1、1ST IC4 RECYCLE COLUMN SYSTEM SHUTDOWN TO T&INOTE: This is for Training only, and is not intended to be used as a step by step procedure.PO/MTBE1st IC4 Recycle Column System Shutdown To T&IPurposeA shutdown to T&I of the 1st IC4 Recycle Column 01C0114 System is when the column feed has stopped, the
2、steam to the reboiler is stopped, all levels are pumped down to less than 10%, and all pumps are shut down. All valves to and from the system are to be manually closed. A shutdown to T&I is done prior to 1st IC4 Recycle Column 01C0114 System clearing and safing process.ConditionsThe 1st IC4 Recycle
3、Column 01C0114 is shutdown. Maintenance is required on the 1st IC4 Recycle Column 01C0114 System.NOTE: This is for Training only, and is not intended to be used as a step by step procedure.PO/MTBEGUIDELINE Ensure that Peroxidation Reactors have been shut down. Ensure forward flow from the reactors h
4、as stopped. Close reactor weir valves to 1st Isobutane Column. Ensure that the TBHP Concentration Column is feeding the TBHP Tank. Close FV-11403 on Recycle/Make-up line Ensure the valve on recirculation line upstream of FV-11403 is closed. Clear the recirculation line of liquid. Close the S0.6 stea
5、m to reboiler. De-inventory condensate from condensate system. Shut down condensate pump. Continue to reflux column on overhead reflux to cool column. If column sufficiently cooled, deinventory reflux drum to Purified Isobutane Storage Sphere through PV-11407. Discontinue reflux and shut down reflux
6、 pump when reflux drum has been deinventoried. Close reflux flow control valve to 1st IC4 Recycle Column. Using system pressure deinventory column and reboiler to 2nd IC4 Recycle Column. Close FV-11418 using FC-11418 when flow falls to zero. Block in valve downstream of FV-11418 on feed line to 2nd
7、IC4 Recycle Column. Close and block in temperature control valves on condensate return header. Open condensate pump drains and drain condensate to grade. Close pressure control valve on the purge stream from Peroxidation Purge Condensate Collection Drum to 1st Isobutane Recycle Column Condenser. Dei
8、nventory and close level control valve on process water to Degassing Drum Block in valves downstream level control valve on process water from Reflux Drum. Block in valve downstream FV-11407 on stream to Isobutane Feed Drum. Block in valve downstream FV-11406 on Reflux line. Close and block in level
9、 control valve on the Propylene Refrigerant to 1st Vent Condenser. Close and block in level control valve on the Propylene Refrigerant to 2nd Vent Condenser. Block in valve upstream LV-11460 on Propylene Refrigerant to 1st Vent Condenser. Deinventory level in Recycle Vent Condensate Drum to Purified
10、 Isobutane Storage tank and when flow falls to zero. Shut down 1st Isobutane Column Vent Condenser pumps. Block in valve downstream of LV-11468 on isobutane to 1st IC4 Recycle Column Drum Reflux 01D0116. Close and block in flow control valve on N20 nitrogen to overhead line of Reflux Drum. Block in N20 nitrogen to instrument purges. Isolate
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- GB/T 48132.9-2026绿色矿山建设规范第9部分:水泥用灰岩矿山
- 报表系统课程设计片
- Nodejs在线投票教程总结课程设计
- 产品运营课程设计
- 成人口才培训课程设计
- 送料装置定制设计课程设计
- 模拟退火优化车间调度方法详解课程设计
- 城堡线条创意课程设计
- 采血化验课程设计
- Snort数据加密设计课程设计
- 2025年澳洲amc9年级竞赛题库及答案
- 2025-2026学年统编版语文二年级上册第一单元早读课件
- 钢丝绳安全使用培训课件
- 六堡茶课件教学课件
- 挡墙重点难点施工方案
- 电工电焊工安全培训课件
- 2025年贵州省初、中级专业技术资格考试(给排水)历年参考题库含答案详解(5卷)
- 2025年秋季小学六年级上册语文教学计划及教学进度表
- 测绘服务质量保障措施及方案
- 反走私宣传课件教案
- 手术室的时间管理
评论
0/150
提交评论