文档简介
1、中交四航局沙特吉达排洪渠项目 (明渠、 涵洞、维修道路、 现 有明渠连接段 )的施工组织设计目录第一章 工程概况 11.1 工程名称 11.2 工程地点及项目说明 11.3 项目内容 31.4 工程量清单 5第二章 总体施工安排 22.1 施工总平面布置 22.2 施工工期安排 22.3 总体施工工艺流程 3第三章 施工方案 43.1 土方开挖 43.2 整平及碾压 53.3 回填料施工 63.4 土工布铺设 63.5 涵洞施工 73.6 道路施工 8第四章 施工进度计划 11第五章 拟投入的船机设备表 14第六章 劳动力使用计划 17第一章 工程概况1.1 工程名称PACKAGE 10 :J
2、EDDAH STORMWATER DRAINAGE PROGRAMAL-KHUMRA )1.2 工程地点及项目说明本工程位于沙特吉达市。The Jeddah Governorate is located on the Red Sea coastal plain and receives rainfall runoff from the foothills to the east through natural drainage pathways known as wadis.During intense rainfall events, runoff causes flooding in th
3、e urban areas of the coastal plain.Currently, there are nine (9) dams and three (3) main channels that were built to improve the flood protection systems for the City of Jeddah. Furthermore, there is in adequate stormwater drainage network inside the urban area.本标段为 package 10 scope of work al-khumr
4、aThe channels for Wadi Al Khumra consist of approximately 37km of reinforced concrete trapezoidal channels. There are three distinct branches; easterly branch, central branch and westerly branch. They converge into a common channel at the existing Southern Channel. These channels predominately follo
5、w the line of the existing naturally low ground, with localized deviations to minimize the impact on the adjacent road network and pre-developed areas. The channels commence at the south-east of the Al Khumra catchment and tie into the existing Southern Channel to the north of the catchment.The trap
6、ezoidal section of the channels is to be provided with a guardrail located 1m from the outer edge of toe wall at top of the channel. There is a 4m maintenance road beyond this guardrail, and where the channel is lower than ground level a 3H:1V slope is provided to tie into the existing ground. The m
7、akeup of the maintenance road comprises geotextile and a 400mm layer of aggregate sub-base Class A. There is a 20m buffer zone from the guardrail to the outside edge of the works, which coincides with the Land Acquisition Boundary, and provides a nominal 10m wide strip along the boundary. Refer to t
8、he channel cross sections drawings for more information.There are also 17 roadway crossings which will be reinforced box culverts.1Detours and reinstatement of these roadways will be required.Al Khumra is located to the south of Jeddah, and has a catchment of approximately 458km2.Al Khumra Channels
9、are located to the south of Jeddah and run in a northerlydirection to a confluence and discharge point on the existing Southern Channel.图 1.1-1:工程位置21.3 项目内容本工程施工内容主要包括:明渠施工、涵洞施工、维修道路施工以及 与现有明渠连接段的施工。明渠施工:The channels for Wadi Al Khumra consist of approximately 33 km of reinforced concrete trapezoid
10、al channels and 3 km of natural channels. There are three distinct branches split into reaches. The easterly branch is split into reaches K6A, K2, K5, K3 and K4. The central branch is split into reaches K6B, K9B, K9A and K8. The westerly branch is split into reaches K12, K11C, K11B and K11A. They co
11、nverge into a common channel at the existing SouthernChannel. These channels predominately follow the line of the existing naturally low ground, with localised deviations to minimise the impact on the adjacent road network and pre-developed areas. The channels commence at the southeast of the Al Khu
12、mra catchment and tie into the existing Southern Channel to the north of the catchment.The trapezoidal sections of the channels are to be provided with a guardrail 1m from the edge of channel toewall. There is a 4m maintenance road beyond this and where the channel is lower than ground level a 1 in
13、3 slope is provided to tie into the existing ground. The make-up of the maintenance road comprises geotextile and a 400mm layer of aggregate sub-base Class A. Generally, there is a 20m buffer zone from the guardrail to the outside edge of the works, which coincides with the Land Acquisition Boundary
14、, and provides a nominal 10m wide strip along the boundary.涵洞施工:The internal dimensions and length of each box culvert is as follows:Reach K3 1 No. RCB -226.5m long, 4 cell, 4m wide by 2.3m high.Reach K4 3 No. RCB -226.5m, 70m & 32.5m long, 4 cell, 4m wide by 2.1mhigh.Reach K5 1 No. RCB - 37.5m
15、long, 7 cell, 4m wide by 2.3m high.Reach K6A 1 No. RCB -56m long, 9 cell, 4m wide by 2.5m high.Reach K6A 1 No. RCB -175m long, 7 cell, 4m wide by 2.5m high.Reach K6B 1 No. RCB - 130.5m long, 13 cell, 4m wide by 3m high.Reach K9A 1 No. RCB - 115m long, 7 cell, 4m wide by 1.5m high.3Reach K11B 1 No. R
16、CB - 90m long, 4 cell, 4m wide by 3m high.Reach K11C 3 No. RCB - 30m, 40m & 60m long, 9 cell, 4m wide by 3.3m high. Reach K12 3 No. RCB -26.25m, 26.25m & 119.5m, 9 cell, 4m wide by 3.3m high.Reach K13 1 No. RBC -115m, 12 cell, 4m wide by 1.5m high. 维修道路施工:A 5m wide maintenance strip is to be
17、 provided on either side of the channel. Where land take is restricted or an existing highway runs parallel to the channel the maintenance strip has been omitted, with access undertaken from the existing/new highway. To prevent maintenance or highway vehicles from entering the channel, new guardrail
18、s (metal post and beam) have been provided on either side of the channel over its full length. Access gates will be provided at the maintenance access ramp locations.连接段施工:The new channels will connect in confluence areas at several locations. The main confluence is located at the connection of reac
19、h K6B and K12 at the downstream end of the channels and will connect to the existing Southern Channel at its downstream extent. There is another major confluence which is located adjacent to an existing telecom mast located at the downstream end of reach K6A and K9B. There are a number of further mi
20、nor confluences located at: K5 and K2, K4 and K3, K9A and K13, K8 and K9A. Details of these confluence areas are provided as part of this submission.4图 1.1-2:平面位置图1.4 工程量清单明渠及维修道路工程量备注:明渠底压实度95%。涵洞及过渡段工程量6连接段工程量道路工程量1第二章 总体施工安排2.1 施工总平面布置由于本工程覆盖面积广,施工范围广,因此生活办公区考虑设置在业 主提供水、电接口的位置处(由于业主提供水、电的接口未具体确定,
21、因 此生活办公区的位置也未确定) ,在施工段设置临时饮用水点和移动厕所2.1.1 搅拌站本工程混凝土采用商品混凝土,不自行建搅拌站2.1.2 生活办公区办公生活区布置在业主提供水、电接口的位置处。生活区包括宿室及 配套的生活设施;办公室、宿舍、食堂、冲凉房、厕所、活动室均为一层 活动板房结构。此外,生活办公区内设一个篮球场。生活办公区总占地面 积约为 11220m2。2.2 施工工期安排本工程按时间划分为四个施工期,分别如下:2.2.1 施工准备期(第 12 个月)施工准备期为 2013年 7月 8日2013年 9月 5日,共 60天。按施工 总进度计划要求安排施工人员、机械设备进场等,有序推
22、进,主要完成项 目包括:( 1)施工船机、设备及人员进场;( 2)临时设施建设(包括业主办公室等);( 3)砼、钢筋等主要采购订单;( 4)主要施工方案的提交2.2.2 施工启动期(第 23 个月) 各项工作开始启动,围绕着明渠和涵洞全面开展。主要为:(1)明渠施工于 2013年8月7日开始;( 2)涵洞施工于 2013年8月17日开始 施工。2.2.3 施工高峰期(第 415 个月) 各工序按计划安排紧密施工,各节点按总承包要求及时完成。( 1) Completion of Road Crossing 1 Zone A (Reach K6B) 于 2013 年 11月 25日完成;( 2)
23、Complete Channel Construction (Including Crossing) for Zone E 于 2014年 8月 16日完成;( 3) Complete Channel Construction (Including Crossing) for Zones A & C 于 20142年 7 月 22 日完成;( 4) Complete Channel Construction (Including Crossing) for Zone F 于 2014年 9月 23日完成;5) Complete Channel Construction (Includi
24、ng Crossing) for Zones B& D 于 2014年 9月 30日完成。2.2.4 结束期(第 1516 个月)( 1) Mechanical Completion 于 2014 年 9 月 30 日完成;( 2) Complete As Built Drawings and Project Handover 于 2014 年 10 月 30 日完成。2.3 总体施工工艺流程 根据本工程设置的节点里程碑,本工程的总体施工工艺流程为先进行 连接段的明渠和涵洞的施工,然后同时进行E区域(K11C和K12)和A、C区域(K6A、K6B、K9A和K9B )的明渠和涵洞的施工,
25、E区域施工完成后紧接着进行 B、D区域(K2、K3、K4、K5、K8和K13 )的施工,A、 C区域施工完成后紧接着进行 F区域(K11A和K11B)的施工。具体的施 工工艺流程如图 2.3-1 。图 2.3-1 总体施工工艺流程图3第三章 施工方案3.1 土方开挖3.1.1 工程概况本工程共需幵挖土方 3419604m3,主要幵挖的位置为明渠、汇流区及 道路施工区域。3.1.2 施工顺序 根据本工程里程碑的要求,本工程土方开挖的施工顺序如下:3.1.3 工艺流程 开挖顺序与总体施工工艺流程相同,先进行连接段明渠的开挖,然后同时进行E区域及A、C区域的幵挖,最后进行 B、D区域和F区域的幵 挖
26、。3.1.4 主要施工方法明渠采用挖掘机直接开挖,分层进行开挖,开挖坡度为1:2。根据现场情况,需多个工作面同时实施。开挖时,严格按照设计边坡开挖。根据 开挖的工程量及本工程的施工时间,采用斗容 2.0m3 的挖掘机。特别的,在开挖通信管线、雨水管线、饮用水管线、电缆线等与本工 程明渠交叉的管线前,应先通知各个管线的管理单位,并协调将其相应管 线移动至本工程的施工范围外。另外,在交叉处,应先进行试开挖,以防 止管线的破坏。4图 3.1-1:土方开挖示意图3.1.5 装车、运输对开挖出的土方直接进行装车,并运输至附近的弃土区。运输车辆采用 15m3 的自卸汽车。3.2 整平及碾压3.2.1 工程
27、概况本工程需进行整平及碾压的位置为明渠渠底、涵洞基础、明渠两侧维 修道路的基础以及道路施工。本工程整平及碾压工程量约为90万 m2。3.2.2 施工方法( 1)用平地机对碾压场地进行整平。( 2)在碾压场地上选取典型区域按设计技术要求进行振动碾压,并 测量顶面标高是否满足设计标高及误差要求。( 3)碾压前对干燥得土层表面应先洒水后碾压。通过对土体取样试 验,使碾压后的密实度不小于 95。( 4)参照典型区域标高,对其它振动碾压区进行碾压施工,直至无轮迹,无漏压、无死角,碾压均匀,并满足设计标高及误差要求。( 5)在振动压路机不易到位的边角拟采用小型打夯机夯压密实。图 3.2-1:振动碾压施工示
28、意图53.3 回填料施工3.3.1 工程概况本工程回填料施工共594148m3,回填区域主要是明渠、汇流区两侧以及道路施工区域。3.3.2 施工方法(1)回填土及块石理坡采用15m3自卸车运送到指定地点,挖掘机进 行理坡。( 2)挖掘机理坡 理坡时将挖掘机行驶至回填土方、块石边坡顶部,在要理坡的施工段 两端头横向断面上,用竹竿把堤顶和坡脚的土方、块石边线及相应的标高 放样出来并树立标杆,用测尺将标杆上的三维坐标点连接起来并绑紧,两 条测尺所确定的平面就是土方、块石的设计坡面,施工员可以根据标志指挥挖掘机司机进行理坡3.3.3 陆上块石推填与理坡的质量保证措施( Quality Control
29、)( 1)质量控制指标a. 石料规格和质量控制符合设计的要求和规范规定。b. 块石分段取测点,进行断面测量,厚度不小于设计厚度。c .块石断面轮廓不小于设计断面,分段取测点,进行断面测量。d .块石理坡要控制标高偏差在标准允许偏差范围内。(2)陆上块石推填与理坡分项工程质量控制措施a.施工前对所有参与施工作业的相关工作人员进行技术交底,做到人人清楚。b.石料规格和质量控制:对使用的混合石料定期抽查,块石严 格进行分选,分规格堆存,经验收后才使用。c .测量控制:根据推填工艺要求及推填工艺流程,及时放出出边坡线。d. 理坡控制:用直观的检查手段进行检查。e. 每次填筑断面及长度要符合工艺设计要求
30、。f. 采用挖掘机理坡,挖掘机在施工员的指挥下, 按一定长度分段且按 设计要求理出一定宽度的标准坡面,中间参照两端标准坡面理坡;或每隔 一定长度立一个坡架理坡。3.4 土工布铺设3.4.1 工程概况本工程土工布主要应用于明渠底部及明渠两侧维修道路的底部。63.4.2 工艺流程土工布加工T现场测量定位T土工布铺设3.4.3 施工方法土工布采用钢管活动捆装好,用装载机运输及人工滚动钢管铺装。(1)土工布应按先坡顶、坡面、再坡脚的顺序,垂直于坡脚轴线向 下摊铺土工布,不得横向摊铺。(2)土工布的铺设应平顺、松紧适宜,不能绷拉过紧,应考虑适宜 的缩水率,一般在坡长方向应预留一定的松弛富余量。但注意不要
31、形成折 皱,以确保土工布与底面紧密贴合。( 3)土工布铺设完毕,需尽快在其上回填块石。3.5 涵洞施工3.5.1 工程概况本工程共有 17个涵洞,根据涵洞孔数分为4孔、 7孔、 8孔、 9 孔、12孔和13孔六种型式。本工程涵洞施工共需 72706.2m3混凝土,14241.6t钢筋。3.5.2 施工顺序根据本工程里程碑的要求,本工程涵洞施工的顺序如下:图 3.5-1:涵洞施工顺序图由于受到里程碑的限制, 涵洞 K6B-1、K12-5、K11C-3、K6A-2、K11B-1 、K13-1 、K3-1 、K4-3 和 K4-4 涵洞需要从中间往两边开 2 个工作面进行施 工,剩余的涵洞可按 1 个工作面进行施工。73.5.3 施工工艺本工程涵洞按 10m 一段进行施工,每段分为两层,底层施工高度为1.5m,顶层施工至涵洞顶。涵洞施工的施工工艺如图3.5-2
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2025年心理咨询与家庭教育基础知识考核试卷及答案
- 2025年现代物流与供应链管理考试卷及答案
- 2025年图书馆学与信息管理考试试卷及答案
- 2025年跨文化交际与沟通能力考试试卷及答案
- 合伙合同协议书样本图
- 租房合同到期协议书
- 2025届高考语文复习:句子效果赏析+课件
- 重读新时期以来关+于中国电影民族化的论争
- 全国创新杯机械类说课大赛一等奖作品12mm板厚Q235V对平二保焊说课课件
- 江苏省无锡市第三高级中学2024-2025学年高一下学期期中考试数学试卷(解析)
- DB43-T 2927-2024 中医护理门诊建设与管理规范
- 《额定电压1kV(Um=1.2kV)到35kV(Um=40.5 kV) 铝合金芯挤包绝缘电力电缆第2部分:额定电压1 kV (Um=1.2 kV)和3 kV (Um=3.6 kV)电缆》
- 走进现代舞智慧树知到期末考试答案章节答案2024年浙江大学
- HIV-1病毒载量测定及质量保证指南
- 围手术期血糖管理指南
- GB/T 45007-2024职业健康安全管理体系小型组织实施GB/T 45001-2020指南
- 刘强东创业故事
- 智慧农业中的农业无人机技术与应用
- 2023年马克思主义原理考试知识点汇总
- 智慧监狱智能管控解决方案
- 凤凰实验中学校服供应商评价和退出机制
评论
0/150
提交评论