1、.Method Statement for Pipe Jacking1. Construction of PitsThe jacking pit with a dimension of 6mx5 clear opening with depth of 250mm below invert level of the steel pipe.The floor will be leveled by 100mm thick concrete blinding fixing tow I beams(1.5mx15cm) in the center of the pit for fixing jackin
2、g frame.2. Installation of Jacking FrameAfter the construction of drive, the jacking rig will be lowered into the pit and adjust to the control line and level. The rig will be used on this contract consist of two number of hydraulic cylinders with a capacity of 150 ton each to give a total jacking f
3、orce of 300 tons. The rig will have guided rails, pushing plate and base plate to hydraulic power back with control unit. The hydraulic system will run through a diesel engine installed the top of the pit.The rig will installed to the correct line and level and check by the consultant in respect to
4、level and alignment.3. Thrust WallConstructing a concrete block behind the base plate of the rig to a dimension of 2x1.5x0.5m will be provided to take and distribute the jacking load.4. Pipe Jacking OperationA steel shield is used at the front of the pipe to accommodate the.miner and to allow for st
5、eering of the pipe jack. The soil within the shield is manually excavated and loaded into a wheel skip for transport to the pit bottom. The miner does not dig outside the shield (both in front and radically) and the front, or cutting edge, of the shield is always kept buried in the face, so stabilit
6、y is maintained. The shield is thus used to trim the excavation to the size of the pipe thus minimizing the potential for settlement of the ground above the pipe jack.In the pit bottom, the skip is hoisted to the surface, emptied and returned to the used to loosen it prior to digging. The exact diam
7、eter of shield will be selected to suit the pushing pipes.As excavation continues, the shield is jacking forward using two hydraulic jacks thrusting from the back wall. When the shield is buried, the jacks are retracted and the first sleeve pipe lowered on to the rails. This in then pushed up to the
8、 shield and excavation can then continue. When the sleeve pipe is pushed home, the hydraulic jacks are retracted and the services (lighting& ventilation) disconnected. The next sleeve pipe is lowered on to the rails and the services reconnected and the cycle repeated until the shield is pushed into
9、the receiving pit and the pipeline pushed into final position.5. Maintaining Line and LevelIn order to maintain the correct line and level, a graduated target plate.is located within the shield. The site engineer notes the position of the visible sport on the target, this initial position is used as
10、 reference value to locate the relative position of the shield at all times during the drive. At each push, the site engineer monitors the position reference value with the help of level instrument and theodalite, thus giving a shield position (high or low, right or left) relative to the design posi
11、tion. Based on this information, the operator manipulates a correct course.Extending or retracting a combination of steering rams causing the front of the shield to articulate in the required direction carries out the steering. As the pipe follows the shield, the correct line and level will be maint
12、ained. At all times, the amount steering applied is kept to minimum.6. Fixing Carrier PipesAfter completion of the pipe jacking , we check the line and level for the steel pipe and we take the exact line and level for the carrier pipe with the help of survey instruments.A 3 steel anglebar fixed by w
13、elding in the correct bottom level of the carrier pipe, then 3mm thick flat bar half moon claps will fixed through wielding in the correct line after that we put neoprene rubber 3mm thick in the clamp to avoid the scratches of the carrier pipes.Then we start laying the carrier pipe one by one and fi
14、x the clamps.through nuts and bolts. After fixing the nuts and bolts we make angle support in between the top of the clamp and top of the pipe. Then we fix the other pipe in the same manner. The same procedure will continues up to the requirement.7. GroutingUpon completion of pipe jacking we make 4
15、2 holes like ventilationin every meter, it helps the concrete fill the gap between the steel pipeand ground. Then we fixed six inch grouting pipe vertically one meterheight in the top of the pipe both end jacking and receiving. One sidewillkeep ventilation and the otherside forconnection andtheconcr
16、ete pump.Afterthat we lay the carrier pipe inthe correct line and levelthencheck with the consultant and make the test required fromtheconsultant then we close the both end between steel and carrier pipe by m/s plate welding or masonry, the gap between steel sleeve and ground in the both end we clos
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 空调外机隔声屏障工程安装施工方案及技术措施
- 通风空调工程施工方案
- 定时器-计数器编程举例
- 监理工程师之监理概论考试题库附答案(基础题)
- 初级出版专业技术人员职业资格题库带分析2025
- 2026年教育心理学综合考试题及答案
- 门套线条安装施工方案及技术措施
- 2026年化工自动化控制仪表考试题模拟考试题库及答案
- 2025年煤矿企业主要负责人模拟考试题库试卷(含答案)
- 2026四川眉山市第一幼儿园考核招聘部属公费师范毕业生1人模拟试卷附参考答案详解(B卷)
- 港口维修安全培训
- 第十一章、工程技术管理与质量管理措施
- 换届舆情培训课件
- 樊昌信通信原理第10章-信源编码(7版)课件
- 2022年四川省成都市辅警协警笔试笔试
- 常州市房屋租赁合同(常州市2021版)
- GB/T 7113.4-2011绝缘软管第4部分:丙烯酸酯玻璃纤维软管
- GB/T 12009.3-2009塑料多亚甲基多苯基异氰酸酯第3部分:黏度的测定
- FZ/T 70010-2006针织物平方米干燥重量的测定
- 新标准大学英语综合教程2 单词
- 养老护理解决方案之商业计划书
评论
0/150
提交评论