1、plant construction contractarticle 1-definitions'the owner' shall mean .'the contractor' shall mean .'the plant' shall mean all or any part of the machinery, equipment andmaterials forming the permanent installation as specified inappendix.'the site' shall mean all th

2、e land where the plant is to be constructed in accordance with this contract.'the works' shall mean the works to be done by the contractor under this contract.'the contract price' shall mean the total sum payable to the contractor by the owner for the works.article 2-contractor'&

3、#39;s responsibilities1. the contractor shall design, engineer, and construct the plant at the site.2. the contractor shall provide all equipment, materials, tools, facilities,labour and services necessary for the successful constructionof the plant except those items and facilities to be supplied b

4、y the owner under article.3. the contractor shall perform the works in accordance with the schedulein appendix.4. the contractor shall provide the owner''s personnel with training of peration and maintenance of the plant in accordance with appendix.5. the contractor shall supply the owner wi

5、th the spare parts specified in appendix.6. the contractor shall supply the owner with the maintenance equipment specified in appendix.article 3-owner''s responsibilities1. the owner shall make available the site and grant the contractor freeand uninterrupted access thereto throughout the du

6、ration of this contract.2. the owner shall provide those items and facilities specified in appendixat the time therein established.3. the owner will obtain from the relevant authorities those licenses and permits necessary to construct and operate the plant on the site including work permit for the

7、contractor''s employees.4. the owner shall pay the contractor for the works performed the contract price set out in article.article 4-contract price1. within days after the effective date of this contract, the owner shall pay the contractor as full and complete compensation for accomplishing

8、 the works and assuming all obligations under this contract the contract price in the amount of .2. the contract price is not subject to escalation, and the cost of executing he works shall be the risk of the contractor who shall be deemed to have btained all information and taken into account all c

9、ircumstances which may affect the cost in agreeing the contract price.article 5-drawings1. the contractor shall submit to the owner for approval and review within he time specified in appendix _ such drawings as may be required for construction of the plant under this contract. within one month afte

10、r receiving such drawings the owner shall review and approve or disapprove the drawing.2. the contractor shall be responsible for any defects, errors or omissions in the above drawings unless such defects, errors or omissions are caused by inaccurate information furnished in writing to the contracto

11、r by the owner.3. all drawings and technical documentation delivered by the owner or the contractor to the other party shall be treated as confidential by the receiving party unless agreed otherwise, and shall not be used by that party for purposes other than those connected with this contractarticl

12、e 6-inspection1. the contractor shall perform all inspection and testing of the plant required by law and normal engineering practice.2. the owner shall be entitled at all reasonable times and at its own cost to inspect, examine and test the materials and workmanship of the plant under construction.

13、 such inspection, examination or testing if made shall not release the contractor from any obligation under the contract.3. the completed plant shall be inspected, examined and tested by the owner,and the contractor shall give the owner reasonable notice in writing of the date on which the plant wil

14、l be ready for testing.4. the contractor shall provide such assistance, labour, materials, electricity,fuels, apparatus, stores and instruments as may be required and as maybe reasonably demanded to carry out such tests by the owner properly andefficiently.5. when the plant shall have passed the abo

15、ve tests, the owner shall furnish the contractor with a certificate in writing to that effect. no plant shall be delivered until any faults discovered during inspection are satisfactorilyrectified.article 7-inspection1. the contractor shall provide at the site to the reasonable satisfaction of the o

16、wner all materials, labour, equipment, services and facilities that may be necessary for the proper execution and completion of the works.2. without prejudice to the generality of the above, the contractor shallprovide, as may be necessary, the following:a. construction equipment.b. means of transpo

17、rt within the site including temporary roadways.c. fencing, lighting and guarding and all other materials and servicesnecessary for the safety and security of persons and property.d. temporary stores, offices and other buildings or structures for materialsand persons engaged in the words, including

18、persons employed by the owner.e. telephones, fire-fighting equipment and first-aid equipment until thewhole works have been taken over.f. sanitary and canteen facilities for the use of persons engaged in theworks.3. the contractor shall observe all safety and other regulations imposedon the site by

19、local laws.4. the contractor shall at all times keep the owner''s property and theadjoining premises, driveways and streets free of construction materialsand rubbish caused by the works, and at the completion of the works shallremove all remaining materials from and about the premises and sh

20、all leavethe site and plant safe, clean and ready for use.article 8-inspection1. the contractor will supply at his own cost food, transprot and all necessaryfacilities for all his own personnel.2. on signing the contract, the contractor shall appoint a project managerwho will represent the contracto

21、r at all times be present at the site duringworking hours. all communications issued by the owner to the project managershall be binding as if given to the contractor.3. the owner may request the removal and replacement of any person employedby the contractor on the site if such person is in the own

22、er''s opinionguilty of misconduct, incompetence or negligence.article 9-inspection1. the contractor shall be responsible for all losses of or damage to theplant before final acceptance, and shall make good al such loss or damageat the cost of the contractor and to the reasonable satisfaction

23、 of theowner provided, however, in the case of loss or damage to the plant arisingfrom or occasioned by causes for which the contractor is mot responsibleunder the contract, the same shall be made good by the contractor but atthe cost of the owner, if the owner so directs.2. the contractor shall ind

24、emnify the owner in respect of all damage andinjury occurring before the issue of the final acceptance certificate toany property and person and against al l actions, suits, claims, demands, charges and expenses arising in connection therewith which shall be occasio ned by the negligence of the cont

25、ractor or any of his sub-contractors or by defective design, materials or workmanship but not otherwise.3. in the event of any claim being made or actions brought against the owner arising out of any matter in respect of which the contractor is or may be liable under this article, the owner shall pr

26、omptly notify the contractor in writing thereof and the contractor shall at his own expense take over and conduct in the name of the owner all negotiations for the settlement of the same and any litigation that may arise therefrom. the owner shall at the request of the contractor afford all such inf

27、ormation and assistance as the contractor may reasonably require for the purpose of dealing with any such claim or action.article 10-inspection1. without limiting the contractor''s liabilities the contractor will at his own expense take out the following insurance:a. transportation insurance

28、 on the machine and equipment from its deliveryex works to arrival at the site.b. workers compensation insurance for all contractor''s and subcontractor''s employees engaged or similar statutory social insurance in accordance with the applicable laws and regulations.c. product liabil

29、ity insurance against damage to property or injury to persons until the end of the maintenance period in the sum not less that (amount) us dollars per occurrence.d. comprehensive automobile liability insurance in respect of all vehicles used by the contractor or his sub-contractor in connection with

30、 his contract.2. the aforesaid policies of insurance will be taken out in the names of the contractor and its sub-contractors, the owner, their engineer, consultant and employees and agents as the joint insured and the policies shall contain a waiver of insurer''s rights of subrogation again

31、st the owner, its engineer, consultant and employees and agents.3. the contractor shall maintain the aforesaid policies in full force and effect until the discharge of his obligations under this contract, and the owner shall have the right to demand from time to time copies of the policies, endorsem

32、ents and renewals and receipts for payment of insurance premiums. if the contractor fails to maintain any of these policies in full force and effect, the owner shall have the right to rake out such policies and pay all relative premiums on behalf of the contractor and to deduct the relevant costs fr

33、om and sums owing to the contractor.article 11-inspection1. on completion of all construction and erection work of the plant, the contractor shall inform the owner and shall carry out mechanical erection completion tests specified in appendix  to the satisfaction of the owner.2. on satisfactory

34、 completion of such tests the owner will issue a certificate of completion of erection of the plant. no feedstock shall be fed into the plant until a certificate of completion of erection has been issued.3. in the event of minor deficiencies in the construction and erection work which do not prevent

35、 erection completion and/or in the event of defects revealed by the tests which do not prevent the start-up of the plant, the owner shall issue a certificate of completion of erection and the contractor shall be obliged to rectify the deficiencies as quickly as possible thereafter.article 12-inspect

36、ion1. following the issue of the certificates of completion of erection the contractor shall give the owner days notice of the date when he will be ready to carry out performance tests of the plant.2. the owner shall provide the feedstock and other facilities required in appendix to enable the tests

37、 to commence on time and the contractor shall begin the performance tests at the time so notified.3. the performance tests will be carried out in acceptance with the provisions of appendix  and on their successful completion, the owner shall issue a final acceptance certificate stating that the

38、 plant has been taken over by the owner as from the date thereof.4. if the plant fails to pass its performance test, then the contractor,after making such adjustments as he considers necessary, shall repeat such tests in the presence of the owner at a time to be agreed upon under the same terms and

39、conditions as the original tests.5. the plant shall not be commercially operated before the issue of the final acceptance certificate. notwithstanding the failure of the plant to pass its performance tests, the owner may at his discretion issue a final acceptance certificate subject to the contracto

40、r remedying the plant defects as soon as possible.article 13-inspection1. in the event of any repeat of a performance test failing for reasons imputable to the contractor, and there being no mutual agreement to continue retesting, the results of the final test will be measured and the contractor wil

41、l be liable to pay to the owner liquidated damages on the scale set out in appendix up to a maximum of % of the contract price.2. if the contractor is unable for reasons within his control to obtain a final acceptance certificate for the whole plant by months from the effective date of this contract

42、, he shall be liable to pay to the owner for each month''s delay liquidated damages of% of the contract price up to a maximum of% of the contract price in accordance with appendix.3. the contractor shall establish, in favour of the owner, a guarantee for% of the contract price in the form se

43、t out in appendix in support of his obligations under this article.article 14-inspection1. the contractor warrants, for a period of  months from the date of issue of the final acceptance certificate or months from the effective date of this contract whichever is the earlier, the supplied plant

44、against faulty design, material and workmanship.2. the owner shall inform the contractor in writing of all claims arising under this provision within days of the detection of fault, if the contractor''s representative is on site or withindays if not, to the contractor''s head office

45、by telex r recorded air mail delivery with supporting data. the contractor shall have the option to replace or repair all parts proved deficient. for this purpose the contractor shall have the option to replace or repair all parts proved deficient. for this purpose the contractor shall have an acces

46、s to the site to inspect the faulty parts at any time and to enable him to comply with the terms of this guarantee. should the contractor fail to carry out agreed remedial work within any period of time reasonable in the particular circumstance, the owner shall have the right to do this work at the

47、contractor''s expense.3. this warranty is given subject to the owner storing, operating and maintaining the plant in accordance with the contractor''s instructions and specified operating parameters and may be nullified in the event of the owner attempting rectification work without

48、the contractor''s agreement.4. this warranty does not include items which fail due to natural wear and tear, or consumables or similar items whose natural life is  months or less.5. if pursuant to the above warranty the contractor repairs or replaces any equipment, materials or workmans

49、hip, the provisions of this article shall them apply to said repaired or replaced equipment, materials or workmanship for a period of one year from the date such repairs or replacements are completed.article 15-patent rights and royalties1. the contractor shall fully indemnify the owner against all

50、actions,claims, demands, costs, charges and expenses arising from or incurred by reason of any infringement of patents, design or copyright of third parties by the use of the plant supplied by the contractor.2. the contractor shall also be responsible for the payment to third parties of all fees, ro

51、yalties and other charges, if and, that may be payable under the terms of any license or permission in respect of any design of the works provided by the contractor, the manufactured and supply of the plant and any work done or method employed in the construction of the works.however, the owner shal

52、l be responsible for the payment to third parties of all fees, royalties and other charges, if any, that may be payable under the terms of any license or permission in respect of the operation or use of the plant or any part thereof.article 16-suspension1. the owner shall have the right to instruct

53、the contractor to suspend any part or the whole of the works at any time upon giving written notice to the contractor provided that any period of suspension exceeding days shall be treated as termination under article.2. if the owner fails to make any payment to the contractor under this contract wi

54、thin days of the due date, or if the contractor is otherwise interrupted or delayed in the performance of the works due to the owner''s contractual default, the contractor shall be entitled to suspend performance of this contract.3. in the event of suspension of the works in accordance with

55、this article the contractor shall be entitled to receive such reasonable additional payment as may be necessary to compensate for the additional costs arising out of such suspension, interruption or delay and such reasonable extension of time for performance of contract.article 17-termination1. in t

56、he event of suspension in accordance with article lasting for a period of more than  days either party shall have the right to give notice to the other party of the immediate termination of this contract.2. the owner may at any time by written order to the contractor order the contractor to cea

57、se further execution of the works, and the contractor shall upon receipt of a termination order, cease all further work on the site other than such work thereon as the engineer may instruct for the purpose of protecting, making safe or tidying up such parts of the works as may already have been exec

58、uted or be in course of erection. the contractor shall, as soon as practicable after receipt of the termination order, also cease all such further work as is being done off the site in the performance of this contract.3. upon termination of this contract under this article and under article, the con

59、tractor shall be entitled to be paid:a. that part of the contract price which is proportionate to engineering and services carried out, andb. that part of the contract price which is proportionate to the plantcompleted but not delivered.article 18-force majeure1. no party to this contract shall be liable to the other party for any failure of or delay in performance of its obligations hereof nor be deemed to be in br

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论