实施SAPR3软件中项目管理
TeachingMaterialfortheDepartmentof
ProductionManagement
WIRTSCHAFTS
UNIVERSITAT
ViennaUniversityofEconomicsand
BusinessAdministration
AndreasMild
AlfredTaudes
v.1.0
1Introduction3
2Basics&Keywords4
3Gettingreadyfortheworkshop7
4CaseStudy12
4.1Casedescription12
4.2DataforProjectRealization13
5Planningtheprojectstructure14
5.1General14
5.2ImplementationinSAP16
6Scheduling25
6.1General25
6.2Basiccalculations28
6.3Implementation.^30
6.4Theprojectplanningboard39
7Costplanning&Controlling45
7.1General.45
7.2Implementation..46
8Lookingupthecosts58
9CapacityPlanning61
9.1General.61
9.2ImplementationinSAP62
10EarnedValueAnalysis66
10.1General66
10.1.1Measurementtechniques66
10.1.2CalculationofEarncd-ValueandDeviationAnalysis70
10.1.3Aggregation71
10.2Implementation71
11Execution74
11.1Implementation74
11.1.1Confirmingnetworkactivities74
11.1.2Invoices76
11.1.3Material79
12InformationSystem83
12.1Implementation83
12.1JCostreports83
12.1.2Earncd-ValueAnalysis88
13Literature94
1INTRODUCTION
Thisscriptservesasabasisfortheworkshop"ProjectManagementwithSAPR/3”.
ThisworkshopispartofaseriesofSAP-relatedworkshopswhichareheldbythe
DepartmentofProductionManagementoftheViennaUniversityofEconomicsand
BusinessAdministration,headedbyProf.Dr.AlfredTaudes.Theworkshopwas
developedbyAndreasMild.
ThegoalofthisProjectManagementWorkshopisthat,afterhavingattendedit,each
studentshouldbefamiliarwiththetheoreticalbackgroundsandbeabletoplanand
controlaproject.Theprojectmanagerhasthetaskofensuringthattheprojectis
executedefficiently,ontime,andwithinthebudget-whichhe/sheachievesby
makingcertainthattherequiredresourcesandfundsareavailablewhenneeded.
Everystudentshouldthenbeabletoputhis/herSAPknowledgeintoaction.
Tomakethecontinuousimprovementofthisscriptpossible,pleasereportmistakes
foundorideasforfurtherdevelopmenttod@wu-wien.ac.at.
2BASICS&KEYWORDS
SAPR/3isanintegratedandindustry-independentstandardsoftwarewhich
covers,integratesandconnectsallfunctionalareasinabusiness.SAPAGdefines
integrationas"definedcommunication".1AlthoughR/3isdesignedforcomplete
integration,itcanalsobeusedforacoupleofbusinessareas.23
SAPistheabbreviationforSysterne,Anwendungen,ProduktetheGermanwords
fbr"Systems,Applications,Products”.'
Projectsaretaskswithspecialcharacteristics.Attributesofaprojectarethe
followingissues:
•complexity,non-repetitivity,highrisk
•detailedgoalstobeachieved
•timerestrictions
•highcostandcapitalexpenditure
•qualityrequirements
•oftenstrategicsignificance
Tobeabletoplan,monitor,control,andcarryoutaprojectasawhole,theproject
goalsmustbepreciselydescribedandtheactivitiestobeperformedhavetobe
structured.
Aprojectcanbedescribedasfollows:
•accordingtohowitisorganized,i.e.byexplainingtheprojectstructure,
•accordingtotheprocessesinvolved.
Aprojectstartsoutasastatementofworkwhichiseitherawrittendescriptionof
theobjectivestobeachievedandthedesiredroughschedulelikestartandenddates.
Inthedescriptiononecouldincludealsoperformancemetricsandbudgetconstraints.
Aprojectisfurthersubdividedintomeaningfulpieces,refenedtoastasks.Taskstake
usuallylessthanafewmonths.Thetaskcanbefurthersubdividedintosubtasks.
Aworkpackagecanbedefinedas“agroupofactivitiescombinedtobeassignableto
asingleorganizationalunit."4
Theprojecttasks,subtasks,andworkpackagesarebroughtintoahierarchyby
definingaworkbreakdownstructure.
Theindividualelementsrepresentactivitieswithintheworkbreakdownstructureand
arecalledworkbreakdownstructureelements(WBSelements).
WBSelementscanbe;
•tasks
•partialtaskswhicharesubdividedfurther
AFOS(Hrsg.)SAPArbeit,Management.Braunschweig/Wiesbaden1996p.59
2ComputerweltNo.13of13.3.1998,p.20
3AFOS(Hrsg.)SAPArbeit,Management.Braunschweig/Wiesbaden1996p.59
4ChaseR./AquilanoN./JacobsR.ProductionandOperationsManagement:
ManufacturingandServices,p.48
•workpackages
WBScanbestructuredaccordingto
•object
•function
•phase
Whichkindofstructuringisuseddependsonthefocusoftheproject.Objects
orientationisoftenused,ifthemainpartoftheprojectisaphysicalobjectlikea
powerplant.Functionalorganisationispreferred,ifmanydifferentpartsofan
organisationormanyorganisationsareinvolved.
Inpractice,allthreekindsofstructuringareusedwithinoneWBS.
“ProjectManagementcanbedefinedasplanning,directing,andcontrolling
resources(people,equipment,material)tomeetthetechnical,costandtime
constraintsoftheproject.'"Theprimaryreasonwhyprojectsfailisinsufficient
effortintheplanningphase.*6ProjectManagementthusisconsideredasvery
important.
TheSAPProjectSystemenablescloseandconstantmonitoringofallaspectsofa
projectbyhavingconstantaccesstodatainallthedepartmentsinvolved.
Piqjectinaiiagemeiilcanbesubdividedintoprojectplanning,i.e.thetaskwhichwill
beundertakenbeforetheprojectstarts,andprojectcontrollingduringthe
implementationoftheproject.Planningmustinclude:
•organization-service
•process-dates
•costs
•capacity
Therearemanypossibleprojectgoalssuchas,forexample,torealizeapositivenet
presentvalue,toachieveahighimputedinterest,tominimizecosts,tocovercosts,to
maximizegrossprofit,orsimplytofinishasearlyaspossible.However,itis
important,thatgoalsaredefinedoperationally,thaitiswhenitispossibletomeasure
towhichextentthegoalhasbeenachieved.
Theprojectmanagerbreakstheprojectdownintoasetofactivities.Thenhealso
definestherelationshipsamongtheseactivities.Theoutcomeisaguideline
regardingtheactivitiesthatcanbeperformedinparallelandthosethathavetobe
doneinasequentialorder.Thistaskisdoneviaplanningbynetwork.
Now,thereareactivitiesthatrequirecapacitiesandresourceslikepersonneland
material.Suchresourcesarelimitedandtheserequirementshavetobeconsideredin
ordertobeabletodevelopafeasible,soundplan.Informationfromothermodulesas
e.g.thematerialplanningmoduleisrequired.
、ChaseR./AquilanoN./JacobsR.ProductionandOperationsManagement:
ManufacturingandServices,p.48
6ChaseR./AquilanoN./JacobsR.ProductionandOperationsManagement:
ManufacturingandServicesp.69
Thesystemcalculatesthematerialrequirementsforeachstepoftheprojectand
organizesthatmaterialsareboughtintimetoavoiddelays.Whenpurchasingmaterial,
thesystemtakesintoaccountordersizes,inventorypoliciesaswellasother
information.
Topreparethefinancialstatements,thevalueofworkinprogress(includingproject
work)hastobecalculated.ThisalsorequiresinteraclionofsomeR/3modules.
Thus,thesystemneedsinformationfromallbusinessareassimultaneously.Andthis
isexactlywhatintegrationdoes.
IheprojectmoduleispartottheintegratedconceptofSAPR/3providinginterfaces
toothermoduleslikeAccounting,Distribution,MaterialManagementandProduction
PlanningandControl.Eachareawithintheorganizationhasitsownstructureandits
ownviewoftheproject,butdatahastobeenteredonlyonce.
3GETTINGREADYFORTHEWORKSHOP
Thischapterprovidesinformationonthefirstuseofthesystem.
LoggingonR/3
Loggingoff
SAPR/3isaclient/serverapplication.Therefore,youhavetocanceltheconnection
withtheserverbytellingitthatyouwanttologoff.
CreateSession
Oftenitisusefultoopenmorescreens.Youcandothisbycreatinganewsession,like
anewdocumentinawordprocessor.
SAPHelp
Ifyouwanttogetsomebasicinformationaboutaspecificfield,focusthisfieldwith
yourmouseandpress<F/>.Thedialogboxindicateswhatthefieldisfor.Sometimes
evendependenciesarcexplained.
Matchcodes
Matchcodesarcusefulforfindingdata,becauseitisdifficulttoknow/rcmcmbcrthe
identificationnumberofalinepositionsuchasamaterial.
Example:
Youwanttoeditthematerialmasterofamaterial.Youdon'tknowthenumber,but
youknowthatthematenaldescriptionstartswithsomethinglike“PM”
IfyoupressF4yougelasearch-maskwhereyouareabletosearchwithwildcards
AfterhavingpressedEnteryougetalistwiththesearchresults.
HitList□
MaterialdescriptionLanguage^Material
ii
XX
PM_CABINEEN1008000000000001105I
|PMCONTRniUNITFN
PMELEUATORENGINEEN^8000000000000011041
PMENGINEENi800000000000091101j
PMMECHANICALPARTSEN^000000000000001106
“I哈|四词阴|x|
Thenyoucanselectonematerial,youcansortorcancel.
TransactionCodes
Thefollowingscreenwillbeoftenusedduringtheworkshop.Thus,wecanuse
TransactionCodesforfasteraccess.
ThenselectStructureplanning-ChangeProject.
Now,wewantto“bookmark“thisscreen.
So,welookupthetransactioncode.
Thestatusdialogboxopens:
Hereweseealotofinformationconcerningimportantrelevanttechnicaldetails.
Whereveryoufindyourselfinthesystem,youcangettothisscreenbyenteringCJ20
intheTransactionscreen.
Letusrefinethisalitllebit.Ifyouhaveseveraltransactioncodes,youmaygel
confused.Keyintheappropriatetransactioncodeandthecommenteditproject
structure.
Then,ifyouopenthecomboboxofthetransactioncodesafterhavingenteredmore
codes,youwillfindtheappropriateone.
TheStandardToolbar
Inmanyscreensyouwillfindthestandardtoolbar.
Savebutton
Whenyoupressthesavebutton,thesystemalsovalidatesyourinput.Iftherewasan
error,youhavetocorrecttheerrorfirst,beforeyoucanproceed.
Backbutton
Ifyouclickthebackbuttonyoureturntothepreviousscreenwithoutsavingyour
data.
Help
丁
Enterbutton
Whenyouhavefinishedenteringinformationonascreen,youpresstheEnterbutton
whichperformsthesamefunctionaspressingtheEnterkey.
Exitbutton
Pressit,ifyouwanttoleavethecurrentapplicationtogobacktothepreviousmenuc.
Cancelbutton
Clickonthisbuttontoexitthecurrenttaskwithoutsaving.TheCancelbutton
performsthesamefunctionasCancelintheEditmenu.
Printbutton
H
Pagingkeys
U打站幻Q
Find/Findnextbutton
M埔
Clickonthisbutton,ifyouwanttoperformasearchfordatarequiredinthescreen
youarecurrentlyworkingin.
4CASESTUDY
4.1Casedescription
ThiscasewasdevelopedinordertodemonstratetheprojectsystemofSAPR/3.All
pricesanddataarcpurefictionandheldverysimple.
Theobjectoftheprojectisthespecificationandinstallationofanelevator.
Physically,theElevatorconsistsof
•acabine
•anengine
•mechanicalparts
•acontrolunit
Inthecourseoftheproject,thesepartsmustbeconstructed,procuredandassembled.
Attheend,anexternalinspectionoftheentiresystemisprescribed.
Theprojectmustbefinishedby30.6.2000.
Thecompanyconsistsoftwoworkcenters:
•Development(PROJ-RD)
•Installation(PROJ-INS)
SpecificationactivitiesareperformedbytheDevelopmentdepartment.Procurement
activitieswillbedoneoutsidetheprojectorganisation,andneithercostnorcapacity
considerationsareplannedwithinaprojectforprocurement.Installationisdoneby
theInstallationdepartment.
Inparticular,theactivitiesareasfollows:
ActivityDurationWorkWork-center
Specificationofthecabine1020Development
Specificationoftheengine1010Development
Specificationofmechanicalparts2010Development
Specificationofthecontrolunit210Development
Procurementofthecabine20
Procurementoftheengine50
Procurementofmechanicalparts10
Procurementofthecontrolunit10
InstallationI15100Installation
InstallationII20100Installation
ExternalInspection1external,80.000
Specificationactivitiescanbeperformedinaconsecutiveorderonly.Specification
startswiththecabine.Aftercompletion,thespecificationoftheenginecanbedone.
Then,themechanicalpartscanbedesigned.Thelastactivityisthedesignofthe
controlunit.
Afterthecompletionofeachspecificationactivity,theprocurementofthespecific
itemcanbeeffected.
AftertheprocurementofallpartstheInstallationcanstartandmustbedoneintwo
consecutivesteps(I+II).
Thefinalactivityoftheprojectisexternalinspection.
A10%planningreserveonthebaisisofplannedcostisrequired.Noactualcost
shouldbepostedtothisWBSelement.
Correspondingmaterialsassignedtothepurchasingactivities
Structure
ParametersfiirEamed-ValueAnalysis
AllspecificationactivitiesandInstallationIIusethe20-80Methodforperformance
measurement.Procurementactivitiesuse0-100method.
InstallationIhas3milestones,viz.Preparationfinished(20%),Installationfinished
(80%),Qualitychecked(100%).
4.2DataforProjectRealization
ActivityStartEndWork
Specificationofthecabine24.1.200004.2,200020
Specificationoftheengine07.2.200005.3,200030
Specificationofmechanicalparts06.3.200022.3,200020
Specificationofthecontrolunit
Procurementofthecabine06.3.200006.3.2(X)0
Procurementoftheengine07.3.200007.3,2000
Procurementofmechanicalparts08.3.200008.3.2000
Procurementofthecontrolunit09.3.200009.3.2(X)0
InstallationI
Installation11
ExternalInspection
Externalinspectionhadtobepaidinadvanceat3.2.2000(100000ATS).
Allmaterialwastakenfromstockatgiventime.
5PLANNINGTHEPROJECTSTRUCTURE
5.1General
Eachprojectstartswiththedefinitionandclassificationofthestructuresrequired
forprocessingandtheincorporationoftheseintotheexistingenterprisestructure.
TheProjectSystemhasnoorganizationalstructuresofitsown;ithastobe
incorporatedintotheexistingstructurebymakingassignmentstothe
organizationalunitsinAccountingandLogistics.7
Afterthat,theprojectisbrokendownintomeaningfulpiecesinahierarchy
reachingfromtaskstothelowestlevel,theworkpackages.
DatastructureinSAP
Asmentionedabove,theprojectmustbeincorporatedintotheexistingstructureby
assigningorganizationalunitsinAccountingandLogistics.
7SAPOnlineDocumentationIDESRelease4.0B
Projectdtfinition
-Cortrollingarea
—Companycode
WBSdements
-Businessarea
—Profitcerter
—Companycode—PIG
—Busnessarea
Networks
—Plart
—Proftcenter
-Profitcartar—Teutniudloudtiuit
-Businessarea-Responsivecosteerier
Activities
—Captalirvestmertprogram
一Jcrisdctioncode
—JLTisdctioncoda
Plart
Jdrtvertire
Internally-processed
activities
—Plart—Businesssrea
-Vtorkeerier—Prefitcenter
—Juisdicticncode
Ext9nally-precessed
activities
—Purchasingerganization—Plant
—Purchasinggxxp—Businessarea
一Profitcerter
-Jurisddicn8色
Generalcostsactivities
।—Plart—Businessarea
—Profitcerter
—Jurisddicncoda
Materialconponenls
—Pixchasingerganization
—Pirchasinggioip
—Plart
—Stcogelocation
Source:SAPOnlineDocumentationIDESRelease4.0B
Thischartprovidesanoverviewofwhatcanbeassignedtoaprojectandits
components.WcwilldefinetheSAPvocabularylateron.
Thework-breakdown-structure(WBS)definesthehierarchyofthetaskswithina
projectanddividestheprojectintousefulsteps.
TocontrolcostsassignedtoWBSelements,operativeindicatorsareused.
ThefollowingoperativeindicatorscanbeassignedtoaWBSelement:
PlanningWBSelementsforwhichcostscanbeplanned
AccountWBSelementstowhichcostscanbeassigned
assignment
BillingWBSelementstowhichrevenuescanbeposted
5.2ImplementationinSAP
Inthissectionwecreateanewproject.Wethenwillhavealookatthecontrol
parameters.Afterthatweentertheworkbreakdownstructure.Finally,thestatus
conceptofSAPR/3willbeexplained.
Createnewproject
Thus,wegettotheinitialscreen:
Weenterourprojectdefinition,adescriptionofourprojectandselectthestandard
profileforprojects.
Inourcase,weonlysetafinishdate.WhenpressingEnter,awarningmessagethat
thisdateisnotaworkingdaymightoccur.Onecanpassthewarningbypressing
Enter
Wethensaveourworkandgettheconfirmationthattheprojecthasbeencreated.
Note:Itiswisetosaveyourworkfromtimetotime.Wewillnotmentionthesave
procedureintherestofthemanuscript!
Tocontinue,wehavetochoosetochangeourproject.
Makesurethatthecheckboxwithactivitiesisalwayschecked.Clickexecuteto
proceed.
Nowhehavecreatedanewproject.Althoughwehavenotkeyedinanydataexcept
theProjectProfileNumber,manyparametershavealreadybeenassignedtoournew
project.
Generalcontrolparameters
Clickheretoviewtheglobalparameters.Thissectionshouldprovideyouwithabasic
insightintowhichparametersareset.IfyoufeelthattheresultscalculatedbyR/3are
notlogical,youshouldhaveanideawheretostartsearchingtherelevantcustomizing
details.
TheprojectprofilespecifiesThenetworkprofilespecifiesIntheWBSscheduling
generaldatalikeControllinggeneraldatalikesettingsforprofileitemslikethe
area,Plant,Factorythegraphicalrepresentation,schedulingtype(forward,
calendar,Planningmethodactivityparameters,likethebackward)arespecified.
etc.Whencreatingthecurrencydefaultofexternally
project,theprofileischoosen.processedactivities.
ChongcProjccrProjectdefinition
❷ogyQCdA&&oWBS•UmerAEMII*:System\
v।3@中含/住第菖君*不:也与
fl晶dShuctueSetttemenlwte
Rwcidel.|r1ILD_ELEV_1O[^lElevatorProject
B&itc必aContid(Adnmsljatnn
一10000001r
AccountingTfneschedj%ng
Budgetptc6leNetwxkprolie|01^p0002
Planmgprc6leWBSschediingprof|OGBOOO03OOO1
Paymentplanprolier
IhLcakproIteCX^jthacl.F
Phrvmc^b^iF
Invotmonip,061crOpenpUmng
Retuh4n必?rkey000001Phame<h/fctlOpenpUmng
Smdabonp*/NeMakat饮Forjxoyecl(felnbon
ThebudgetprofilespecifiesitemslikebudgetingTheplanningprofilespecifies,e.g.,
currency,thevalidtimehorizonforbudgetingbackincostingvariantandtimehorizon.
tothepastorintothefuture
Planningparameters
Inthegeneralparametersection,manyparametersarcsetasdiscussedabove.
Naturally,onecanoverrideapartoftheminthecurrentproject.However,wearenot
changinganyparameters.
Hereyoucanspecifyifyouwanttousetop-Down,up,oropenplanning.
HerewespecifywhatthesystemshoulddoifAnimportantparameteristhescheduling
schedulingdeterminesdateswhicharenottype.Hereyouspecify,ifyouwanttouse
withinthebasicdates.Incase,thescheduledforward,backwardorotherscheduling
datesshouldbetakenoverasnewdates.types.
Startenteringthedatagiveninthescreenshotbelow.Ifyouarefinished,pressEnter.
Then,yourscreenshouldlooklikethis:
ChangeStructurePlanningBASICBI3D
PtogeclEd*GotoDe4afcSellngsExbasSyrtemHelp
心厂39Bccee均组
同旧30Q80式盹名品能巴]听口AComponentovezew臣Ditplayawgnmert4*te拗
Projectdef,StortFrwhDiroftonTinCol
“ILD_ELEV_10(ElevatorProject|300600|0,0|DAY^U
WBSBosedates|F.cgdjix|ActwMydataI
SAc|LevWBSetemertActElernDe$ciip!bnSttdar|Fn<tet|InE>G(A/DS
听MILD_ELEV_1OElevatorProject.
吒2MILD.ELEV.10-100Construction—
0101ConstructionofThecabineyrrr
0102Constructionoftheengine9rcc
0103Constructionofthemechanicalpartsyrrr
0104Constructionofthecontrolunitsrrr
)W2MILD_ELEV_10-200Procurement
0201Procurementoftheengine9crc
0202||
Procurementcabineerrr
叱1MILD_ELEV_10-300LJHInstallation
0301InstallationI$rcr
0302匚InstallationII9ccc
1
I—I
——accc
Levelingup/downWBSElements
Thereisamistake.WBSElementELV_000-300shouldhavelevel2.
SelecttheWBSElementtolevelingitdown.
InsertingWBSElements/activities
WehaveforgottenloenterenterActivity203,Procurementofthemechanicalparts
andActivity204,Procurementofthecabine.
・ChangeStructurePUnningBoticdatci
,:3a♦盘x|昌置i蔺电七归羽曾
ClfKOOTK,
Q]\$!如,,乳6国£吐2品熬臼°?。幺Component-V即Ditplayaw9nmert4为匕拗
Selecttherowabovewhichyouwanttoinsertarowandadditbymenueorsimply
bypressingF6.Proceedwiththesecondrowinthesameway.Donotforgetthat
theseactivitiesdonothavealevel.
Afterthesechangesyourscreenshouldlooklikethis:
"ChangeStructurePliinningBasicdotes
PlooectEdAGotoDetais$ellr)9sE)dra:SyrtemHdp
,IJa♦x昌M同cooe也幻曾
旧殡IdBOQ◎起©国商"品必任]*?DdCc<nponentoveiviest•Disp.sgnmE幺PS匕融
Prcwt<fetDe$c<iptknStartFir^hDira(onTimCai
hILO.ELEV.1O(ElevatorProjectI|3006oo|O7O|DAY|AU
WBSbaticda13Baacdates|Foteevd«w|Actwtydale|
Strt3|Fndat
sAcLevWBSetemeriActElemDexiptnnInE>Sc61A4)
1W2MILD.ELEV.10-100Construction
Constructionofthecabine9rr
—019-
0102Constructionofth©engine3rrc
0103Constructionofthemechanicalparts•rrr
—
0104Constructionofthecontrolunit•rrr
耳2MILD.ELEV.10-2001Procurement
0201Procurementoftheengine$rrr
0202Procurementcabine9rrr
0203Procurementofthenechanicalparts3crr
0204Procurementofthecontrolunit*rrr
0312ExternalInspectionrr(5
耳2MILD_ELEV_10-300Installation
—r
0301InstallationI9rrr
0302InetollotionII3rrr
0322Externa
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 质量管理风险评估指引
- 智慧物业智能管理平台及智慧安防平台建设方案
- 建筑混凝土浇筑质量控制与检查指引
- 事业单位文秘岗2026面试全真模拟专业面试试卷及答案
- 初中数学教资面试试讲2026高频考题题库及解析
- 事业单位计算机岗面试经典考题专项考题题库及解析
- 事业单位计算机岗2026经典考题题库及答案
- 2026小学科学教资面试试讲历年真题题库及解析
- 2026年外汇结算催办函(6篇范文)
- 协调场地使用计划的函4篇
- (正式版)DB51∕T 2628-2019 《司法所外观及室内标识规范》
- 担保公司业务培训制度
- 2025年全国性体育社会组织(秋季)公开招聘人员确认表笔试历年典型考题(历年真题考点)解题思路附带答案详解
- 精神康复护理实践技能
- GB/T 28164.2-2025含碱性或其他非酸性电解质的蓄电池和蓄电池组便携式密封蓄电池和蓄电池组的安全要求第2部分:锂系
- 变压器增容合同范本
- 中国子宫内膜增生管理指南
- 西学中题库及答案
- 《危险化学品目录》(2026版)
- 肾病中医食疗课件
- 陶瓷厂工艺设计概论(山东联盟)智慧树知到期末考试答案章节答案2024年齐鲁工业大学
评论
0/150
提交评论