid the scratches of the carrier pipes.Then we start laying the carrier pipe one by one and fi
14、x the clamps.through nuts and bolts. After fixing the nuts and bolts we make angle support in between the top of the clamp and top of the pipe. Then we fix the other pipe in the same manner. The same procedure will continues up to the requirement.7. GroutingUpon completion of pipe jacking we make 4
15、2 holes like ventilationin every meter, it helps the concrete fill the gap between the steel pipeand ground. Then we fixed six inch grouting pipe vertically one meterheight in the top of the pipe both end jacking and receiving. One sidewillkeep ventilation and the otherside forconnection andtheconcr
16、ete pump.Afterthat we lay the carrier pipe inthe correct line and levelthencheck with the consultant and make the test required fromtheconsultant then we close the both end between steel and carrier pipe by m/s plate welding or masonry, the gap between steel sleeve and ground in the both end we clos
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 业务商务订房管理制度
- 化肥行业业务员管理制度
- 业务员退货管理制度
- 业务绩效薪酬管理制度
- 信贷业务制度管理办法
- 外贸业务部管理规章制度
- 市容管理业务规章制度
- 归口业务管理制度
- 快消品公司业务管理制度
- 房产测绘业务管理制度
- 无线局域网应用技术第3版全套教学课件
- 《幼儿园课程概论》课件-第一章 幼儿园课程概述
- 河北省中等职业学校对口升学考试计算机类专业考试大纲(2026版专业课)
- 日本概况-日本历史及中日关系
- 高考英语3500单词表(带音标)(乱序版)默写背诵通用版
- 00067自考财务管理学知识点
- 内蒙古自治区锡林郭勒盟对口单招考试2023年医学综合测试题及答案二
- 2022年浙江省高中生物竞赛试题真题及答案详解(A卷)
- 2023年学位英语考试模拟试题二及答案
- 第一章 网络与生活课件 【知识精讲+备课精研+高效课堂】 教育科学出版社选择性必修二网络基础
- GA/T 823.2-2009油漆物证的检验方法第2部分:红外吸收光谱法
评论
0/150
提交评论