1、精选优质文档-倾情为你奉上Course ProjectRoad Pavement Engineering Highway School of Changan University XXX Advisor: XXX 2016-xx-xx专心-专注-专业Part I Data CollectionThe project is segment A of Shijiazhuang to Zhengzhou grade 1 highway. 1.1 Climate dataNatural Zone: II4Annual Rainfall: 570mm; HT: 37C; LT: -7C Frost-th
2、aw: Max frozen depth of 60cm; Frozen index of 1023C on average and 1540C in Max 1.2 Geological and subgrade conditionsSoil Type: alluvial soil(as clay soils of low liquid limit) Embankment: 0.6m of height ;Water table: 2.7m from the roadbed surface in mid-wet state;Subgrade width: 24.5m=4*3.75+2*2.5
3、(Hard shoulder)+2*0.75(soil shoulder)+3.0(central median) 1.3 Traffic dataTable 1. Traffic combinationNO.ClassificationVehicle modelsDaily traffic flow(veh/d)Vehicle conversion coefficient1Medium sizeMitsubishi T653B 3201.52Medium sizeJieFang CA390 2201.53Large sizeJAC HF15018024Large sizeCNHTC JN16
4、223025TrailerXJ HQP4014036TrailerDFM EQ155903Note: NO. 5 & 6 is vision traffic, only considered in the calculation of the pavement structure.Part II Asphalt Pavement Design1.1 Traffic AnalysisESALs calculation Specific calculating process is in excel, and applied equations are:Deflection and asphalt
5、 layer bottom tensile stress as design criteria Tensile stress at the bottom of semi-rigid base as design criteria Accumulative equivalent ESALsIncreasing ratio for every five years are1=8%,2=7%, 3=5% so the total increasing ratio G can be calculated as:G1= (1+8%)5-1/ 8%=5.87 G2= (1+8%)5*(1+7%)5-1/
6、7%=8.45G3= (1+8%)5*(1+7%)5*(1+5%)5-1/ 5%=11.39G=G1+G2+G2=25.71According to specification for design of highway asphalt pavement clause 3.1.7, Ne= Ne1 =365*8534*25.71*0.5=40.04msa(Deflection and asphalt layer bottom tensile stress as design criteria)Ne2=365*82980*25.71*0.5=389.3msa(Tensile stress at
7、the bottom of semi-rigid base as design criteria)1.2Subgrade ModulusFrom the table 5.1.4-1 in JTG D50-2006, consistency is between 0.95-1.10, the corresponding MR is less than 40 MPa and for extremely heavy traffic subgrade MRmin=40MPa, so MR=40MPa.2. Combination Design2.1 Asphalt surface course & B
8、ase and subbase coursesAsphalt surface and Base and subbase material and thickness selection limit is from the table below in JTG D50-2006:2.2 SummaryThree combination schemes areScheme1: (Asphalt + asphalt + granular )4cmAC13+5cmAC16+7cmAC25+20cmAM20+30cm graded macadamScheme2 : (Asphalt + HBM + Gr
9、anular) 5cmAC10+7cmAC16+10cmSMA20+30cm cement stabilized base+15cm graded macadam Scheme3:(Asphalt + Asphalt + HBM)4cmAC10+7cmAC16+18cmSMA20+30cm limestone soilAnd choose scheme2 to check whether it meets requirement.3. Material proportion properties3.1 Asphalt surface Materials The corresponding ma
10、terial properties can be found in the Table E.1& 2:Namely:typeEC(20C)MPaEC(15C)PMaSplitting strength(MPa)AC10150021001.5AC16130018000.93.2 Base and subbase materialsTypeEC(deflection)MPaEC (tensile stress)PMaSplitting strength(PMa)Cement macadam160040000.55SMA150019000.8Graded macadam450-4. Thicknes
11、s Design4.1 Determine design criteriaDetermine Design Deflection Ld: Equation givenAC=1(1 for expressway & class I, 1.1 for class II, and 1.2 for others) AS=1(1 for AC and 1.1 for others)Ab=1(1 for semi-rigid base, and 1.6 for flexible base)So Ld =600*4004*104*1*1*1=18.1(0.01mm)Determine Tensile Str
12、ess at bottom of each layerEquation given AC10 layer: Ks=0.09Ne0.22/Ac=0.09*.22/1=4.23 , R=sp/ks=1.5/4.23=0.36MPaAC16layer:Ks=0.09Ne0.22/Ac=0.09*.22/1=4.23 , R=sp/ks=0.9/4.23=0.21MPaSMA20layer:Ks=0.09Ne0.22/Ac=0.09*.22/1=0.55 , R=sp/ks=0.9/4.23=0.21MPaCement stabilized base layer:Ks=0.35Ne0.22/Ac=0.
13、35*.22/1=16.47 R=sp/ks=0.55/16.47=0.03MPa4.2 Determine calculated criteriaBISAR Solution for surface resilient deflection:BISAR Solution for layer bottom tensile stresses Layer1Layer2Layer3Layer44.3 Finalize the thickness designCompare the design criteria and the calculated criteria:Correction of BI
14、SAR solution for deflection:Assuming ls=ld=18.1(0.01mm), then F=1.63*(18.1/(2000*10.65)0.38* (40/0.7)0.36=0.476 Therefore, corrected BISAR solution is Ls=33.03*0.476= 15.72(0.01mm) 40cm, there is no need to set another layer.Finial thickness design of scheme2:Part III Cement Concrete Pavement Design
15、1. Project StatementNatural Zone II4Pavt width: 7mSubgrade soil: clay with a low liquid limitWater table: 1.2m beneath the roadbed surfaceAggregate: ganitePavt type: JPCPPs=80KN, Pm=150KNADTT=4500saAnnual increasing rate: 5%2. Design data2.1 Traffic AnalysisWheel-track coefficient:Design period: 20y
16、s, and Safety level: class-II, pavt width=7m, according to JTG D40-2011 figure=0.62, so accumulative equivalent ESALs can be calculated as: Ne=NS(1+gr)t-1365/gr=4500(80/100)16(1+5%)20-13650.62/5%=saNe is between 0.03msa1msa belonging to moderate traffic level.2.2 Subgrade ModulusAccording to JTG D40
17、-2011 appendix E, reference MR=90MPaAnd Humid coefficient= 0.75So MR=90*0.75=67.5MPa 3. Combination Design3.1 Concrete Surface courseAccording to JTG D40-2011, concrete slab recommended thickness select 240mm3.2 Base and subbase coursesAccording to JTG D40-2011, available materials for base areLight
18、 or ModerateGraded Crushed StonesCement-stabilized, lime-ash-stabilized crushed stonesAnd available materials for subbase areLight or ModerateUnscreened crushed stones, graded crushed stones, or no subbaseConstruction thicknessGraded Crushed stones/ Unscreened crushed stones or gravels100-200Therefo
19、re, 200mm graded crushed stones as base layer and no subbase.3.3 SummaryLayerMaterialThickness(mm)SurfacePPC230SubaseGraded crushed stones2003.4 Other design parameterReliability : for class II highway, safety level is II and target reliability is 85 percent, reliability index is 1.04.And from table
20、 below the variance level is moderate, so reliability coefficient is 1.13.Temperature Gradient is 88 C/m based on table below.4. Joint Design4.1 Transverse JointsTransverse Joint spacing: 4.5m and no dowel bars are used at the transverse joints 4.2 Longitudinal JointsLongitudinal joint spacing: 3.5m
21、 and tie bars are used at the longitudinal joints. Besides, the size of tie bar is 14*700*600 based on table below from JTG D40-2011.5. Material proportion properties5.1 Concrete MaterialsRupture strength is 4.5MPa, MR=29GPa, Poissons ratio is 0.15, Thermal coefficient is 1E-5Traffic classPlain Ceme
22、nt Concete (PCC)Moderate=4.55.2 Base and subbase materialsMR=300MPa based on JTG D40-2011 appendix E6. Calculation and analysis of load-induced stress6.1 Load-induced fatigue stress Because concrete slab on granular base can be considered as single-layer plate system on elastic foundation, so the eq
23、uation for Load-induced fatigue stress is Kr=0.87 (0.870.92, tire bar) Kc=1.05(checked in table as follow) Kf= Ne =(94.78104)0.057=2.191And in ,Equivalent modulus of unbound materials: Et=130Mpa Ex= (hi2Ei)/ hi2=h12E1/h12=300MPa Hx= hi=h1=0.20m =0.86+0.26ln( hx )=0.86+0.26ln(0.20)=0.442 Et=(Ex/E0)E0
24、=(300/67.5)0.44267.5=130.51MPaBending stiffness: 34.17MNm Dc=Echc3/(12(1-vc2))=290000.243/(12(1-0.152)=34.17MNmr=1.21 (Dc/ Et )1/3=0.775mso ps=1.4710-3r0.70hc-2Ps0.94=1.4710-30.7750.700.24-2800.94=1.313MPaThus pr = kckrkfps =1.052.1910.871.313=2.627MPa6.2 Load-induced ultimate stresspm=1.4710-3r0.70hc-2Pm0.94=1.4710-30.7750.700.24-21500.94=2.541MPap,max=krkcpm=0
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2026年大学试题(管理类)-旅游管理历年参考题库含答案解析
- 2026年大学试题(管理类)-个人与团队管理历年参考题库含答案解析
- 2026年大学试题(法学)-反家庭暴力法历年参考题库含答案解析
- 2026年大学试题(汽车专业)-汽车运用工程历年参考题库含答案解析
- 2026年宁夏工商职业技术学院高职单招笔试物理历年参考题库含答案解析
- 2026年娄底职业技术学院高职单招笔试英语历年参考题库含答案解析
- 2026年大学试题(教育学)-论文写作指导历年参考题库含答案解析
- 2026年天津工程职业技术学院高职单招笔试综合素质历年参考题库含答案解析
- 2026年大学试题(大学选修课)-法学人生历年参考题库含答案解析
- 2026年大兴安岭职业学院高职单招笔试英语历年参考题库含答案解析
- 瓦斯检查工岗位安全生产责任制
- 新版中华民族共同体概论课件第八讲共奉中国与中华民族内聚发展(辽宋夏金时期)-2025年版
- 赣韶线铁路桥施工方案
- 中药煎药上岗培训课件
- 高校PI团队管理办法
- 设备采购类可行性研究报告
- 企业管理咨询顾问合作协议样本
- 三人心肺复苏
- 初中写字课程-课件
- 海南盛亨美安混凝土搅拌站建设项目建设环境影响评估报告表
- 水运工程质量奖申报培训
评论
0/150
提交评论