版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领
文档简介
1、Copyright Yokogawa Engineering Asia Project Engineering Knowledge Exchange Panel Design28-Sep-2009YSW Copyright Yokogawa Engineering AsiaAgendaProject Engineer Work FlowSystem Architecture DesignPanel Design机柜设计Hardware ChecklistProject Database2 Copyright Yokogawa Engineering Asia Objective3Standar
2、dization the Panel Design Copyright Yokogawa Engineering AsiaPanel Definition4A panel is defined as “Are fabricated as per Yokogawas Control Panel General Specification.” CABINET CONSOLE DESK ENCLOSURE HOUSING Copyright Yokogawa Engineering AsiaPanel Classify5CLASSIFIED AS STANDARD NON- STANDARDv YO
3、KOGAWA MAKEv RITTAL MAKE SYSTEM / MARSHALLING / POWER DISTRIBUTION INSTRUMENT / WALK THRU / MATRIX PANLES Copyright Yokogawa Engineering AsiaBasic Design6BASIC DESIGN CUSTOMER SPECIFICATIONv INPUTSv OUTPUTS PANEL GENERAL SPECIFICATIONTYPE OF PROJECT (GRASS ROOT / REVAMP)项目性质项目性质,改造项目改造项目,新项目新项目 REST
4、RICTIONS IF ANY MOUNTING & CABLE ENTRY电缆走向电缆走向 OUR PAST EXPERIENCESELECTION OF PANEL COMPONENTS机柜尺寸,设备的重量机柜尺寸,设备的重量 TYPICAL PANEL LAYOUTS PANEL SIZES & QUANTITY PROTECTION STANDRADS (NEMA / IP) Copyright Yokogawa Engineering AsiaDetailed Design7BASIC / DETAILED DESIGN v CABLES & WIRES SI
5、ZE / COLOR / MATERIAL / TAGGINGv POWER SUPPLY REQUIREMENT & DISTRIBUTION PHILOSOPHYv GROUNDING AC (230 V or 110V) / DC (24 V) INSTRUMENT (IS & NON-IS) / SAFETY GROUNDING SYSTEM / ELECTRICv STANDARD ACCESSORIES FILTERS / THERMOSTAT / DOOR SWITCH / CABLE SUPPORT电缆槽电缆槽 Copyright Yokogawa Engine
6、ering AsiaDesign8BASIC / DETAILED DESIGN v ENGINEERED COMPONENTS POWER SUPPLY UNIT (PSU) / MAIN CIRCUIT BREAKER (MCB)直流交流供电电缆走直流交流供电电缆走线;考虑电源,网络线干扰线;考虑电源,网络线干扰 BARRIERS / TERMINAL BOARDS RELAYS / RELAY BOARDS TERMINAL BLOCKS / ELCO BOARDSv ENVIRONMENTAL CONDITIONS ELECTROMAGNETIC COMPATIBILITY (EMC)
7、 ANTI - VIBRATION PADS EX-PROOF PURGING Copyright Yokogawa Engineering AsiaDocument Format9DOCUMENT / DRAWING STANDARDv STANDARD OUTTER TEMPLATEv DIMENSIONED DRAWINGSv STANDARD GROUNDING PRESENTATIONv STANDARD COVER SHEET / INDEXv STANDARD POWER DISTRIBUTION PRESENTATIONv STANDARD AUTOCAD BOM / EXCE
8、L BOM Copyright Yokogawa Engineering AsiaDocument Format10AUTOCAD STANDARDS A4 SHEET A3 SHEET端子生成块端子生成块 v AUTOCAD - SETTINGSRE-USE LAYOUTS / REFER OLD PROJECTS DCS HARDWARE COMPONENTS BARRIERS / TERMINAL BOARDS COMMONLY USED COMPONENTSUSE COMPONENTS FROM STANDARDS LIBRARY Copyright Yokogawa Engineer
9、ing AsiaSummary11GOOD PANEL DESIGN TO INCLUDEv SAFETY FIRST交流电缆标识交流电缆标识v RIGHT POWER CONSUMPTION & HEAT DISSIPATION CALCULATION散热量计算散热量计算v ADEQUATE VENTILATIONv GOOD REDUNDANCY DESIGNv CARE FOR FUTURE MAINTENANCEv ERGONOMICS经济性经济性v ABLE TO MEET CUSTOMERS SPECIFICATIONS/REQUIREMENTS.v COST LEADIN
10、G Copyright Yokogawa Engineering Asia Summary12Panels/ConsoleSystem CabinetMR Cabinets/PDPs Misc. CabinetsConsolesYokogawaStandard FCS19” FCS/NodesProSafe PLCOther PLCs备板备板Rittal19” FCS/NodesProSafe PLCOther PLCsYokogawa / RittalIntrinsically Safe-MRsNon-Intrinsically Safe MRsCombined MRsFieldBus/Ha
11、rt CabinetsRelay CabinetsHigh Voltage PDPLow Voltage PDPCCS (Bentley Nevada Cabinets)Yokogawa / RittalWalk Thru CabinetsThird Party ItemsMatrix PanelWith PushbuttonsWith InstrumentsWith AnnunciatorWith MatrixWith CRT/LCD Copyright Yokogawa Engineering AsiaAgendaProject Engineer Work FlowSystem Archi
12、tecture DesignPanel DesignHardware ChecklistProject Database13 Copyright Yokogawa Engineering AsiaCheck List Type14Hardware Check List mainly Incld.Physical checkIO checkFunction checkBOM checkNetwork Structure & Security Copyright Yokogawa Engineering AsiaPhysical Check15Physical check- Apply t
13、o the following : Panel Integration Power Up check上电检查 Hardware internal test Hardware FAT SAT- Objective:To verify the project hardware installation, manufacture, quantity, quality etc are as per the ITB, customer specification, and project specification. Copyright Yokogawa Engineering AsiaPhysical
14、 Check16Physical check-Main Check Point: Panel Integration Hardware internal test Hardware FAT SAT Installation ConditionNANANAPower UpConstuction & AppearanceLayoutLabelEarthCable RoutingSignal TerminationPower DistributionBOM(Quantity) Copyright Yokogawa Engineering AsiaBOM Check17System Archi
15、tecture & BOM check- Apply to the following : Hardware internal test Hardware FAT SAT- Objective: Verify and confirm the system architecture designed is satisfied with the customer and meet Yokogawa specification. Verify that the DCS System staged for testing is as per the DCS System Architectur
16、e Drawing Verify all the material supplied is tally with the contract Copyright Yokogawa Engineering AsiaFunction Check18Function check- Apply to the following : Panel Integration机柜集成 Power Up check Hardware internal test Hardware FAT SAT- Objective:To verify the Network, IO Bus, power supply redund
17、ancy, System start up, CPU back up , FCS offline/online loading, media backup/ restore, FCS/network load etc are as per the ITB, customer specification and project specification. Copyright Yokogawa Engineering AsiaFunction Check19Function check-Main Check Point: Panel Integration Hardware internal t
18、est Hardware FAT SAT RedundancyNASystem StartupCPU BackupOnline/Offline LoadMedia Backup/RestoreNAFCS/Network LoadingNA Copyright Yokogawa Engineering AsiaIO Check20IO check- Apply to the following : Hardware internal test Hardware FAT SAT- Objective: To verify that the interconnection connection sy
19、stem cables between the IO modules and the termination panels have been installed and terminated properly. To verify the software configuration for the individual IO is match with the design input (DCS tag name, Range, Unit, Comments etc) To verify all the IO module accuracy is as per the ITB and Yo
20、kogawa specification. Copyright Yokogawa Engineering AsiaIO Check21IO check- Main items to be included: Instrument tag DCS Tag DCS range & Unit量程单位 IS/Non IS Marshalling Panel Termination Info. IO address in system panel Expected test value for 3 test point Test result Copyright Yokogawa Enginee
21、ring AsiaAgendaProject Engineer Work FlowSystem Architecture DesignPanel DesignHardware ChecklistProject Database22 Copyright Yokogawa Engineering Asia IO Database设备类设备类型型,微耗微耗,本安本安,有源有源,无源无源23Objective To Reduce man-hours by using the standard tools Can provide standardized Hardware Spec Document.
22、Convenient for data exchange between EPC & Yokogawa To reduce the mistake for the project engineering It is the common platform for the project team. Copyright Yokogawa Engineering Asia IO Database24Main workflow for the engineeringPrim toolsAssign RulesSort order SettingIO Module AssignIO ListP
23、RIM Tools SettingHW SpecRevised IO ListPrimDBSPDB Copyright Yokogawa Engineering Asia IO Database25Main workflow for the engineeringPrim MRLoop TypicalPanel InformationCable ListPRIM Tools SettingCable List reportPrimDBIO information by HWFCS MP connectionJB MP connection Copyright Yokogawa Engineer
24、ing Asia IO Database26Main workflow for the engineeringPrim RPAssign RulesBlock AssignmentPRIM Tools SettingPrimDBCable NamePID_TAGFCSModuleTitlePJT NameTypical BlockDrawing DefinitionPJT NameTXCVPJT NameTXCVPJT NameTXCVLoop Drawing Copyright Yokogawa Engineering Asia IO Database27 The project datab
25、ase is the basis for the engineering Project quality rest on Database qualityConclusion:What to do . Try to lead the customer to support our database format Use the excel Macro to compile the DB to reduce the mistake To make sure the information correct Copyright Yokogawa Engineering AsiaProject Dat
26、abase 28Main Parameter Include:SNDescriptionRemark1UnitThe area or unit for the process2pid_shtP&ID sheet number3Instrument_tagInstrument tag name4commentTag service or description5dir_revController output label reverse or not6RedundantThe signal is redundant or non redundant7eng_loEngineering l
27、ow limit value8eng_hiEngineering hi limit value9eng_unitsEngineering unit10linerThe square root to be calculated in DCS for the DP transmitter or not11ctrl actController control action12alarm_hhAlarm high-high limit13alarm_hiAlarm high limit14alarm_llAlarm low-low limit15alarm_lAlarm low limit16IS_NON_ISIntrinsic safety loop or notSNDescriptionRemark17Ext_powerExternal power requirement , 220VAC, 24VDC or others18instrument_typeInstrument type code, TX, SV, CV, etc19Instrum
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 内部股东合作协议书
- 卫生院医院工作总结
- 员工个人承诺书15篇
- 夜班出租车承包合同15篇
- 售票员工作总结14篇
- 2025重庆泰科防务科技有限公司招聘10人笔试参考题库附带答案详解
- Unit 12 What did you do last weekend大单元整体说课稿2025-2026学年人教版英语七年级下册
- 五年级信息技术下册 第十二课 贺卡与大树说课稿 龙教版
- 第16课 瓶花教学设计小学美术赣美版四年级上册-赣美版
- 第二章第一节 位置和疆域说课稿2025-2026学年中图版(北京)地理七年级上册
- 2025广东房屋租赁合同范本官方版
- 新版中华民族共同体概论课件第八讲共奉中国与中华民族内聚发展(辽宋夏金时期)-2025年版
- 2025定制衣柜安装承揽合同范本
- 2025年MicroLED行业研究报告及未来行业发展趋势预测
- 《彩虹》课件 部编版语文二年级上册
- 2025年全国企业员工全面质量管理知识竞赛试题及答案
- 麻醉恢复室护理要点
- 水下激光探测-洞察及研究
- 7.2 量身高(课件)-2025-2026学年三年级数学上册北师大版
- DB44∕T 2499-2024 海堤生态化建设技术导则
- GWZBQ-10(6)G 型微机高压启动器保护装置产品使用说明书
评论
0/150
提交评论