1、1.1 海堤施工方案 Revetment Construction Proposal1.1.1 主要施工内容 Main Construction Works海堤施工主要包括西侧海堤,长约 285m;东侧海堤,长约129.4m;南侧 海堤,长约519m。其断面结构形式均为300KG以内开山石作为堤心料,内侧 采取二片石、倒滤层、土工布的护坡形式,外侧采取碎石垫层、护面块石的 护 坡形式。根据海堤结构形式,结合其底高程的变化,西侧、东侧堤心石施工 考 虑全部陆上抛填;南侧堤心石施工考虑陆上和水上抛石相结合施工的方法。海堤施工计划14个月完成,平均每月 施工强度约18500方。There are t
2、hree revetments to be constructed, that is, west, east & south revetment, which are around 285m,129.4m& 519m respectively in length. All of these revetments are constructed with quarry stone core less than 300kg serving as revetment core materials, and the inner slope protection isconstructedwith In
3、termediate stone, mixed filter layer and geo-textile, while the outer slope protection is constructed with stone cushion layer and armor stone. In consideration of therevetment structure and bottom elevation ranges,the backfilling of quarry stonecoreof the west& eastrevetmentis to be performed in th
4、e manner of onshore construction, while the backfilling of quarry stone core to the south revetment is to be executed via the combination of onshore construction and offshore construction. The revetment is proposed to be completed in 14 monthswith monthly construction strength of 18,500m3.1.1.2 施工顺序
5、 Construction Sequence西侧海堤施工一东侧海堤施工一南侧海堤施工West Revetmentf East RevetmentfSouth Revetment1.1.3 施工流程 Construction Flow基槽开挖一堤心石填筑一海堤内侧护坡施工一护脚施工一外侧护坡施工 Foundation excavation- quarry stone core fillinginner slope protectiontoeprotectionf outer slope protection1.1.4 施工方法Construction MethodA 基 槽开挖 Foundati
6、on Trench Excavation 海堤的基础表层为淤泥质粘土,需要进行基槽开挖。陆上部分采用反铲开挖,自卸车运至抛泥区。水上部分考虑与疏浚工程相结合,采用抓斗式挖泥船进行基槽开挖,1000方 泥 驳运输至附近业主指定的海域进行卸驳。The foundation surface of revetment to be excavatedis silty clay. Onshore excavation is to be carried out with backhoeand the excavatedmaterials are to be transported to the dispos
7、al area by dumpers; offshoreexcavationis to be carried out by grab dredger, 1000m3 hopper barge will be used to transport excavatedmaterials to designatedsea disposalarea.B 堤 心石填筑Filling Quarry Stone Core堤心石填筑考虑陆上抛石和水上抛石相结合施工的方法。陆上抛石是石料直接运输至抛填地点进行抛填,水上抛石是石料运输至临时码头后装驳,方驳运到施工现场,方驳上反铲进行抛石。东侧、西侧海堤采取陆上推进
8、施工从堤根开始,堤心石填筑直接填筑,海堤施工时每隔50m 处设置会车平台。南侧海堤堤心石抛填分两步施工。第一步粗抛,方驳上反铲抛填,考虑长臂反铲上方驳理坡;第二步由陆上推进,自卸车填筑,推土机碾压,反铲或长臂反铲修坡(结合反铲作业半径,海堤底高程为0m 以上 施工段考虑普通反铲修坡,0m 以下施工段考虑长臂反铲修坡,并潜水组配合修坡)。Back-filling of quarrystonecore is to be completed via rip-rap onshore& offshore. For the rip-rap onshore, stone materials are dump
9、ed aftebr eing transported to the site. For the rip-rap offshore, stone materials are shifted to the temporary jetty firstly, then transported to the site by flat barge, and lastly dumped to the site by backhoe on the barge. During the construction of east & west revetment, commence the construction
10、 from the revetmenttoe andfrom the onshore,back-fill corestoneandarrangea vehicle meeting platform every other 50m. The construction of south revetment is to be completed in two steps. In the first step, dump stone roughly by backhoe + flat barge; in thesecondstep, perform construction from onshore,
11、filling with dumper, compacting with bulldozer, trimming the slope with backhoe or long-arm backhoe. Taking intoaccountof the backhoe operation radius, for the construction of trimming slope, use normal backhoe for the revetment with bottom elevation above 0m, and use long arm backhoefor the revetme
12、ntwith bottom elevation under0m with the help of diver team.Fig 4.9 Dumping Stone with Backhoe + Flat BargeFig 4.10 Picture of Filling Quarry Stone CoreC.内侧护坡施工 InnerSlope Protection考虑内侧护坡需在厂区回填前完成,因此每段海堤堤心施工完成之后,需 要先完成内侧的护坡作业,计划采用水陆相结合的施工工艺,自卸车运输石 料 至海堤堤顶,反铲进行抛填并理坡,反铲作业范围外的区域,考虑采用 50T履 带吊上方驳,水上吊抛网兜
13、;Consideredthat the inside slope protection working must be completed before backfilling of station area,the inside slopeprotection is requiredto be completedfirst after completion of dike core construction of eachsection of seawall, for which it is plannedto adopt onshoreand offshore constructionte
14、chnology, i.e., dumpersare used to transportstonematerial to crest of the seawalland backhoeare used to conduct riprapping andslopemaking and it is plannedto riprapping with the 50t crawler crane + flat bargeto lift the steel wire bag in the areabeyond the working scopeof the backhoe.Crawler Crane L
15、ifting and Dumping of StoneD. 土工布铺设 Laying of Geotextile土工布运至现场就位,听从指挥由陆上往水下摊铺,施工尽量选在低潮时 进行,水下施工时派潜水员水下配合。土工布要求紧贴混合倒滤层,并留有 一 定的余量,以平衡土工布收缩和倒滤层基面凹凸不平产生的误差。土工布铺设完毕后,应及时进行其上部袋装碎石压坡施工,以防被水流和波浪冲开,同 时 避免受太阳紫外线照射,使其老化变脆,强度降低,影响土工布铺设质量。After geo-textile being mobilized to the designatedsite,lay thegeo-texti
16、lefrom onshore to offshore. The placement of geo-textile shall be performed during low tide as much as possible and theunderwater laying shall be done with the help of divers. The geotextiles shall be laid closely to the mixed filter layer with certain space, so as to minimize the deviation causedby
17、 the shrinkage of geo-textile and the uneven surface of mixed filter layer. Upon the completion of placing geo-textile, bagged crush stone on the geo-textile shall be laid timely, in case that the geo-textile is washed away by water flow and waves. Meanwhile, the already-laid geo-textile shall be pr
18、otected from the suns ultraviolet rays, since that the exposure under sunshine may cause the geotextile aging, brittle and strengthreducing, and further affect thegeo-textiles quality.E 海 堤护脚施工Toe Protection of Revetment海堤护脚施工待内侧护坡施工完成后开始,反铲装网兜,25T 汽车吊吊网兜装车,自卸车运输至海堤堤顶,50T 履 带吊进行吊抛。After the inner sl
19、ope protection is completed, commencethe construction of revetment toe protection via the mannerfrom onshore.Putstonesinto steelwire bagsby backhoe, lift them with 25T truck crane and transport to site by dumper and then dump them by 50T crawler crane.F 外 侧护坡施工Outer SlopeProtection外侧护坡施工考虑在护脚块石完成后开始,采用反铲直接抛填和履带吊吊抛相结合的工艺进行。反铲作业部分,3m3装载机装块石,自卸车运输至施工场
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2025企业外包合同
- 2025企业间借贷合同应包含的要素
- 管理学中的知识管理试题及答案
- 2025年行政管理考试重点概念试题及答案
- 2025年个体土地赠与合同样本
- 行政管理与社会舆论试题及答案
- 2025电子书赠与的合同范本
- 尝试2025年公文写作与处理试题及答案
- 现代管理技能应用试题及答案
- 管理心理学对情商培养的作用试题及答案
- 江苏交控笔试试题及答案
- 邻补角、对顶角、同位角、内错角、同旁内角经典习题-一对一专用
- HP系列培训手册
- 常见病媒生物分类鉴定
- 毕业论文-原油电脱水方法与机理的研究
- 陕西省2022年普通高中学业水平考试(真题)
- 事故池管理的有关规定
- 2021-2022学年甘肃省天水市第一中学高一下学期第二阶段考物理试题(原卷版)
- 重庆市参加企业职工基本养老保险人员退休审批表
- 混凝土结构课程设计244
- GE全球供应链的管理与实践
评论
0/150
提交评论