版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领
文档简介
1、外立面石材装饰工程 技术标外立面石材装饰工程技术标目录第一章、工程概况及施工计划··········································3第一节、工程概
2、况·················································3第二节、
3、工程施工奋斗目标·········································3第三节、施工现场安排措施计·····
4、183;·································3第二章、施工组织部署··············
5、83;·································4第一节、施工管理组织机构及管理人员配置·············&
6、#183;············4第二节、劳动力使用计划···································&
7、#183;······5第三章、施工组织设计·········································
8、183;······5一、技术准备··········································&
9、#183;·········5二、安装施工准备······································
10、3;·········6三、放线测量·······································
11、83;············6四、后置预埋件安装····································
12、;··········7五、金属骨架安装······································
13、183;·········7六、挂件安装·······································&
14、#183;············7七、石材饰面干挂安装···································
15、183;········8八、嵌缝、打胶········································
16、··········8九、清洗和保护······································
17、3;···········9十、成品保护:·····································
18、183;·············9十一、施工注意事项··································
19、3;···········9第四章、幕墙安装技术规范····································
20、83;·······10一、幕墙竖向和横向板材的组装允许偏差···························10二、幕墙安装允许偏差··········&
21、#183;································10第五章、施工质量保证措施和目标··············
22、183;······················11第一节、施工质量目标及工期保证························
23、83;·········11第二节、施工质量保证体系······································&
24、#183;·11第三节、建立质量管理体系·······································12第四节、材料采购及验收质量保证措施···
25、3;·························12第五节、施工工艺质量保证措施······················
26、·············12第六节、工程养护和冬雨季的施工措施·····························12第六章、施工总进度计划及主要施工机械配置·&
27、#183;·························13一、施工总计划进度的编制说明·····················
28、83;·············13二、施工进度计划表··································
29、3;··········13三、施工进度的控制······································
30、;·······13四、施工机械设备使用计划·······································15五、机械设备使
31、用、维护、保养制度································16第七章、安全文明施工··············
32、83;·······························16一、现场保卫保证措施················
33、83;··························16二、现场消防保证措施·····················
34、83;·····················16三、现场安全生产保证措施··························&
35、#183;············17四、现场文明施工保证措施···································
36、;····18第八章、项目经理、项目工程师及主要管理人员名单及简况···············18第一节、项目经理简况························&
37、#183;··················18第二节、主要管理人员简况·····························
38、;··········18第九章、投标单位相关资料·····································
39、83;·····19第一节、成本系统信息登记表······································19第二节、近三年已完工程与在建工程一览表
40、83;·························20第一章、工程概况及施工计划第一节、工程概况一、工程简介本工程为门廊石材装饰工程,主体为钢筋混凝土框架结构,装修以石材幕墙装饰为主。使用的石材主要是平板及石材装饰线条。幕墙立秆采用槽钢,角码和横梁为角钢,根据设计图纸及具体要求,结合石材干挂的情况,制定以下施工组织设计,以确保工程保质、保量、
41、按期完成,争创优质工程。二、工程主要内容干挂石材幕墙装饰工程。三、工作量工期安排根据该工程的工作量、确定工程施工工期为30天,确保按期保质、保量完成施工任务,满足业主的要求。第二节、工程施工的奋斗目标一、工程施工控制的奋斗目标1、工程质量目标:本工程质量确保合格,争创优质工程。2、施工工期目标:确保在30天工期内,保质、保量全面完成本工程的整体施工任务。3、安全施工目标:按“五无”标准(无死亡、无重伤、无火灾、无中毒,无倒塌)组织施工。4、文明施工目标:要求达到企业文明样板工地十二条标准,做到现场整洁,文明施工。第三节、施工现场安排措施计划根据本工程的特点,对施工现场做出如下安排计划:1、施工
42、管理人员常驻工地,根据施工现场实际情况,与甲方、监理方、土建施工方,协商确认具体施工现场布置。主要包括石材存放场地、钢材存放场地、现场加工场地、临时办公场所、室内仓库、等场地;2、有效利用施工场地,材料单层立体放置。同时按进度做好“来料安装来料”的施工良性循环,做到“工完料尽场地清”。3、做好各项施工协调,如搭设脚手架与土建方合作,提高脚手架使用率,保证进度的同时提高效率。4、在工程施工过程中,做好原有设施的保护。5. 施工用电采用自备移动电闸箱,自楼层业主方提供的配电箱接引。用水由现场业主方提供上楼的供水管线。第二章、施工组织部署第一节、施工管理组织机构及管理人员配置根据该工程的实际情况,由
43、经验丰富的项目人员组建工程项目部。项目承保人负责本项目从开工到竣工,交付使用全过程的施工管理,确保本工程的质量、工期、安全作业、文明施工等得以全面落实。管理人员配置情况(一)项目经理负责从工程准备至安装完工交付全过程的实施和管理,对工程的质量、进度、安全、供应、财务等全面负责;协调和处理甲、乙双方单位的关系,项目部内部各职能机构的关系、以及项目与公司内各部门之间的关系.(二)质检员严格执行设计、工艺质量标准检验制度,组织对工程材料及施工质量的自检、互检、抽检和修检,经常分析质量状况,掌握质量动态;各分项工程开工前作好质量及规范要求布置会;在检查过程中做到各负其责,不错检、不漏检、不拖检,做好各
44、项检查的质检记录并及时归档,对不合格施工及时开出整改通知并监督执行,直到合格。(三)安全员协助项目经理做好安全文明生产管理工作,制定相关的规章制度,贯彻执行劳动保护和安全生产方针、政策、法令及规章制度;负责施工过程安全检查,制止违章指挥及违章作业,确保正常施工和人身、财物安全。(四)施工班(组)长对本工程队施工范围的工程质量、进度全面负责,领导工人按照图纸、施工规范,并严格按照施工程序组织施工,及时填写施工日志,随时掌握工程质量进度情况;认真组织贯彻落实安全生产、文明施工的规章制度,对所承担的工程安全生产、文明施工工作直接负责。第二节、劳动力使用计划我们根据该工程需要所派人员均为经验丰富者,各
45、工种工人既配备齐全,且人数配置合理,整个工程共投入26人以避免施工中出现人员不够或窝工现象。一、劳动力配置工种人数电工1人焊工6人测量员1人打胶工4人安装工12人清理工2人二、劳动力配置说明:1、施工安装队分安装一组、二组,安装职工的素质直接影响到工程的质量、进度及安全,各安装组认真挑选素质高、专业技术水平高的安装职工。2、作业职工的来源:施工队挑选优秀的作业技术工人,要求作业人有从事幕墙安装的经历,技术水平高、劳动态度积极、业务熟练、身体素质好的职工,再针对该工程项目具体情况进行专项培训后,保证队伍的整体素质。3、合理安排作业人数:根据工程量、工期以及工程质量的要求,合理安排施工人员进退场,
46、形成合理的劳动力高峰配置。第三章、施工组织设计一、技术准备1、施工图纸审核交底施工人员要充分熟悉施工图,对图纸疑点逐项记录,结合设计交底配合设计,共同完善设计图纸。2、实测结构的偏差偏差的实测是理石加工及排板的先决条件,应配足人力在短时间内完成并保证数据准确。3、图纸排板与向厂方交底排板过程中要密切与设计结合,向加石材工厂方交底前应请设计对图纸予以确认;向厂方交底要细,并办理签认手续。4、排板放线排板放线的依据是排板图,任何更改必须与二次设计人进行协商。二、安装施工准备1、搬运、吊装构件时不得碰撞、损坏。2、构件储存时应依照安装顺序排列放置,放置架庆有足够的承载力和刚度,在室外储存时应采取保护
47、措施。3、构件安装前应检查制造合格证,不合格的构件不得安装。4、配电箱需安放在靠近施工的现场,方便施工。5、对土建使用的脚手架及时地进行整改,使之符合幕墙施工要求。三、放线测量 外墙面水平线以设计轴线为基准。要求各面大墙的结构外墙面在剔除胀模墙体或修补凹进墙面后,使外墙面距设计轴线误差不大于1cm。1、考虑到幕墙装饰工程施工要求精度高,所以不能依靠土建水平基准线,必须由基准轴线和水准点重新测量,并校正复核,如果主体结构的水平、轴线误差大于规定的允许偏差时,包括垂直偏差,应在得到业主、监理和设计人员的同意后,适当调整幕墙的标高、轴线,使其符合幕墙的构造需要;2、按照设计在底层确定幕墙
48、定位线和分格线。3、用经纬仪或激光垂直仪将幕墙的阳角和阴角引上,并用固定的角落钢支架上的钢丝线作标志控制线。4、使用水平仪和标准钢卷尺等引出各层标高线,沿每层楼板外沿弹出水平墨线并用钢丝标定,从而决定整片幕墙水平位置;5、确定好每个立面的中线。6、测量时应控制分配测量误差,不能使误差积累。7、测量放线应在风力不大于4级的情况下进行,并要采取避风措施。使用铅垂线作业时,必须严格等待至无风力影响的静止状况才能开始测量。8、放线定位后要对控制线定时校核,以确保幕墙垂直度和金属竖框位置的正确。四、后置预埋件安装通过对所有外立面装饰工程统一放基准线,根据幕墙施工图纸,进行后置预埋件安装,主要是采用不绣钢
49、膨胀螺栓,并使用镀锌铁板锚固。根据该工程基准轴线和中线以及基准水平点对安装完的预埋件进行检查和校核,一般允许位置偏差为±20mm。如有预埋件位置超差而无法使用或漏放时,应及时给予调整,并必须报监理和设计单位审核批准,全部安装完后,应在现场做拉拔试验,做好记录。以保证以后幕墙的抗风压能力。五、金属骨架安装1、根据施工放样图检查放线位置。2、安装固定竖框的铁板,连接件采用角钢与结构预埋铁三面围焊,为保证连接部位的耐久性,角钢下缘增加一道焊缝,即实际为四面围焊。焊接完成,按规定除去焊渣并进行焊缝隐检,合格后刷防锈漆。连接件的固定位置按连接件弹线位置确定,采取水平跟线、中心对线、先点焊、确定
50、无误后再满焊的方法。3、先安装同立面两端的竖框,然后拉通线顺序安装中间竖框。4、将各施工水平控制线引至竖框上,并用水平尺校核。5、按照设计尺寸安装金属角钢横梁。角钢横梁一定要与竖框垂直。(角钢横梁在施工前须刷防锈漆)6、立柱和横梁之间采用焊接,焊接时要采用对称焊,以减少因焊接产生的变形。检查焊缝质量合格后,所有的焊点、焊缝均需作去焊渣及防锈处理,如刷防锈漆等。7、上下立柱的连接用钢板,不锈钢螺栓连接。8、待金属骨架完工后,应通监理公司和建设单位对隐蔽工程检查验收,验收合格后,方可进行下道工序的施工。9、所有的立秆、竖梁和角码的连接均采用围焊。六、挂件安装待连接件或次龙骨焊接完成后,用不锈钢螺栓
51、对不锈钢挂件进行连接。不锈钢销钉位置,不锈钢挂件位置通过挂件螺栓孔的自由度调整,板面垂直无误后,再拧紧螺栓,螺栓拧紧度以不锈钢弹簧垫完全压平为准,隐检合格后方可进行下道工序。七、石材饰面干挂安装石材上墙前,先清除槽内浮尘、石渣;试挂(板位、板垂直等要求见第四章表)后,槽内注胶、安装石板,靠尺校核。外饰面允许偏差执行“JGJ73-91”规范。根据图纸做法干挂板材用挂件连接,自下而上分层托挂。板面原则上大面压小面,建筑物大角阳角及柱阳角为V形角。板材开槽宽60mm,孔深16mm,孔中距板材外表面为12.5mm。板材安装必须跟线,按规格按层找平、找方、找垂直。1、将运至工地的石材按编号分类,检查石材
52、尺寸是否准确和有无破损、缺楞、掉角,按施工要求分层次将石材饰面板运至施工面附近,并注意摆放可靠。2、先按幕墙面基准线仔细安装好底层第一片石材规格平板。所有挂件采用不锈钢挂件。3、注意安放每片石材金属挂件的标高,金属挂件应紧托上片饰面板,而与下片饰面板之间留有一定的间隙。4、安装时,要在饰面板的销钉孔或切槽口内注入石材胶(或者环氧树脂胶),以保证饰面板与挂件的可靠连接。5、安装时,宜先完成窗洞口四周的石材板镶边,以免安装发生困难。6、安装到每一楼层标高时,要注意调整垂直误差,不要积累。7、如果石材与平面线不平齐则调整微调螺栓,调整平齐,紧固螺栓。8、在搬运石板材时,要有安全防护措施,摆放时下面要
53、垫木方。八、嵌缝、打胶石材板间的胶缝是石材装饰幕墙的第一道防水措施,同时也使石材幕墙形成一个整体, 所以需用特制板刷清理石材板缝,将缝内滞存物、污染物、粉末清除干净,以增加密封胶的附着能力。1、要按设计要求选用合格且未过期的耐候嵌缝胶。最好选用含硅油少的石材专用嵌缝胶,以免硅油渗透污染石材幕墙表面。2、用带有凸头的刮板泡沫塑料圆条,保证胶缝的最小深度和均匀性,选用的泡沫塑料圆条直径应稍大于缝宽。3、在胶缝两侧粘贴纸面胶带纸保护,以避免嵌缝胶迹污染石材板表面质量,影响美观。4、用专用清洁剂或稀草酸擦洗缝隙处石材表面,石材的表面,特别是缝隙处,必须清洗干净,以保证嵌缝胶与石材的粘贴。5、注胶应均匀
54、无流淌,边打胶边用专用工具勾缝,使嵌缝胶成型后呈微弧形凹面。6、施工中要注意不能在漏胶污染墙面,如墙面上沾有胶液应立即擦去,并用清洁剂及时擦净余胶。7、为保证施工质量,在大风和下雨时不能注胶,胶枪嵌缝分段一次完成,速度应保证嵌缝无气泡、不断胶。嵌缝胶镏压应在初凝成型时完成,保证外形一致。九、清洗和保护施工完毕后,除去石材板表面的胶带纸,用清水和清洁剂将石材表面擦洗干净,按要求进行打蜡或刷保护剂。十、成品保护:1、要及时清擦,净残留在门窗框、玻璃和金属、饰面板上污物。 2、认真贯彻合理施工顺序,少数工种的活应做在前面、防止损坏、污染外挂石材饰面板。 3
55、、拆改架子和上料时,严禁碰撞饰面板。 4、外饰面完成后,易破损部分的棱角处要钉护角保护,其他工种操作时不得划伤面漆和碰坏石材。5、完工的外挂石材应设专人看管,遇有危害成品的行为,应立即制止,并严肃处理。十一、施工注意事项1、严格控制石材板质量,材质和加工尺寸都必须合格。2、要仔细检查每块石材板有没有裂纹,防止石材板在运输和施工时发生断裂3、测量放线要十分精确,各专业施工要组织统一放线、统一测量,避免各专业施工因测量和放线误差发生施工矛盾。4、预埋件的设计和放置要合理,位置要准确。5、根据现场放线数据绘制施工放样图,落实实际施工和加工尺寸。6、安装和调整石材板位置,可用垫片
56、适当调整缝宽,所用垫片必须与挂件是同质材料。7、固定金属挂片的螺栓要加弹簧垫圈,或调平调直拧紧螺栓后,在螺帽上抹少许石材胶固定。第四章 幕墙安装技术规范一、幕墙竖向和横向板材的组装允许偏差(mm)项 目尺寸范围允许偏差检查方法相邻两竖向板材间距尺寸(规定端头)/±2.0钢卷尺两块相邻的石板/±1.5靠尺相邻两横向板材的间距尺寸间距2000时间距2000时±1.5±2.0钢卷尺分格对角线差对角线2000时对角线2000时3.03.5钢卷尺或伸缩尺相邻两横向板材的水平标高差/2钢板尺或水平仪横向板材水平度构件长2000时构件长2000时23不平仪
57、可水平尺竖向板材直线度/2.52.0m靠尺、钢卷尺二、幕墙安装允许偏差(mm)项目允许偏差检查方法竖缝及墙面垂直度幕墙高度H(m)10激光经纬仪或经纬仪H30 60H3015 90H6020 H902.5 幕墙平面度2.52.0m靠尺、钢板尺竖缝直线度2.52.0m靠尺、钢板尺横缝直线度2.52.0m靠尺、钢板尺缝宽度(与设计值比较)±2卡尺两相邻面板之间接缝高底差1.0钢板尺第五章、施工质量保证措施和目标严格按规范要求施工,确保幕墙达到优质工程。第一节、施工质量目标及工期保证1、本工程质量保证满足业主要求,工程质量确保达到合格。2、根据设计要
58、求,工程严格按照施工合同的要求实施,确保工期30天完工。3、按照工作计划,做好与各施工小组的协调,制定现场碰头会、每周一次的各工种协调会,及时发现及解决工程中出现的各种技术及相关问题。4、指定专人负责跟踪各种材料,以保证材料的按时发运到货。5、按计划安排足够的施工力量进场施工,有计划地预留场外的补充施工力量,以便在工程实施时发现计划未能如期进立即加派人手进场加强。按工地规定的正常时间进行施工外,必要时将视工程进度组织进行加班作业。第二节、施工质量保证体系一、施工质量保证体系工程实施过程的质量控制1、干挂结构与块材的连接形成一个稳固的装饰面,达到牢固要求。2、材质符合设计要求,块材表面质感和色泽
59、形成均匀一致的整体。3、平直面的整体表面平坦,拼接横平竖直、缝宽均匀、表面顺畅、异形部位达到设计要求。二、施工质量保证措施1、组建强有力的质量管理班子。施工人员均选拔经专业培训的技工和安装工。2、配备先进的水准仪、激光经纬仪等检测设备3、严格落实内部自检制度,即在阶段性验收关,班组之间进行自检、互检,专职检验员在班组自、互检的基础上,再进行核验,核验后填写质量评定记录,再报质管部组织验收,验收合格后报业主及监理验收。4、严格落实有关质量管理的规章制度,确保工程现场的质量管理符合IS09001的管理模式。第三节、建立质量管理体系建立质量管理制度,以承保人为该工程质量的第一责任者。对工程质量方针及
60、目标进行制定和实施负责,使其对施工现场人员职能进行合理分配,尤其确保质量成本、材料质量、现场质量检验、安全生产、施工进度等各职能的协调与管理,并严格执行质量检验规范。第四节、材料采购及验收质量保证措施1、采购每项材料前,应真正了解材料的名称、型号、级数,向供应商索取材料的有关技术资料、合格证书、样板在与定材料样板核对无误后方能进行订货,同时在与供应商签订的订货合同中必须明确验收标准等有关措施。2、对各种到货的定购材料必须严格把关,按样验收,不合格的材料坚决退货,绝对禁止流入工地并使用在工程上。3、对已运进施工现场的各种材料,统一安排分类按规范堆放,将主要材料送到相关部门进行检验,以确保材料的二
61、次检验符合标准并做好材料的防潮、防变形等工作措施。4、各工种对领用的各种材料,必须在施工前再次进行认真核对,在颜角、花纹差异的,更应该由较有经验的各工种工人员进行挑拣分类,力求使这些天然的饰面材料做到区域上的统一。第五节、施工工艺质量保证措施1、为确保本工程的施工质量符合标准,各工种必须严格执行及遵守国家有关部门颁发的施工规范、标准。4、在施工过程中,各工种应密切配合,自觉地做好工种之间交叉作业的检查、产品保护工作,此工作必须从工人的日常素质教育做起,各工种主管、施工员经常巡查,发现不足应立即纠正并采取有效措施改正。5、在全工程基本完工后,经内部验收自检后,联络甲方和监理进行工程的正式验收交工
62、工作。第六节、工程养护和雨季的施工措施本工程工期30天,如遇雨季,施工时应做好以下措施:1、进场材料分类堆入于仓库,仓库应通风干燥。材料堆放应符合规范,如石材应斜放并有木垫。2、按规范做好成品、半成品的养护,确保工期与质量。3、现场中外露的设备应搭防雨棚作业,外露的物资应用塑料或其它防水物品盖好,避免雨季造成进水。4、施工机具要有防水罩或置于室内,电气设备的电源线要悬挂在上,不能拖拉在地,拉开电闸。5、施工人员在脚手架上作业要注意防滑、防风。第六章、施工总进度计划及主要施工机械配置一、施工总计划进度的编制说明本次编制的施工总计划进度是根据工程情况分析、工期自行安排竞争力度以及我公司长期以来的施
63、工进度实施、控制经验编制的计划总进度。如一旦中标实施,我公司将根据总计划进度安排实际编制周计划。我公司着重分析了本工程的工期特点,经过慎重分析安排,本工程在30日历天内完成。二、施工进度计划表施工总进度计划表具体反映了各个部位分项工程的计划进度时间和交错搭接工序的安排。详见后附表。三、施工进度的控制1、 施工进度控制的基本原理及程序工程项目的进度受许多因素的影响建设者需事先对影响进度的各种因素进行调查预测它们对进度可能产生的影响,编制可行的进度计划,指导建设工作按计划进行。这就要求我们在执行计划的过程中在握动态控制原理不断进行检查将实际情况与计划安排进行对比,找出偏离计划的原因。特别是找出主要
64、原因然后采取相应的措施对进度及时调整控制使实际结果始终达到进度计划2、 施工进度的内容(1) 根据合同工期目标,编制施工准备工作计划、施工方案、项目施工总进度计划和单位、单项工程施工进度计划以确定工作内容、工作顺序、起止时间相衔接关系,为实施进度控制提供依据。(2) 编制月(周)作业计划和施工任务书作好进度记录以掌握施工实际情况,加强调度工作以促成进度的动态平衡,从而使进度计划的实施取得成效。(3) 采用实际进度与计划进度对比的方法以定期检查为主,应急检查为辅,对进度实施跟踪控制。实行进度控制报告制度,在每次检查之后,写出进度控制报告,提供给建设单位、监理单位和企业领导作进度控制参考。(4)
65、监督并协助分包单位实施其承包范围内的进度控制。(5) 对项目及阶段进度控制目标的完成情况、进度控制中的经验和问题作出总结分析,积累进度控制信息,使进度控制水平不断提高。(6) 接受监理单位的施工进度控制监理。3、 施工进度控制方法及措施(1) 从组织体系上保证工期的组织措施:为保证按质、按期完成任务,成立精干的项目经理部,从组织上起到保证。(2) 施工进度的三级动态控制措施:1) 一级进度计划是业主要求的进度计划,二级进度计划是项目经理部根据业主要求制定的进度计划,三级进度计划是各施工作业队伍根据项目经理部要求制定的进度计划,这三个计划要求总体衔接、稳定平衡,通过信息反馈,对计划实施的全过程作
66、有效的动态控制。2) 编制月计划以外还要求编制得更具体,更具有实践性的周计划,凡是条件变化了,都要在周计划上加以调整。3) 每天召开一次现场会,每周召开一次协调会,把反馈的信息立即作出正确的处理。<1> 劳动力的投入方面,根据合同内容所涉及的工作范围配足各工种的劳动力数量,并相应合理搭配操作工人的技术等级,做到各工序间的质量一次成优,避免产生不必要的返工而延误工期。<2> 合理组织工序间的交叉流水作业,封闭施工尽可能地提前完成,为其他专业系统的施工提供足够的时间。<3> 对部分可以在夜间操作的工作,在施工面展开后,充分利用施工现场、施工机具,我公司采用二班制进行夜间施工。<4> 加强对材料供应的管理,材料供应要及时,做到材料等人,不允许出现人等材料的现象。<5> 制定必要的奖罚制度,对于按计划完成工作的施工人员进行必要的奖励,对未按计划完成的施工人员作出相应的经济处罚,甚至开除。<6> 为了做好现场管理和成品保护工作,除了在施工现场设立值班室由专门值班人员负责值班外, 本公司所有施工人员均住宿在临时宿舍,专人管理。(3) 施工进度控制的计划系统:施工准备工作计划;施工总进度计划;单位工程进度计划;施工项目月度(周)进度计划。(4) 施工进度计划实施中的监测与调整1) 进度监测的系统过程:进度计划招待中
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
评论
0/150
提交评论