




版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领
文档简介
1、Method Statement forConcrete Works-SuperstructureDocument No:Rev : 0Date:Page 1 of 11METHOD STATEMENT FORCONCRETE WORKS - SUPERSTRUCTUREMethod Statement forConcrete Works-SuperstructureDocument No:Rev : 0Date:Page 2 of 11Revision Record1. This cover page is a record of all revisions of the document
2、identified above by number and title. All previous cover pages are hereby superseded and are to be destroyed.2. The contractor has the full right to modify, amend or change Method Statement and supporting documents as required or as deemed necessary. All such documents will be submitted to the CONSU
3、LTANT ” for approval.RevDatePrepared ByReviewed byApproval forIssuance byDescription & page Number of RevisionMethod Statement forConcrete Works-SuperstructureDocument No:Rev : 0Date:Page 3 of 11CONTENTS1.0 PURPOSE2.0 SCOPE3.0 REFERENCES4.0 DEFINITIONS AND ABBREVIATIONS5.0 RESPONSIBILITIES6.0 MA
4、TERIALS7.0 EQUIPMENT & TOOLS8.0 SAFETY & HEALTH9.0 PROCEDURE10.0 ATTACHMENTSMethod Statement forConcrete Works-SuperstructureDocument No:Rev : 0Date:Page 4 of 111.0 PURPOSEThe purpose of this document is to lay down the systematic procedures for the various activities required for CONCRETE W
5、ORKS- SUPERSTRUCTURE (CAST IN-SITU) to ensure that all works are carried out in accordance with the approved shop drawings and project specification.2.0 SCOPEThis procedure cover all activities related to concreting superstructure:? Shuttering? Reinforcement? Concrete pouring? Concrete finishing? Co
6、ncrete curing3.0 REFERENCES? Project Specifications for Cast in Place Concrete? Approved shop drawings? Approved reinforcement? Material approval? Approved mix design and trial mix details? Contract Drawings? Approved supplier details? Project Quality Plan? Project HSE Plan4.0 DEFINITIONS & ABBR
7、EVIATIONSConsultant/Client:Contractor:PM:Project ManagerCM:Construction ManagerPE:Project EngineerSE:Site EngineerQCE:Quality Control EngineerQA QC:Quality Assurance and quality ControlMethod Statement forConcrete Works-SuperstructureDocument No:Rev : 0Date:Page 5 of 11PPE:HSE:Personal Protective Eq
8、uipment5.0RESPONSIBILITIESHealth, Safety and Environment? Project Manager is responsible for overall project execution, quality and safety. Adopt a leading role with respect to Contractor quality and safety procedures. The PM is responsible for the overall implementation of this method statement. Th
9、e Project Manager shall ensure that the key personnel are well aware of the specifications and method statement.? CM / Project Engineer shall arrange all materials, equipment, safety related items & manpower & direct the Site Engineers & Foremen to resort appropriate action for the smoot
10、h execution of the works.? Safety Engineer shall be responsible for safe working environment & conditions. Coordinate with Site Engineer to identify potential hazards before works and advice methods of safe working from new developments.? Surveyor shall be responsible for setting out for levels,
11、 layout, and lines & establish top levels. Ensuring setting out books are properly maintained and filed when completed. To coordinate with the CONSULTANT surveyor in determining coordinates, levels, and limits.? QA/QC Engineer shall be responsible for ensuring that execution of works are complyi
12、ng with approved method statement; specifications, approved shop drawings and ensure ITR are submitted based on ITP requirements.? Site Engineer shall ensure that all works are carried out according to approved shop drawings. He shall direct the surveyor for the setting out lines & levels in con
13、currence from the Construction Manager/Senior Civil Engineer.? MEP Coordinator / Engineer shall be responsible for proper execution of MEP works involved before, during and after the works.6.0M ATERIALS? As per the approved material submittal.7.0EQUIPMENTS & TOOLS? Vibrators? Concrete Pumps? Chu
14、te? CraneMethod Statement forConcrete Works-SuperstructureDocument No:Rev : 0Date:Page 6 of 11? Transit Mixtures? Generator-For night concreting? Air compressor? Hand tools, hand saw, wire cutter, brush,? Line dory? Measuring tapes? Tamper? Shovel? Wooden Float? Power float? Calibrated survey instru
15、mentsThe capacity / size of the above tools and equipment shall be judged in accordance with site conditions, requirements, and availability at the time of execution8.0 SAFETY & HEALTHSafety of the personnel and properties is to be given prime importance and all the works to be carried out witho
16、ut causing any accidents or property damages. Concrete works involves the following activities.1. Shuttering and de-shuttering2. Fabricating and fixing reinforcement.3. Transportation of concrete.4. Placing of concrete at siteHSE rules and regulations shall be strictly adhered during execution of th
17、e above mentioned works.Adequate access and egress should be provided to the site of work. All the personnel should wear basic personnel protective equipments. All the equipments, tools and tackles being used for the work should be in good working condition and maintained. All the personnel will be
18、provided with toolbox talk on the procedures to execute the work safely.Necessary risk assessment of the activities is reflected in the enclosed risk assessment.5. 0 PROCEDUREGeneral:? Prior to start any activity on site, the Engineer must be notified.? Ensure that all workers are aware of the evacu
19、ation plan.? Cordon off the work area to prevent unauthorized entry.? Discuss the method of working with all supervision staff.Method Statement forConcrete Works-SuperstructureDocument No:Rev : 0Date:Page 7 of 11? All the related documents such as shop drawings, method of statements, material approv
20、als, subcontractor approvals, test certificates etc. must be approved and available upon request.? Ensure the source of supply of ready mix and grade of concrete.? Arrange initial trial mix and conduct specified test.? Submit mix design and trial mix test result for Client/Engineer approval.? Site l
21、ab with cube mould, Thermometer, Slump cone etc shall be arranged prior to the concreting operation.? Spacer block shall be provided as per approved material.? Arrange the concrete testing area with proper shading/and lighting.? Polythene sheets, hessian cloths sweet water etc shall be arranged for
22、the proper curing.? Access scaffoldings, ladder etc. will be erected to allow reinforcement to be fixed.? Setting out, MEP clearance and civil work approval shall be obtained prior to proceeding.Formworks.? Setting out shall be done by the surveyor prior to proceeding.? Form work shall be erected as
23、 per approved shop drawings for the superstructure.? Approved materials used for temporary formworks should be clean strong and clear from any deflection.? Shutter will be treated with approved shutter releasing agent to enable easier stripping.? Install formwork to its dimensions correctly and ensu
24、re that lines and levels are within the tolerances.? The shutters will be braced and anchorages properly as per the approved shop drawings to maintain the proper alignment and plumbness of the forms.? Line and level of the shuttering will be set out by the surveyor. Shutters must be checked for corr
25、ectness in their final position.? Tie rods shall be used for proper alignment.? Tie roads are to be correctly tightened and rechecked prior to casting.? Gaps in the shutter must be plugged out to minimize the possibility of grout loss during the casting operation.? Cover to concrete shall be provide
26、d as per the drawing and specifications.Fabrication and Fixing Of Steel ReinforcementMaterialsAll reinforcing materials shall be as per approved materials.FabricationBar bending schedule shall be prepared in accordance to approved shop drawing and comply with relevant BS 4466.Method Statement forCon
27、crete Works-SuperstructureDocument No:Rev : 0Date:Page 8 of 11All reinforcement shall be cut to length and bend it to the shape shown in BBS. Slow and steady pressure shall be ensured during bending process. After bending all bars must be securely tied together in bundles and appropriately belted wi
28、th member reference identification.Fixing of Reinforcement? Setting out shall be done by the surveyor prior to proceeding and ITR shall be raised for the CONSULTANT inspection and approvals.? Prefabricated steel shall be placed in position as per approved shop drawings. Approved 1.6mm dia. black ann
29、ealed mild steel wire shall be used to tie reinforcing bar. The ends of the wire shall be bend back away.? Spacer blocks of approved types shall be used to maintain the cover.? Support the reinforcing bar by approved concrete spacer appropriately to prevent displacement during concreting operation.
30、The thickness of cover block shall be as per approved shop drawing and specifications.? Wherever reinforcements are placed in two or more layers, minimum 25mm spacer shall be placed between layers. All bars in upper layers must be placed directly above those in the bottom layers.? All embedment or i
31、nserts related to MEP shall be placed as per approved shop drawings.? All reinforcement must be cleared to ensure that it is free from all oil, corrosion, dust and deleterious materials.Concrete Placing, Compaction & FinishGeneralConcrete placement shall not start until all other trades have com
32、pleted / installed their embedment. Once all embedment are completed CONSULTANT approval shall be obtained by ITR. MEP clearance shall be obtained prior to proceeding.Preparation for PlacingAll surfaces shall be cleared thoroughly, remove any water. De-shuttering oil shall be placed on the formwork.
33、 Adequate safety measures shall be in place. Logistic plan shall be submitted to the CONSULTANT prior to proceeding with concrete pouring.Method Statement forConcrete Works-SuperstructureDocument No:Rev : 0Date:Page 9 of 11Concrete Pouring? Appropriate arrangement and approval for conveying concrete
34、 (Chutes, pump, manual) shall be obtained from CONSULTANT.? Ensure that all the required construction tools, no. of vibrators, lighting arrangement (if needed for the night shift concreting), sufficient supervision staff and manpower is available.? Cranes, concrete bucket, Pumps, chute, Shovel and m
35、anual methods will be used as per the elevation ' quantity of concrete and to suit the site condition towards conveying & spreading concrete.? Concrete shall be delivered to site within 75 minutes after the introduction of the water to the cement, and shall be placed and compacted within 45
36、minutes of arrival. The concrete shall be compacted and in its finial position within 120 minutes of the introduction of the cement to the aggregate. Elapsed time between batching and placing of concrete using combination of GGBS and OPC of 180minutes can be accepted. Subject to trial mix and approv
37、al of slump chart for such period.? Target slump will be 160mm to the mix with a tolerance +40mm as per approved mix design.? Concrete shall not be dropped from a height more that 1.5m to avoid segregation.? Surveyor shall mark the concrete finish level.? Concrete shall be placed in layers not excee
38、ding the specified thickness. The number and size of the vibrators shall be such as to ensure thorough compaction of the entire volume of concrete being placed. The vibrators shall be applied systematically at such intervals and for such periods that dense, compact, homogeneous concrete is produced
39、and segregation and voids do not occur.? Casting of any of superstructure member with their full design depth shall be done in one operation.? Delay between two successive layers must be minimize in order to avoid any cold joint and the next successive layer shall be placed with in initial setting t
40、ime of previous?Adequate illumination shall be provided during night concreting.?Concrete temperature shall be maintained below 30 o C at the time of pour.Method Statement forConcrete Works-SuperstructureDocument No:Rev : 0Date:Page 10 of 11? Adequate 川uminationshall be provided during night concreting and priorapproval to be obtained for night concreting.Concrete Finishing and CuringFinish concrete surface as specified in the approved s
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 盾构隧道施工成本控制考核试卷
- 稀土金属在照明领域的应用考核试卷
- 游戏创意构思与项目策划考核试卷
- 船舶自动消防系统设计与效能评估考核试卷
- 粮食仓储海外仓建设考核试卷
- 火力发电厂运行安全与风险控制技术应用实践考核卷考核试卷
- 多媒体教学模型设计与实现考核试卷
- 肉类副产品在宠物食品领域的应用考核试卷
- 火车站客运服务标准化考核试卷
- 影视特效制作与特效技术交流合作合同
- 杭州铭赫科技有限公司新增年产1260万件精密粉末冶金零部件技术改造项目环评报告
- 福建武夷旅游集团限公司下属子企业2025年上半年社会公开招聘易考易错模拟试题(共500题)试卷后附参考答案
- 2025届上海市华东师范大学二附中高三(最后冲刺)历史试卷含解析
- 雾化吸入疗法合理用药专家共识(2024版)解读 2
- 单位食堂劳务外包服务投标方案(技术方案)
- 养老院老年公寓养老机构医养结合机构院科两级质量管理体系及目标及实施方案2-5-10
- 贵州乌江煤层气勘探开发有限公司招聘笔试题库2025
- 穿线分包合同协议
- 2025年磁化水防垢除垢装置项目可行性研究报告
- 2024年司法考试历年真题答案
- 2025年广东省汕头市高三二模生物试卷(含答案)
评论
0/150
提交评论