1、Spatial scheduling for large assembly blocks in shipbuildingAbstract: This paper addresses the spatial scheduling problem (SPP) for large assembly blocks, which arises in a shipyard assembly shop. The spatial scheduling problem is to schedule a set of jobs, of which each requires its physical space

2、in a restricted space. This problem is complicated because both the scheduling of assemblies with different due dates and earliest starting times and the spatial allocation of blocks with different sizes and loads must be considered simultaneously. This problem under consideration aims to the minimi

3、zation of both the makespan and the load balance and includes various real-world constraints, which includes the possible directional rotation of blocks, the existence of symmetric blocks, and the assignment of some blocks to designated workplaces or work teams. The problem is formulated as a mixed

4、integer programming (MIP) model and solved by a commercially available solver. A two-stage heuristic algorithm has been developed to use dispatching priority rules and a diagonal fill space allocation method, which is a modification of bottom-left-fill space allocation method. The comparison and com

5、putational results shows the proposed MIP model accommodates various constraints and the proposed heuristic algorithm solves the spatial scheduling problems effectively and efficiently.Keywords: Large assembly block; Spatial scheduling; Load balancing; Makespan; Shipbuilding1. IntroductionShipbuildi

6、ng is a complex production process characterized by heavy and large parts, various equipment, skilled professionals, prolonged lead time, and heterogeneous resource requirements. The shipbuilding process is divided into sub processes in the shipyard, including ship design, cutting and bending operat

7、ions, block assembly, outfitting, painting, pre-erection and erection. The assembly blocks are called the minor assembly block, the sub assembly block, and the large assembly block according to their size and progresses in the course of assembly processes. This paper focuses on the spatial schedulin

8、g problem of large assembly blocks in assembly shops. Fig. 1 shows a snapshot of large assembly blocks in a shipyard assembly shop.Recently, the researchers and practitioners at academia and shipbuilding industries recently got together at “Smart Production Technology Forum in Shipbuilding and Ocean

9、 Plant Industries” to recognize that there are various spatial scheduling problems in every aspect of shipbuilding due to the limited space, facilities, equipment, labor and time. The SPPs occur in various working areas such as cutting and blast shops, assembly shops, outfitting shops, pre-erection

10、yard, and dry docks. The SPP at different areas has different requirements and constraints to characterize the unique SPPs. In addition, the depletion of energy resources on land put more emphasis on the ocean development. The shipbuilding industries face the transition of focus from the traditional

11、 shipbuilding to ocean plant manufacturing. Therefore, the diversity of assembly blocks, materials, facilities and operations in ship yards increases rapidly.There are some solution providers such as Siemens and Dassult Systems to provide integrated software including product life management, enterp

12、rise resource planning system, simulation and etc. They indicated the needs of efficient algorithms to solve medium- to large-sized SPP problems in 20min, so that the shop can quickly re-optimize the production plan upon the frequent and unexpected changes in shop floors with the ongoing operations

13、on exiting blocks intact.There are many different applications which require efficient scheduling algorithms with various constraints and characteristics (Kim and Moon, 2003, Kim et al., 2013, Nguyen and Yun, 2014andYan et al., 2014). However, the spatial scheduling problem which considers spatial l

14、ayout and dynamic job scheduling has not been studied extensively. Until now, spatial scheduling has to be carried out by human schedulers only with their experiences and historical data. Even when human experts have much experience in spatial scheduling, it takes a long time and intensive effort to

15、 produce a satisfactory schedule, due to the complexity of considering blocks geometric shapes, loads, required facilities, etc. In practice, spatial scheduling for more than a six-month period is beyond the human schedulers capacity. Moreover, the space in the working areas tends to be the most cri

16、tical resource in shipbuilding. Therefore, the effective management of spatial resources through automation of the spatial scheduling process is a critical issue in the improvement of productivity in shipbuilding plants.A shipyard assembly shop is consisted of pinned workplaces, equipment, and overh

17、ang cranes. Due to the heavy weight of large assembly block, overhang cranes are used to access any areas over other objects without any hindrance in the assembly shop. The height of cranes can limit the height of blocks that can be assembled in the shop. The shop can be considered as a two-dimensio

18、nal space. The blocks are placed on precisely pinned workplaces.Once the block is allocated to a certain area in a workplace, it is desirable not to move the block again to different locations due to the size and weight of the large assembly blocks. Therefore, it is important to allocate the workspa

19、ce to each block carefully, so that the workspace in an assembly shop can be utilized in a most efficient way. In addition, since each block has its due date which is pre-determined at the stage of ship design, the tardiness of a block assembly can lead to severe delay in the following operations. T

20、herefore, in the spatial scheduling problem for large assembly blocks, the scheduling of assembly processes for blocks and the allocation of blocks to specific locations in workplaces must be considered at the same time. As the terminology suggests, spatial scheduling pursues the optimal spatial lay

21、out and the dynamic schedule which can also satisfy traditional scheduling constraints simultaneously. In addition, there are many constraints or requirements which are serious concerns on shop floors and these complicate the SPP. The constraints or requirements this study considered are explained h

22、ere: (1) Blocks can be put in either directions, horizontal or vertical. (2) Since the ship is symmetric around the centerline, there exist symmetric blocks. These symmetric blocks are required to be put next to each other on the same workplace. (3) Some blocks are required to be put on a certain sp

23、ecial area of the workplace, because the work teams on that area has special equipment or skills to achieve a certain level of quality or complete the necessary tasks. (4) Frequently, the production plan may not be implemented as planned, so that frequent modifications in production plans are requir

24、ed to cope with the changes in the shop. At these modifications, it is required to produce a new modified production plan which does not remove or move the pre-existing blocks in the workplace to complete the ongoing operations. (5) If possible at any time, the load balancing over the work teams, i.

25、e., workplaces are desirable in order to keep all task assignments to work teams fair and uniform.Lee, Lee, and Choi (1996) studied a spatial scheduling that considers not only traditional scheduling constraints like resource capacity and due dates, but also dynamic spatial layout of the objects. Th

26、ey used two-dimensional arrangement algorithm developed by Lozano-Perez (1983) to determine the spatial layout of blocks in shipbuilding. Koh, Park, Choi, and Joo (1999) developed a block assembly scheduling system for a shipbuilding company. They proposed a two-phase approach that includes a schedu

27、ling phase and a spatial layout phase. Koh, Eom, and Jang (2008) extended their precious works (Koh et al., 1999) by proposing the largest contact area policy to select a better allocation of blocks. Cho, Chung, Park, Park, and Kim (2001) proposed a spatial scheduling system for block painting proce

28、ss in shipbuilding, including block scheduling, four arrangement algorithms and block assignment algorithm. Park et al. (2002) extended Cho et al. (2001) utilizing strategy simulation in two consecutive operations of blasting and painting. Shin, Kwon, and Ryu (2008) proposed a bottom-left-fill heuri

29、stic method for spatial planning of block assemblies and suggested a placement algorithm for blocks by differential evolution arrangement algorithm. Liu, Chua, and Wee (2011) proposed a simulation model which enabled multiple priority rules to be compared. Zheng, Jiang, and Chen (2012) proposed a ma

30、thematical programming model for spatial scheduling and used several heuristic spatial scheduling strategies (grid searching and genetic algorithm). Zhang and Chen (2012) proposed another mathematical programming model and proposed the agglomeration algorithm.This study presents a novel mixed intege

31、r programming (MIP) formulation to consider block rotations, symmetrical blocks, pre-existing blocks, load balancing and allocation of certain blocks to pre-determined workspace. The proposed MIP models were implemented by commercially available software, LINGO and problems of various sizes are test

32、ed. The computational results show that the MIP model is extremely difficult to solve as the size of problems grows. To efficiently solve the problem, a two-stage heuristic algorithm has been proposed.Section 2 describes spatial scheduling problems and assumptions which are used in this study. Secti

33、on 3 presents a mixed integer programming formulation. In Section 4, a two-stage heuristic algorithm has been proposed, including block dispatching priority rules and a diagonal fill space allocation heuristic method, which is modified from the bottom-left-fill space allocation method. Computational

34、 results are provided in Section 5. The conclusions are given in Section 6.2. Problem descriptionsThe ship design decides how to divide the ship into many smaller pieces. The metal sheets are cut, blast, bend and weld to build small blocks. These small blocks are assembled to bigger assembly blocks.

35、 During this shipbuilding process, all blocks have their earliest starting times which are determined from the previous operational step and due dates which are required by the next operational step. At each step, the blocks have their own shapes of various sizes and handling requirements. During th

36、e assembly, no block can overlap physically with others or overhang the boundary of workplace.The spatial scheduling problem can be defined as a problem to determine the optimal schedule of a given set of blocks and the layout of workplaces by designating the blocks workplace simultaneously. As the

37、term implies, spatial scheduling pursues the optimal dynamic spatial layout schedule which can also satisfy traditional scheduling constraints. Dynamic spatial layout schedule can be including the spatial allocation issue, temporal allocation issue and resource allocation issue.An example of spatial

38、 scheduling is given in Fig. 2. There are 4 blocks to be allocated and scheduled in a rectangular workplace. Each block is shaded in different patterns. Fig. 2 shows the 6-day spatial schedule of four large blocks on a given workplace. Blocks 1 and 2 are pre-existed or allocated at day 1. The earlie

39、st starting times of blocks 3 and 4 are days 2 and 4, respectively. The processing times of blocks 1, 2 and 3 are 4, 2 and 4days, respectively.The spatial schedule must satisfy the time and space constraints at the same time. There are many objectives in spatial scheduling, including the minimizatio

40、n of makespan, the minimum tardiness, the maximum utilization of spatial and non-spatial resources and etc. The objective in this study is to minimize the makespan and balance the workload over the workspaces.There are many constraints for spatial scheduling problems in shipbuilding, depending on th

41、e types of ships built, the operational strategies of the shop, organizational restrictions and etc. Some basic constraints are given as follows; (1) all blocks must be allocated on given workplaces for assembly processes and must not overstep the boundary of the workplace; (2) any block cannot over

42、lap with other blocks; (3) all blocks have their own earliest starting time and due dates; (4) symmetrical blocks needs to be placed side-by-side in the same workspace. Fig. 3 shows how symmetrical blocks need to be assigned; (5) some blocks need to be placed in the designated workspace; (6) there c

43、an be existing blocks before the planning horizon; (7) workloads for workplaces needs to be balanced as much as possible.In addition to the constraints described above, the following assumptions are made.(1) The shape of blocks and workplaces is rectangular.(2 )Once a block is placed in a workplace,

44、 it cannot be moved or removed from its location until the process is completed.(3 ) Blocks can be rotated at angles of 0 and 90 (see Fig. 4).(4) The symmetric blocks have the same sizes, are rotated at the same angle and should be placed side-by-side on the same workplace.(5) The non-spatial resour

45、ces (such as personnel or equipment) are adequate.3. A mixed integer programming modelA MIP model is formulated and given in this section. The objective function is to minimize makespan and the sum of deviation from average workload per workplace, considering the block rotation, the symmetrical bloc

46、ks, pre-existing blocks, load balancing and the allocation of certain blocks to pre-determined workspace.A workspace with the length LENW and the width WIDW is considered two-dimensional rectangular space. Since the rectangular shapes for the blocks have been assumed, a block can be placed on worksp

47、ace by determining (x, y) coordinates, where 0xLENW and 0yWIDW. Hence, the dynamic layout of blocks on workplaces is similar to two-dimensional bin packing problem. In addition to the block allocation, the optimal schedule needs to be considered at the same time in spatial scheduling problems. Z axi

48、s is introduced to describe the time dimension. Then, spatial scheduling problem becomes a three-dimensional bin packing problem with various objectives and constraints.The decision variables of spatial scheduling problem are (x, y, z) coordinates of all blocks within a three-dimensional space whose

49、 sizes are LENW, WIDW and T in x, y and z axes, where T represents the planning horizon. This space is illustrated in Fig. 5.In Fig. 6, the spatial scheduling of two blocks into a workplace is illustrated as an example. The parameters p1 and p2 indicate the processing times for Blocks 1 and 2, respe

50、ctively. As shown in z axis, Block 2 is scheduled after Block 1 is completed.4. A two-stage heuristic algorithmThe computational experiments for the MIP model in Section 3 have been conducted using a commercially available solver, LINGO. Obtaining global optimum solutions is very time consuming, con

51、sidering the number of variables and constraints. A ship is consisted of more than 8 hundred large blocks and the size of problem using MIP model is beyond todays computational ability. A two-stage heuristic algorithm has been proposed using the dispatching priority rules and a diagonal fill method.

52、4.1. Stage 1: Load balancing and sequencingPast research on spatial scheduling problems considers various priority rules. Lee et al. (1996) used a priority rule for the minimum slack time of blocks. Cho et al. (2001) and Park et al. (2002) used the earliest due date. Shin et al. (2008) considered th

53、ree dispatching priority rules for start date, finish date and geometric characteristics (length, breadth, and area) of blocks. Liu and Teng (1999) compared 9 different dispatching priority rules including first-come first-serve, shortest processing time, least slack, earliest due date, critical rat

54、io, most waiting time multiplied by tonnage, minimal area residue, and random job selection. Zheng et al. (2012) used a dispatching rule of longest processing time and earliest start time.Two priority rules are used in this study to divide all blocks into groups for load balancing and to sequence th

55、em considering the due date and earliest starting time. Two priority rules are streamlined to load-balance and sequence the blocks into an algorithm which is illustrated in Fig. 7. The first step of the algorithm in this stage is to group the blocks based on the urgency priority. The urgency priorit

56、y is calculated by subtracting the earliest starting time and the processing time from the due date for each block. The smaller the urgency priority, the more urgent the block needs to bed scheduled. Then all blocks are grouped into an appropriate number of groups for a reasonable number of levels i

57、n urgency priorities. Let g be this discretionary number of groups. There are g groups of blocks based on the urgency of blocks. The number of blocks in each group does not need to be identical.Blocks in each group are re-ordered grouped into as many subgroups as workplaces, considering the workload

58、 of blocks such as the weight or welding length. The blocks in each subgroup have the similar urgency and workloads. Then, these blocks in each subgroup are ordered in an ascending order of the earliest starting time. This ordering will be used to block allocations in sequence. The subgroup correspo

59、nds to the workplace.If block i must be processed at workplace w and is currently allocated to other workplace or subgroup than w, block i is swapped with a block at the same position of block i in an ascending order of the earliest starting time at its workplace (or subgroup). Since the symmetric blocks must be located on a same workplace, a similar swapping method can be used. One of symmetric blocks which are allocated into different workplace (or subgroups) needs to be

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论