FinanceandEconomicsDiscussionSeries
FederalReserveBoard,Washington,D.C.
ISSN1936-2854(Print)
ISSN2767-3898(Online)
OnCommercialConstructionActivity’sLongandVariableLags
DavidGlancy,RobertJ.Kurtzman,andLaraLoewenstein
2024-016
Pleasecitethispaperas:
Glancy,David,RobertJ.Kurtzman,andLaraLoewenstein(2024).“OnCommer-cialConstructionActivity’sLongandVariableLags,”FinanceandEconomicsDiscus-sionSeries2024-016.Washington:BoardofGovernorsoftheFederalReserveSystem,
/10.17016/FEDS.2024.016
.
NOTE:StafworkingpapersintheFinanceandEconomicsDiscussionSeries(FEDS)arepreliminarymaterialscirculatedtostimulatediscussionandcriticalcomment.TheanalysisandconclusionssetfortharethoseoftheauthorsanddonotindicateconcurrencebyothermembersoftheresearchstafortheBoardofGovernors.ReferencesinpublicationstotheFinanceandEconomicsDiscussionSeries(otherthanacknowledgement)shouldbeclearedwiththeauthor(s)toprotectthetentativecharacterofthesepapers.
1
OnCommercialConstructionActivity’sLongandVariableLags*
DavidGlancyyRobertKurtzmanzandLaraLoewensteinx2
1FederalReserveBoard
2FederalReserveBankofCleveland
March27,2024
Abstract
Weusemicrodataonthephasesofcommercialconstructionprojectstodocumentthreefactsregardingtime-to-planlags:(1)plantimesarelong—about1.5yearsonaverage—andhighlyvariable,(2)roughlyone-thirdofprojectsareabandonedinplanning,(3)propertypriceappreciationreducesthelikelihoodofabandonment.Weconstructamodelwithendogenousplanningstartsandabandonmentthatmatchesthesefacts.Endogenousabandonmentmakesshort-termbuildingsupplymoreelastic,aspriceshocksimmediatelyaffecttheexerciseofconstructionoptionsratherthanjustplanningstarts.Themodelhasthetestableimplicationthatsupplyismoreelasticwhentherearemore“shovelready”projectsavailabletoadvancetoconstruction.Weuselocalprojectionstovalidatethatthispredictionholdsinthecross-sectionforU.S.cities.
Keywords:commercialrealestate,construction,timetoplan
JELClassification:R33,E22,E32,L74
*ThankstotheaudienceattheFederalReserveBoardR&Sworkshopfortheirhelpfulcommentsandsuggestions.TheviewsexpressedinthispaperaresolelythoseoftheauthorsanddonotnecessarilyreflecttheopinionsoftheFederalReserveBoard,theFederalReserveBankofCleveland,ortheFederalReserveSystem.
yPrincipalEconomist,DivisionofMonetaryAffairs,FederalReserveBoard,david.p.glancy@
zPrincipalEconomist,DivisionofResearch&Statistics,FederalReserveBoard,robert.j.kurtzman@xResearchEconomistII,FederalReserveBankofCleveland,lara.loewenstein@
2
1.INTRODUCTION
Commercialconstructionaccountsforasizableportionofprivatedomesticinvestment
(about20%)andisanimportantdriverofinvestmentfluctuations.1
Commercialcon-structioninvestmentisalsowellknowntorespondslowlytoeconomicshocks(
Edge,
2007
),dueinparttoitslongplanninghorizons(
Millaretal.,
2016
).Indeed,Figure
1
plotsyear-over-yearchangesincommercialandtotalgrossprivatedomesticfixedinvestmentandshowsthatcommercialconstructionisbothmorevolatileandslowertorespondtobusinesscyclefluctuations.Ifeconomicconditionsdeteriorateoverthecourseoftheselongplanninghorizons,developersmayabandonprojectsbeforestartingconstruction.Existingworkonsucheffectsislimited,dueinparttodifficultiesmeasuringconstructionactivitythatdoesnotoccur.
Inthispaper,weuseuniquemicrodataonthephasesofconstructionformorethan200,000U.S.commercialconstructionprojectstodisciplineatractabletime-to-planmodelofbuildingproductionwithendogenousabandonment.Ourdataincludesbothcompletedandabandonedprojects,anditincludesapanelofthephasehistoryforeachproject,allowingustoobservetheextentofandtimevariationinabandonmentfromplanning.Wedevelopthemodeltomatchthreefactsfromthemicrodata.First,commercialconstructionprojectshavelongplanninghorizons.Theaveragetimespentinplanningforprojectsthatmakeittoconstructionisabout1.5years,roughlysimilartoaverageconstructiontimes.Second,asignificantnumberofprojectsinplanning(around40percentonavalue-weightedbasis)areabandonedbeforebeginningconstruction.Almostallabandonmentshappenduringtheplanningstage:oftheprojectsthatmakeittotheconstructionphase,over99percentarecompleted.Third,whetherprojectsadvancefromplanningtoconstructionisstatedependent.Specifically,highercommercialpropertypricegrowthattheonsetofaprojectincreasestheprobabilityoftheprojectbeingcompleted.
Inthemodel,developersoptimallychoosehowmuchtoinvestinplanningstartsandwhetherprojectsthatcompleteplanningproceedtoconstruction.Projectsinplanning
1ThesourceistheBureauofEconomicAnalysis.Thenumeratoristhesumofnonresidentialandmultifamilystructuresinvestment(FREDseriesB009RC1Q027SBEAandC292RC1Q027SBEA),whilethedenominatorisFREDseriesGPDI.Notethatnonresidentialstructuresincludesotherstructuretypesthanthoseinthemicrodatainthispaper,suchasmanufacturingandpower.
3
areoptionstoengageinconstructionthatdeveloperschoosetoexercisebasedonpre-vailingpropertyvaluesandbuildingcostsattheconclusionofplanning.Themodelmatchesthefactsfromthemicrodataandalsohasanimportantimplicationforthesupplyofcommercialbuildings:thenear-termresponseofconstructionactivitytopriceappreciationdependsontheavailabilityofprojectsinplanning.Priceappreciationcanaffectconstructionactivitybybothstimulatingplanningstartsandbycausingmoreprojectsinplanningtoadvancetoconstruction.Becauseplanningstartsareslowtotranslateintoconstructionactivity,thissecondchannelisthemaindriverofshort-termsupplyelasticitiesandisdependentontheavailabilityof“shovelready”projectsthatcanimmediatelybeginconstruction.
Wetestthismodelimplicationbyempiricallyexaminingcross-sectionaldifferencesintheresponseofconstructionactivitytopriceappreciation.Specifically,weuselocalprojec-tionstotraceouttheresponseofconstructionstartstocommercialpriceappreciationfor
metropolitanstatisticalareas(MSAs)withdifferentinitialstocksofprojectsinplanning.2
Wedemonstratethatconstructionstartsareincreasinginpricegrowth,andthisresponsedependsimportantlyonthestockofprojectsinplanning,aspredictedbythemodel.Asfurthervalidation,wefindsimilarresultsforemploymentgrowthforthesectorsmostengagedincommercialconstructionactivity.
Inthefinalpartofthepaper,wecalibrateandsolveastandardDSGEmodelextendedtoincludethecommercialplanningandconstructionenvironmentfromourearliersetup.Relativetothepartialequilibriummodel,theDSGEmodelallowsustoendogenizecommercialpricesandtoquantitativelyexaminethemodel’sdynamics.Weshowthatendogenousabandonmentspeedsuptheresponseofconstructionactivitytoshocks(comparedtoanequivalentmodelwithexogenousabandonment).Thishighlightshow,eventhoughplantimesarelong,investmentmaystillrespondquicklytoshocksifthereareprojectsalreadyunderwaythatareonthemarginofadvancingtoconstruction.Additionally,wedemonstratethestate-dependentnatureofhowconstructionactivityrespondstoshocks.Ifaneconomyhasalowstockofprojectsinplanning,itisless
2WeconstructthemeasuresofpriceappreciationandconstructionstartsrelativetothebuildingstockbypropertytypeandMSAsusingacombinationofdatafromCostar,RealCapitalAnalytics(RCA),andCBRESupplytrack.
4
responsivetoeconomicshocksthananotherwisesimilareconomystartingatsteady-state
planninglevels.Namely,theresponseofconstructionactivityqualitativelymatchestheimpulsesfromthelocalprojectionsanalysis.
Thequantitativeworkinthispapermostcloselybelongstotheliteratureontimetobuild.Inseminalworkinthisarea,
KydlandandPrescott
(1982)layoutaninvestment
technologythatincorporatestimetobuildandintegrateitintoamacroeconomicmodel,demonstratingtherelevanceofthistechnologyformatchingkeybusinesscyclefacts.
Christianoetal.
(1996)extendthemodeltoincorporateaplanningphase—aperiodof
less-resource-intensiveinvestment—anddiscussitsroleinexplainingbusinesscyclefacts.Morerecentworkbuildson
MajdandPindyck
(1987)toanalyzehowtheoptionvalueof
delayinginvestment(OhandYoon,
2020)ordiscountrateshocks(
FernandesandRigato,
2023
)affectbuildtimes.Additionally,contemporaneousworkby
Ohetal.
(2024)shows
thatlongdevelopmenttimelinesinresidentialhousingmatterforthebusinesscyclepropertiesofhousing.Ourworkdevelopsfactsthatdisciplinetheroleofendogenousabandonmentintheplanningphaseina“timetoplan”model;inturn,constructionsrespondsmoreswiftlytoeconomicshocksinourmodelbecauseofchangesinwhetherprojectsthatcompleteplanningadvancetoconstruction.
Thispaperalsocontributestotheliteratureexaminingthecommercialconstructionsector.TheU.S.CensustracksconstructiontrendsthroughtheBuildingPermitsSurveyandtheSurveyofConstructiontoassesstheevolutionofthetimeittakestocompletetheconstructionprocessintheUnitedStates.ThesesurveysprovideimportantinsightsintotheevolutionofconstructionintheUnitedStates,withthecaveatthattheyarefocusedon
onlyresidential(asopposedtocommercial)construction.3
Thenonresidentialcommercialrealestate(CRE)constructionprocessislesswellunderstoodgiventhereishistoricallylessqualitydatainthespace.GiventhatnonresidentialCREisalargeandimportantassetclass(
Ghentetal.,
2019
),thisisasignificantgapintheliterature.
Theclosestcounterparttoourempiricalworkisthatof
Millaretal.
(2016).Theauthors
usesimilardatatoexaminethedeterminantsofplanninglagsforcompletedprojects,
3NotallsurveysrelatedtoconstructionfromtheCensusfocusonresidentialconstructiononly.Forexample,theValueofConstructionPutinPlaceSurveyincludesinformationonnonresidentialCREconstructionspending.Thedatausedinthispaperareusedinparttodevelopthestatisticsinthatsurvey.
5
highlightingtheroleofregionaldifferencesinlanduseregulation.
DelBocaetal.
(2008)
providefirm-levelevidencethatstructuresinvestmentissubjecttolongertime-to-planandtime-to-buildeffectsthanequipmentinvestment.Inotherwork,
Bischoff
(1970)
examinesmodelsofnonresidentialinvestmentandtheirrelationtothedata.Ourworkdemonstratesthekeyroleabandonmentplaysinthedynamicsofthesector.
Theremainderofthepaperproceedsasfollows.InSection
2,wedescribethedataand
establishthefactsoncommercialconstructionthatwewillusetodisciplinethemodel.InSection
3,wepresentapartialequilibriummodelofthecommercialconstructionprocess
thatcanmatchthesefactsandderivehowtheshort-termelasticityofbuildingsupplydependsonthestockofprojectsinplanning.InSection
4,wetestthispredictionand
demonstratethattheresponsivenessofconstructionactivitytochangesinpricesisindeedafunctionoftheplanningstock.InSection
5,weembedthePEmodelfromSection
3
inacalibratedDSGEmodelandexaminethequantitativeimplicationsofthemodel.InSection
6,weconclude.
2.FACTSONCOMMERCIALBUILDINGCONSTRUCTION
Inthissection,wefirstdescribethedata.4
Wethenprovideanoverviewoftypicalplanningandconstructiontimelinesincludinghowoftenandunderwhatcircumstancesprojectsareabandoned.Finally,wesummarizethekeystylizedfactsthatwilldisciplinethemodel.
2.1.ConstructionPhaseDataandOtherDataDetails
ThedatafromCBRE-EA/SupplyTrackrelyoninformationcollectedfromDodgeData&Analytics(DD&A).ConstructionstartsfromDD&AareusedbytheU.S.Censusaspart
oftheirmethodologyforestimatingmonthlyconstructionspending.5
Millaretal.
(2016)
4AdditionaldetailsonthedataareavailableinAppendix
A.
5Ourdataincludesdataonconstructionstartsalongwiththepre-andpost-startphasesformultifamily,hotel,office,retail,andwarehouseproperties.ThemonthlyconstructionspendingdatafromtheCensusprovidesestimatesofallconstructionspendingintheU.S.,notjustthepropertytypesconsideredinthispaper.NotethattheCensususesotherdatasourcesandmethodsaswell.Themethodologyforthesurvey
6
documenttimetoplaninthisdatasetthrough2010;oursamplegoesthroughtheendof2022.
Thedataincludesmonthlyinformationontheconstructionphaseforeachproject,wherethephasesare:pre-planning,planning,finalplanning,bidding,underway,completed,deferred,andabandoned.AccordingtoCBRE,thesephasesaregenerallydefinedasfollows.Planningstageprojectshavegenerallyalreadyhiredanarchitectthathasstartedtodrawupplans.Thefirstmonthoftheunder-constructionphase(thestart)occursafteracontracthasbeensignedbetweenageneralcontractorandthedeveloper.Atthispoint,permitswouldtypicallybepulledandtheprojectshouldbreakgroundwithinafewmonths.Aprojectcanbedeferredindefinitelyfromanyphaseinthedata.Thedatadonotincludeinformationonthereasonforthedeferral,butpossiblereasonsincludegoingoverbudget,marketconditionsworsening,orfinancingbeingpulled.Afinalstateforaprojectiseithercompletedorabandoned.Forouranalysis,wegroupprojectsin
pre-planning,planning,finalplanning,andbiddingtogether.6
Wetreatdeferredprojectsasaseparatecategoryunlesswestateotherwise.
Alongwiththephases,thedataincludeinformationontheproperty’stype,itssquarefootage,thetotalcostofconstructionfortheproject(oranestimateforthatspendforprojectsinplanningorbidding),anddetailedgeographicinformation.
Toexaminecommercialrealestatesupplyelasticities,wealsouseinformationoncom-mercialpropertypriceappreciationfromCoStar.ThedatauseCREtransactionstoestimatepriceindexesattheproperty-typeCBSAlevel.Sincesomeofouroutcomes(e.g.,constructionemploymentgrowth)areatthemarketlevel,wetaketheaveragepriceappreciationacrosspropertytypes,weightingbytheirrespectivebuildingstockinthemarket.Afewlargecitieshavepricesreportedbymetropolitandivision;inthesecases,wetaketheaveragepriceappreciationinanMSA,weightingbythebuildingstockineachsubmarket.
canbefoundat
/construction/c30/methodology.html.
6Pre-planningprojectshavenotyethiredanarchitect,buttherehastypicallybeensomeconceptforthebuildthathasbeenannounced,whilefinalplanningprojectsaretypicallyveryclosetoapprovalformovingtoconstruction.Biddingoccursaftertheplansareapprovedandtheprojectislookingforacontractwithageneralcontractor.
7
2.2.Project-levelsummarystatistics
InTable
1,weshowinformationontheroughly260,000projectsinoursample.Thetop
panelpresentsinformationforthewholesample,whilethelowerpanelsdisaggregatebypropertytype.
Westartbyreportinginformationontime-to-plan(timefromplanningstarttoconstruc-tionstart),time-to-build(timefromconstructionstarttocompletion)andtime-to-complete
(timefromplanningstarttoconstructioncompletion).7
Thedatashowthatplantimesareroughlycomparabletoconstructiontimes.Onavalueweightedbasis,theaveragetimeinconstructionandinplanning(forprojectsthatmakeittoconstruction)areabout1.5yearseach.Thesetimelinestendtobelongerforlargerprojects,causingtheaveragetimetoplanandtimetobuildtobeabitunderayeareachonanunweightedbasis.Plantimesarealsomuchmorevariablethanbuildtimes.Thestandarddeviationoftime-to-planisabout16months,comparedwithabout12monthsfortime-to-buildonavalue-weightedbasis.Planningphasesforprojectsthatareultimatelyabandoned(planningstarttoabandonment)arelongeratabitabovetwoyears,likelyreflectingtheoptionvalueofdelaysforprojectswhoseeconomicviabilityisinquestion.
Wehavetwofurtherpiecesofinformationontheproject:itsestimatedcostandsquarefootage.Themedianrealprojectcostisabout3million(2012)dollarsandthemedianbuildingsizeabout32,000squarefeet,withtheaveragesbeinghigher(atabout13milliondollarsand107,000squarefeet,respectively)duetotheright-skewednatureofthedistributionsofprojectsizesandvaluations.
Averageplantimesvarymoderatelyacrosspropertytypes,largelyreflectingdifferencesintypicalprojectsizes.Retailandwarehousepropertieshavetheshortestaverageplanninghorizonsat11and12months,whilehotelandmultifamilypropertieshavethelongestat18and19months.Officepropertieshaveaverageplantimesthatareinthemiddle,withanaveragehorizonof15months.Theotherbroadpatternsdiscussedforthefullsamplealsoholdacrosspropertytypes:theaverageconstructiontimeisalwayswithin4monthsoftheaverageplanningtime,andtheaverageplantimeforabandonedprojectsisalwayslongerthanforthosethatadvancetoconstruction.
7Here,wejustcollectallplanningphasestogetherintoplanning.
8
Figure
2
showstheshareofplansthatareabandonedbypropertytype.Forthesample
ofprojectsthatconcludebytheendofthesample(i.e.,eitherfinishconstructionorgetabandoned),37percentareabandoned(31percentonanunweightedbasis).Acrosspropertytypes,theabandonmentraterangesfrom30percentforwarehousesto50percentforhotels.Thisresultdemonstratesthattheinitiationofacommercialconstructionprojectshouldnotbeviewedasaninvestmentthatwillinvariablyaddtothebuildingstock(withsomeuncertaindelay).Instead,enteringtheplanningphaseisanoptionthatdevelopersmaychoosetonotexercisedependingonwhattheylearnabouteitherthespecificprojectorbroadermarketconditionsoverthecourseoftheplanningperiod.
Figure
3
presentsadecompositionoffactorschangingthestockofprojectsacrosstime.Thenumberofprojectsinplanninginagivenyearisincreasedbythenumberofnewplanstartsanddecreasedbythenumberofprojectsthatleaveplanningduetoconstructionorabandonment.Thefigureshowsthatthenumberofprojectsfellnotablyduringthefinancialcrisisduetoacontractioninplanningstarts(whichfellbyoverhalf)andariseinabandonments(whichexceededconstructionstartsin2009and2010).TheplanningstockthenrosethroughmostoftherecoveryduetoasteadyincreaseinplanningstartsbeforecontractingduringtheCOVID-19pandemicastherateofplanningstartsslowed.
2.3.PhaseTransitionsfortheFullSampleAcrossPhases
Table
2
providesmoredetailonthedynamicswithwhichprojectsadvancethroughvariousphasesofconstruction.Specifically,itshowsatransitionmatrixwhereeachcell(i,j)givestheprobabilitythataprojectthatstartsinphaseiinmonthttransitionstophasejinmontht+1.Thestatisticspertaintothefullsampleofprojectsthatstartin2004orlater.Thestatisticsareunweighted,sotheycorrespondwithaprobabilitythataparticularprojectchangesstatus.Consequently,theimpliedplanspellsdiffersomewhatfromtheweightedsummarystatisticsemphasizedfromTable
1.
Thefirstrowshowsthetransitionsforprojectsthatentertheperiodintheplanningphase.About93percentofprojectsinplanninginagivenmonthremaininplanningthefollowingmonth.Thisimpliesthatprojectsonaverageremainintheplanningstagefor
9
overayear,about15monthsinexpectation.8
About4percentofprojectsinplanning
advancetounderconstructioninthefollowingmonth,withabout2percentofprojectsinplanningbeingdeferredorabandonedeachmonth.
Thetransitionmatrixshowsthatoutcomesintheplanningstageareuncertain;morethanathirdofprojectsexitingplanningaredeferredorabandonedinsteadofproceedingwithconstruction.Constructionoutcomesaremuchmorecertain;only0.1percentofprojectsunderconstructionaredeferredthenextmonthandnexttononeareabandoned.About11percentofprojectstransitionfromunderconstructionpermonth,withalmostallofthoseprojectsgettingmarkedascompleted.Thisimpliesatypicaltime-to-buildofabout9months,closetotheunweightedaverageconstructiontimeinTable
1.
Deferredprojectstendtoremaindeferred,though1percentofprojectseventuallyreturntoplanning,construction,orareeventuallycompleted.Thatsaid,about3percentofdeferredprojectsareabandoned,meaningthatdeferralisnormallyaprecursortoabandonment.
2.4.DeterminantsofAbandonment
Tostudywhatcausesprojectstofailtoadvancetoconstruction,wecollapsethedatatotheprojectlevelandcreateanindicatorforwhethertheprojectevermovesfromplanningtoconstruction.Wethenlookathowcommercialpropertypriceappreciationoverthefirstyearoftheprojectaffectsthelikelihoodofadvancingtoconstruction.
Specifically,werunthefollowinglinearregression:
EverCompletedi,m,t=βln(C1)+gXi,m,t+ei,(1)
whereEverCompletediisanindicatorforwhetherprojectiisevercompleted,ln(C1)
isgrowthinCostar’scommercialpropertypriceindexfortheproject’smarketmintheyearfollowingthestartofplanningt.Xiisavectorofproject-levelcontrolsincludingthelogofthebuildingsquarefootageandtherealprojectcost,aswellasMSA,property
8Theexpectedtimeremaininginagivenstagecanbeobtainedbytaking1/(1-.932).
10
type,andyear-quarterfixedeffects.StandarderrorsareclusteredbyMSA.
Themainobjectofinterestistherelationshipbetweenpriceappreciationandtheproba-bilitytheprojectisevercompleted.Weseeapositiveandsignificantrelationshiphere.InColumn(1),weseethata10percentagepointincreaseinpropertypricesattheonsetoftheplanstartleadstoa5.7percentincreaseintheprobabilitythataprojecteventuallyadvancestoconstruction.Column(2)addsinthepropertytype,MSA,andquarterfixedeffects,whichincreasestheestimatedcoefficientfrom5.7to10.4percent.Column(3)addsthecontrolsforprojectsizeandcost,whichresultsintheestimatetorisingto11.8percent.Theseresultsareconsistentwithadvancementtoconstruction(andconverselyabandonment)varyingwitheconomicconditions.
2.5.ASummaryoftheFacts
Althoughtheconstructiondatacontainanarrayofinterestingpatternsandinformation,weseethefollowingfactsasmostrelevantfordiscipliningamodelwherebuildingacommercialbuildingrequiresplanningandconstruction.
.Projectsspendabout1.5yearsinplanningbeforeconstructionbegins.
.Projectsarefrequentlyabandoned,typicallyduringtheplanningphase.
–About60percentofprojectseventuallyadvancetoconstructionwhileabout40percentareabandoned.
–99percentofprojectsunderconstructionarecompleted.
.Abandonmentsvarywitheconomicconditions.
3.PLANNINGMODELWITHABANDONMENTS
OurgoalistobuildamodelconsistentwiththefactsoutlinedinSection
2.5.
Inthemodel,timeisdiscrete,labeledast=0,1,2,....Thereisarepresentativebuildingproducerwhooptimallydecideshowmuchtoinvestinplanningandconstructionstarts.
11
Fornow,thebuildertakesasgivenaparticularsequenceofinterestrates(rt),rental
ratesofbuildings(r),andcostsofplanningstarts(it).InSection
5,wewillembedthis
section’smodelintoageneralequilibriumbusinesscyclemodel,andthesevariableswillbeendogenouslydeterminedbyhouseholds’consumption/savingsdecisions,thesupplyanddemandforspace,andplanningstockadjustmentcosts,respectively.
Theproductionofbuildingsissubjecttotwofrictions.First,thereisastochastictimelagbeforebuildingconstructionoccurs.Specifically,firmscaninvestinplanningprojects,butonlyashareλoftheseprojectscanadvancetoconstructioninagivenperiod.Whentheplanninghorizoniscompleted,firmsdrawacostκFandcanchoosewhetherornottopayκtoproduceaunitofbuilding.Firmschoosethemaximumamountthey
arewillingtopayforaprojectκ,resultingintheconstructionofλPt__1F(κ)buildings,
wherePt_1istheplanningstockchoseninthepreviousperiod.Projectswithcostsabovethisthresholdareabandoned.
Second,firmsfaceadjustmentcostsinstartingprojects.Thecostofinitiatingaplanning
startattimet,denotedit,isincreasingintheamountofplanninginvestment,denotedI.
Weassumetheseadjustmentcostsareexternaltothefirm(reflectingfactorssuchasthesupplyofpermitsratherthaninternalcapacityconstraints)andthusreflectedinthecostofplanningstarts,whicharetakenasexogenoustothedeveloper.
Consequently,theproblemofthedeveloperisasfollows:
max
fIs,κ+s0
s
EtΣ(Õsi=0
κ+s
)+ss__it+sIs_λPt+s_1ZκdF(κ)),
RentalIncomelanning&Cons
subjecttothelawsofmotionfortheplanningandbuildingstock:
12
Pt+s=(1-δp-λ)Pt+s-1+Is
(2)
{z
Bt+s=(1-δb)Bt+s-1+s-1F(κ+s,
I+s
whereδpandδbarethedepreciationratesfortheplanningandbuildingsstock,respec-tively.Thisproblemhasthesolution:
κ=q
q=Et(r+1+(1-δb)q+1)
(3)
it(I)=q
q=Etλ+1(q+1-κ)dF(κ)+q+1(1-δp-λ),
whereqpandqbaretheLagrangemultipliersontheplanningandbuildingaccumulationconstraints,reflectingthevaluesofaunitoftheplanningandbuildingstock.
Thefirstlineshowsthatdevelopersproceedwithconstructionwhenthecostofconstruc-
tionislessthanq,whichisdefinedinthesecondlinetobethepresentdiscountedvalue
offuturerentalincome(i.e.,thevalueofaunitofBt).Thethirdlinesaysthatdevelopers
willinvestinplanningstartsuntilthevalueofaunitoftheplann
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 大学生2026年春季复学申请
- 实验动物尸体无害化处理与登记管理手册
- 工厂食堂供应商评估与管理手册
- 风力发电项目成本核算与管控手册
- 《教育行业人力资源师德师风建设手册》
- 邮政服务与快递操作手册
- 互联网教育师资培训与认证手册
- 2026年内蒙古乌海黄河职业学院高职单招职业技能考试模拟试卷附答案详解(考试直接用)
- 2027年湖南楚文化职业学院高职单招职业技能考试题库带答案详解(基础题)
- 2026年秦岭中药材学院单招职业技能考试题库及参考答案详解【夺分金卷】
- 恶劣天气行车安全培训课件
- 检测机构软件管理办法
- 肾上腺教学课件
- 医院办公室管理PDCA案例
- 2025年劳动人事争议仲裁员培训考试试题及答案以及劳动合同法复习重点
- 规范诊疗培训课件
- DB11T 751-2025 住宅物业服务标准
- CJ/T 353-2010城市轨道交通车辆贯通道技术条件
- 应急电力故障抢修
- 2024年天津中医药大学第一附属医院人事代理制人员招聘考试真题
- 蓄电池室管理制度
评论
0/150
提交评论