1、Construction Readiness Plan施工准备方案 Version 2 8-7-14Purpose of Construction Readiness Plan施工准备方案的目标The purpose is to simply ensure every member of the team goes home safely. This is to be presented by PCC permit issuer, safety manager and site foreman (core team). The construction readiness plan MUST
2、be measured against risk elements and mitigations and provide Jacobs confidence that the PCC is ready to delivery OR THEY MUST NOT MOBILIZE.简单来说,目标是确保团队所有成员能安全回家,由土建承包商的许可证发行人,安全经理和现场施工经理(承包商核心团队)提供保证。施工准备方案必须参照风险和相关控制措施进行评估,让Jacobs对土建承包商施工准备就绪有信心,否则就 不能开工。This is done in several ways;从三个方面准备:People
3、 人员Process流程Tools工具People人员Qualified to do job correctly 有资质合格的人员可以正确地完成工作Trained in the Jacobs and Shell way 接受过Jacobs和Shell的培训Committed to safety leadership 安全领导力承诺Process 流程Life saving rules 遵守12条救命规则Permit to work 遵守工作许可证制度Job Hazard Analysis 工作危险分析Work Clearance Forms 许可证工作表格(工作清单)Key hold poin
4、ts for project 项目关键检查点Shell Controls Framework 壳牌管理框架Tools 工具Tool box talks 工前安全例会Talk not tick interviews 与工人面谈能力评估Temporary site closure guidelines 临时油站关闭指引Survey Monkey 详细调查Details to be included in plan方案详情In order to mobilise to site the PCC is to present their construction readiness plan (face
5、 to face interview) in order to receive approval to mobilise to site from the Jacobs and client representatives. This presentation will include (at a minimum)为了油站开工,土建承包商需要展示其施工准备方案,获得Jacobs和客户代表的核准(面对面审核)后方可开工。此方案将(至少)包含:The Team团队Core team & competency 核心团队及其资质Site Information & Layout工地信息和总体布局图Ne
6、arest two hospitals with route map ( Ensure availability of anti venom for snakes) 距现场最近的两所医院及路线标注(确保可治愈毒蛇伤害)Nearest fire station telephone numbers最近消防队电话Nearest Police Station telephone numbers最近派出所电话Site visit report by PCC 土建勘察报告Hazards Identification/Site condition- Initial findings & proposed a
7、ctions危害识别/油站情况初期发现和建议动作Contents of Site Lay Out 施工现场布局Proposed Main gate for manpower and equipment人员设备进出的大门Guardhouse / Registration area警卫室/登记室Tool Box Meeting Area 工前例会区域Temporary Facilities details临时设备明细Emergency meeting point.紧急集合点Materials Stock warehouse and stockyard材料仓库以及堆场Emergency Exit 紧
8、急出口Site Green Zone/Red Zone demarcation油站绿区红区及其分界CCTV Camera locations 中央监控摄像头位置Steel Fab area 钢筋加工区Site safe access and egress现场安全出入口Traffic Management 交通管理Site closure process 油站关闭流程Emergency Response应急预案Barricading details 围栏明细Tank Farm design details based on soil condition根据罐区土壤情况制定的详细罐区施工方案及围挡
9、方案Canopy excavation barricading details. 雨棚基坑开挖/围挡方案How installing a culture of safety leadership with front line workers一线工人安全文化及意识培养Mobilisation & Demobilisation Activities动员及离场Work Scope 工作范围Project Schedule施工计划Methodology for Site Activities工地施工方案Building works/scaffolding/working at height站房作业/
10、脚手架/高空作业Piling/Shoring for tank pit area油罐基坑区打桩/支撑Excavation for Tank pit area 罐区基坑开挖Working inside the tank pit油罐区基坑内作业Tank installation油罐安装Backfilling回填TCC & RVI-E 液压升降雨棚/RVI安装Fuel System油管路系统Drive way车道Monolith Installation 主标志牌安装U/G Utilities 地下设施Indicate to support work methodology if site has
11、truck ban on the daytime如果工地白天禁止车辆进出,请说明施工方案Other Equipment, DG, Air compressor, Air Gauge其他设备,发电机,空气压缩机,气压计等Night Work 夜间施工Hot work Management & Key Hold Points that require Jacobs and or third party approval热工作业管理和需要嘉科或第三方核准的关键检查点Civil & Fuel Systems 土建施工及油管路系统Lessons learnt sharing / tool box tal
12、ks and presentations 经验教训分享/工前安全例会和宣讲Handover 完工移交Site HSSE Planner & Duty Roster 工地HSSE规划员和职责表Quality Management质量管理Risk management- HSSE controls 风险管理-HSSE管控Non-spark tools 防爆工具HSSE Audit Schedule HSSE检查计划Who is in charge负责人SITE MANAGER工地经理Permit issuer许可证发行人HSSE Officer安全专员Permit Holder许可证持有人FORE
13、 MAN/ WORKERS/ SUB CONTRACTORS班组长/工人/分包商工人Core Team & Competency核心团队及其资质Evidence of knowledge 资质证明Passport Jacobs passport system & Shell PTW V4.1 安全护照-Jacobs护照系统和壳牌4.1版许可证FFS certification 富兰克林许可证(油管路安装承包商)Lessons learnt 经验教训分享HSSE Training HSSE培训Certified Installers, Permit Issuers, Permit Holders
14、 合格安装工,许可证发行人,许可证持有人What training have sub-contractors has (must show evidence)分承包商的资质审核及培训(必须有文件支持)Crane operator competency certificate吊车工就业证及壳牌HSSE相关资质证照Gas tester/scaffold inspectors 油气测试员、脚手架检查员HSSE Manager qualification HSSE经理(主管)资质We want to see evidence for all workers on site.我们需看到油站所有工人的资质
15、证明。 Site Information & Layout油站信息和布局图SITE INFORMATION example油站信息- 示例Site Location施工现场位置Description of nearest land mark最近地标描述Site plot size油站平面尺寸Short description of site to be built (example: 2-island toll-type, 4 Underground Storage tank, suction type/ pressure type)建站简短描述(如 2个加油岛;收费站类型;4个地下储油罐,自
16、吸式/压力式) Note this information can generally found in the IP documents provided by Shell.注意这些信息通常可在壳牌提供的IP文件中找到Provide aerial photo of the proposed site 提供将建油站航拍图Site Hazards & Mitigations油站危害和缓解措施PCC to have identified hazards and how these will be controlled.土建承包商已经识别所有危险,并了解如何控制相关危险。Example: neigh
17、bouring risks, conflicting sub-contractors例如:临近风险,与分包商工作冲突。VICINITY MAP / EMERGENCY CONTACT NUMBERS临近区域地图、紧急联系人AGENCYNAMENUMBERLOCAL POLICEPOLICE ASSISTANCEPATROLFIRE DEPARTMENTFIRE DEPARTMENTHOSPITAL / AMBULANCEDISASTER, FLOOD, CALAMITYGEN. CONTRACTORPROJECT MANAGERInformation should include proxim
18、ity of proposed site to Hospital, Police, Fire department, etc.信息应包含计划油站到医院,派出所,消防队等的距离AGENCY机构NAME姓名NUMBER号码LOCAL POLICE当地派出所POLICE ASSISTANCE警察援助PATROL交巡警FIRE DEPARTMENT消防部门FIRE DEPARTMENT消防部门HOSPITAL / AMBULANCE医院/救护车DISASTER, FLOOD, CALAMITY灾害,洪水,灾难GEN. CONTRACTOR总包商PROJECT MANAGER项目经理RESCUE PLA
19、N example 救援方案 - 示例Scenario -EXCAVATION WALL COLLAPSE 方案-疏散-基坑坍塌Witness to attract the attention, Security officer by pressing alarm system.目击者须提醒大家注意,安全人员按下警报器Suspend all works/activities immediately.立即停止所有工作活动The EMERGENCY CALLER will immediately call the AUTHORIZED and TRAINED RESCUE TEAM for thi
20、s particular incident the fire department, hospital, ambulance.紧急呼叫人立即打电话给被认可的受过培训的救援队伍,如消防队,医院,救护车等。Certified first aider will assist the recovered injured victims 合格的急救员救助伤者Site authority to secure the accident area and prevent crowding of on-lookers工地主管应隔离事故区域,防止旁观者聚集。Workers to proceed to the ev
21、acuation area for debriefing 工人到疏散区接受询问调查Site Manager to report this immediately to SKM PM/CM 施工经理立即向SKM PMCM汇报WORKING AT HEIGHTS HANGED WORKER高空作业 - 悬空作业Witness to attract the attention , Security officer by pressing alarm system.目击者须立即提醒大家注意力,安全专员按下警报器。Suspend all works /activities immediately and
22、 continue until to do so.立即停止所有工作活动。The EMERGENCY RESPONSE GROUP ( PRESAM fire fighting team) will do the rescue.紧急预案小组(PRESAM消防队)展开救援。The emergency caller will immediately call the support rescue team - fire department, hospital and ambulance紧急呼叫人立即打电话给救援队伍,如消防队,医院,救护车等。Ensure that there should alw
23、ays a standby scaffolding, this will serve as a tool for rescuing a hanged worker.确保现场有备用脚手架可使用来悬空作业的工人。Certified first aider will assist the recovered injured victim.合格的紧急救员救助伤者Workers to proceed to the evacuation area for debriefing.工人到疏散区接受询问调查Site Manager to report this immediately to SKM PM/CM
24、施工经理立即向SKM PM/CM汇报Emergency Response Team- example 紧急预案小组-示例EKO AS/NOVAL嘉科PM/CMSKM PM/CM 0811859562 /ALLAN BARNACHEASITE MANAGER 工地经理081288074932ANTON MSFIRE FIGTHING TEAM消防小组 085210331020ENDANGFIRST AIDER TEAM急救小组 087826858889SUGENGEMERGENCY CALLER紧急联络官及其电话 081380803357SADAMTRAFFIC WATCHER交通观察员MEMB
25、ER成员BUDROEPONOPIOSECURITY保安 EVACUATION WARDEN疏散负责人MEMBER成员PUJOHENDIWARISMANIIPHENDI SELECTRICIAN电工INCIDENT EMERGENCY RESPONSE example 事故紧急预案- 示例AABBCDDDDBBCCCBABCDSECURITY OFFICER保安专员HSSE OFFICER HSSE专员SITE OFFICER 工地管理专员SITE MANAGER工地经理FIRE EMERGENCY RESPONSE-example 火警应急预案- 示例HOSPITAL ROUTE-exampl
26、e 医院交通线路-示例TLP (061) 7345661Berkendara melalui jalan bunga wijaya kusuma 2,7 km sekitar 5mnt.Barricading Details 围挡明细 Site Barricade Details-example油站围挡明细-示例NTI Hard Barricade新建站彩钢板硬质全围挡Deep Excavation Barricade深挖坑硬质围挡+安全网Tank Farm Barricade油罐区硬质围挡Green Zone / Red Zone Mobile Barricade绿区、红区隔离可移动围挡No
27、te: Needs to include all barricading for site, tank farm excavation, canopy etc. 注:施工工地,罐区开挖,雨棚等围挡都包含在内,应该满足嘉科围挡最低标准要求。Mobilisation / Demobilisation Plan动员方案、离场方案The PCC to have a very clear mobilisation and demobilisation plan including but not limited to;承包商需有非常清晰的动员方案,离场方案,包含但不限于如下:Site set up (D
28、efine red & green zones) 现场布置(定义红区绿区)Staff facilities 员工生活设施Traffic Management 交通管理Procedures 作业指导规程Document management 文件管理Lessons learnt 经验教训总结与分享Permits / drawings 许可证/施工图纸Equipment Registers 设备登记(包括检查与维护等记录)Internet / photocopying etc 网络,影印等Waste management 废物管理Inductions 入职培训HSSE controls HSSE管
29、理Reporting 汇报NMPI management隐患事件,险肇事故管理Clean up 现场清理Scope范围 Construction Schedule 施工进度计划Schedule Overview时间安排概述Key Hold points关键检查点Risks 风险Mitigation strategies if required 必要的缓解危险策略Construction Methodology 施工方法Methodology for Site Activities5. Tank farm works. 罐区作业1. Install M (20cm x 20cm x 10M pi
30、le) shoring at tank farm and M (20cm x20cm x12M pile) UST Foundation, ensure to follow assessed layout markings 适当的支撑和或放坡2. Provide 40cm x 40cm concrete beam throughout piled shoring, put concrete maximizer for faster curing. 在桩基支撑的地方提供混凝土梁,并使用 速凝剂加速混凝土凝固3. Excavate tank farm using PC 200 Excavator,
31、 ensure to check specified depth of tank farm. ( Provide 1 unit 5 HP and 1 unit 2 HP submersible pump with continuous pumping of water) 使用PC200挖掘机挖掘油罐区,确保油罐区的深度符合规格(提供5HP和2HP潜水泵各一台已实现可持续抽水)4. Spread geo textile at tank farm area until pile cap beam. 油罐区铺土工膜,直到桩顶梁5. Concrete pouring of tank base and
32、anchor beam , put concrete maximizer for faster curing. 混凝土浇注油罐底和锚固梁6. Provide pea gravel at tank base, ensure standard pea gravel diameter (3/8”). 油罐底使用小卵石,确保使用标准尺寸小卵石(3/8“)7. Lower UGT at tank farm using 50 tonner telescopic crane, ensure tank is properly set before putting the strap. 使用50吨起重机将埋地油
33、罐放进油罐基坑,固定油罐前前确保油罐放置适妥当。8. Test tank integrity by vacuum test. 真空测试法检验油罐完好性9. Backfill remaining pea gravel (screening) until top of UGT. 回填剩下小卵石(经筛选)直到油罐顶部10. Installation of UPP lines for vent, remote, fuel lines ,STP and tank sump. 安装输油管道排气口,输油管线,潜油泵和隔油池11. Installation of electrical lines of STP
34、 and signal line of sensors. 安装潜油泵电缆,传感器信号线缆12. Backfill remaining pea gravel (screening) until sub base level. 回填剩余小卵石(经过筛选)至底基水平13. Concreting top of tank farm. 油罐区顶部铺浇筑混凝土6. Saleshop building works Conventional便利店常规作业Bamboo Piling 竹桩Backfill whole building area until pile cap level, must be tampe
35、red every 30cm level. 回填整个施工区域至桩帽,每回填30cm深必须进行一次夯实3. Spread plastic sheet at the whole building area. 整个施工区域平铺塑料薄膜4. Put pile cap and reinforcing bars, ensure to follow specified materials and diameters. 放置桩帽和钢筋,确保使用规定的材料和直径5. Install under ground electrical lines, waterlines, sewer lines and signal
36、 lines. 安装埋地电缆,水管,排污管和通讯线缆6. Concrete pouring of concrete slab of the whole building area, ensure to follow standard concrete mixture 整个施工区域成混凝土地面混凝土浇注,确保混凝土混合比 符合标准要求 7. Installation of soak well, septic vault and water tank. (ensure to follow installation standard) 安装隔油池,化粪池,和水池(确保符合安装标准)8. Conven
37、tional Building materials.常规建筑材料9. Installation of electrical lines for lightings, convenience outlets, communication lines, etc. until MDB. 安装连接到主配电箱的灯具电缆,方便的电线出口,电信电缆等10. Installation of stabilizer and MDB.安装稳压器和主配电箱11. Installation of other equipment at sale shop building. (ensure to follow insta
38、llation standard procedure) 安装便利店其他设备(确保符合安装标准流程)12. Finishing. 装修Methodology for Site Activities-example油站作业方法-例子7. Canopy works Conventional. 雨篷常规作业1. Install Meter (20cm x 20cm x12 M) pile connection by fully weld ensure pile to reach hard soil. (refer to soil test report) 将计量器(20cmX20cmX12M) 焊接与
39、桩基相连,确保桩基接触到硬土(参照土壤测试报告)2. Excavate for footing/foundation using Excavator, ensure to check specified depth for proper elevation. (refer to standard drawing) 使用挖掘机挖掘柱基或地基,确保达到指定的深度(参照标准图纸)3. Install pile cap and reinforcing bars includes anchor bolts and forms. (refer to standard drawing for accurat
40、e dimension details) 安装板桩帽和钢筋包含锚固带和锚固模板(参照精准尺寸明细的标准图纸)4. Concrete pouring of footing and foundation, ensure to follow standard concrete mixture for good concrete strength.柱基或地基混凝土浇注,确保按照标准比例混合以满足混凝土强度要求。5. Pullout forms then backfill until sub base level. 撤离模板,然后回填至底基水平。6. Install canopy structures
41、( working at heights) 安装雨篷(高空作业)7. Installation of electrical lines for lightings, convenience outlets, communication lines, etc. until MDB.安装连接到主配电箱的灯具电缆,方便的电线出口,电信电缆等。8. Installation of electrical lines for pumps, convenience outlets for payment booth, communication lines, etc. 安装水泵,便利店的支付台的输电线, 通
42、讯线缆等。9. Construction of pump islands includes catch basin and installation of dispensing sumps. 修建加油岛及油盆,加油机安装。10. Installation of pre fab payment booth. 安装预制收银台11. Concreting of canopy area, ( refer to standard drawings for thickness and wire mess details) 雨篷区铺混凝土(参照厚度标准图纸和电路接线明细)11. Installation o
43、f dispensing pumps. 安装加油泵12. Installation of canopy lightings. 安装雨篷灯8. Forecourt area works. 前庭作业1. Backfill whole forecourt area with specified backfill material until assessed elevation and tampered every 30cm level. 使用规定的回填材料回填整个前庭区域至被评估的高度,每30cm夯实。 ( ensure forecourt elevation based on SKM/SHELL
44、 Design). 确保前庭高度符合SKM/壳牌设计)2. Installation drainage system 安装排水系统- excavate whole stretch of drainage (refer to standard drawing for layout and desired depth) 挖掘排水沟(参照布局和需求深度的标准图纸)- backfill drainage pit/tamper. 回填排水孔3. Installation of perimeter lights. 安装路灯- install electrical lines until MDB. 接电缆至
45、主配电箱- provide concrete foundation pedestal. 提供混凝土地基支撑。- Erect perimeter post/install lightings. 安装路灯杆,安装路灯。Methodology for Site Activities-example 施工方法-示例Key Hold Points & High Risk Activities关键检查点和高风险作业Key Holds Points and High Risk Activities关键停工点和高风险作业Risk风险Location位置Hot works热工作业Fuel Systems油路系统
46、Hold points 检查点Who issues permit谁发的许可证Toolbox talk requirements开工前安全会议要求Rating (market/PCC) Competence评估能力(市场、土建承包商)Conflicting Contractor Works与分包商作业相冲突Must also out line how PCC will manage multiple high risk works to ensure there is effective management and control measures.必须也概括土建承包商如何管理诸多高风险作业,
47、以确保其具有有效的管理和风险管控措施。Lessons Learnt Sharing & Tool Box Talks经验教训分享&工前安全会议How we share lessons Learnt 我们如何进行经验教训分享What lessons learnt are being shared分享什么经验教训At which stage of project项目的哪个阶段进行分享Provide Examples 提供例子How?如何分享?Handover 移交 Handover Process移交流程PCC to provide information on how these element
48、s are to be addressed.土建承包商提供如何解决如下事项Defects Closeout 问题关闭Equipment Register 设备登记As Built Mark-ups 竣工图标识Defects liability period 保修期Missing or outstanding info prior to start of project 项目开工前缺失的信息或者不完善的信息Site HSSE Planner & Duty Roster工地安全规划和职能分配表Site HSSE Planner & Duty Roster Contents 工地HSSE规划和职能分
49、配表-内容SITE HSSE PLANNER AND DUTY ROSTER油站安全规划和职能表Site Code油站号: Site Name油站名称:Name of Main Contractor (PCC)土建承包商名称:Name of Site Manager现场经理姓名: Contact Number合同号:Project Dates项目日期Start开工:Finish完成:Details of the HSSE compliance documentation required and when it is required to be completed/submitted/mai
50、ntained at site by the Contractor必需的HSSE合规文件以及何时需要承包商完成/,提交及归档保存Before the Kick -off Meeting (i.e. prioir to mobilisation to site)项目开工会前(即进场动员前)On a daily basis Documented evidence must be placed in site HSSE file and made available for audit/verification purposes.每天 -归档文件必须放进现场HSSE文件夹,以便于审计稽核时取阅。On
51、 a weekly basis Documented evidence must be placed in site HSSE file and made available for audit/verification purposes.每周 归档文件必须放进现场HSSE文件夹,并便于审计稽核时取阅。On a monthly basis Documented evidence must be placed in site HSSE file and made available for audit/verification purposes.每月-归档文件必须放进现场HSSE文件夹,并便于审
52、计稽核时取阅。On a “as-and-when basis” (i.e. situational and related to activity at site) Documented evidence must be placed in site HSSE file and made available for audit/verification purposes.随时随地 (例如:情境性的和现场作业相关的)-归档文件必须放进现场HSSE文件夹,并便于审计稽核时取阅。HSSE PLAN (Refer to Contactor HSSE Package Part 1) - To be su
53、bmitted to PMC for approval prior to kick-off meeting. One (1) plan per NTI/KDR and one (1) plan per program works.HSSE管理程序(参照承包商HSSE管理程序第一部分)- 项目开工会前提交给PMC核准。HSSE方案须根据NTI/KDR分别制定。WORK CLEARANCE FORM(S) - Contractor to fill in the details and obtain consent from PMC/Dealer prior to commencement of a
54、ny works at site AND also obtain acknowledgement from PMC/Dealer upon successful completion of the days work.工作清表 - 承包商填写详情,并须在现场开工前获得PMC或者或油站代表认可,并且,当天工作成功完成后通知PMC和或油站代表。FIRST AID INSPECTION CHECKLIST (Refer to First Aid Inspection Checklist C11 in Contactor HSSE Package Part 5) 急救检查表(参照承包商HSSE管理程序
55、第五部分的急救检查表C11)EMERGENCY RESPONSE (MOCK) DRILL - Contractor to conduct emergency response drill and forward documented evidence to PMC. Contractor could use Site Emergency Response Plan Template (Refer to Annexure A2 in Contactor HSSE Package Part 5) or similar template.紧急预案演习-承包商每个月必须进行一次进行应急演习,并将证明
56、文件交给PMC。承包商应使用紧急预案方案模板(参照承包商HSSE管理程序第五部分的附件A2)或者相似模板。WORK AT HEIGHT INSPECTION CHECKLIST (Refer to Work at Height Inspection Checklist C3 in Contactor HSSE Package Part 5) 高空作业检查表(参照承包商HSSE管理程序第5部分的高空作业检查表C3)Site HSSE Planner & Duty Roster Contents 工地HSSE规划和职能分配表-内容Before the Kick -off Meeting (i.e.
57、 prioir to mobilisation to site)项目开工会前(即进场动员前)On a daily basis Documented evidence must be placed in site HSSE file and made available for audit/verification purposes.每天 -归档文件必须放进现场HSSE文件夹,以便于审计稽核时取阅。On a weekly basis Documented evidence must be placed in site HSSE file and made available for audit/
58、verification purposes.每周 归档文件必须放进现场HSSE文件夹,并便于审计稽核时取阅。On a monthly basis Documented evidence must be placed in site HSSE file and made available for audit/verification purposes.每月-归档文件必须放进现场HSSE文件夹,并便于审计稽核时取阅。On a “as-and-when basis” (i.e. situational and related to activity at site) Documented evid
59、ence must be placed in site HSSE file and made available for audit/verification purposes.随时随地 (例如:情境性的和现场作业相关的)-归档文件必须放进现场HSSE文件夹,并便于审计稽核时取阅。EMERGENCY INFORMATION FORM (Refer to Emergency Information Form 001 in Contactor HSSE Package Part 1) - To be submitted to PMC prior to kick-off meeting. One (
60、1) form per NTI/KDR and one (1) for per region for program works.紧急情况信息表(参照承包商HSSE管理程序第一部分的紧急情况信息表001.-启动会议前提交给PMC核准。HSSE方案须根据NTI/KDR分别制定。TOOLBOX MEETING - To be conducted prior to start of work for the day and include briefing on the JHA details. Documented evidence to be placed in site HSSE file.
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2026文娱部面试题目及答案
- 2026西藏编制面试题目及答案
- 2026相亲节目面试题及答案
- 2026心电监护面试题及答案
- 剧毒化学品经营企业安全技术措施制度
- 电力企业主要负责人检修维修安全操作规程
- 合作项目管理监督合同三篇
- 事业单位财务年终总结
- 调酒师个人实习总结
- 健康评估课程标准
- 《2025版CSCO肿瘤心脏病学临床实践指南》
- 2025 AHA心肺复苏与心血管急救指南
- 广西机电职业技术学院招聘教职人员工作人员考试真题2024
- 湘钢岗前培训考试试题及答案
- 2025年国家基本公共卫生服务岗位职业技能考试题库含答案
- 公司例会管理制度
- DB15∕T 3937-2025 典型地物遥感智能解译技术规程
- 以赛促教 课题申报书
- GB/T 5617-2025钢件表面淬火硬化层深度的测定
- 急诊护理培训课件
- 招聘面试识人有术面试官培训讲师手册
评论
0/150
提交评论