FullofColdAir-PJM's$12Bmodelingmistake

RobertBoswall,ReykKnuhtsen,JeremieEliahouOntiveros,OliverKennon,DylanPatelAugust16,2026

Earlierthisyear,weexplainedwhyresidentsofthePJMarea,America'slargestelectricitymarket,haveseentheirpowerbillsriseby~20%.Wearguedthatthemainculpritwas

PJM'sauctiondesignchoicesandhowPJMmodelsdemandandsupply.Tobetter

understandtheextentoftheproblem,ourEnergyModelteamspentthelast6months

reverse-engineeringPJM'smainsystemmodel,the'ReserveRequirementStudy’,whichtodatehasbeenablackbox.ThisstudyishowPJMdecideswhattypeofandhowmany

powerplantstobuytomakesureelectricityisreliable,usinganannualauction,andspendingbillionseachyear.

Armedwithareconstructedmodelwearguethattheproblemisworsethanwethought.

PJM'smodelincludeserrorsthatweestimatehavecostallofits66millionresidentsatotalof$12Bbetween2025and2027alone.Weshareourmethodintheannexofthis

newsletterforoursubscribers:aswellastheresultsofthemodelinourPJMModel

dashboard.OurliverebuildoftheReserveRequirementModelisatabavailable

exclusivelytoourEnergyModelclients;whichalsoincludesaquarter-by-quarterforecastofthewholeUSgridtracking>40,000grid-connectedpowerplants,andeverysingle

behind-the-meterdatacenterpowerorder.

PJM'smodelisstructurallyanti-growthwithapoorlydesignedcapacitymarketthatisgloballyuniqueandagovernancesystemthatistoobigtofunction.

Thesefailingsmagnifythenegativeimpactofbadsystemmodeling,whichisthefocusofthisreport:

2/33

1.PJMunderestimatesby~4gigawattstheexistingpowerplantsitalreadyhas;owingtoamethodologywhichdoesn'taccountforthehigherefficiencyofpowerplantsin

winterandimprovedpowerplantresiliencesinceStormElliott.

2.PJMhaswasted~$12billionofratepayers'moneyfrom2025to2027duetothis

weakmethodology,whichdramaticallyoverstatedthesupply/demandshortfallitfaced.HouseholdelectricitybillswouldhaverisenmuchlessifPJM'smodelwasaccurate.

3.PJM'semergencyauctionisputtingratepayersatriskbysigningcontractsfortoomuchpowerwithoutcommittedcounter-parties.

PJMCapacityBills,Winter-CorrectedPaidperdeliveryyear,Sbnnominal

semiánalysis

Sources:SemiAnalysisEnergyModel,SemiAnalysisPJMModel

$T1.6bnovercharged

acrossthetwouncappedyears

$16.4bnpaid

Atcap:

$0saved

bymechanism

$16.1bnpaid

$16.4bnpaid

$14.7bnpaid

Atcap:

$4.9bnsaved

$Osaved

$6.7bnsaved10

bymechanism

S71.2bn

CorrectedBill

$8.0bn

CorrectedBill

2026/27

$329atcap

2027/28

$333atcap

2025/26

Cleared$270/MW-day

2028/29$325atcap

Sources:SemiAnalysisEnergyModel;SemiAnalysisPJMModel

UsingPJM'sdemandandsupplycurveswecalculatethatbettermodelingwouldhaveresultedin$6.7Bofsavingswithonly0.014GW(yes,14MW)lesspowerprocuredfor

2025/26;then$4.9Band0.8GWfor2026/27.Morepowermeaninglessinsavingsmightbecounter-intuitivebutwehavethesupplyanddemandcurvestoshowhowthese

disproportionateimpactsoccur.PJMhasforceditselfintooperatingatthelimit,so

inaccuratelymodelingpowerplants'capacitieshasamassiveimpactonauctioncosts.

PJMhasconstraineditsownsupplyofnewpowerbyhavingone-yearcontractsthatstarttoosoonaftertheyaresigned,aswellasbeingslowtoconnectthesenewplantstothegrid.Thismeansfulfillinganydemandgrowthrequirespayingabigpremiumfornew

powerplantstobebuiltatunrealisticspeeds.PJMalsorunstheonlycapacitymarketintheworldthatdoesnotdistinguishbetweennewandexistingpowerplants.Sothat

premiumpaidfornewpowerplantsisalsopaidtoexistingpowerplantsfordoingnothing.Thesamegrowthinamarketthatsplitsnewandexistingpowerplantauctionsavoidsthe

3/33

volumeeffectofrepricingtheentirefleet;whichmeansratepayersarebetterprotectedfrompricespikes.

Despitefourrecord-breakingauctionscosting$63B,PJMwillbeshortoftheamountof

generationitneedstorunreliably,andplanstorunan“emergencyauction”from

September30thtoOctober21stwithresultsbyDecember2nd.SemiAnalysisconcludesthereisanadditional3.8GWofreliablepoweronPJM'ssystembytakingintoaccount

increasedturbineefficiencyfromcoldair,andreducedriskofwinterfailureafterfederallymandatedassetwinterizationinvestments.Thisistheequivalentofeightlargegaspowerplantswhichwouldcostaround$10billiontobuildtoday.This3.8GWwouldnegate56%ofthe6.8GWthatPJMplanstoprocureinitsemergencyauction.

2009

TheLastFourAuctionsCost$63.9Billion

All-incapacityrevenuebydeliveryyear,nominalSbn(bars);auctionclearingprice,S/MW-day(dots)Revenueperthemarketmonitor's2025StateoftheMarketreport;2028/29isauctionrevenueonlySources:SemiAnalysisEnergyModel,SemiAnalysisPJMModel

S10B

2016/T

semiánclysis

Sources:SemiAnalysisEnergyModel;SemiAnalysisPJMModel

PJM'semergencyauctionpresentsseriousrisks,itwillsigncontractsrunningto2043thataresupposedtobepaidforbynewlargeloads.Thesearenotsalesofelectricity;the

plantsgetpaidjustforexisting,whetherornottheforecastdemandeverarrives.ButPJMisdoingthiswithnocommittedcounter-parties.PJMdoesnothaveitsownmoney,

everythingitspendsisfromratepayers.

EveryPJMstatewillhavetopass(butnonehavedonesoyet)theirowncost-allocation

policytopassoncoststoparticipatingnewlargeloads.Butthoselargeloadscanoptoutiftheycontracttheirownadditionalpowerplantsdirectly.Iftheyparticipatethereislittle

clarityonhowmuchoftheauction'scapacitytheyareexpectedtopayfor.Participation

bringsnootherbenefits,likeacceleratedinterconnectiontimelines.Manydatacenter

developershavewrittenoffPJMregardless,goingelsewhereorplanningbehind-the-meter

4/33

【价值目录】网整理:

powerconfigurations.Ifnoothercounter-partyemerges,thenonceagainthoseleftholdingthebagwillbetheresidentialratepayers.

Inthisreport,wediveintoPJM’scapacitymarketandintroduceourproprietaryreverse-engineeredmodel.WebelievethatPJMfailstoaccuratelymodeltwocriticalsupply

characteristics,despitekeystakeholdersrecognizingthemtobebothrealandofimportance:

1.PJMdoesnotcredithowcold,denseairmakesgasplantsstrongerelectricitygeneratorsbyupto25%inwinter;and

2.PJM’sriskcalculationshavenotbeenupdatedtorecognizethataslongagoas2024,400ofPJM’s~700gasplantshadinvestedinwinterreliabilitymeasuresinresponsetotheoutagesfromStormElliott.

TherearedeeperproblemsatPJMthanjustmodeling.Itscurrentauctionsweredesignedtwodecadesago,andithasnotexperienceddemandgrowthsince.TodayPJMis

structurallyanti-growth.PJMisfailingtoadapttothisneweraofloadgrowthbecauseofagovernance

deadlock

,avetocracyofvestedinterests.Ifitcannotachievemarketreformperhapsitcanstemtheratepayerbleedingbyimprovinghowcapacityismodeled,

especiallywhenwinteriscoming.

ThisreportwilldigdeepintoPJM’scapacitymarket.Afterprovidingsomeintroductorycontext,weadoptthefollowingstructure:

WestartwiththefundamentalsandexplainhowPJMmodelssupply,demand,andreliabilityrisks.Wecovertheirmajormodelingmethodologychangein2024fromEFORdtoReserveRequirementStudyandtheimplicationsofthatchange.

Weintroduceourreverse-engineeredmodelandcoveringreaterdepthhowwecalculatetheroleofvariousresources,outages,reliability,andfleetsize.

Wegettothecoreissue:PJM’slackofconsiderationoftheincreasedthroughputofgaspowerplantsinthewinter,andtheirimprovedreliabilitythroughAsset

Winterization.

Wethendiveintothepricingimpact.PJM’scapacityauctionsarehighlycomplexandweexplainwhyandhowPJM’s66Mresidents’electricitybillswere$12Bhigherthantheyneededtobe.

Lastly,weprovidesomethoughtsonthefutureofPJManditsupcomingReliability

BackstopAuction.Thisisanemergencymechanismhopingfordatacenterstopayfortheirowncapacity.Webelievethatratepayerscould,again,beatrisk.

Let’sgo.

5/33

【价值目录】网整理:

ThisreportisacollaborationbetweenSemiAnalysisandNathanIyerinhispersonalcapacity.

Context

Ifyouhavenotbeenfollowingalong,letuscatchyouup:

PowerbillsinPJMstatesjumped17-24%inJune2025,andthestateregulatorslabeledthecapacityauctionasthemaindriver.Readour

PJMvsERCOT

articletounderstandPJM’scapacityauction,andhowsingularitisrelativetootherenergymarkets.

PJMconstrainsitsownsupplyofnewpowerplantsbyrequiringthemtobebuiltunrealisticallyquicklyandnotevenacceleratingthegridconnectionsofcriticalprojects.Thisconstrainedsupplygreatlyincreasespricesintheauction.

PJM’scapacityauctionsrestartedinJuly2024afterextendeddelays.Thiscuttheleadtimefornewgenerationtogetbuiltfromtheintended36months(pertheIndependentMarketMonitor)to10months,risingtoonly23monthsforthelatestauction.Power

plantstaketimetobuildandneedlongtermvisibilitysogivingonlya23-monthleadtimemakesitnearimpossibletobuildnewgeneration.

Thefourauctionssincehaveeachprocured134-138GWayearofaccreditedcapacityatpricesthatjumpedfrom

$28.92

beforethedelayto$270-333permegawatt-day,

raisingthecostofacapacityauctionfrom$2.2Bto$16.4B,andthefour-auctiontotalto$63.6B.

ThismoneyispaidbyeverysinglehouseholdandbusinessinthePJMarea,andis

littlemorethanatransferfromratepayerstoexistingpowerplantsasoverthelastfourauctionsonly4.8GWofnewcapacityhasbeenprocured.

Alreadybuiltcapacitydoesnotneed$325/MW-day:PJM’sownmarketmonitorsaysexistinggeneratorsbidat

$8-14/MW-day

,andGreatBritain’slatestauctionpaid

existinggeneration$18/MW-day(£5/kW-year).

Thesegasplantsdonotneedthemoneytostayonline.Themedianexisting

combinedcyclemade

407%

ofitsgoing-forwardcostsintheenergyandancillaryservicesmarketsalonein2025,beforeadollarofcapacityrevenue.

PJMpreventednewprojectsfromgettingagridconnection.FromOctober2021therewasnostudypathwhilePJMclearedits

backlog

;ageneralapplicationwindowdidnotreopenuntilApril2026,when

220GWapplied

.

6/33

·NowPJMhastwounder-performinginterconnectionfast-tracks:1.TheReliability.

ResourceInitiative,51shovel-readyprojectspickedMay2025,now41with31.5%ofthemegawattswithdrawn,firstoutputscheduled2030;2.The10-units-a-year

ExpeditedTrackopenedJuly31,2026.Neitherhasenergizedasinglemegawatt.

·PJMcannotreformitself:rulechangesneedatwo-thirdsmajorityacrossfiveequallyweightedmembersectors,soanytwosectorscanvetoanything,andtheyoftendo.TheBoardcanoverridedependingonthereformbuthaschosennottoonthese

problems.

·FERChasnowgivenPJMuntiltheendofSeptembertoreformitsgovernance

otherwiseFERCwillintervene.ButFERCmainlyhasreactiveratherthanproactivepowersandthisthreatisnotstrictlyaboutthecapacityauctionsormodeling.

·PJMisalsotheonlymarketintheworldwherethecapacityauctionpriceisforthewholegenerationstack.Japanwasthelastothermarkettopricethewholefleetononeyeartermsbuthasnowconcludedthedesignbuildsnothingandboltedonaseparate20-yearauctionfornewentries.

Lead

semicnalysis

2025/26

~10mo

$270

135.7

14.7

0.9

96%

2026/27

~10mo

(at

cap)

134.2

16.1

2.7

98%

2027/28

~18mo

(at

cap)

134.5

16.4

0.8

99%

2028/29

~23mo

(at

cap)

138.3

16.4

0.5

98.5-99.4%

Total

63.6

4.8

~98%

Sources:SemiAnalysisEnergyModel;SemiAnalysisPJMModel

Action

FERCisacceptingcommentsonPJM'sbackstopfiling,until21stAugust.Anyonemay

participateat.SemiAnalysiswillbesubmittingthisanalysis.We

encourageotherstodothesameandwewelcomeanyinputonthemodel,pleasewritetousatenergy@.

7/33

【价值目录】网整理:

WealsoencouragePJM’sBoardtofileimprovedmodelingcriteriaatFERCtochangethetariffandReliabilityAssuranceAgreement,throughthesamefast-pathprocessitusedtoinstallthecurrentrulesin2023andtolaunchthebackstopthisJuly.FERCmustacceptitifitisjustandreasonable,andFERCacceptedseasonalaccreditationatMISOin2022.Thewinter-ratingstextwas

written

inPackageCinAugust2025,passedbyPJM’sowntask

force,butwasnotpassedbytheseniorcommittee.TheBoardcanpickituptomorrow.

Creditingmandatedwinterizationhasnotbeendrafted.Theclosestattemptwasthe

marketmonitor’sblunter

version

todeletethestormdataoutright,whichwasrefusedinthesamesession.FERCshouldrequirethattheemergencyauction’s6.8GWtargetbe

recalculatedbeforePJMsignscontractsthatwilllastuntil2043.

Ourmainrecommendationsare:

1.Thesemodelingrecommendationsshouldbeimplementedfortheemergencyauctionaswellasfutureauctions;

2.Thereshouldbeaninquiryintotheoverspendingofratepayers’moneyinthe2025/26and2026/27auctions;and

3.Auctionsforexistingvsnewcapacityshouldbesplit.

Ourmorelooselyheldthoughtsare:

1.TheEmergencyAuctionshouldprobablybecanceledforposingtoogreatariskto

ratepayersifnewlargeloadsdonotarrive,insteadonlyusedirectcapacitycontractingaspartofacceleratedinterconnectionagreements;and

2.IftheEmergencyAuctioniskepttomakeuptheshortfallitshouldbepaidforbyexistingdemandwithashorttermfixoffurtherloweringthepricecapfortheBaseResidualAuction,thiswouldeffectivelycreateseparateexistingandnewcapacityauctions.

3.Datacentersarehowelectricitycanbecomecheaperthaneverbeforebypayingdownhighsystemcostsusingeconomiesofscaleandunprecedentedvaluecreation.To

attractmoredatacentersandachievethisaffordableenergyfutureStateGovernors

andcustomeradvocatesneedtofocusonthebureaucraticfailurestocreatefunctionalmarkets.

1.PJMunderestimatesthepowerplantsitalreadyhasby~4gigawattsofreliablepower

ForaprimeronPJM’scapacitymarketandauctions,readourprevious

report

.AsaTLDR:PJMactsasacentralplannerandrunsauctionstoensurethereisenoughsupplytomeetpeakdemand,withasafetybuffer.PJMmadeitsplanningmoresophisticatedin2024,but

8/33

【价值目录】网整理:

duetofailedstakeholdervotes,didnotincludeimportantinputs.TheresultofleavingouttheseinputsisthatPJMoverestimatessystemriskduringwintermonthswhichleadsto

tryingtoprocuretoomanynewpowerplantsasbackup.ButPJMalsohasaconstrainedsupplyofnewpowerplantswhichleadstopricespikes,tryingbutfailingtofixthisscarcity.

Thingsweren’talwaysthisway.

In2024,thesameyearthecapacityauctionpricesfirstspiked,PJMoverhauledtheir

resourceadequacymodeling.Previously,thePJMsystemoperatedunderasystemcalled“EquivalentDemandForcedOutageRate”orEFORd.Thecapacitytargetwassetby

takingthepeakdemandandaddingamarginbasedonthechanceageneratormightbeoffline.However,thissystemisnotabletoeffectivelycapturecorrelatedfailures,whicharemorecommonincoldwintermonthsfornaturalgaspowerplants.Italsofailstoaccountfornewertechnologiesonthegrid.Specificallyvariableresourceswhichrequiremodelingonatleastanhourlybasistocapturetheircontributionstocapacity.Theseareintermittentgenerationsuchaswind,solar,orrun-of-riverhydro;aswellas‘limited’

resources,likestorageofallkinds.

Theselimitationscametolightin2022.DuringWinterStormElliott,PJMlost

24%

ofitstotalgenerationduetoforcedoutagesandderates,andtwothirdsofthelosscamefromnaturalgasgenerators.StormElliottledtoasubstantialoverhauloftheReserve

RequirementStudymakingitintoanhourlyriskframework.InthisstudyPJMmodels

demandagainstsupplyforeveryhouroftheyearforanumberoftheoreticalyears,usingbothhistoricandforecast-basedrandomizeddata.Thismoredetailedapproachidentifiedthatatcertaintimesoftheyearthereisnotenoughsupplyrelativetodemand.

Asaresult,gasinparticularsuffereda10-20%knock-down.Thesetwochangeshada

largesystemimpact,clearedcapacityfellby8%(12GWfrom147GWto135GW)betweentheauctionsfor2024/25and2025/26.Itisasifthesystemlostascoreoflargepower

plants.ThecapacityauctionshavebeenexpensivesincePJMbasicallyhadtobuyreplacementplants.

9/33

GasCombinedCycleCreditFellFrom95%to74%PJMELCCclassratingsbydeliveryyear,%ofnameplatecredited

Sources:SemiAnalysisEnergyModel,SemiAnalysisPJMModel

MarginalMethodStarts(2025/26)

-GasCombinedCycle

20

2023/242024/252025/262026/272027/28

semiánalysis

Sources:SemiAnalysisEnergyModel;SemiAnalysisPJMModel

TheshiftfromasummerrisksystemtoawinterrisksystemisamuchbiggerdealinPJM.Ithasonecentralauction,versusothercapacitymarkets,whichinsteaddistinguish

specificallybetweenwinterandsummer.ForPJM,awinterrisksystemdegradesthe

reliabilityvalueofstrongersummerresources(e.g.solarandstoragewhichcanbridgeafternoonpeaks),andenhancesthestrongerwinterresources(e.g.nuclear,coal).Evenaminorimprovementinwintergasriskcanhaverippleeffectsacrosseveryresource,withmajorcommercialimplications.

Thestudy'shourlymatchingagainstweatheranddemandscenariosdefineshoweach

newgeneratorimprovesreliabilityofthesystem.Tomanythisnewsystemisablackbox.PJM,toitscredit,publishesaportionofitsworkanddata.ItiscomplexbutitsnuancesareimportantforunderstandingPJM'scurrentproblems.Withwhich,combinedwithother

publicdata,wehavegivenourbestshotatreconstructingthemodelandscrutinizingitsinnerworkings.Indoingso,we'veidentifiedandcorroboratedanumberofweaknessesthatareofgreatimportancetorecentpricespikes;reliabilityconcerns;andtheupcomingbackstopauction.

TheReserveRequirementStudy

PJM'snew(ish)systemoverestimatestheriskinwintermonthswhichleadstooverbuildingpowerplants.Ourmodelre-runstheReserveRequirementStudyonthesamewhole-

systembasisPJMuses.Ourconclusionisthatthesamefleetisworthmorereliable

capacitythanPJMcreditsit,sotheauctionrequirementagainsttotalelectricitydemandfalls.

10/33

WhilePJMmodelsdemandwithitsyear-roundvariations,itcapssupplyatgenerators'

summeraccreditations.Ononehand,thatmakessenseasPJMisasummerpeaking

system.Thereismoreairconditioningelectricitydemandinthesummerthanthereis

heatingdemandinthewinter,andsothehighestdemandpointsintheyearareinsummer.Evenwhennettedoffagainsttheincreasedoutputofsolar,thedemandforreliablepowerplantsisstillhigherinthesummerthanitisinthewinter.

Ontheotherhand,historicallyfailureratesofgenerationaremuchhigherinthewinter,tendtobecorrelatedacrossfleets,andalignedwithperiodsofhighestdemand.Higherfailureratesmeanthatwintercanbethemostprobabletimeforsupplytofallshortof

demand.Gasislessreliableinwinterasstormscancausethemalltofreezeatthesametime,asseenwiththePolarVortexandStormElliott.

ThistypeofwinterriskisrecognizedinPJM'smodelingbutthedetailsareoutofdateandlackprecision.Theydonotconsiderhowcoldimprovestheoperationsoftheplantsthatdonotfail,orhowplantshavehardenedthemselvesagainsttheweatherinrecentyears.

FixWinterandtheSameMachinesRe-Rate

Capacitycreditbyresourceclass,%ofnameplate,PJMmarginalaccreditationmethod,2028/29

Sources:SemiAnalysisEnergyModel,SemiAnalysisPJMModel

sales@

semicnalysis

MachineavailabilityPJMposted2028/29●Riskinsummer(afterwinterfixes)

Storage

GasCT

GasCC

Steam

Solar

Dependsonwhen

OilCT

WTESteam

Sources:SemiAnalysisEnergyModel;SemiAnalysisPJMModel

PJMuseshistoricaldataforperformance.Thismeansthatfaresourcefaltersonetime,theonlywaytoincreasereliabilityistowaitoveradecadetoflushtheeventoutofthe

system.Noamountofinvestments,regulations,orassurancescanliftthisjudgment.Asa

11/33

result,thelargestdriverofreliabilityrisktothisdaywasdrivenbyapolarvortexin2013andthesecondisStormElliottin2022.

TwoWintersCarry72%oftheRisk

Shareofexpectedshortfallenergy(EUE)byweatheryear,%;committed2028/29fleetWeatheryearsrunJunetoMay;sharesroundindependently;onefrozenmodelrun

Sources:SemiAnalysisEnergyModel,SemiAnalysisPJMModel

POLARVORTEX201374

STORMELLIOTT2022/23

2012

4.5%

■Winter-drivenyear

3.2%

2.5%

1.8%

1.7%

1.6%

1.5%

1.3%

2015

2024

2018

2016

2021

2014

2023

2020

2019

2017

semicnalysis

■Summer-drivenyear

2013

2022

47.9%

Sources:SemiAnalysisEnergyModel;SemiAnalysisPJMModel

Self-Supply

Whyaren'tPJMratepayersbetterprotectedfrompriceswings?Inmostotherpower

markets,retailcustomershavelong-termcontractswithutilitiesandarenotexposedtoyearlycapacitymarketchanges.Themarketnextdoor,MISO,alsoexperienced

substantialcapacityswings,butthevastmajorityofhouseholdswereunaffectedbecauseutilitieshadlong-termcontracts.

ThereareanumberofreasonsPJMissoall-or-nothing,butitcomesdowntoa

combinationofretailchoiceandderegulation(shorterandlesscertaincontracts),a

SupremeCourtcasethatstruckdownstateeffortstosupportlong-termcontracts,andalong-standingFERCfightthatboileddowntoapartisanbattlebetweenresource

preferences.

Theothermainoptionremainingisforutilitiestoprocureenoughcapacityforthemselvesandtheneffectivelyejectthemselvesfullyfromthecapacitymarketfor5years.Thisshowsuponthecapacitymarketsasbigswings,butendsupbeingrelativelyneutralimpacts

becausethesupplyanddemandimpactisbalanced.

FleetUncertainty

12/33

WhiledataforPJM'soverallfleetisrelativelytransparentanddrivestheirriskmodel,theauctionitselfdivergesinoftenunpredictablewaysandcannotbefullyreplicated.

TheReserveRequirementStudyisbiggerthanjusttheBaseResidualAuction,assomeutilities'self-supply'.TheFixedResourceRequirement(FRR)alternativeallowsutilitiestooptoutoftheauctionandfiletheirowncapacityplans,withanobligationsetbytheirshareofload,whichis~8%ofthePJMsystem(e.g.12GWfor2026/27).

SoPJM'sReserveRequirementStudymodelsan‘AssumedFleet,andproducesawhole-systemnumber(e.g.146GWofreliablecapacityfor2026/27).Theauction'stargetistherequirementminustheself-supplyobligation(e.g.134GWfor2026/27).

TheCommittedFleetistheresultoftheauctionandself-supply.In2026/27theauctioncleared134.3GW,0.2GWshortofitstarget,whiletheself-supplyplanscommitted12GW,about0.3GWmorethantheirobligation.Thesystemendedtheauction0.1GWabovethewhole-systemrequirement,butonlybecauseself-supplyover-deliveredbymorethantheauctionmissed.Behindallofthissitsthetotalfleet,thepowerplantsthatphysicallyexist.

TheRequirementHasOutgrownPJM'sCommittedFleetGW,byauctiondeliveryyear

Sources:SemiAnalysisEnergyModel,SemiAnalysisPJMModel·

■Self-Supply(FRR)■AssumedAdditional

156.0

2027/28

semianalysis

Sources:SemiAnalysisEnergyModel;SemiAnalysisPJMModel

13/33

PJMSupplyvsDemand,FleetbyFuel

Capacity,GW.Leftbar:totalfleet(ICAP).Rightbar:committedfleet(UCAP,planbasis).Amberdot:demand(forecastpeak).Whitediamond:requiredcapacity.

Sources:SemiAnalysisEnergyModel,SemiAnalysisPJMModel

COAL

NUCLEAR

TOTALFLEETCOMMITTED

2025/262026/27

semianalysis

Sources:SemiAnalysisEnergyModel;SemiAnalysisPJMModel

Reverse-EngineeringtheModel

Togettherealnumbersweneededtorebuildthemodelinfull.SowetookPJM'sManual,whichexplainshowtheydothisstudyandturneditintocode.Thenweranonthatcode

theweather,demand,andgenerationdatathattheypublish.Fordatathattheydonotgiveweusedpubliclyavailableproxies,mainlyfromtheU.S.EnergyInformationAdministration.WegotahighlevelofaccuracytotheoutputsthatPJMpublishesacrossthelastfour

auctions.ThedetailedstepbystepisincludedintheMethodologyAnnexofthisnewslettertohelpsubscriberswhowishestorecreateorauditourwork.

ModelReconstructionsvsPJMPublishedValues

Committed2028/29planningquantities,MWanddaysperyear

TheenginelandswithinatwentiethofapercentofPJM'spublishedanswers

semianclysis

Quantity

Model

Solvedpeakload(2028/29)PJMpublishedsolvedpeak

162,107MW

+44MW(+0.03%)

Reliabilityrequirement(UCAP)PJMpublishedrequirement

156,013MW

155,938MW

-75MW(-0.05%)

Committed-fleetLOLESourcepacket'sownrun

0.487days/yr

0.478days/yr

-0.009(-1.85%)

Sources:SemiAnalysisEnergyModel;SemiAnalysisPJMModel

Improvingthemodel

Intheauctionfor2026/27,coldairupliftaloneshouldhavereducedtherequiredcapacityby1.5GWandweatherizationalone2.5GWatonly60%.Togethertheywouldhavebeen

14/33

worth3.1GWasthereisasignificantoverlapbetweentheireffects.

PJMAuctionRequirements,Winter-Corrected

semiánclysis

Sources:SemiAnalysisEnergyModel,SemiAnalysisPJMModel

140

2025/26(50%)2027/28(70%)

2028/29(80%)

Sources:SemiAnalysisEnergyModel;SemiAnalysisPJMModel

WecalculatedthisbyusingourreconstructedReserveRequirementStudytotesthow

muchtheoutputswouldchangeifwealteredtwoinputassumptionsthathavebeenwidelydebatedandpreviouslyproposed:creditingcoldairupliftandassetwinterizat

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论