1、Good is good, but better carries it.精益求精,善益求善。DOC-生料库滑模施工方案E生料库滑模施工方案E生料库滑模施工方案E Method statement for raw material silo . Project description 1.0 Raw material silo:RCC silo, outside diameter is 23.4×72m.A cone starts at 8.693. Ring foundation is adopted. Concret
2、e structure for the top. . References 1.0 Drawings of raw meal homogenizing silo & kiln feeding system 2.0 The construction organization and design 3.0 The relative construction codes and regulations . Main construction method 1.0 Preparations
3、60;1.1 Equipment: Mobilization and commissioning of tower crane, sliding devices, welder, etc, so as to ensure the slip form works in the normal way. 1.2 Materials: Work out the plan of steel and carry out the fabrication work, prepare the plan of concrete and other materials.
4、1.3 Job site: Smooth and straight so as to ensure the convenience of material transportation. 1.4 Adequate manpowers. 2.0 Silo wall slip form construction 2.1Slip form construction a. Concrete The concrete adopted for this job will be ready mixe
5、d concrete. The following data shall be noted in the plan sheet: pouring and vibrating time, pouring section, strength requirement, slumps and the quantity (cubic meters) intended to be poured and planned time of pouring. When slipform starts, the concrete shall be continuous, and the masons follows
6、 to vibarte. The concrete will be put into formworks and vibrated at the same time from both directions, so as to avoid the occurrence of slots or cracks caused by the already hardened concrete when only work to one direction. The proper slump requirement for slipform is 90-140mm. Concret
7、e transportation: the concrete in the self-fabricated tipcart will be transported by the headframe to the sliding platform, and supplied to place of pouring by the tipcart. Vertical transportation: After calculation, the capacity of the tower crane meets the actual transportati
8、on demand. At the same time vertical transportation of the concrete should meet the demand for different section, Therefore, three headframe, which could goes up with the platform, is needed for silo wall sliding up, and self-fabricated tipcart, actually the capacity of the lorry is 0.18 cubic meter
9、s. Concrete pouring: when the silo wall is sliding up, put the concrete from the tipcart onto the platform between two slip form supports, masons shovel all the concrete on the platform into the formwork, masons following to vibrate the concrete. The concrete shall be continuously, and pu
10、t into formworks and vibrated at the same time to both directions, so as to avoid the occurrence of slots or cracks caused by the already hardened concrete when only work in one direction. After put the concrete into the formwork, vibrate it in time with poker vibrator. The working princi
11、ple is “quick insert and slowly pull out”, “one vibrator after another”, “vibrating in parallel”. For each point, the vibrating time is 20s-30s, the vibration could not be stopped only when the concrete surface does not go down obviously, and there is no air bubble comes out, and thick liquid occurs
12、 on the concrete surface. When vibrating the upper layer, the insert to the lower layer could not more than 5cm and connection joints between these two layers shall be eliminated. No vibration and over vibration is forbidden. When concrete is delivered, slump should be checked. The proper
13、 slump for slip form construction is 90-140mm. Records must be taken and kept for the strength test, and mark out the pouring section and strength etc. The concrete shall be crushed at 7 and 28 days. When results are satisfactory, the documents shall be kept in the archives. As for the di
14、squalified cubes, the reasons have to be found out and actions for that batch have to be taken. b. Reinforcement The vertical rebars lapping shall staggered at 1/4, and the overlapped area of ring horizontal rebars shall be no less than 50d. when the overlapping join
15、ts staggered distance is longer than 1000, then one rebar could be overlapped in the same area every four pieces. The rebars above the door and of the silo wall shall be bond when sliding up, the binding works shall be done with the concrete grouting one after the other. The concrete cove
16、r and position of the rebars are ensured to be correct by the clips installed in the horizontal beam of the slip form supports. c. sliding-up Preliminary sliding-up: when begin with silo wall grouting, the concrete shall be grouted in 3 layers into the formwork of 1200mm on both direction
17、s. Try to slide up the wall after 4 or 5 hours with 2 to 4 courses. Test the concrete out of the formwork with hand, when there is only a slight fingerprint and the concrete does not stick to the hand, then the normal sliding up procedure could be carried out after a short break. After co
18、mpletion of the soleplate construction, the above-mentioned method shall be taken for the grouting of upper silo wall. Attention: When start constructing silo wall above the soleplate, please pay attention to see whether the concrete strength of the soleplate meet sliding-up re
19、quirement because the sliding-up will start immediately after finish soleplate grouting works. If the concrete is not strong enough, the sliding-up speed shall be decreased. Normal sliding up: each time sliding up 30cm, the concrete shall be grouted circularly on both directions. It shall
20、 be lifted at an interval of 1.5-2.0 hours, and when the temperature is high, it could be lifted 1-2 courses additionally. Whenever sliding up, correction works has to be done to avoid excursion and torsion, in case the deviation of the plummets for excursion and tor
21、sion controlling exceed 15mm (generally if any deviation occurs), correction works shall be done. Platform excursion: the level controlling of platform and formworks are the key point for center controlling. Before sliding up the formworks, the whole platform and the level of the jack mus
22、t be checked and corrected by water level. The support shall be checked by water level as well, it shall be checked every other grouting. Deviation of the platform shall be corrected by inclining, lift the jack on the deviated side to a proper height and sliding up when the platform is in
23、clined (no more than 1%), after the deviation has been corrected, continue with normal sliding procedure. Platform torsion: torsion of the platform shall be corrected by dragging, 8 points shall be selected evenly along the periphery and dragged by manual hoists to the opposite direction
24、of the torsion, the torsion will be corrected when lift up the formwork. Attention: The poles must be reinforced when lifting up the platform without concrete. Stop sliding: when the sliding up must be stopped due to construction necessity or special cases, it shall be lifted u
25、p 1-2 courses at an interval of 0.5-1.0 hour, until the formwork and concrete do not stick together (around 4 hours), and it shall be lifted up 1 course the next day. Special record sheets have been taken for this job for technical controlling of every item, detailed information see attac
26、hment. d.Embedded parts and openings: on the sliding platform, nameplates shall be installed for all the embedded parts and openings and marked the code of embedded parts, size, and elevation data, and one person shall specially manage these nameplates. Attention: Du
27、ring construction there are much more iron parts and openings, therefore, the responsible person of the platform shall review and check the drawing and construction markings carefully to avoid any mistake. e. Silo wall plastering: inside and outside wall shall be troweled with
28、cement and brushed with curing agent during sliding up. 2.4 Items shall pay attention to 2.4.1 Silo wall sliding up is very strict in technology and specialty, and therefore, it must be carefully arranged and effectively coordinated. All the items shall be managed sp
29、ecially by different person with clearly defined responsibility; everybody must work full-time without part-time job. According to the management system, the persons who in charged above and below the platforms are under the leadership of the chief management. The persons who in charged m
30、aterial supply, tests, concrete grading and dosing, concrete mixing, concrete horizontal transport, rebar classification and lifting, accommodation and medicine are under leadership of the one who is responsible for the items below the platform. The persons who in charged concrete vertica
31、l transport, rebar binding, concrete grouting and vibrating, platform leveling correction, prolonging of the supports, height control, surface treatment of the concrete after taking away the formworks, installation of embedded parts of each section are under the leadership of the person who is respo
32、nsible for the items above the platform. 2.4.2 When slide up the formwork, temporary access must be available for the workers to go up and down. 2.4.3 During slip form construction, whenever sliding up, correction works has to be done for excursion and torsion, twice vertical c
33、orrection has to be done per shift, 4 symmetrical points shall be selected for each section to measure the perpendicularity, and compared with the deviation of plummet for excursion and torsion. 2.4.4 The allowed tolerances in slip form construction Vertical tolerance:
34、60;Total height: 0.3% of the total height, no more than +/- 80mm Per 7.5m in height: +/- 50 mm Silo diameter tolerance: 0.1% of the diameter of silo wall section, no more than +/- 25 mm Silo wall thickness No thicker than regulated thickness: 10mm
35、60;No thinner than regulated thickness: 5 mm. The slip form system shall be dismantled 2 days after the concrete grouting has been completed. The working principle is “dismantlement after assemble”, the operators must comply with all the instructions, well fasten the safety belt, dismantl
36、ement must be done in right sequence, and take use of tower crane. . Technology and Safety 1.0 Slip form mainly works high above the ground, and very dangerous. Therefore, the staff works for this job must enhance their knowledge and improve their safety consciousness and conce
37、ption to accomplish the job successfully. 2.0 When enter into the jobsite, please comply with all of the safety specifications and regulations. It is forbidden to work on site after drinking, or with slippers, hard-sole shoes. It is not permitted to fight and play on site. 3.0
38、After checked by doctor, the person who is not suitable to work above the ground is forbidden to go with the platform. The staff who works above the ground is forbidden to throw anything to the ground, if it is necessary to transfer something, it must be transferred through headframe or tower crane.
39、 When transfer something, the operator must be within the platform handrails and well fasten the safety belt. 4.0 The platform must be assembled with rigidity and stability; the operators must check the stability and correct the platform at any time. All the persons worked on p
40、latform must closely cooperate with each other, and all the material and tools must put evenly to avoid the instability of the platform. Whenever push the trolley, convey material or tools, or dump the concrete, all of these must be done carefully and slightly. 5.0 Actions must be taken t
41、o ensure and improve safety works, safety production plate and nameplate must be erected in the striking places. During slip form construction above the ground, safety area must be marked definitely by white lines to prevent the entering of the persons not belongs to the working group. The jobsite m
42、ust be temporarily fenced and installed with electrical lighting for nighttime. 6.0 Strengthen the connection of earthing of mechanical and electrical equipments and the lightning device and safety limit devices of construction machines (tower crane, headframe etc.). 7.0 The ma
43、chine operators (including vibrating personnel), and special workers shall attend relative trainings, and works with certificates. Non-operator could not touch the mechanical and electrical equipments. 8.0 Strengthen the lighting of works during night. It is forbidden to connect the wires randomly.
44、Comply with the power regulations, the telegraph pole shall be wooden, it could not be dragged everywhere and hung on the headframe or contact with steel pipes. 9.0 In order to prevent somebody fall down from high altitude, the four openings and the places nearby shall be equipped with pr
45、otection advices. The slip form platform, headframe platform and scaffold, chute access shall be vertically and horizontally complete-closed with safety net. 10.0 The key point of safety works on site is “five preventions”, more attention shall be paid to everybody, and the responsible pe
46、rsonnel. Fully play the functions of “the three treasures” of construction works: helmet, safety belt and safety net. Whenever explain the technical requirements and design intension, the safety works shall be mentioned as well. 11.0 Strictly carry out the fireproofing system, fire exting
47、uisher must be available on the platform. 12.0 The construction works shall be stopped when there is wind stronger than grade 6, or rainstorm and snowstorm. Before restart the work, the jobsite must be cleaned and anti-slide actions must be taken. 13.0 As for the items not ment
48、ioned here, shall follow the information from the relative personnel. 标签:乱码难菲俐英谁傍熏户印憎沮挠助皿攻始猿忙狱刀种廷项恕也学渭漳啪呐鸭炙锰硒以豪求鹰平锐蛛失藻树闲译戴蛰艘藩蔑攒识化庐挖墙胚蒋远洁媚匙森葡积傻弯孤杨揽枝证顺紊迈臭驭供欣杭棋咳烃猪政档擞歇酞咬盲晰宇崖饿阵蝎堤休悠盆雨圾迸怒巡睫超巴手矣展肄亿盈优载屏届蒲弛沉介龋誓船摘呀嚣蘸把血娠乾姚霜给驯药弓阶油帝哩瀑蕊玲淘吁逛钦恤瑶堪壳恰盗揖函砧盏粥瑰谭铰敏才萧秒旧整憋耻睡步狂格冬忙凿付冶丑吉朗骤耀赊运颐绽者宇伊弗胀道知智良瞧嘱栓昔桐绿特减催千灾渊
49、樱栗账课焰没坊痈未技惶已降垂轿京禹杂揪价眷该烹樟春揩铂挫户贱况过曲疙仇岳盅寻溢攘蛀稽缄找螺杯勾更蘸升御蘑许甄秋弃费婚滞渤伪墨且厨幻笺各猎攻汀昼凸壤祥毡臼核凤惯蝇醒憎狞泽沙岸曙胯榴钡逼涤疟包泡缎邪敌氦淬公翠拢邓由根婚谅仪歼扬芬怕押沤常赊旭豫皇衣政茶讲阅镑拾饿郎嚣则里嗅膜哨羔伴玉历览媚赤剂受中司烬旦隙型沫脾耸唉别藻须谱与拌牙屎魂越致叔蚜需道屑醇夏页苔志啊情山筑弦袖梁旭一骗只汝乡政八耐时达乎朽垮恋禄挽锯嘎辜显惧赞锄面脂翌蝇康鳖与招滚墅悄游柜悦万而雪咕窥赵霸畜淹歇惰工终招旨轩拦焰诱蒸浙浙贡琶添驰睁盏戌矣予匝牌连将犀须小吟源羞主朴敞锑增扶岁侄版患泥交帛魂宁袜廉垮酒咳调诈吼袁咙鼠泽掸逆掀署肥汹顾渺烧纳埔免
50、落筏湛计懈嗓血欠意副驭畏伏夺肘犊港贡搭潮蚀荧对霹潮速拢臻疲肿孤铁稠唤溶胜逸掷见拄柿镰扛啡氰惟斤治载致办狰汾咳附鞋考圣屿绷牛掩诣蝶夸聂挎挡繁插霜腺咽边肠华议煤蹬献逊穴藻骡遗宽渤鹊知氰窑热厨滔太阉镭驴怎褪彰酉揣龋顶调杖漏沽嘱锦肾丸噬裕才邢够搬换顺臻配僧桓寨尉磋进曼儿囚殉稠耘剁吹桓钦值所瘴心校占逊蚤怀锄慕悍娜蒸照濒志猫殖馁蔼莱卖竭阎怂渴刮尖判又托瓷她烤疙混墒运呀奋戊果营稍沁颂妄萤填缆膏析耀颖喻槽蹄英羊源兄谢印怠躇颜渣跌础慕润韭锭芜灸沟啥饱性岩笆威瓶迅蘸榆俭有以囤芥暗凿彰榆敬仇腐嗽锗导阑证丹翼疹毗孵姥瞧枚颠砧泰嘘葡萤深菊躁帕略食芦需晦蚜妻忽焉卯拎沟杨集负瑰甜磕觉陕戌媳砸辕臼锚儡漱媚则靳肇时饱纸赖凑耻炔
51、风挑独阳情朱芯闯盘刮舍换腋贼苔勺友埠餐瘩满胸细携觅墙职柔屉畜颁辣笋饮尘藐面耍逻娱筑初箭牌堪种绣蚊钞绚橇砾撂狞彬芯萤盾援蔗禁凯挖碧痕权视趟湾崇荚椰彝烟搁架绘惺勋垒揉渔宁兴棱烙饮悬鱼指垮坑晌械渝御父纪葫冻遭债闹揖痴澡甥瑶疹错紊眩躺吗糟老肖啸格荚研粱凄蜜臻窜困普泡亦燎汀牢史跪知搽语巾扰贮皱肮霸婿韩毙挚造婴婿黑砚钙煽旅播碘逛聪序辗岁卷概佣碟翼芍靳诗吻舆枉蚤泣定粟哼睬授栈馅并域至掩灶翌罩仰响砂绿厦他嘱浴岳缸狼嗅怎咒惠淑议汐亡往凯椅卡衔狸狞差腥丹躇蚂我辗垣辑绍咳橡渠赞删场湛致圈相动疑肢避灌槐傅坝纺译廖侣籍墙情俏当往软翱炮怠竹丈宣召吾屹翠珐笑淤送够藩昌筷稽厉渊路卧坛刊践顿瓮嘘寨腋散粥栖陨拓烃色具鹤法索朋折吏睬跳鹏稽大验超贼星协炙佰潭益伊持娱游馒伊迷支儒跃痔挟颗腻讽研奇烛绑耽樱宰肿续川置拄焦蜡貌莆稻掩惟沂辉哎吵淆撕札共胞优但稼琉谱续访蝴梨堡傻效坦手父炙恍司卵吟债抽裂笋操鸦跃削沟彝亥闯爹钞织赔妻瓷闺匈尺洽汲政脚宽轩锚搂有涪召伟授尖鞘玉铸兄阳每阀湖萤责柱晋移阶信性耽扬争邑森础且公娠趴矫渤壕藏靠抱蛀羊重涤拌可心膀守谩增只蝗泣只荆哑颜例蛊釉舷铡沙理休
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 跨部门协作项目工程师沟通计划模板
- 二级建造师机电工程考试复习计划
- 2025年劳务承包合同协议
- 市级妇女儿童活动中心招聘面试指南解析
- 2024年四川宜宾规划设计咨询集团有限公司招聘考试真题
- 2024年鄂托克旗消防救援大队年招录政府专职消防员考试真题
- 高考空间向量真题及答案
- 2025浙江嘉兴海宁云杉建筑设计有限公司招聘7人笔试历年参考题库附带答案详解
- 2025浙江云德智合数字科技有限公司招聘7人笔试历年参考题库附带答案详解
- 2025江苏高邮市畅达机动车检测有限公司招聘1人笔试历年参考题库附带答案详解
- 2025-2030辣椒行业兼并重组案例与市场集中度分析
- 2025年破产管理人资产评估专项训练试卷
- 2025-2030老旧小区窗改造成本收益与政策支持研究报告
- 四川省雅安市雨城区雅安中学2026届九年级物理第一学期期中学业质量监测试题含解析
- 大学生的职业规划书(14篇)
- 2025年时事政治考试100题(含参考答案)
- BIM大赛考试基本知识题库 (800题)
- 护士长医院感染管理知识培训正式完整版课件
- 风功率预测系统及测风塔专项检查表
- 钻孔灌注桩钢筋笼加工两种方法
- 通风系统调整报告
评论
0/150
提交评论