市政基础设施工程,,,,,,,,,,,,,,,,,,,,,,,,

CFG桩施工记录表,,,,,,,,,,,,,,,,,,,,,,,,

项目名称,佛山创智新城道路工程(一期),,,,施工单位,,广东兴业路桥工程有限公司,,,,监理单位,,上海斯美科汇建设工程咨询有限公司,,,,合同段,,,公路等级,城市支路,,,

路段桩号,DK0+040-DK0+080,,,,,,,,设计配合比,,水泥,粉煤灰,石屑,碎石,水,实际配合比,,水泥,粉煤灰,石屑,碎石,水,,

试桩确定长度,22,,,,,,,,,,1,1.53,3.529,8.555,1.01,,,1,1.53,3.529,8.555,1.01,,

桩编号,1-1,3-1,5-1,7-1,9-1,11-1,13-1,15-1,17-1,19-1,21-1,22-2,20-2,18-2,16-2,14-2,12-2,10-2,桩位示意图,,,,,0:04

开始时间,12:10,12:36,12:59,13:23,13:45,14:08,14:32,14:49,15:12,15:34,15:56,16:17,16:40,17:02,17:24,17:48,18:08,19:02,,,,,,0:01

结束时间,12:31,12:54,13:19,13:45,14:03,14:28,14:49,15:08,15:33,15:51,16:13,16:39,16:58,17:22,17:44,18:07,18:25,19:23,,,,,,

设计长度(m),22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,,,,,,

实际桩长(m),22,22.2,22.1,22,22.2,22.1,22.1,22.3,22.1,22.1,22.2,22.2,22.3,22,22,22.3,22.3,22.2,,,,,,

竖直度(1%),1,0.8,0.8,0.9,0.8,0.9,1,0.9,0.9,0.9,0.9,1,1,1,0.9,0.9,1,0.9,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

施工间断记录,施工无间断,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

自检意见,,,,,,,,,,,监理意见,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

项目技术负责人,,,,质检员,,,,,,施工员,,,,,,监理,,,,,,,,

2013年11月21日,,,,,,,,,,,,,,,,,,,,,,,,

市政基础设施工程,,,,,,,,,,,,,,,,,,,,,,,,

CFG桩施工记录表,,,,,,,,,,,,,,,,,,,,,,,,

项目名称,佛山创智新城道路工程(一期),,,,施工单位,,广东兴业路桥工程有限公司,,,,监理单位,,上海斯美科汇建设工程咨询有限公司,,,,合同段,,,公路等级,城市支路,,,

路段桩号,DK0+040-DK0+080,,,,,,,,设计配合比,,水泥,粉煤灰,石屑,碎石,水,实际配合比,,水泥,粉煤灰,石屑,碎石,水,,

试桩确定长度,22,,,,,,,,,,1,1.53,3.529,8.555,1.01,,,1,1.53,3.529,8.555,1.01,,

桩编号,8-2,6-2,4-2,2-2,1-3,3-3,5-3,7-3,9-3,11-3,13-3,15-3,17-3,19-3,21-3,22-4,20-4,18-4,桩位示意图,,,,,0:04

开始时间,19:26,19:48,20:11,20:36,20:55,21:18,21:43,22:09,22:33,22:56,23:22,23:47,0:30,0:50,1:13,1:36,1:58,2:19,,,,,,0:01

结束时间,19:43,20:06,20:32,20:55,21:14,21:38,22:04,22:29,22:52,23:18,23:42,0:07,0:50,1:09,1:32,1:56,2:15,2:38,,,,,,

设计长度(m),22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,,,,,,

实际桩长(m),22,22.2,22.2,22,22,22.3,22.2,22,22.1,22.1,22.3,22.2,22.2,22.2,22.1,22.1,22.2,22,,,,,,

竖直度(1%),0.8,1,0.9,0.9,0.9,0.8,1,0.8,1,1,0.8,0.9,0.8,1,0.9,0.8,0.8,0.8,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

施工间断记录,施工无间断,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

自检意见,,,,,,,,,,,监理意见,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

项目技术负责人,,,,质检员,,,,,,施工员,,,,,,监理,,,,,,,,

2013年11月22日,,,,,,,,,,,,,,,,,,,,,,,,

市政基础设施工程,,,,,,,,,,,,,,,,,,,,,,,,

CFG桩施工记录表,,,,,,,,,,,,,,,,,,,,,,,,

项目名称,佛山创智新城道路工程(一期),,,,施工单位,,广东兴业路桥工程有限公司,,,,监理单位,,上海斯美科汇建设工程咨询有限公司,,,,合同段,,,公路等级,城市支路,,,

路段桩号,DK0+040-DK0+080,,,,,,,,设计配合比,,水泥,粉煤灰,石屑,碎石,水,实际配合比,,水泥,粉煤灰,石屑,碎石,水,,

试桩确定长度,22,,,,,,,,,,1,1.53,3.529,8.555,1.01,,,1,1.53,3.529,8.555,1.01,,

桩编号,16-4,14-4,12-4,10-4,8-4,6-4,4-4,2-4,1-5,3-5,5-5,7-5,9-5,11-5,13-5,15-5,17-5,19-5,桩位示意图,,,,,0:04

开始时间,2:41,3:02,3:25,3:50,4:14,4:40,5:06,5:31,5:54,6:17,6:43,7:50,8:09,8:31,8:54,9:17,9:40,10:00,,,,,,0:01

结束时间,2:58,3:21,3:46,4:10,4:36,5:02,5:26,5:49,6:12,6:38,7:00,8:08,8:26,8:49,9:12,9:36,9:59,10:22,,,,,,

设计长度(m),22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,,,,,,

实际桩长(m),22.2,22.2,22.3,22,22.2,22.1,22.3,22.2,22.3,22.1,22,22.2,22.2,22.1,22.1,22,22.1,22.1,,,,,,

竖直度(1%),0.9,1,0.9,0.9,1,0.9,0.9,0.8,1,0.9,0.9,0.8,0.9,0.8,0.8,0.9,1,0.8,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

施工间断记录,施工无间断,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

自检意见,,,,,,,,,,,监理意见,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

项目技术负责人,,,,质检员,,,,,,施工员,,,,,,监理,,,,,,,,

2013年11月22日,,,,,,,,,,,,,,,,,,,,,,,,

市政基础设施工程,,,,,,,,,,,,,,,,,,,,,,,,

CFG桩施工记录表,,,,,,,,,,,,,,,,,,,,,,,,

项目名称,佛山创智新城道路工程(一期),,,,施工单位,,广东兴业路桥工程有限公司,,,,监理单位,,上海斯美科汇建设工程咨询有限公司,,,,合同段,,,公路等级,城市支路,,,

路段桩号,DK0+040-DK0+080,,,,,,,,设计配合比,,水泥,粉煤灰,石屑,碎石,水,实际配合比,,水泥,粉煤灰,石屑,碎石,水,,

试桩确定长度,22,,,,,,,,,,1,1.53,3.529,8.555,1.01,,,1,1.53,3.529,8.555,1.01,,

桩编号,21-5,22-6,20-6,18-6,16-6,14-6,12-6,10-6,8-6,6-6,4-6,2-6,1-7,3-7,5-7,7-7,9-7,11-7,桩位示意图,,,,,0:04

开始时间,10:34,10:59,11:24,11:47,12:08,13:04,13:26,13:46,14:06,14:31,14:55,15:21,15:43,16:06,16:24,16:48,17:08,17:29,,,,,,0:01

结束时间,10:55,11:19,11:42,12:04,12:28,13:22,13:46,14:06,14:26,14:51,15:17,15:41,16:01,16:23,16:43,17:06,17:25,17:51,,,,,,

设计长度(m),22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,,,,,,

实际桩长(m),22.1,22.2,22.3,22.1,22,22.1,22.3,22.1,22.2,22.2,22.1,22.1,22,22.3,22.2,22,22,22.2,,,,,,

竖直度(1%),0.9,0.9,1,0.8,0.8,1,0.9,0.9,1,1,0.9,1,0.8,0.8,0.9,1,0.9,0.9,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

施工间断记录,施工无间断,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

自检意见,,,,,,,,,,,监理意见,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

项目技术负责人,,,,质检员,,,,,,施工员,,,,,,监理,,,,,,,,

2013年11月22日,,,,,,,,,,,,,,,,,,,,,,,,

市政基础设施工程,,,,,,,,,,,,,,,,,,,,,,,,

CFG桩施工记录表,,,,,,,,,,,,,,,,,,,,,,,,

项目名称,佛山创智新城道路工程(一期),,,,施工单位,,广东兴业路桥工程有限公司,,,,监理单位,,上海斯美科汇建设工程咨询有限公司,,,,合同段,,,公路等级,城市支路,,,

路段桩号,DK0+040-DK0+080,,,,,,,,设计配合比,,水泥,粉煤灰,石屑,碎石,水,实际配合比,,水泥,粉煤灰,石屑,碎石,水,,

试桩确定长度,22,,,,,,,,,,1,1.53,3.529,8.555,1.01,,,1,1.53,3.529,8.555,1.01,,

桩编号,13-7,15-7,17-7,19-7,21-7,22-1,20-1,18-1,16-1,14-1,12-1,10-1,8-1,6-1,4-1,2-1,1-2,3-2,桩位示意图,,,,,0:04

开始时间,18:00,18:24,19:20,19:42,20:06,20:32,20:54,21:17,21:41,22:06,22:27,22:50,23:12,23:32,23:57,0:41,1:03,1:27,,,,,,0:01

结束时间,18:20,18:44,19:37,20:02,20:28,20:49,21:12,21:37,22:01,22:23,22:46,23:12,23:32,23:52,0:15,0:59,1:23,1:45,,,,,,

设计长度(m),22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,,,,,,

实际桩长(m),22.1,22,22,22,22.3,22.2,22.1,22.1,22.2,22.2,22,22.2,22.1,22.1,22.3,22.3,22.3,22.1,,,,,,

竖直度(1%),0.9,1,0.9,0.9,0.9,1,1,0.9,0.9,1,0.9,0.9,0.8,0.9,0.8,0.8,0.9,0.9,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

施工间断记录,施工无间断,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

自检意见,,,,,,,,,,,监理意见,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

项目技术负责人,,,,质检员,,,,,,施工员,,,,,,监理,,,,,,,,

2013年11月23日,,,,,,,,,,,,,,,,,,,,,,,,

市政基础设施工程,,,,,,,,,,,,,,,,,,,,,,,,

CFG桩施工记录表,,,,,,,,,,,,,,,,,,,,,,,,

项目名称,佛山创智新城道路工程(一期),,,,施工单位,,广东兴业路桥工程有限公司,,,,监理单位,,上海斯美科汇建设工程咨询有限公司,,,,合同段,,,公路等级,城市支路,,,

路段桩号,DK0+040-DK0+080,,,,,,,,设计配合比,,水泥,粉煤灰,石屑,碎石,水,实际配合比,,水泥,粉煤灰,石屑,碎石,水,,

试桩确定长度,22,,,,,,,,,,1,1.53,3.529,8.555,1.01,,,1,1.53,3.529,8.555,1.01,,

桩编号,5-2,7-2,9-2,11-2,13-2,15-2,17-2,19-2,21-2,22-3,20-3,18-3,16-3,14-3,12-3,10-3,8-3,6-3,桩位示意图,,,,,0:04

开始时间,1:51,2:16,2:38,3:02,3:25,3:50,4:13,4:37,4:59,5:24,5:49,6:12,6:36,7:00,8:00,8:24,8:48,9:14,,,,,,0:01

结束时间,2:12,2:34,2:58,3:21,3:46,4:09,4:33,4:55,5:19,5:45,6:08,6:31,6:56,7:20,8:19,8:44,9:10,9:31,,,,,,

设计长度(m),22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,,,,,,

实际桩长(m),22.3,22.2,22.3,22,22.1,22,22.1,22.3,22.2,22.1,22.1,22.2,22.1,22.2,22.1,22.1,22.2,22.3,,,,,,

竖直度(1%),0.9,0.8,0.9,1,0.8,1,1,0.9,1,1,0.9,0.9,0.9,0.9,0.8,0.8,0.9,0.9,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

施工间断记录,施工无间断,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

自检意见,,,,,,,,,,,监理意见,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

项目技术负责人,,,,质检员,,,,,,施工员,,,,,,监理,,,,,,,,

2013年11月23日,,,,,,,,,,,,,,,,,,,,,,,,

市政基础设施工程,,,,,,,,,,,,,,,,,,,,,,,,

CFG桩施工记录表,,,,,,,,,,,,,,,,,,,,,,,,

项目名称,佛山创智新城道路工程(一期),,,,施工单位,,广东兴业路桥工程有限公司,,,,监理单位,,上海斯美科汇建设工程咨询有限公司,,,,合同段,,,公路等级,城市支路,,,

路段桩号,DK0+040-DK0+080,,,,,,,,设计配合比,,水泥,粉煤灰,石屑,碎石,水,实际配合比,,水泥,粉煤灰,石屑,碎石,水,,

试桩确定长度,22,,,,,,,,,,1,1.53,3.529,8.555,1.01,,,1,1.53,3.529,8.555,1.01,,

桩编号,4-3,2-3,1-4,3-4,5-4,7-4,9-4,11-4,13-4,15-4,17-4,19-4,21-4,22-5,20-5,18-5,16-5,14-5,桩位示意图,,,,,0:04

开始时间,9:31,9:53,10:19,10:42,11:05,11:26,11:49,12:45,13:10,13:33,13:58,14:19,14:42,15:07,15:33,15:59,16:23,16:45,,,,,,0:01

结束时间,9:48,10:14,10:37,11:00,11:22,11:45,12:10,13:01,13:29,13:53,14:15,14:38,15:02,15:28,15:54,16:19,16:40,17:05,,,,,,

设计长度(m),22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,,,,,,

实际桩长(m),22.1,22.2,22.2,22.3,22.3,22.2,22,22,22.3,22,22.3,22.3,22.2,22.1,22.1,22,22.2,22,,,,,,

竖直度(1%),0.8,0.8,0.9,0.8,1,1,0.8,0.9,1,1,0.8,1,0.9,0.9,0.8,0.8,0.9,0.9,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

施工间断记录,施工无间断,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

自检意见,,,,,,,,,,,监理意见,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

项目技术负责人,,,,质检员,,,,,,施工员,,,,,,监理,,,,,,,,

2013年11月23日,,,,,,,,,,,,,,,,,,,,,,,,

市政基础设施工程,,,,,,,,,,,,,,,,,,,,,,,,

CFG桩施工记录表,,,,,,,,,,,,,,,,,,,,,,,,

项目名称,佛山创智新城道路工程(一期),,,,施工单位,,广东兴业路桥工程有限公司,,,,监理单位,,上海斯美科汇建设工程咨询有限公司,,,,合同段,,,公路等级,城市支路,,,

路段桩号,DK0+040-DK0+080,,,,,,,,设计配合比,,水泥,粉煤灰,石屑,碎石,水,实际配合比,,水泥,粉煤灰,石屑,碎石,水,,

试桩确定长度,22,,,,,,,,,,1,1.53,3.529,8.555,1.01,,,1,1.53,3.529,8.555,1.01,,

桩编号,12-5,10-5,8-5,6-5,4-5,2-5,1-6,3-6,5-6,7-6,9-6,11-6,13-6,15-6,17-6,19-6,21-6,22-7,桩位示意图,,,,,0:04

开始时间,17:04,17:29,17:52,18:15,19:11,19:33,19:56,20:19,20:42,21:05,21:28,21:53,22:16,22:39,22:59,23:24,23:47,0:11,,,,,,0:01

结束时间,17:25,17:48,18:11,18:34,19:29,19:52,20:15,20:38,21:01,21:24,21:48,22:12,22:35,22:58,23:19,23:42,0:07,0:33,,,,,,

设计长度(m),22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,22,,,,,,

实际桩长(m),22.2,22.1,22.2,22.2,22.1,22.2,22.2,22.2,22.1,22,22.2,22,22.3,22.1,22.1,22.1,22.1,22,,,,,,

竖直度(1%),0.9,0.9,0.9,0.8,0.8,0.9,0.8,1,0.9,1,0.9,0.8,1,0.9,0.9,0.8,0.9,0.8,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

施工间断记录,施工无间断,,,,,,,,,,,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

自检意见,,,,,,,,,,,监理意见,,,,,,,,,,,,,

,,,,,,,,,,,,,,,,,,,,,,,,,

项目技术负责人,,,,质检员,,,,,,施工员,,,,,,监理,,,,,,,,

2013年11月24日,,,,,,,,,,,,,,,,,,,,,,,,

市政基础设施工程,,,,,,,,,,,,,,,,,,,,,,,,

CFG桩施工记录表,,,,,,,,,,,,,,,,,,,,,,,,

项目名称,佛山创智新城道路工程(一

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

最新文档

评论

0/150

提交评论