1、Construction method statement for Steel Structure cleaning up and touch up 钢结构清理及补漆施工措施方法A. Description工作描述This method statement is prepared for cleaning up the dust、scrap iron and rust iron remained on steel structure during transport before.此方案主要是针对前期运输(海运)过程中残留在钢结构上的灰尘、铁屑、铁锈等的清理工作制定的。B. Manpower人
2、员计划The following is for one group and can be adjusted by adding manpower according to actual site condition when constructing.Painter 4, mainly responsible for steel structure cleaning and painting .Watcher 1, for preventing unauthorized people from entering.以下人员为一个班组人员配置,施工时可以根据现场实际情况适当增加施工人员及施工班组。
3、油漆工4人,主要负责钢结构清理及涂漆刷漆。现场监护1人,主要监护非施工人员禁止进入。C. Preparation施工准备1. To verify with each discipline if there are still constrution personnel enter into the area to be cleaned and the platform below it, to avoid working at the same time.向各个专业确认即将清理的区域及清理区域的下一层平台是否还有施工人员进入,尽量避免交叉作业。2. Material: primer and t
4、op coat for steel structure, disc, nail.材料准备:配备钢结构底漆及面漆、圆盘、尖头钉。3. Tools: scissor lifts,100 grinding machine, planning wheel, blower, roller(used by painter), inside grinding machine, inside grinding head, rag, safety belt.工机具准备:剪刀式升降机、100磨光机、刨光轮、压缩机、滚刷(油漆工专用)、内磨机、破布、安全带。D. Construction area definati
5、on and construction sequence 施工区域划分及施工顺序Principle for construction area: from up to down, from outside to inside, locally enclosed, locally cleaning. According to the actual condition and construction personnel quantity on site, steel structure in different area can be cleaned at the same time, prec
6、ondition is to avoid working at the same time. Reasonable adjustment can be made to the area to be cleaned when constructing according to the actual condition on site.施工区域遵循从上至下,从边向内,局部封闭,局部清理的原则,根据现场实际情况及施工人员数量,可以同时对不同区域的钢结构进行清理,前提是尽量避免交叉作业,具体施工时可以根据现场实际情况对清理区域临时做出合理的调整。E. Construction method 施工方法
7、1. Using100 grinding machine to clear the debris on structure (whole structure, including flange plate and web).用100磨光机对结构进行清理,清除结构上的杂物,清理时必须对结构整体进行清理(包括翼缘板及腹板)。2. After grinding, use blower to blow the dust on steel beam and wipe by dry rag.打磨完成后,用压缩机对钢梁上的灰尘吹扫并用干布擦拭。3. After blowing, painters do to
8、uch up (Reference Photos) for steel beam. If no primer for the beam, primer must be done at first, then do top coat after the primer is dry.吹扫完成后油漆工对钢梁进行涂漆,如果钢梁缺少底漆,必须先补底漆,底漆干燥后方可涂刷面漆。4. During applying paint, if some place the roller can not reach, the handle of the roller can be extended, the exte
9、nded point must be strong enough and the extended handle can not wobble to much. If the height of the steel structure is too high, even if the use of the extended handle cannot achieve, we can consider to use scissor lifts already ready. Homework in the scissor lifts, the painters must wear safety b
10、elts, safety belts must be high up the painter, ensure the personal safety.油漆工施工时如果有滚刷无法伸到刷漆位置,可以对滚刷手柄加长,加长处必须有足够的强度,加长手柄不可以晃动幅度太大。如果钢结构的高度太高,即使使用加长手柄也无法达到的话,我们就可以考虑使用早就已经准备好的剪刀式升降机。在升降机上作业时,油漆工必须要佩戴安全带,安全带一定要做到高挂抵用,保证作业人员的安全。 E. Safety precaution安全注意事项1. Hand strings must be used for all tools and
11、make sure hand string is tie on hand or on secured object when using tools. 所有使用工机具必须系好手绳并且保证使用工具时手绳固定在手上或者已固定的物体上。2. Mask must be worn when using planing wheel, the same with the watcher, to avoid the spreading iron thread from the planing wheel hurting people. 使用刨光轮时必须佩戴面罩,旁边监护人员也必须佩戴面罩,防止刨光轮铁丝飞溅伤人。3. Watcher for barricade must make sure no unauthorized personnel entering.维护旁的监护人员必须保证无关人员不可以进入。4. Sign easy to be seen on barricade.维护上要有醒目的标识牌。5. All temporary unused tools must be kept in the tool basket or on the fire blanket.所有暂时不使用的
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 森林康养基地植物配置设计方案
- 森林康养基地健康促进项目方案
- 精益生产实施路径方案
- 防火分隔施工方案
- 2026年河南推拿职学院招聘人事代理工作人员4名备考题库含答案详解(考试直接用)
- 2026山东济宁市东方圣地人力资源开发有限公司招聘辅助服务人员1人备考题库附答案详解(综合题)
- 2026贵州黔东南州施秉仁康医院招聘备考题库附答案详解(能力提升)
- 2026陕西汉中职业技术学院及附属医院招聘高层次及急需紧缺专业人才31人备考题库附答案详解(达标题)
- 2026浙江温州市洞头人才发展有限公司招聘3人备考题库(食堂人员)含答案详解(研优卷)
- 2026中华书局大众图书出版中心招聘营销编辑1人备考题库附答案详解(综合题)
- 江苏省常熟市重点名校2026届中考数学全真模拟试卷含解析
- 新高考教学教研联盟(长郡二十校)2026届高三年级4月第二次联考英语试卷(含答案详解)
- 聘任委员会工作制度
- 浙江省杭州二中2025学年第二学期高三年级三月月考语文+答案
- 2026年3月山东济南轨道交通集团运营有限公司社会招聘备考题库附完整答案详解(考点梳理)
- 山东省潍坊市寿光市、安丘市2026届中考适应性考试数学试题含解析
- 2026年现代医疗背景下手术室护理技术的挑战与机遇
- 2026年黑龙江齐齐哈尔高三一模高考生物试卷试题(含答案详解)
- 新能源汽车充电桩线路故障排查手册
- 兽药药品陈列管理制度
- 专题 功和功率、动能定理(解析版)
评论
0/150
提交评论