1、BASIC DESIGN OFBZ34-1 OIL FIELD DEVELOPMENT ADJUSTINGJOB NO. 2013BD-005STRUCTUREPage 1 of 902013.1 .05 ISSUED FOR APPROVAL(0)2013.09.02 ISSUED FOR REVIEWB2013.07.02 ISSUED FOR COMMENTSA2013.06.09 ISSUED FOR WORKINGREV.DATEDESCRIPTIONBYCH K.REV W.EXAM.APPR.CLIENTCNOOC Ltd.TianjinSPECIFICATIONFORJACKE
2、T LOADOUT AND SEAFASTENINGDESIGN CERTIF. NO .CNOOCResearch Institute A111008717 RICHTECH A231014242DOCUMENT NO.REV.BD-SPC-GEN(JK)-ST-00060(CN-USP-BHB-BZ34-1)COSIGN DISCIPLINESIGNATUREDATECNOOC RIAPPROVEDSIGNATORYSIGNATUREDATEREVWEXAM.APPR.BASIC DESIGN OFBZ34-1 OIL FIELD DEVELOPMENT ADJUSTINGBD-SPC-G
3、EN(JK)-ST-0006REV. 0CONTENTS1.01.11.2SCOPE3General3Definition Of Terms32.02.4CODES AND STANDARDS3Conflicting Requirement And Deviation Control3National Regulation3COMPANY Specification3Industry Codes And Standards43.0GENERAL MARINE WARRANTY44.04.4LOADOUT4Procedure4Calculations4Weig
4、hts5Loadout Operations55.05.4SEAFASTENING7General7Welding7Materials7Inspection76.06.16.2MARINE EQUIPMENT7Delivery7Moving And Mooring Facilities87.0PROTECTION88.0PACKAGING OF LOOSE ITEMS8SPECIFICATION FOR JACKET LOADOUT AND SEAFASTENINGPage 2 of 9BASIC DESIGN OFBZ34-1 OIL FIELD DEVELOPMENT A
5、DJUSTINGBD-SPC-GEN(JK)-ST-0006REV. 01.0SCOPE1.1GENERALThis specification recognizes a CNOOC requirement that the offshore structures and associated works shall be fabricated in the most economic manner with due consideration of International Standards and Ruling Code of Practice.This Specification d
6、efines the minimum technical requirements for the loadout and seafastening of jacket structures, equipment, and accessories on transport vessel(s).1.2DEFINITION OF TERMSShall mean the party contracted to perform the work in accordance with the drawings, specifications and work scopeShall mean CNOOC
7、or the designated CNOOC representativeShall refer to CNOOCs approved Certifying Authority.ContractorCompanyCertifying Authority2.0CODES AND STANDARDS2.1CONFLICTING REQUIREMENT AND DEVIATION CONTROLThe following document requirements:hierarchy shall be adhered to in the event of conflictingNational R
8、ule of LawProject Specification and DrawingsCNOOC Engineering Specifications and Procedures International Standards and CodesFirst Priority Second Priority Third PriorityFourth PriorityCompliance with this specification shall not relieve CONTRACTOR of the obligation to follow sound engineering pract
9、ice throughout. For any deviation from this specification or their respective priorities, written agreement shall be obtained from COMPANY prior to execution of the related changes.2.2NATIONAL REGULATIONNE&TC, PRC, “Safety Rules for Offshore Platform” (2000)2.3COMPANY SPECIFICATIONThe following COMP
10、ANY specifications supplement this specification:BD-SPC-GEN(JK)-ST-0001Specification for Design of Jacket Structural DesignBD-SPC-GEN(JK)-ST-0002Specification for Jacket Structural MaterialBD-SPC-GEN(JK)-ST-0003导管架结构材料规格书SPECIFICATION FOR JACKET LOADOUT AND SEAFASTENINGPage 3 of 9BASIC DESIGN OFBZ34
11、-1 OIL FIELD DEVELOPMENT ADJUSTINGBD-SPC-GEN(JK)-ST-0006REV. 0BD-SPC-GEN(JK)-ST-0004Specification for Jacket Structural FabricationBD-SPC-GEN(JK)-ST-0005Specification for Jacket Structural Welding andInspectionBD-SPC-GEN(JK)-ST-0007Specification for Jacket Transportation andInstallation2.4INDUSTRY C
12、ODES AND STANDARDSThe latest edition of the following standards and codes listed shall be complied with unless specified.a.API RP2A “Recommended Practise for Planning, Designing, and Constructing Fixed Offshore Platforms”, Working Stress Design. 21st, (2007).b.American Institute of Steel Constructio
13、n (AISC), Specification for structrual Steel Buildings, (2005)c.American Welding Society(AWS), D1.1/D1.1M, Structrual Welding Code Steel, (2010)d.“DNVRulesforDesign,ConnectionandInspectionofOffshoreStructures( and Associated Appendices)”e.American Bureau of Shipping(ABS), Rules for Building and Clas
14、sing Mobile Offshore Drilling Units.3.0GENERAL MARINE WARRANTYAll designs and executions shall be in accordance with requirements of Marine Warranty Surveyor. Any changes as a result of Marine Warranty Surveyor shall be for contractors account.4.0LOADOUT4.1PROCEDUREContractor shall prepare a written
15、 and/or graphical description of the loadout procedure. In particular, the items listed below shall be included in the procedure.a.A barge ballasting procedure.b.Allowances for tides and currents.c.Contingency plans in the event of breakdown or failure of mechanical equipment.4.2CALCULATIONSSPECIFIC
16、ATION FOR JACKET LOADOUT AND SEAFASTENINGPage 4 of 9BASIC DESIGN OFBZ34-1 OIL FIELD DEVELOPMENT ADJUSTINGBD-SPC-GEN(JK)-ST-0006REV. 0Contractor shall provide calculations to COMPANY which show the adequacy of all elements of loadout system, at least the following items shall be included:a.Structure
17、member stresses shall not exceed API and AISC basic allowable during any stage of loadout operation. This shall include performing detailed three-dimensional computer stress analyses of the structure. The loadout analyses shall include studies to determine the allowable differential deflections at t
18、he structure support point which shall become the basis for deflection tolerances during loadout.b.Structural strength of barge should be checked.c.Ballasting calculations.4.3WEIGHTSThe weight and centre of gravity of all the structures shall be accurately reported by the Fabrication Contractor prio
19、r to loadout operations. The final weight control report shall be submitted to the COMPANY at least one (1) month prior to loadout.The Contractor shall be satisfied as to the skid/lift weights of all items.4.4LOADOUT OPERATIONS4.4.1GENERALContractor shall ensure that all equipment and accessories in
20、volved in the skidding/lifting of the structures have the proper rating and are free of damage.Critical mechanical equipment, such as ballast pumps, shall have a 100 percent backup system, hooked up & ready for immediate use in the event of failure or breakdown of the critical equipment.For a skiddi
21、ng loadout, pulling equipment such as strain jacks shall have a sufficient pulling power to overcome a static friction coefficient of 0.15The Contractor shall loadout all items which the fabricates and/or supplies along with any Company supplied materials and equipment. The loadout shall be performe
22、d using good construction and engineering practices, and the Contractor shall be solely responsible to ensure that it is done in such a manner that no damage or overstressing occurs to the said items.There are two manners to loadout structure onto the transportation barge, direct lift and horizontal
23、 movement onto barge.If direct lifting is to be used then all calculations shall be in accordance with the structural design specification. Operation procedures refer to the section of INSTALLATION of BD-SPC-GEN(JK)-ST-000PROCEDURESThe detailed procedure shall include drawings of all the temp
24、orary works, including support points and jacking points. In particular, the items listed below shall be included in the procedure.a.Calculations on the structural integrity of the fabricated item. They shall beSPECIFICATION FOR JACKET LOADOUT AND SEAFASTENINGPage 5 of 9BASIC DESIGN OFBZ34-1 OIL FIE
25、LD DEVELOPMENT ADJUSTINGBD-SPC-GEN(JK)-ST-0006REV. 0designed to meet the differential deflection criteria which may be applied during loadout.b.Design of all temporary works including runway beams etc. for the intended path of travel.c.Design of a retrieval or back-up system for continuation of load
26、out on failure of primary method.d.Calculations on the soil conditions at the site with particular reference to settlement and the strength of the quay wall.e.Check on the structural integrity of the barge.f.Ballasting calculations.TheContractor shall give due consideration to the potential loss of
27、support at anydiscrete point supports during loadout. All supporting steel shall comply with the requirements of the AISC code, with no increases in normal allowable stresses permitted.4.4.3BARGE PREPARATIONA suitable mooring arrangement shall be adopted for mooring of the barge to the quayside thro
28、ughout the loadout operation.The condition of the barge deck will be specifically suited to the loadout of the fabricated items. All obstacles shall be removed, skidding surfaces will be correctly spaced, continuous and greased.Seafastening grillages beneath the fabricated items are to be complete.W
29、inches, pulleys, blocks, ramps and other devices required to transfer the fabricated item onto the barge are to be preinstalled.4.4.4BALLAST CONTROLThe barge ballasting system should have sufficient capacity to compensate for both change of load and change of tide during the entire loadout operation
30、.The nominal ballasting capacity should be determined by the worst combination of tide velocity and loadout velocity expected during the loadout.The ballasting system should preferable have capacity to compensate for the tide through one complete tide cycle.The ballasting system should have back-up
31、capacity and spare pumps to ensure that the loadout may be completed or the fabricated item may be retrieved within the time restrict determined either by the tide or the weather window.Adequate power supply for the ballasting pumps during the loadout operation shall be ensured plus a back-up power
32、supply. The entire system shall have been recently tested and to the satisfaction of the Company.Contractor shall satisfy himself as to the skid/lift weights of all items.SPECIFICATION FOR JACKET LOADOUT AND SEAFASTENINGPage 6 of 9BASIC DESIGN OFBZ34-1 OIL FIELD DEVELOPMENT ADJUSTINGBD-SPC-GEN(JK)-S
33、T-0006REV. 04.4.5INVENTORY LISTAn inventory list of all items to be loaded out shall be prepared by Contractor.5.0SEAFASTENING5.1GENERALContractor shall submit to COMPANY for review and approval all seafastening calculations and drawings.Seafastening shall prevent the cargo from sliding or rolling o
34、ff the barge when subjected to motions at sea.Seafastening shall be designed to accept hog, sag and twisting of barge in seaway.Seafastening shall be installed after the barge has been reballasted from the loadout condition to the tow condition.For cargoes that will be removed offshore, the seafaste
35、nings shall be capable of being released in stages. The stages shall be such that the cargo is secure for a 10 single amplitude roll until the release of the final stage.The seafastening shall be not over stress the cargo onto which they bear. The structure shall be checked locally by Contractor to
36、ensure that it is capable of withstanding the seafastening loads.Seafastening lines cutting shall be clearly identified with paint marks of distinctive color, in order that the cutting crew on a cargo barge understand what has to be done before an item can be lifted or skidded off.Connection onto th
37、e jacket shall have doubler plates at the seafastening joint.The seafastening removal sequence shall be planned so that the seaworthiness of the seafastening is preserved for as long as possible prior to lift. Seafastening shall be cut25 mm from the jacket leg. On all other platform components, scar
38、s from the seafasteners shall be repaired to a smooth, flush finish. Care shall be exercised to assure that structural elements are not gouged. All attachment areas are inspected visually after seafastening removal and non-destructively tested.5.2WELDINGWelding shall be in accordance with BD-SPC-GEN
39、(JK)-ST-0005.5.3MATERIALSMaterials shall be in accordance with BD-SPC-GEN(JK)-ST-0002.5.4INSPECTIONInspection shall be performed in accordance with BD-SPC-GEN(JK)-ST-0005.6.0MARINE EQUIPMENT6.1DELIVERYSPECIFICATION FOR JACKET LOADOUT AND SEAFASTENINGPage 7 of 9BASIC DESIGN OFBZ34-1 OIL FIELD DEVELOP
40、MENT ADJUSTINGBD-SPC-GEN(JK)-ST-0006REV. 0Contractor shall deliver all barges/vessels ready to receive cargo from the Fabrication Contractor in accordance with the Contract Schedule.Delivery of the barge/vessel shall be either in harbor or deep water.If Fabrication Contractor or Contractor causes th
41、e tug and barge/vessel to stand by, all costs incurred thereby shall be borne respectively.If alternative berthing facilities are provided by Contractor, then all costs for such berthing, mooring, and subsequent movement of the barge/vessel shall be to Contractors account.6.2MOVING AND MOORING FACILITIESContractor shall provide all labor and facilities for the movement and safekeeping of the barge/vessel while it/they are in his care.These facilities shall include but not be limited to:a.Harbor tugs,b.Adequate moo
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 押运人员培训技师考试试卷及答案
- 2026年湖南省涟源市高二生物下册期末考试考试卷(突破训练)附答案
- 2025年浙江省龙泉市高二生物下册期末考试试卷含答案(新)
- 2026年陕西省兴平市高二生物下册期末考试测试卷附完整答案(名校卷)
- 2026年广东省化州市高二生物下册期末考试考试卷附参考答案(综合题)
- 2026年云南省文山市高二生物下册期末考试考试卷附参考答案【预热题】
- 2026年辽宁省凌源市高二生物下册期末考试测试卷完整参考答案
- 2025年浙江省瑞安市高二生物下册期末考试检测卷及参考答案【培优B卷】
- 2026年广东省阳春市高二生物下册期末考试测试卷及参考答案【达标题】
- 2026年湖南省湘乡市高二生物下册期末考试检测卷含答案【轻巧夺冠】
- 2024-2025学年山东省济南市高新区统编版四年级下册期末考试语文试卷(解析版)
- 促进睡眠的好方法
- 《财务管理学(第10版)》教案 王化成 - 第8-12章 运营资金管理-并购与重组
- 商业写字楼综合体物业服务方案
- 防汛责任人培训课件
- 2024-2025学年上海市松江区五年级下学期期末数学试卷(含答案)
- 物业员工服务意识培训
- 2025年省级农产品质量安全检测机构评审员技能考试题库(含答案)
- 高钾血症护理诊断与措施
- 2025年贵州省中考物理试题【含答案、解析】
- 城管协管考试试题及答案
评论
0/150
提交评论