1、- Page 1-SARAWAK ENERGY BERHAD(沙捞越能源有限公司)SIMILAJAU TO TADA 500KV TRANSMISSION LINE PROJECT (500KV BACKBONE TRANSMISSION PROJECT PHASE I) TADA SIMILAJAU 500千伏输电线工程项目任务书(500千伏主干网输电工程-第1阶段)VOLUME 1 PART C: SUMMARY OF PRICE SECTION 1: PREAMBLES第一册-PART C:总价-第1部分:前言SIMILAJAU TO TADA 500KV TRANSMISSION LI

2、NE PROJECT(500KV BACKBONE TRANSMISSION PROJECT PHASE I)TADA SIMILAJAU 500千伏输电线工程项目任务书(500千伏主干网输电工程-第1阶段) TENDER REFERENCE: PLS-110090 PART C: SUMMARY OF PRICE 招标引用的标准请参考: 110090 C部分:概算 SECTION 1 PREAMBLES 第1部分 前言1.0 INTRODUCTION (简介)The method of measurement and payment shall be in accordance with u

3、nits specified in the Bill of Quantities.测量方法和付款方式应当按照工程量表中的规定要求进行。The system of units of measurement shall be the International System of Units (SI) metric. 此工程项目的计量单位应当执行国际体系(SI)度量标准。The Summary of Price in volume 1 Part C, comprised of Preliminaries, Overhead Line Equipment and Civil Works which

4、covers the entire scope of works in the Contract, made up of 2 components of prices namely: the Lump Sum price work and Bill of Quantities work. 第1卷C部分价格概算包括初设、架空线路设备和土建工程的概算,它由2部分组成即:大包价格概算和建筑施工价格概算,其中土建工程概算的合同涵盖了整个项目工程任务。Lump Sum (LS) price work are fixed and firmed price and shall not be subject

5、to any re-measurement whereas the Bill of Quantities work shall be subjected to re-measurement according to the Conditions of the Contract. 总和最小价格都是固定而且稳定工作的价格,不受任何re-measurement而此清单工作应当受到re-measurement根据合同的条件。The Summary of Price also provided two (2) currencies price namely: USD and MYR. 摘要价格也提供了两

6、(2)货币的价格即:美元,最高产量研究。The preambles shall be applicable on each trade and service of the Bill of Quantities for any variation work instructed by the Engineer. In the event that no applicable preambles against the Bill of Quantities, the Standard Method Measurement (SMM) edition 2 shall be applicable t

7、o the Bill of Quantities. 适用的preambles每个贸易和服务的任何变化量法案所委派的工作的工程师。如果没有适用的preambles反对该法案的数量、标准方法测定(煤柱第二版适用于此清单。The Contractors attention is drawn to the fact that other contractors will be working on the Site co ncurrently with the Contractor. 承包商注意力能在这样一个事实:其他承包商在现场工作的公司ncurrently承包商。The Contractor sh

8、all make due allowance within his rates and prices for coordinating and programming the works in the order that he meets his programme requirements without unduly prejudicing or obstructing other contractors in their efforts to meet their programmes. 承包商应在他做出应有的费率和价格补贴的协调和编程的工作以便他遇见了他的计划没有过多要求损及其他承包

9、商或受到阻碍,他们在努力满足他们的节目。Pursuant to the Conditions of Contract and Instruction to Tenderers the Contractor is deemed to have visited the Site prior to the submission of Tender. No claim for extra payment will be entertained where, in the opinion of the Engineer, a Site visit would have adequately inform

10、ed the Contractor of the complexity or nature of an item of work. 根据指令的合同条件,承包人应被视为前访问网站的招投标。没有要求额外的款项将被受理哪里,认为工程师,网站访问将有充分通知承包商的复杂性与性质的一项工作。The rates and prices shall not be subjected to any increase or decrease because of:- 费率和价格的不应受到任何增加或减少,因为:-a) Any error or omission by the Contractor in estima

11、ting the cost of the work; 任何错误或遗漏时由承包人在估计成本的工作;b) Any additional compensation paid to supervisory personnel or operatives; 任何额外赔偿或特工监察人员c) Any premiums or bonus paid to secure or accelerate deliveries of materials, plant, tools or equipment. 任何溢价或奖金支付安全或加速交货的材料、机械、工具或设备。The rates and prices quoted

12、shall be considered fixed and firm for the duration of the Contract. 引用的费率和价格将被认为是固定的,公司持续的合同。Materials not supplied by the Contractor are described as Free Issue Material in Appendix 5. The Contractor will be responsible for collecting all free issue materials from the storage facilities (for Tende

13、r pricing purposes, the Contractor may assume supplier warehouse base in Kuching, Sarawak) designated by the Employer and transporting to the placement area. Mechanical lifting equipment if required shall be supplied by the Contractor. 教材不提供免费承包商被描述为在附录5分发材料。承包商将负责收集所有免费资料仓储设施问题(投标价格的目的,承包商可以假定供应商仓库

14、基地、沙唠越古晋市)指定由用人单位与输送到位置区。如果需要机械起重设备应由承包商提供。The Contractor shall supply all labour and transport and will become entirely responsible for all materials once accepted at the storage facility. 承包商应提供所有劳动、运输和将成为全面负责所有材料在存储设备一旦接受了。PLS-110090 PRE/1 - Page 2-SARAWAK ENERGY BERHAD SIMILAJAU TO TADA 500KV TR

15、ANSMISSION LINE PROJECT (500KV BACKBONE TRANSMISSION PROJECT PHASE I) VOLUME 1 PART C: SUMMARY OF PRICE SECTION 1: PREAMBLES The Contractor is deemed to have take cognizance of all local environmental, climatic and weather conditions and the effect these may have on the construction process. No clai

16、ms for extra payment on these grounds will be entertained where, in the opinion of the Engineer, the impact could have been foreseen by a competent Contractor. Each item shall be priced separately and be inclusive of supply, freight, landing, insurance, foundations, erecting, connecting, testing and

17、 finishing off and to include accommodation and a correct sum for maintenance during the maintenance period. The total of the separate items shall include everything necessary to leave the plant complete and in full working order at the expiration of the maintenance period in accordance with the pro

18、visions of the Contract. 每一个单项项目须将供给,运费,码头,保险费,基金会,装配,套管、测试和完成,包括住宿和维修期内的维修费用的单价单独标出,在合同中规定总分项目应包括所有有必要离开工厂完成完全工作秩序,维护周期届满的。The present quantities entered in the Bill of Quantities are estimated only. The final quantities of the various items will be established after the selection of support positi

19、ons has been finalised on completion of the check survey of the route. 目前进入到工程量清单中的项目仅是估计出来的而已,最后的大量的各种各样的物品将选择支持后成立的位置已经完成的检查完成调查的路线。最后被确定Where a nil quantity is shown a rate shall nevertheless be entered. 在零速度量显示仍然应当被进入。Payment will be made in accordance with the rates and prices set against the i

20、tems in the Bill of Quantities as amplified in this section and against the final quantities approved by the Engineer. These rates and prices shall include all of the work, temporary and permanent, necessary to comply with the Contract. Measurement for the purposes of payment shall where appropriate

21、 be made jointly by the representative of the Engineer and the Contractor. The Contractor when requested shall attend for purposes of measurement, or otherwise accept measurements made by the Engineer alone. Where applicable the Contractor shall indicate on each invoice the identification number of

22、each support to which items in the invoice refer. Rates and prices in the Bill of Quantities where applicable shall be deemed to include for all work on site irrespective of access conditions, including if necessary helicopter transportation, slope of ground, nature of subsoil, presence of water or

23、other obstacles adjacent to or across the line of the route except as provided for in Section 5 - Wayleave, Access And Site Preparation of the Technical Specification. All rates and prices shall include all incidental expenses which the Contractor or specialist Subcontractor may incur in the prepara

24、tion of maintenance of access, in the provision of site services and of all transportation for labour whether skilled or unskilled. The rates and prices in the Bill of Quantities shall include all out allowances or other supplementary payment to skilled or unskilled labour, customary, authorised or

25、required by regulations in force at the date of the Tender. All rates and prices shall be deemed to include payment to labour, or other expenses incurred for idle time during which work on site is interrupted by weather conditions or flooding by storm overflow or the like. Whilst every assistance wi

26、ll be provided to facilitate line construction activities in sequence in accordance with the Contractors agreed programme of work, there could be occasions when this may not be possible. No claims for additional costs to the Contractor will be accepted solely for such discontinuity of working, excep

27、t where this involves the out of sequence movement of the conductor stringing plant and equipment. The Tenderer should indicate the cost that would be incurred in the event of an out of sequence movement of the conductor stringing plant and equipment. Only those prices shown in the miscellaneous rat

28、es will be accepted as additional to the contract price where the use of such rates is authorised by the Engineer. PLS-110090 PRE/2 - Page 3-SARAWAK ENERGY BERHAD SIMILAJAU TO TADA 500KV TRANSMISSION LINE PROJECT (500KV BACKBONE TRANSMISSION PROJECT PHASE I) VOLUME 1 PART C: SUMMARY OF PRICE SECTION

29、 1: PREAMBLES Check survey and easement clearing for the horizontal distance involved measured along route centre line. Construction of new access tracks will be based on the lump sum basis. Rates for earthing of structures under the transmission line shall include all the necessary materials for th

30、e earthing installation. Any items not in Summary of Prices but required by the specification for the project completion shall be deemed to be included in the overall contract price. All structure extra-over items shall be assumed applicable to complete structures in any type of ground. Final paymen

31、ts shall be made for the finally erected quantities extended at the rates herein. 1.1 PREAMBLES FOR PRELIMINARIES 1.1.1 The Tenderer shall quote a Fixed Lump Sum for the cost of all Preliminaries, Conditions of Contract and Project Requirement indicated below in paragraph 1.2.1 to 1.2.7 inclusive. I

32、ndividual unit cost items are to be identified in the Preliminaries which shall include the cost for General Conditions and Project Requirement. The lump sum price breakdown is required for evaluation purposes. 1.1.2 The prices for the Preliminaries, Conditions of Contract and Project Requirement ma

33、y only be increased if the final total cost of the measured work (excluding Dayworks, Preliminaries, General Conditions and Project Requirement) exceeds by twenty-five percent (25%) the total cost of the measured work (excluding Dayworks, Preliminaries, General Conditions and Project Requirement) qu

34、oted in the Tender. 1.1.3 In such case, the Preliminaries, Conditions of Contract and Project Requirement may be increased by an amount to be agreed between the parties. The basis for calculation of the compensation amount shall based on the difference between the sum that is over and above twenty-f

35、ive percent (25%) the sum quoted for the tender (excluding Preliminaries, General Conditions and Project Requirement) and the actual final total cost of the measured work (excluding Preliminaries, General Conditions and Project Requirement). Such addition shall constitute full and total compensation

36、 for any increase in costs or liabilities attributable to changes or alterations to the Works and no other claims will be considered by the Employer (except on the basis of 1.2.6 below). In the event of the Contractor claiming for increased Preliminaries, General Conditions and Project Requirement u

37、nder this clause, he shall demonstrate to the satisfaction of the Employer that he has suffered extra costs due directly to the increased volume of work and which costs could not reasonably have been allowed for in the Tendered Price. 1.1.4 The prices for the Preliminaries, Conditions of Contract an

38、d Project Requirement shall only be reduced if the final total cost of the measured work (excluding Dayworks, Preliminaries, General Conditions and Project Requirement) is reduced by more than 25% (twenty-five percent) of the total cost of the measured work (excluding Dayworks, Preliminaries, Genera

39、l Conditions and Project Requirement) quoted in the Tenders. 1.1.5 In such case the Preliminaries and Conditions of Contract shall be reduced by an amount to be agreed between the parties and as described in Clause 1.1.4 above. 1.1.6 The provisions of Clauses 1.1.3 to 1.1.4 shall only apply to chang

40、es in the work and quantities generally within the broad scope of the Project as described in the Technical Specification. Should the Employer require additions or deletions to the Project which are clearly outside the broad scope and intent of the Technical Specification, such variations will be me

41、asured and valued in accordance with the Conditions of Contract. 1.1.7 The Preliminaries, Conditions of Contract and Employer shall be fully inclusive of all fees, charges, duties, taxes and expenses and all other costs incurred to administer the execution of the work including costs for the adminis

42、tration of Sub-contracts (if any) and these costs shall comprise but not be limited to, the terms included below: PLS-110090 PRE/3 - Page 4-SARAWAK ENERGY BERHAD SIMILAJAU TO TADA 500KV TRANSMISSION LINE PROJECT (500KV BACKBONE TRANSMISSION PROJECT PHASE I) VOLUME 1 PART C: SUMMARY OF PRICE SECTION

43、1: PREAMBLES a) Supervision Costs i) Supervisory staff, satisfactory to the Employer as to numbers, qualifications, experience and duration of assignment, as are required to ensure the efficient prosecution of the work in accordance with the agreed programme, shall be included; ii) Costs shall inclu

44、de all salaries, burden, transfer costs, housing, travel and other living expenses, personnel transport and all other allowances, costs and other charges incurred by or as a result of providing such personnel. b) Administration, Clerical, Security and Warehousing Personnel i) Administration and cler

45、ical personnel as are required to ensure that efficient prosecution of the work shall be included; ii) All necessary security services shall be included for the protection of the Contractors plant, equipment, materials, or any such under his care; iii) Warehouse staff for the safekeeping and adminis

46、tration of materials intended for incorporation in the works shall be included; iv) The costs shall include all salaries, burden, transfer costs, housing, travel and living expenses, personnel, transport and all other allowances, costs and other charges incurred by or as a result of providing such p

47、ersonnel; v) Contractors head office costs, overhead, fees, profits, expenses and the like required for the performance of the works and all costs necessary for the fulfillment of all obligations and responsibilities required under the Terms of the Contract. c) Temporary Buildings i) All buildings f

48、or the use of the Contractors personnel; ii) Contractor to list all buildings it is intended to bring on to site; iii) All necessary office furniture, furnishings, and equipment and the installation of a telephone system as may be required for the proper administration of the Contract shall be inclu

49、ded; iv) Delivery, erection and subsequent dismantling and removal from site after the Employers written permission has been obtained; v) Restatement, make good the area. d) Temporary Facilities The Contractor shall include for the provision, installation, maintenance and dismantling of all temporar

50、y facilities, which may be required for the efficient prosecution of the work, including, but not limited to materials, equipment and labour for:- i) Temporary electrical power supplies; ii) Temporary water supply (including drinking water); iii) Temporary plant and equipment air supplies; iv) Temporary access roads, crossings, hard stands and culverts, as may be required; PLS-110090 PRE/4 - Page 5-SARAWAK ENERGY BERHAD SIMILAJAU TO TADA 500KV TRANSMISSION LINE

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论