July2025
Mcsey
&company
PublicSectorPractice
UnlockingUSfederal
permitting:Asustainablegrowthimperative
Thepermittingprocessforlargeinfrastructureprojectsiscostlyandtimeconsuming.Acceleratingtimelinescouldhelpmeetcriticalinfrastructureneedsandfuelfuturegrowth.
byBobSternfels,AdiKumar,andBrodieBoland
withBoboStankovikjandTimCarter
BigplansareafoottobuildintheUnitedStates.Thecountryneedsadditionalenergy
generationcapacity,transmissionlines,broadband,raillines,andmore.Thegoodnewsisthatplentyofprovidersarelininguptobuildtheseprojects.Morethan650infrastructureprojectstrackedbytheUSPermittingDashboardareawaitingfederalapprovaltobeginconstruction.1Thebadnewsisthattheseprojectswilllikelybewaitingforalongtime.Largeinfrastructure
projectsintheUnitedStatesfacepermittingwaittimesstretchingforyears.
Theintentionsofpermittingaretosafeguardthehealthandpropertyrightsofcommunities,
preserveecosystems,upholdairandwaterqualitystandards,protectculturalandhistorical
landmarks,andmitigatetheeffectsofclimatechange.Manytimes,permittingstatuteshave
provedcriticalinprotectingAmericansagainstthepotentiallyharmfuleffectsofproposed
development.TheNationalEnvironmentalPolicyAct(NEPA)andtheNationalHistoric
PreservationAct(NHPA)weremeaningfuladvancementsthathaveaffordedlocalandtribal
groupsalegalplatformtoadvocatefor—andensure—robustenvironmentalreviewsontheir
traditionallands.2Naturalecosystemsareinvaluablebothintheirownrightandintheservicestheyprovidetosocieties—forexample,cleanair,cleanwater,qualitysoils,climaticregulation,
andrecreation.Permittinghasplayedanimportantroleinprotectingtheseecosystems,whosecriticalbenefitsmustbepreserved.
Yetasthegapgrowsbetweenthecountry’sexistinginfrastructureandwhatisneeded,many
stakeholdersareaskingwhetherpermittingcouldachievetheseobjectivesmorequickly.As
permittingincreasinglybecomesatopicoffocus,itisimportantthatproposedreformsimprovetheeffectivenessofpermittingbothinpreventingharmstopeopleandecosystemsandin
enablingdevelopmentthatwillbenefitthosepeopleandecosystems.Althoughsubstantialbenefitsmayarisefromshorteningpermittingtimelines,thoughtfulreformsdonotseektheeliminationofpermittingreview.EnsuringsocialandenvironmentalsafeguardsandmeetingAmerica’sinfrastructureneedsdon’thavetobezero-sumgames.
Tounderstandthescopeofthisproblem,weusedmultiplelensestoestimatethefederal
permittingtimelinecostsforUSinfrastructurestakeholders,includingthepublic.Weestimate
that$240billionto$280billionininfrastructurecapitalexpendituresacrosseightkeysectors
enterthefederalpermittingprocesseachyear.Wefindthateachdollar,onaverage,takes
aboutfourtofiveyearstomovethroughpermitting.Thesefindingscombinedsuggestthere
is$1.1trillionto$1.5trillionofinfrastructurecapitalexpenditurecurrentlyinfederalpermitting,
costingstakeholdersbillionsofdollarsinlostrevenueandwithholdingprojectbenefits,includingincreasedGDP,increasedpowergenerationcapacity,lowercarbonemissions,andopportunitiesforpublictransit.
Inresponsetotheseestimates,wehighlightreformsthatcouldempowertheUSfederalgovernmenttostreamlinepermitreviewsandunlocknecessaryinfrastructure.
Criticalinfrastructureisneededandsubjecttofederalreview
IntheUnitedStates,infrastructureprojectsmayfaceseverallayersofpermitting,includingatthefederal,state,andlocalormunicipallevels.Forsomesectors,suchashousing,permittingisprimarilyastateorlocalexercise.Largerinfrastructureprojects—inenergy,transport,
1“PermittingDashboard:FederalInfrastructureProjects,”PermittingCouncil,updatedJuly18,2025.
2DinéCitizensAgainstRuiningOurEnvironmentv.Bernhardt,No.182089,923F.3d831,USCourtofAppeals,10thCircuit,May7,2019.
UnlockingUSfederalpermitting:Asustainablegrowthimperative2
UnlockingUSfederalpermitting:Asustainablegrowthimperative3
communications,ormanufacturing,forexample—arelikeliertobesubjecttofederalpermitting,whichisthefocusofouranalysis.
TheUnitedStatesisstrivingtoaddressthegrowingneedforinfrastructure:TheInfrastructureInvestmentandJobsAct(IIJA)authorizedapproximately$1.2trillionforinfrastructure;the
CHIPSandScienceActdedicatedaround$53billiontosemiconductormanufacturing;and
environmentalinitiativesreceivedmostoftheapproximately$152billionininfrastructure
spendingfromtheInflationReductionAct.
3
Asthevolumeofinfrastructureprojectsincreases,sodoestheneedforpermittingefficiency.
Hundredsoftransportationprojectsareinprogress,pertheUSPermittingDashboard(Exhibit1A).
Exhibit1A
AlargevolumeofinfrastructureisproposedintheUnitedStates,acrossmanysectors.
HI3
Transportationprojectsinfederalpermittingdashboard,2025,numberinprogress
01022+Nodata
WA
14
OR
4
NV
6CA
124
AK
5
ND
2
SD
3
NE
2
KS
8
OK
3
TX
22
MN
8
IA
6
MO
6
AR
31
LA
2
MT
2
WY
1
CO
5
NM
2
NY11
PA12
WV
4VA10
NC8
ID
7
UT
13
AZ
22
ME0
MA4
RI0
CT5
NJ1
DE1
MD3
DC1
WI
5
IL
5
MI
6
IN
9
KY3TN9
VT2
NH1
OH
2
MS
7
GA
19
SC
9
PR
1
AL
5
FL
10
Source:USDepartmentofTransportation
McKinsey&Company
3AdieTomerandBenSwedberg,“Federalinfrastructurehub,”BrookingsInstitution,updatedonNovember25,2024;AdieTomeretal.,“Americahasaninfrastructurebill.Whathappensnext?,”BrookingsInstitution,November9,2021;
“InfrastructureInvestmentandJobsAct(IIJA)implementationresources,”GovernmentFinanceOfficersAssociationofthe
UnitedStatesandCanada,accessedJune2025;USDepartmentofCommerceBlog,“Twoyearslater:FundingfromCHIPS
andScienceActcreatingqualityjobs,growinglocaleconomies,andbringingsemiconductormanufacturingbacktoAmerica,”blogentry,August9,2024.
UnlockingUSfederalpermitting:Asustainablegrowthimperative4
EspeciallyinthesouthernUnitedStates,hundredsofmilesofnaturalgaspipelineshavebeenproposed(Exhibit1B).
Exhibit1B
AlargevolumeofinfrastructureisproposedintheUnitedStates,acrossmanysectors.
Proposednaturalgaspipelineprojects,bystate,2025,number
Naturalgaspipelines
Pipeline-relatedprojects
No
projects
PA23
VA26
NC28
SC
WI
8
IL
112
TN154
AL
TX
20
LA
73
NM
OK
GA
Source:USFederalEnergyRegulationCommission,2025
McKinsey&Company
UnlockingUSfederalpermitting:Asustainablegrowthimperative5
EveryregionoftheUSgridhasatleasthundredsofmilesofelectricaltransmissionlines
proposed,withsomeregionshavingasmanyas2,500milesofproposedlines(Exhibit1C).
Exhibit1C
AlargevolumeofinfrastructureisproposedintheUnitedStates,acrossmanysectors.
Ready-to-gomilesofelectrictransmissionlines,bysupplier,2023,number
05501,0001,4002,500Nodata
SPP³
SPP
ISO-NE⁹
NYISO⁸
WECC²
PJM⁷
CAISO¹
Southeast⁶
ERCOT⁴
¹CaliforniaIndependentSystemOperator.²WesternElectricityCoordinatingCouncil.³SouthwestPowerPool.⁴ElectricReliabilityCouncilofTexas.⁵MidcontinentIndependentSystemOperator.⁶SoutheasternElectricReliabilityCorporation.⁷PJMInterconnection.⁸NewYorkIndependentSystemOperator.⁹ISO-New
England.
Source:AmericansforaCleanEnergyGrid,2023
McKinsey&Company
UnlockingUSfederalpermitting:Asustainablegrowthimperative6
Furthermore,recentinvestmentsundertheBroadbandEquity,Access,andDeployment(BEAD)Programcouldresultinhundredsofbroadbandprojectsenteringthefederalpermittingqueue,addressingthegapsinhigh-speedinternetaccessnationwide(Exhibit1D).
Exhibit1D
AlargevolumeofinfrastructureisproposedintheUnitedStates,acrossmanysectors.
Householdswithoutaccesstohigh-speedinternet,2024,%
0102030Nodata
HI3
WA
10
OR
9
NV
3CA
3
AK
30
ME10
MA1
RI1
CT0
NJ1
DE2
MD2
DC0
PR
-
ND
1
SD
6
NE
9
KS
7
OK
8
TX
5
MN
7
IA
7
MO
10
AR
11
LA
13
MT
22
WY
22
CO
7
NM
11
NY2
PA5
WV
22VA21
NC8
WI
15
IL
6
MS
16
ID
15
UT
5
AZ
7
MI
7
IN
6
KY11TN5
VT20
NH4
OH
4
GA
7
SC
4
AL
13
FL
4
Source:USFederalCommunicationsCommission,June2024
McKinsey&Company
UnlockingUSfederalpermitting:Asustainablegrowthimperative7
LargerinfrastructureprojectstypicallyrequirefederalpermittingunderNEPA,which
requiresfederalagenciestoassessaproject’senvironmentalimpact,includingeffectson
naturalandhistoricresourcesandcommunities(seesidebar“NationalEnvironmentalPolicyAct”).Roughly100,000actionsfaceNEPArevieweveryyear,fromthelargestinfrastructureprojectsinenergy,transportation,andmanufacturingtosmallerprojectssuchasshort-termlandusagebyindividualsandsmallbusinesses.
4
Projectsmayalsoneedtoobtainsomecombinationofapproximately60project-specific
federalpermitstrackedbythePermittingCouncil.
5
Specificprojectcharacteristicsdefinewhichpermitsareneeded(forexample,CleanWaterActandCleanAirActpermits;USCoastGuard
bridgepermits;migratory-birdpermits;andMarineProtection,ResearchandSanctuariesActpermits).Someofthesepermitprocessesremainunstandardized,decreasingthepredictabilityoftimelines.
Litigationcandelayprojectsandintroducenewexpenses.Approximately30percentofprojectsundergoinganenvironmentalimpactstatement(EIS),themostinvolvedtypeofreviewunder
NEPA,facelitigation;nearly90percentofplaintiffsinthesecasesclaimaNEPAviolation,
amongotherlegalobjections.
6
Theseclaimsarepresentedbyadiversesetofplaintiffs—
includingnongovernmentalorganizations(NGOs),localgovernments,andindividuals—oftenalleginginadequateanalysisinanEISorfailuretoconsiderareasonablerangeofalternatives.
Specificprojectcharacteristics
definewhichpermitsareneeded.
Someofthesepermitprocesses
remainunstandardized,decreasingthepredictabilityoftimelines.
4“Factsheet:ModernizingCEQ’sNEPAregulations,”USCouncilonEnvironmentalQuality,July15,2020;NationalNEPARegister,USBureauofLandManagement,accessedJune2025.
5PermittingDashboard,FederalInfrastructureProjects,accessedJuly23,2025.
6MichaelBennonandDevonWilson,“NEPAlitigationoverlargeenergyandtransportinfrastructureprojects,”EnvironmentalLawReporter,October2,2023.
UnlockingUSfederalpermitting:Asustainablegrowthimperative8
NationalEnvironmentalPolicyAct
TheNationalEnvironmentalPolicy
Act(NEPA)requiresagenciestoanalyzetheexpectedenvironmentalimpactsof
infrastructureprojects,withdifferent
proceduresdependingonaproject’s
anticipatedeffects.Projectswiththe
greatestpotentialimpactundergo
anenvironmentalimpactstatement
(EIS),whichtypicallytakesatleast
twoyears—excludingpreplanningand
potentiallitigation(exhibit).1ThelengthsofeachphaseoftheEISprocessvary
considerablydependingontheindustryandscaleofagivenproject.WhiletheEIS
permittingprocesstechnicallybegins
withthereleaseofanoticeofintent,
developersmaydedicatesubstantialtimeandcapitaltoprescopingactivities,suchascoordinatingwithconsultantsand
engineersandmeetingwithmembers
ofthepublicandwithrepresentativesof
federal,state,local,andtribalpoliticalandgovernmentalgroups.Effortsduringthisperiodoftenattempttogatherpreliminaryenvironmentaldata,anunderstandingofpotentialalternatives,andadeterminationofwhatdepthofNEPAassessmenta
projectwilllikelyundergo—forexample,if
theactionwillpotentiallyhaveasignificantenvironmentaleffect,itwilllikelyface
anenvironmentalassessment(EA);if
itisclearthattheprojectwillcauseasignificantenvironmentaleffect,itwilllikelyfaceanEISreview.2
WhilethedevelopmentoftheEISisacollaborativeendeavor,therelevant
leadfederalagencybearsresponsibility
forfulfillingtheprocessrequirements
andmanagingpotentiallitigation,while
theprojectdeveloperownsthepre-EIS
planningperiodandtheconstructionphase.
Exhibit
Year1Year2Year3Year4Year5Year6
Keymilestones
lA.ReleasenoticeofintentlB.PublishdraftEISlC.PublishfinalEISlD.Issuerecordofdecision
1EPAmandatesminimum45-daywaitingperiodfollowingdraftEISsubmission.
Source:CouncilonEnvironmentalQuality,2018;FederalPermittingImprovementSteeringCouncil,2019;NASA,2015;PermittingCouncil,2020;McKinseyanalysis
McKinsey&Company
Developercompletesearlyproject
planning(eg,feasibilityandpermittingneedsassessments,scoutingresearch)
LeadagencydraftsEIS(eg,scoping,
definingalternatives,testing,completingimpactassessments,compilingdraft)
Leadagencycollectspubliccomments(eg,solicitandconsiderfeedback)¹
Leadagencyrevisesplansbasedoninput(eg,addresspublicfeedback,
conductadditionaltestingasneeded)
Agencyawaitsapproval(eg,waitforEPAtopublishrecordofdecision)
Agencyrespondstopotentiallitigation(notuniversallyapplicable)
Developerbeginsconstruction(multipleyears;variesgreatly)
B
20–26
C
1–2
D7–13
1–7
12–18
Permittingtimelinescanstretchtomanyyearsforprojectsrequiringanenvironmentalimpactstatement.
Illustrativetimelineforprojectsrequiringanenvironmentalimpactstatement(EIS),1months
Year1Year2Year3Year4Year5Year6
3–9
A
1“Environmentalimpactstatementtimelines(2010-2024),”USCouncilonEnvironmentalQuality,January13,2025;MarioLoyola,“Globalinfrastructurepermitting:Asurveyofbestpractices,”CompetitiveEnterpriseInstitute,July7,2023.
2Projectsthataren’texpectedtodeliversignificantimpactsonthehumanenvironmentmayreceiveacategoricalexclusionunderNEPAthatexemptsthemfromfurtherreview.“NationalEnvironmentalPolicyActreviewprocess,”USEnvironmentalProtectionAgency,updatedonApril11,2025.
Permittingtimelinesarelengthyandcostly
Whilelongfederalpermittingtimelineshaveattractedpublicattention,researchquantifyingtheireffectsoninfrastructuredevelopmentremainslimited.Ouranalysisaddressesthisknowledge
gap,usinggovernmentdatatocalculatetheimpactoflongtimelinesusingseveralmeasures(seesidebar“Methodology”).Foreachofouranalyses,theestimatedimpactwassubstantial.
Ourresearchconfirmsthatthepermittingprocessforlarger,moreexpensiveprojectsistypicallyfarlongerthanitisforsmallerprojects.Asaresult,calculatingtheaveragepermittingtime
acrossallprojects(agnostictoandundifferentiatedbysize)underestimatesthesubstantialsocialandeconomicimpactsofpermittingfortheselargerinitiatives.Weenlistweighted
averagestoaddressthisnuance.
Methodology
Eachmeasurementoftheestimated
economicandsocialimpactofUSfederal
permittingtimelinesreliesononeorbothoftwofundamentalinputsthatweestimated:expectedpermittingdurationandvolumeofcapitalexpendituresubjecttofederal
permitting.Whileexistingstudiesfocus
ondiscretecomponentsofthefederal
permittingprocess,theresearchdoesnotofferabroadviewoftotaltimelinesand
theirimpacts.Inrecognitionofthis,weadoptedamulti-lensapproachtoinformourestimations.
Tocalculatetheexpectedpermitting
durationbysector,weestimatedthe
durationspentonNationalEnvironmentalPolicyAct(NEPA)review,additional
approvalsthatextendbeyondNEPA
review,andassociatedlitigation.WeuseddatafromtheCouncilonEnvironmental
Quality(CEQ),thePermittingCouncil,federalagencies,andacademic
researchtodevelopbaselineestimates
foreachsector.Basedonconsultation
withpractitioners(forexample,former
regulatorsandcompliancespecialists),
wethenadjustedbaselineestimatesfor
categoriesofprojectsineachsectorbasedonthefollowingcriteria:
—Projectsize.Basedonconversationswithindustryexperts,weestimated
thatboththedurationandlikelihoodofmorestringentNEPAreview,additionalpermittingapprovals,andlitigationarehigherforlargerprojectsandlowerforsmallerprojects.
—LevelofNEPAreview.Weassume
thatboththedurationandlikelihoodofadditionalpermittingapprovals
andlitigationarehigherforprojectswithmorestringentlevelsofNEPAreview(forexample,environmentalassessmentsandenvironmental
impactstatements)andlowerforprojectswithlessstringentlevelsofNEPAreview(forexample,
categoricalexclusions).
Ultimately,ourresultsarecapital-
expenditure-weightedduration;inotherwords,theyareestimatesoftheamountoftimetheaveragedollar(ratherthantheaverageproject)thatissubjecttofederalpermittingwillspendinthepermitting
process.Basedondatafromthe
PermittingCouncil,weassumethatthelargestprojects,thoughfewerinnumber,accountforthemajorityofcapitalexpenditure.
Toestimatethevolumeofcapital
expendituresubjecttofederalpermittingineachsector,weusedhistoricaldata
fromtwoUSCensusBureausurveys—
theAnnualCapitalExpendituresSurvey(ACES)andtheValueofConstruction
PutinPlaceSurvey(VIP)—andconsultedadditionalgovernmentsources(for
example,theBureauofTransportation
StatisticsandtheEnergyInformation
Administration)tosupplementestimatesforspecificsectorsnotfullycaptured
bytheCensusBureausurveys.Basedonavailabledataandconsultationwith
practitioners,wethenestimatedthe
proportionofinfrastructurecapital
expenditureineachsectorthatislikelysubjecttofederalpermitting.
Finally,toaccountfordatalimitationsandtheinherentuncertaintyassociatedwith
thisexercise,weconductedasensitivity
analysisonthreekeyvariablesthatwere
importantdeterminantsofourestimates
andhadcomparativelylimitedavailable
data:thedistributionofcapitalexpenditureacrossprojectsize,thedistributionof
projectsacrosslevelofNEPAreview,andtheproportionofinvestmentsubjectto
federalpermittingbysector.Thisprocessallowedustodevelophighandlow
estimates,resultingintherangesseenthroughoutthisarticle.
UnlockingUSfederalpermitting:Asustainablegrowthimperative9
UnlockingUSfederalpermitting:Asustainablegrowthimperative10
Throughthatapproach,weestimatethattheaverageproposedprojectdollartakesfourtofive
yearstomovethroughthepermittingprocess,withlargevariationsbysector:Manufacturing
dollarstaketwotothreeyearstomovethroughpermitting,forexample,whileminingdollars
takeeighttonineyears(Exhibit2).ThelongestwaittimesareforprojectsrequiringanEISreview,whichalsotendtobethelargestprojects.
Projectssubjecttolitigationindistrictcourtstypicallyfacedelaysof1.0to2.0years,andthosethatappealincircuitcourts(approximatelyone-thirdofallNEPA-relatedcases)requirean
averageof4.2yearstoresolve.
7
Despitethesetimelines,NEPA-relatedlitigationrarelyleadstomeaningfulchange;80percentofappealscasesbetween2013and2022weredecidedinfavoroffederalagencies.
8
Slowdownsinthepermittingprocesscanincreasecosts,hindereconomicgrowth,andcreate
negativeeffectsonsocietyandtheenvironment.Whilesomeamountofvaluewillalwaysbe
awaitingpermittingreview,unlockingbackloggedinfrastructurecouldreducetheselosses.Weestimatethatatanygiventime,reducingthefederalpermittingtimelinebyonlyoneyearcould
unlockaminimumof$22billioninreturnsoninvestedcapitalamongprojectsseekingapprovals.
9
Exhibit2
Weightedaveragepermittingtimeforprojectsvariesbysector.
Averagepermittingtime,byindustrysector,2025,years(range)
Mining Oilandgaspipelines EnergygenerationElectricitytransmission
Transportation OilandgasextractionBroadbandandtelecom
Manufacturing
0123456789
Years
Source:BLMNEPANationalRegister;BreakthroughInstitute;ColumbiaUniversity:USFSNEPADatabase;CouncilonEnvironmentalQuality:EISLength
database;FederalPermittingDashboard;FederalPermittingImprovementSteeringCouncil:BaselinePerformanceSchedules;FederalRegister:Section404Permits;GovernmentAccountabilityOfice;FederalEnergyRegulatoryCommission;NOAA:EFHConsultation;PNAS;StanfordUniversity;UniversityofUtah
McKinsey&Company
7NikkiChiappaetal.,“UnderstandingNEPAlitigation:AsystematicreviewofrecentNEPA-relatedappellatecourtcases,”BreakthroughInstitute,July11,2024.
8JohnC.RupleandKaylaRace,“MeasuringtheNEPAlitigationburden:Areviewof1,499federalcourtcases,”EnvironmentalLaw,2020,Volume50,Number2;MichaelBennonandDevonWilson,“NEPAlitigationoverlargeenergyandtransport
infrastructureprojects,”EnvironmentalLawReporter,October2,2023;NikkiChiappaetal.,“UnderstandingNEPAlitigation:AsystematicreviewofrecentNEPA-relatedappellatecourtcases,”BreakthroughInstitute,July11,2024.
9Thisestimatereflectstheexpectedannualpostconstructionreturnsonthe$240billionto$280billionininvestedcapitalexpendituressubjecttopermittingacrosseightkeysectors.
UnlockingUSfederalpermitting:Asustainablegrowthimperative11
Economicimpact
Whilepermittingrequiresbillionsofdollarsindirectspend—$5billionto$14billion,byour
estimate—italsoleadstoindirectcosts(Exhibit3).Thefour-to-five-yearpermittingtimeline
meansthattheunrealizedreturnsonprojectsinthepermittingpipelineamountto$100billionto$140billioneachyear,roughlyhalfoftheproposedcapitalexpenditureenteringthefederalpermittingpipelineeveryyear.Constructioncostscanincrease24to30percentoverprojecttimelines,spurredmainlybymaterialandlaborcostinflationandaddedoverheadcosts.
Capitaltiedupinpermittingdoesn’tcontributetotheeconomy,whichlimitsGDPgrowth.To
quantifythis,weestimatedtheinducedGDPeffects—includingunrealizedhouseholdspendingbyworkersandsupplierspaidtoexecutetheproject—ofcapitalinthepermittingqueueto
determinethesecond-ordereffectsofthesetimelines.Wefound$1.7trillionto$2.4trillioninunrealizedcumulativeGDP.
TheUSpermittingprocess
requires$5billionto$14billionindirectspend,byourestimate,andalsoleadstoindirectcosts.
UnlockingUSfederalpermitting:Asustainablegrowthimperative12
Exhibit3
TheproblemwithslowpermittingintheUS
HiddencostsMissingimpact
$5billion–$14billion
indirectpermittingcostsperyear(eg,applicationfees,
legalfees)1
24%–30%
totalincreaseinconstructioncostduetopermittingdelays²
$100billion–$140billion
inunrealizedreturnsfrominfrastructurein
³permittingannually
$1.7trillion–
$2.4trillion
ofunrealizedGDPfrominfrastructurecurrentlystuckin
⁴permitting
Emissionsnotsaved⁵Energynotcreated⁶
CO₂emissionsequivalenttothosefrom
17million–26milliongas-poweredcarsintheUS
1milliongas-poweredcars
Enoughenergytopower38million–54millionUShouseholds
1million
households
That’s~80million–120millionmetrictonsinCO₂sav-ingseachyearfromclean-energyprojectsthatare
trappedinthepermittingstage
That’s~410–580terawatt-hoursofunrealizedelectricitygenerationfrompotentialcapacitytrappedwaitingfor
permits
1millionpublictransitrides
Publictransitnottaken⁷
~130millionpublictransitrides,or2%ofUSannualridership,islostannuallyinpublictransitprojectsstuckinpermitting
¹CommonGood,RetiefandChabalala,2009;OECDandMcKinseyGlobalInstitute,2020;TrackUnit.²CommonGood,2015.³BLMNEPANationalRegister;BreakthroughInstitute;ColumbiaUniversity:USFSNEPADatabase;CouncilonEnvironmentalQuality:EISLengthdatabase;FederalPermittingDashboard;FederalPermittingImprovementSteeringCouncil:BaselinePerformanceSchedules;FederalRegister:Section404Permits;GovernmentAccountability
Office;FederalEnergyRegulatoryCommission;NOAA:EFHConsultation;PNAS;StanfordUniversity;UniversityofUtah.⁴OECDandMcKinseyGlobalInstitute.⁵EIACO₂cofactor,2024;WorldResourcesInstitute,2020.⁶EIAcapacityadditions,2025;EIAcapacityfactors,2023.⁷MTA,2022;PermittingCouncil,Apr2025;McKinseyanalysis.
McKinsey&Company
UnlockingUSfederalpermitting:Asustainablegrowthimperative13
Societyandtheenvironment
Acceleratingfederalpermittingcouldstreamlinethefulfillmentofcitizens’basicneeds,such
asaccesstoelectricity.Heightenedefficiencyacrosskeysectorssupportsenvironmental
objectivesbyincreasingaccesstorenewableenergyandpublictransportation.Thelengthy
paceofpermittingamountstoamissedopportunityfortheUnitedStatestopower38millionto54millionhouseholdsandreduceannualcarbondioxideemissionsequaltotheamountemittedby17millionto26milliongas-poweredvehicles,6to9percentofthetotalnumberofregisteredvehiclesintheUnitedStatesin2025.Inaddition,approximately2percentofallUSpublictransitjourneysaretiedupinpermitting.
Thesecostsandimpactsrepresentonlythosethatwecouldquantify.Othercostsareless
knowablebutarealmostcertainlypresent.Forexample,thedesiretoavoidlongerpermitting
reviewsmayincentivizesuboptimalprojectdesigns,suchasavoidingfederalland,thatminimizepermitexposure.Fearoflitigationoftenleadsto“litigationproofing,”whichcancauseagenciestosignificantlyexceedrecommendedEISpagelengths,durations,orboth,expendingmore
resourcesinanefforttopreemptlawsuitsandprolongingtheprelitigationperiodofthereviewprocess.
10
Furthermore,theUnitedStatescouldbelosingoutonprivatecapitalfrominvestorswhodeemtheriskandunpredictabilityoflengthytimelinesastoohigh.
Finally,thepermittingprocessisfeltsociallyandenvironmentally,asth
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2026年健康管理师三级理论重点难点试题
- 2026年江苏省建筑施工企业专职安全员C1机械类考试题库含答案参考27
- 2026年美甲师(五级)(理论知识)试题及答案
- 2026年内科医师定期考核试题库150道附参考答案(黄金题型)
- 2026年农村文化礼堂管理题含答案
- 2026年全国大学生英语竞赛真题及答案
- 2026年人工智能基础知识详解与真题解析
- 2026年人工智能训练师三级技能培训题库
- 10 蟋蟀的住宅 课件 2026-2027学年统编版语文四年级上册
- 2026年校招:质量管理QA试题及答案
- (知识清单)-2026-2027学年五年级上册科学教科版
- 2026年云南省考面试真题及答案解析
- 李白《山中问答》课件
- 《地球的公转》地理授课课件
- 【完整版】铁路站场路基工程施工组织设计
- 雨课堂学堂在线学堂云《中国电影经典影片鉴赏(北京师范大学)》单元测试考核答案
- 彩钢瓦屋面施工应急方案
- 数独8宫格游戏(初级难度)题目100道
- 舞台灯光音箱施工方案
- 鹅圆环病毒感染
- 2025年内蒙古自治区中考物理试卷真题(含答案)
评论
0/150
提交评论