V.ConstructionSiteCoordinationManagement
ConstructionGeneralLayoutPlanCoordination
Basedonconstructiondeploymentandmilestonedeliveryrequirementsinvariousphases,GeneralContractorisinchargeofformulatingoverallplanforgenerallayoutplananddelivertechnicaldisclosuretosubcontractorsforcarryingoutdynamicmanagement.
Generalcontractorisresponsiblefordispatchingroad,temporarystorageyard,fixedstorageyardwithinconstructionsiteunitedly.
Thesubcontractorshallsubmit“temporaryaccessroadorstorageyardapplicationsheet’toGeneralcontractorasperproductionrequirementsateachstageforapprovalbyprocedures.
Thesubcontractorshallsubmit“Useofexistingfixedstorageyardapplicationsheet”(Sheet7-2)toGeneralContractorProductionCoordinationDepartmentasperproductionrequirementsateachstageforapproval.
Thesubcontractorsareresponsibleforstandardizedmanagementandmaintenanceofpublicfacilities,surroundingroadswithinfixedstorageyardortemporarysitetheyused,aswellastocaterforGeneralContractor’sstandardizedmanagementrequirements.
TemporaryWaterandPowerSupplyCoordination
GeneralContractorisinchargeofoverallplanningandimplementationfortemporarywaterandpowersupplydeploymentanddelivertechnicaldisclosuretosubcontractors.
Thesubcontractorsareinchargeofconfiguringfull-timetemporarywaterandpowersupplymanagerialpersonnel,whoshouldsubmittoGeneralContractor“Subcontractingusepowergeneralschedule”withinstipulatedperiod,aswellastosign“Temporarywaterandpowerusemanagementagreement”withGeneralContractorwithinoneweek.
Thesubcontractorshallsubmit“Useoftemporarypowersupplyapplication”toGeneralContractorProductionCoordinationDepartmentasperproductionrequirementsateachstageforapproval.
ThesubcontractorsareinchargeofsafetymanagementoftemporarywaterandpoweruseandacceptdailyinspectionfromGeneralContractor,aswellasrectifythediscoveredproblemsduringinspectionandmakereplyimmediately.
TemporaryFacilitiesCoordination
GeneralContractorisinchargeofoverallplanningandimplementationfortemporaryfacilities,formulatingusageallocationschemeanddelivertechnicaldisclosuretosubcontractors.
Thesubcontractorshallsubmit“Useoftemporaryfacilities(office,living)applicationsheet”toGeneralContractorProductionCoordinationDepartmentasperproductionrequirementsateachstageforapproval.
ThesubcontractorsareinchargeofmaintainandmanagetemporaryfacilitiesuseandacceptdailyinspectionfromGeneralContractor,aswellasrectifythediscoveredproblemsduringinspectionandmakereplyimmediately.
ThesubcontractorsareinchargeofapplyingoverallacceptanceandhandovertoGeneralContractoraftertemporaryfacilitiesusagecompleted.
MaterialandEquipmentMobilizationandDemobilizationCoordination
Thesubcontractorsshallsubmitdetailedmaterial,equipmentmobilizationapplicationscheduleinaccordancewithGeneralContractor’sconstructionprogresstoconfirmmaterial,equipmentname,specification,modelandmobilizationtime.
Thesubcontractorsareinchargeofmaterialmobilizationanddemobilization,whoshallpreparedocumentswhichinclude,butnotlimitedto,materialtype,transportationmode,qualityassurance,etc.aswellassubmit“Material/equipmentmobilizationanddemobilizationapplicationsheet”toGeneralContractorProductionCoordinationDepartmentforapproval.
ThesubcontractorsareinchargeofabidebyGeneralContractor’ssitematerialandequipmentmanagementsystem,pileupmobilizedmaterialandequipmentingoodorder,acceptdailyinspectionfromGeneralContractor,aswellasrectifythediscoveredproblemsduringinspectionandmakereplyimmediately.
VerticalTransportationCoordination
GeneralContractorisinchargeofoverallplanningandimplementationforverticaltransportationequipment,formulatingprojectverticaltransportationschemeanddelivertechnicaldisclosuretosubcontractors.
Thesubcontractorsshallsubmit“Subcontractverticaltransportationequipmentuseschedulesheet”toGeneralContractorforapproval.
Thesubcontractorshallsubmit“Useofverticaltransportationapplicationsheet”toGeneralContractorProductionCoordinationDepartmenteverydayasperdailyconstructiondemandforapproval.
GeneralContractorisinchargeofplanningallsubcontractors’verticaltransportationequipmentusesituationasawholeandformulatingandpublic“Dailyusedistributionsheetofverticaltransportationequipment”,aswellascoordinateandresolveemergentproblemsamongsubcontractorsforusingverticaltransportationequipment.
Thesubcontractorsareinchargeofconfigurefull-timestafftomanageverticaltransportationwithinsubcontractorsandcooperateGeneralContractortocoordinateandresolveemergentproblemsamongsubcontractorsforusingverticaltransportationequipment.
GeneralContractorisinchargeofarrangingverticaltransportationequipment’skeepandmaintenance,attachment,jackingtimereasonablyandgivetopublicitytimely.
PublicOperationPlatformCoordination
GeneralContractorisinchargeofformulatingoverallplanforpublicoperationplatformanddelivertechnicaldisclosuretosubcontractorsinaccordancewithcontractorganizationorentrustsubcontractorstoerect,dismantleandmaintainpublicoperationplatform.
Thesubcontractorshallsubmit“Dismantleofpublicoperationplatformapplicationsheet”toGeneralContractorProductionCoordinationDepartmentforapprovalduetotheneedofaltering,dismantlingplatform,dismantleshallbeconductedonlyafterobtainedtheapproval,whichcouldbeusedonlyafterinspectionandacceptanceofdismantlingandalteration.
GeneralContractorisinchargeofsupervisingpublicoperationplatform’susecondition,handlingmisusetimely.
PublicSecurityProtectionCoordination
GeneralContractorisinchargeofunifyingpublicsecuritystandardinaccordancewithcontractorganizationorentrustsubcontractorstofitwithpublicsecurityprotectionfacilities,aswellasdelivertechnicaldisclosuretosubcontractors.
GeneralContractorisinchargeofpublicsecurityprotectionandsupervisionwithinpublicarea,thesubcontractorsareresponsibleforsecurityprotectionandsupervisionwithinworkingface.
Thesubcontractorshallsubmit“Dismantleofpublicsecurityprotectionapplicationsheet”toGeneralContractorProductionCoordinationDepartmentforapprovalduetotheneedofaltering,dismantlingsafetyprotection,dismantleshallbeconductedonlyafterobtainedtheapproval,whichcouldbeusedonlyafterinspectionandacceptanceofdismantlingandalteration.
GeneralContractorisinchargeofmanagingsecurityprotectioninconstructionsiteasawhole,aswellasexecutesupervisionandacceptanceworksforsafetyprotectiondismantlingandalteration.
SiteElevationAxisCoordination
GeneralContractorisresponsibleforpreparingoverallsurveycontrolscheme,establishingLevel1planeandverticalcontrolnetwork,mainaxis,elevationcontrolnetworkswithinsitearea,aswellasmakeidentificationandcarryoutdailymaintenance,meanwhiledelivercontrolpointandcontrolaxisdisclosuretosubcontractors,finishhandoverworks.
Thesubcontractorsareinchargeofconfiguringqualifiedsurveyors,surveyinginstrument,calibratesurveyinstrumentperiodicallyandsubmittoGeneralContractorforregister.
Thesubcontractorsareinchargeofmeasuringpass,settingout,measurementtesting,deformationmonitoring,etc.
SiteConstructionInterfacesCoordination
GeneralContractorisinchargeoforganizesubcontractorstoidentifyallinterfaces,form“Interfacematrixtable”,“Interfacedivisionschematicdiagram”.
Thesubcontractorsareinchargeoffamiliarizingwithconstructioncontract,incaseofrequiringothersubcontractors’cooperationmatters,draftalistandsubmitGeneralContractorforregister.
GeneralContractorisinchargeofformulatingsubcontractors’workingfacetransferplanasperprogressprogramme,aswellasorganizerelatedpartiestotransferworkingfacesasscheduled.
Asreceiverofworkingfaces,thesubcontractorsareinchargeofpreparingcriticalarea’stransferlist,underGeneralContractor’smanagement,makethreetiertransfercheckandformcheckrecord.
Asreceiverofworkingfaces,thesubcontractorsareinchargeofcompletingtheremainedworksandrectifyingthedefectedworkstoachievetransferrequirementsasscheduledpursuantto“Keyarea’sworkingfacetransferlist”requirementsprovidedbythereceiver.
VI.PublicResourcesManagement
ManagementKeyPointsatEachStage
ManagementProcess
ManagementKeyPoints
Planemanagement
(1)Layoutplanninganddeployment
(2)Siteandroadapproval
(3)Dailymanagementoftrafficorganizationandcivilizedconstruction
Temporarywater,powersupplymanagement
(1)Planningandtotalquantitycontrolfortemporarywaterandpowersupply
(2)Managementagreementsigningfortemporarywaterandpowersupply
(3)Temporarywaterandpowersupplyapproval
(4)Managementresponsibilitydivisionanddailymaintenance
Temporaryfacilitiesmanagement
(1)Implementationoftemporaryfacilitiesplanninganddeploymentpursuanttocontracttype
(2)Approvalandacceptanceoftemporarilyusedlandandfacilities
(3)Dailysupervisionoftemporaryfacilities
(4)Transferandcountertransferoftemporaryfacilities
Verticaltransportationequipmentmanagement
(1)Planninganddailymaintenanceofverticaltransportationequipment
(2)Supervisionofsubcontractors’verticaltransportationequipmentusageplan
(3)Dailyapprovalanddisplaytopublicforverticaltransportationequipment
(4)Dailysupervisionandstatisticalanalysisforverticaltransportationequipmentuse
Publicoperationplatformmanagement
(1)Publicoperationplatformplanninganddeployment
(2)Dailysupervisionandcoordinationforpublicoperationplatformuse
(3)Approvalofpublicoperationplatformdismantleandalter
Publicsecurityprotectionmanagement
(1)Prepareunifiedstandardanddeploymentforpublicsecurityprotection
(2)Publicsecurityprotectiondismantleandalterapprovalandacceptance
(3)Publicsecurityprotectiontransfer,acceptanceandcountertransfer
(4)Dailymaintenanceandsupervisionforpublicsecurityprotection
Surveymanagement
(1)Preparationandimplementationofgeneralsurveycontrolscheme
(2)Transferanddailymaintenanceofcontrollingpointandaxis.
(3)Supervisionandmanagementforsubcontractors’surveyexecution,surveyresult,personnelandequipment.
PlaneManagement
Basedonconstructiondeploymentandmilestonedeliveryrequirementsinvariousphases,toorganizegenerallayoutplan’soverallplanning,deploymentanddeliverdisclosuretosubcontractorsforcarryingoutdynamicmanagementtoensureitseffectiveness.
Temporarywater,powersupplymanagement
Toberesponsibleforoverallplanningconstructionsitetemporarywater,powersupplyarrangement,implementorentrustimplementationaccordingtocontractrequirementsanddeliverdisclosuretosubcontractors.
Temporaryfacilitiesmanagement
MakeOverallplanningfortemporaryfacilitiesandimplementaccordingtocontractrequirements,establishusescheduleanddeliverdisclosuretosubcontractors,whoareinchargeofusenormallyandmaintainperiodically.
Verticaltransportationequipmentmanagement
DesignandTechnicalDepartmentareresponsibleformakeoverallplanninganddeploymentofverticaltransportationequipment,constructionandcoordinationteamareinchargeofdeliveringdisclosuretosubcontractors,aswellasinstall,dismantle,maintainverticaltransportationequipmentaspercontractorganizationorentrustimplementation.
Publicoperationplatformmanagement
DesignandTechnicalDepartmentareresponsibleformakeoverallplanninganddeploymentofpublicoperationplatform,constructionandcoordinationteamareinchargeofdeliveringdisclosuretosubcontractors,aswellasinstall,dismantle,maintainpublicoperationplatformaspercontractorganizationorentrustimplementation.
Publicsecurityprotectionmanagement
Tounifypublicsecurityprotectionstandard,organizeorentrustimplementationofpublicsecurityprotectionfacilitiesanddeliveringdisclosuretosubcontractors,thesubcontractorsareinchargeoferectingormaintainself-workingface’ssafetyprotection.
SurveyManagement
Totransferplaneheightmeasurementcontrolpointtotheemployeranddore-measurementforcontrolpoint,topreparegeneralsurveycontrolschemeandestablishlevel1planeandheightcontrolnetworkswithinsite,thesubcontractorsshallcompletetheirownsurveyingworksandberesponsibleforsurveyingresults.
Tosetupmainaxis,elevationcontrolnetworkswithinsite,aswellasmakeidentificationanddailymaintenance,deliverdisclosuretosubcontractorsinrespectofcontrolpointsandcontrolaxiswithinsiteandcompletehandoverworks.Toinspectandchecksubcontractors’surveyors,surveyinginstrumentandsurveyscheme.
Tourgesubcontractorstoestablishsurveyinstrumentmanagementlist(Table9-2);tosupervisesubcontractorstocalibratesurveyinstrumentperiodicallyandsubmittoGeneralContractorforregister.
Toreviewsubcontractor’ssurveyingresultandorganizesubcontractorstoresolvesurveyingtolerancetimelytoformsurveyingresultasawhole.
Tosupervisesubcontractorstocompletesurveypass,settingout,measurementdetection,deformationmonitoring,etc.,supervisesubcontractorstomakeidentificationandmaintenanceoftheirsurveyingaxis,elevationcontrolpoints.
VII.InterfaceManagement
ConstructionProcedureInterfaceManagement
Toorganizesubcontractorstoprepare“Keypartsconstructionprocedureslist”asper“Interfacematrixtable”,“Interfacedivisionschematicdiagram”submittedbydetaileddesignteam.
Toberesponsibleforprepareimplementationscheduleforkeyparts’constructionprocedureprocessandurgesubcontractorstoorganizeconstructionasscheduled.
Toorganizesubcontractorstohandoverworkingprocedure,asfordefectedworksdiscoveredinhandingoverprocess,recordtimelyandsuperviseinvolvedpartytorectifyasscheduled.
Afterrelatedparties’rectificationcompleted,recordinwritingandsignatureon“Keypartsconstructionprocedureflowchart”.
ConstructionWorkingFaceManagement
Topreparesubcontractors’workingfacetransferscheduleaccordingtoprogressplan,toarrangeworkingfacetransferasawholeandminimizeprofessionalsubcontractorsinsoleworkingface,aswellasminimizesiteconflictandcontradiction.
BuildingDepartmentisresponsibleforcoordinatingprofessionalsubcontractorswithinsoleworkingface.
Toorganizesubcontractorstopreparekeyparts’workingfacetransferlistforprovidingbasisforthreetierjointinspection.
Toorganizeallrelatedsubcontractorsandsupervisorstoinspectjointlyforsiteworkstoensureallinterfaces’workscouldtransferasscheduled.
Tourgetransfersubcontractorimplementrectificationplanasper“Workingfacethree-leveltransfercheckinglist”,tohandleformaltransferformalities.
VIII.CoordinationandCooperationMeasuresfortheEmployerandDesigner
CoordinationandCooperationMeasureswiththeEmployer
Service
Contents
Strengtheningcommunicationandmutualunderstandingwiththeemployer
Toconsulttheemployerforrelatedsuggestionsonprojectconstructionsubjecttotheemployer’sconstructionintention,forquestionsproposedbytheemployer,whichshallberepliedandhandledinatimelymanner,toimproveourworkuninterruptedly.
Beagoodassistantandadviserfortheemployer
Todevelopourcompany’stechnologyadvantageintofullplaysubjecttotheemployer’sconstructionintention,takeintoconsiderationofproblemsfromtheperspectiveofproject’susagefunction,designreasonability,constructionreliabilityandtogivereasonablesuggestions.Inaccordancewithcontractrequirements,organizeconstructionscientificallyandreasonably,coordinationandmanagementofprojectuniformly,aswellastosolvevarioustroublesappearedinperformanceoftheworkstolettheemployertrust.Todevelopprojectregularmeetingsystemandstrengthencommunicationtosolvequality,progressrateproblems,aswellastosetupsitemanagementteamtostrengthencorrelationwithlocalauthoritiesandsolvepossibledisturbanceoflocalresidents’problemstimely.Asforsectionalacceptance,incaseofobtainingsupportfromProjectManagementBureau,whichisbeneficialforfutureworkconstruction.
Serviceforfinaluser
Tocarryoutconceptof“withfinaluserasguidance,lifecyclemanagement”asrequiredbytheemployer.Inthelightofcoordinationplan,tocoordinatewithfinaluserrepresentativeandlistentoopinionsandsuggestionswhattheyhaveforperforminggoaldirectedin-depthdesignpriortodetaileddesigninvolvedwithfinaluser’susagefunction.
Collectionserviceforprocessinformation
Inthecourseofinformationtransfer,keyinformationtendtobelost,whichwillresultinvarioustroublesappearedforfinaluser’susage.Adoptionofinformationmanagementtechnologyincooperationwiththeemployercaneffectivelytransferimportantinformation,aswellasprovideserviceforwholelifecycleofbuildings.
CoordinationManagementMeasureswithDesigner
Weherebycommitthat:tocompletelyensuremutualcoordinationandcooperationwithdesignerduringperformanceoftheworks,aswellastocooperatedesignertosolveproblemsinrelationwithprojectdesignandtechnologyeffectivelyandtimelytoensuretheworksconstructioncouldcaterfortheemployerandspecificationrequirements.
S/No.
CoordinationandCooperation
1
Cooperatewiththeemployerfororganizingdesigndisclosure,drawingreviewingandberesponsiblefortechnologycoordinationinaspectsoforganizationdesignandconstruction,whichincludethefollowing,butnotlimitedto,toproposesuggestionsforanyqueriesforshopdrawings.Onceobtainedtheapprovalfromtheemployeranddesigner,issueddesignvariationorworksalternationimmediatelywithoutmodificationofdrawings;Inperformanceoftheworks,incaseofproblemsoccurred,tocommunicatewiththedesignersandsolveproblemstimely,aswellasproposequestionspriortoconstructionstartforavoidingcausinglosses.
2
Coordinatewithvariousprofessionalsubcontractorswhoneedtonegotiatewithdesignerinconstructionforresolvingproblemstorefrainfromlargequantitydismantleandalterationworksinlaterstage,makeM&Econstructionproceduresmoothly;UrgemainM&Esubcontractortocarryoutin-depthdesignasperprojectrequirementsandsubmittotheemployer,thedesignerandtheengineerforapprovalwithanexpeditespeed.
3
Projectconstructionisbasedondetailedconstructiondesigndocuments.GeneralContractorwillassumeresponsibilityofdoingconstructabilityanalysisinpremiseofcoordinationwithdesigner,aswellasinvitethemtojoininmajordesignschemeandkeyequipmenthoistingschemestudy.
4
Designworkisthebasisforequipmentandmaterialprocurement,siteconstruction,whichalsosetgoalsforrealizingprojectgeneralcontracting,duringthecourseofimplementation,controlandclosing,equipmentandmaterialpurchaseareonthepremiseofdesign.Generalcontractorwillactivelyverifywithdesignerforsupplier’stechnicaldocumentanddrawingsforreviewandconfirmation.Inequipmentmanufacturingprocess,thedesignerwillassistpurchasertoresolverelevanttechnicalproblems,wherenecessary,heshouldjoininkeyequipmentandmaterial’sinspectionorganizedbypurchaserstoensurelargeequipment’stimelymobilizationintositefortheproject.
DrawingReviewingandCooperationMeasureswithDesigner
ProjectContents
KeyPointforDrawingReviewingandCooperationMeasureswithDesigner
CivilWorks
Tocalibrateaxis,elevationandstructuraldimensioninalignmentwithstructureandshopdrawing,toprepareannotationinalignmentwithstructuraldesigngeneraldescriptionanddrawingdetails,calibrateconcretegradeofvariouselevationsegmentandstructuralpart;tocalibraterebaroverlapping,anchorage,nodedetailsinalignmentwithstructuraldesigngeneraldescriptionandstandardschematicdrawings;tocalibrateallfunctionalroom’sarchitecturalpracticeinlinewitharchitecturaldesigngeneraldescription,architecturalpracticelistandvariousbuildingfloorlayoutplan;tocalibratereservedholes,componentinpipelineinlinewithstructure,buildinganderectiondrawings.Promptlyreporttodesigner,adjustandrectifyincaseofproblemsfound.
M&Eworks
TocalibrateM&Ereservedpre-buriedholes,ironaccessories’location,equipmentbaselocationinalignmentwithM&Eandcivilworksdrawing;tocalibratecorrelationinalignmentwithwater,power,heatingandventilation,airconditioning,etc.drawing.Promptlyreporttodesigner,adjustandrectifyincaseofproblemsfound.
W
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2026年南京视觉艺术职业学院单招职业适应性考试题库附答案详解(黄金题型)
- 2026年保定职业技术学院单招职业适应性考试题库含答案详解(新)
- 2026年北京科技大学天津学院单招职业倾向性考试题库及答案详解(考点梳理)
- 2026年六盘水幼儿师范高等专科学校单招职业技能测试题库及答案详解参考
- 2026年南昌交通学院单招职业适应性测试题库附参考答案详解(黄金题型)
- 2026年汽车维修技师专业试题含新能源汽车维修
- 2026年法律职业道德与职业规范试题
- 2026年公务员面试技巧与心理测评综合试题库
- 2026年环保技术与绿色发展政策试题
- 2025年建筑工程实验员面试题库及答案
- 2025年潍坊工程职业学院单招职业适应性考试题库附答案解析
- 安全生产费用投入等制度
- 2026版离婚协议书(官方标准版)
- 工业工程女生职业发展指南
- 生产过程安全基本要求
- 北京市2025北京市公园管理中心所属事业单位招聘111人笔试历年参考题库典型考点附带答案详解(3卷合一)2套试卷
- 2026年江苏医药职业学院单招职业倾向性测试题库含答案
- 湖北交投集团考试真题及答案
- 人体八大系统课件
- 2025年安全生产典型事故案例
- 济宁殡葬管理办法
评论
0/150
提交评论