*****J2地块7#楼外墙保温施工方案目录1 工程概况····························································································32 材料性能及要求··················································································33 施工条件环境要求··············································································54 施工机械及工具················································································55 工艺流程····························································································65.1基层清理·······················································································75.2吊顺直线·······················································································75.3配制水泥砂浆··············································································75.4水泥砂浆抹灰施工······································································75.5配制粘结砂浆···············································································75.6排板·······························································································85.7粘贴聚苯板施工············································································95.8施工要点························································································105.9特殊部位施工················································································125.10锚固件安装··················································································155.1抹面层施工··················································································155.12质量控制·····················································································166人力资源管理··························································································167安全生产保证措施·················································································168 文明施工及成品保护·············································································181、工程概况****J2地块7#楼工程,工程地址位于**市****部,东靠***,南面***号路,西面***路,北接****公园.7#楼工程为地下2层,地上25层的框架剪力墙结构。本工程高层楼体外墙采用挤塑聚苯乙烯泡沫板为主要保温隔热材料,以粘、钉结合方式与墙身固定抗裂砂浆复合耐碱玻纤网格布为保护增强层涂料饰面的外墙保温系统.2、材料性能及要求2。1保温材料2。1。1聚苯板(EPS板)的性能除符合《绝热用模塑聚苯乙烯泡沫塑料》GB/T10801。1标准的规定外,还应符合表1的要求。2。1。2EPS板的规格为1200m×600mm×45mm平头式阻燃型其尺寸偏差应符合表2的要求.2。1。2聚乙烯泡沫塑料棒用于填塞膨胀缝作为密封膏的隔离背衬材料其直径按缝宽的1.4倍选用。2。2水泥拌合在胶粘剂和抹面胶浆中的水泥应采用普通硅酸盐水泥或低碱硫铝酸盐水泥。普通硅酸盐水泥应符合《硅酸盐水泥、普通硅酸盐水泥》GB175的要求。硫铝酸盐水泥应符合《快硬硫铝酸盐水泥》JC933的要求.EPS板技术性能指标表1检验项目技术指标表观密度,kg/318。0~22。0垂直于板面方向的抗拉强度,MPa≥0.10且破坏部位不得位于粘贴界面尺寸稳定性(700C,48h),%≤0。3导热系数,W/(m·K)≤0。041压缩性能(形变10%),MPa≥0。10燃烧性能氧指数,%≥30燃烧等级E级养护时间,d自然养护≥42蒸汽养护(600C)≥5EPS板尺寸允许偏差表2检验项目厚度长度宽度对角线差板边平直板面平整度≤50>50允许偏差(mm)+1.5+2.0+2。0±1.03.0±2。01。02。3专用聚合物粘结剂、抹面胶浆厂家已配制好,现场施工时加水用手持式电动搅拌机搅拌,重量比为水:聚合物砂浆等于1:5,可操作时间不小于2h。其中胶粘剂性能指标应符合L07J110表3的要求,抹面胶浆应符合L07J110表5的要求。2。4锚栓金属螺钉应采用不锈钢或经过表面防锈处理的金属制成,塑料钉和带圆盘的塑料膨胀套管应采用聚酰胺、聚乙烯或聚丙烯制成,制作塑料钉和塑料套管的材料不得使用回收的再生材料。锚栓的有效锚固深度在混凝土墙中不小于25mm,在砌体墙中不小于50mm,塑料圆盘直径不小于50mm,单个锚栓抗拉承载力标准值不小于0。3KN,且应进行拉拔力现场试验。2。4耐碱玻纤网格布用于增强保护层抗裂及整体性;选用孔径4×4的耐碱玻纤网格布,其性能指标应符合《耐碱玻璃纤维网布》JC/T841的要求外,还应符合L07J110表4的要求。3施工条件环境要求3。1施工条件3.1。1主体验收通过,外墙已满足施工工作面要求。3.1.2材料进场,施工队伍已选定,并进场。项目部对其进行安全教育和安全、技术交底工作完毕.3。1。3外用吊蓝安装调试完毕。3.1.4相关材料产品合格证书、性能检测报告等相关资料齐全,并合格。墙体节能工程使用的保温隔热材料进场后,应在监理(建设)单位的见证下取样,并送至有资质的检测机构进行进场复验。进场复验应符合下列要求:
1)复验项目eq\o\ac(○,1)、保温材料的导热系数、表观密度、抗压强度或压缩强度和燃烧性能;eq\o\ac(○,2)、粘结材料的粘结强度;
eq\o\ac(○,3)、增强网的力学性能、抗腐蚀性能.2)检验数量
同一厂家、同一品种产品,当单位工程建筑面积在20000m²以下时各抽查不少于3次;当单位工程建筑面积在20000m²以上时各抽查不少于6次。3。2环境要求3.2.1外墙外保温工程施工期间以及完工后24h内,基层及环境空气温度不应低于5℃.夏季应避免阳光曝晒。3。2。2在5级以上大风天气和雨天不得施工。4施工机械及工具4。1施工机械eq\o\ac(○,1)外用吊蓝,选用ZLP630型号吊篮。选用型号其主要参数如下:型号ZLP630额定载荷(kg)630升降速度(m/min)9—11额定功率(kW)1。5×2工作平台尺寸长×宽×高(mn)6000×690×1230配重(kg)900外用吊篮应有产品合格证书、出场证明等相关资料。eq\o\ac(○,2)根据现场要求计划投入4台上述外用吊篮就以满足施工要求。这样既可以满足流水作业,亦能保证施工进度要求。4.2施工工具壁纸刀、电锤、手持式电动搅拌抹子、角抹子、靠尺、刷子、灰浆托板、拉线、米尺、毛辊、手锤、钳子、电热丝切割器、开槽器等。5工艺流程基层清理→吊铁丝顺直线(间距1.5m)→根据顺直线打20mm厚灰饼(间距1。5×1.5m)→配制1:3水泥砂浆→水泥砂浆找平层施工→拌制粘结聚合物砂浆(胶粉聚苯颗粒保温砂浆)→粘贴45厚(20厚)聚苯板→部分造型梁顶面及侧面抹20厚胶粉聚苯颗粒保温砂浆→细部处理→钻孔安装固定件→挤塑板打磨、找平、清理→中间验收→拌制面层聚合物砂浆→刷一遍界面剂→抹3~5厚抹面胶浆中间压入耐碱玻纤网格布→分格缝内填塞内衬、封密封胶→验收5。1基层处理5.1。1清理混凝土墙面上残留的浮灰脱模剂油污等杂物及抹灰空鼓部位等。5。1.2剔除剪力墙接槎处劈裂的混凝土块、夹杂物、空鼓等,并重新进行修补;外墙各种洞口填塞密实.5。2吊顺直线5.2。1选择无风的好天气在女儿墙顶间距1.5米吊铁丝线,并做好墙面2cm的顺直控制线,并在中间适当位置固定以防止线太长因风吹误差过大。5。2.3乘坐吊笼自上而下打灰饼,间距1.5×1.5m.5.3配制水泥砂浆5.3.1施工时用砂浆搅拌机搅拌1:3的水泥砂浆。搅拌时间不少于2in搅拌必须充分均匀稠度适中。5。3。2水泥砂浆搅拌应随拌随用,并应在3h内用完。5.4水泥砂浆抹灰施工水泥砂浆拌制后应自上而下分段抹灰施工,要求抹牢,应无明显抹纹。施工过程中不得垂直交叉作业,严禁自下而上作业以防止施工过程中污染已施工完毕的墙体。抹灰24小时后检查是否有空鼓现象.如有超过200c㎡空鼓,应及时处理。抹灰后的墙体平整度应控制在3㎜以内(2米范围内)。并要求阴阳角方正、上下通顺。5。5配制粘结砂浆5.5.1施工使用的砂浆分为专用粘结砂浆、胶粉聚苯颗粒保温砂浆及面层聚合物抗裂砂浆。5.5.2施工时可用砂浆搅拌机或用手持式电动搅拌机搅拌,拌制的粘结砂浆重量比为水:砂浆=1:5边加水边搅拌搅拌时间不少于5in搅拌必须充分均匀稠度适中,并有一定黏度。5.5。3砂浆调制完毕后须静置5in使用前再次进行搅拌拌制好的砂浆应在1h内用完。5。6排版5.6。1外墙部分粘贴保温板的墙体和门窗洞口必须严格按要求进行排版粘贴保温板.洞口四角处的聚苯板应采用整块聚苯板切割成型,不得拼接。接缝距四角距离应大于200㎜,且必须有锚固措施。(如图1)5.6.2聚苯板下料按照事先排好的尺寸切割挤塑板(电热丝切割器或壁纸刀切割)从拐角处垂直错缝连接,要求拐角处沿建筑物全高顺直、完整.保温板转角排板施工如图2。5。7粘贴聚苯板施工5。7。1聚苯板施工采用点框粘法粘贴聚苯板施工.5.7。2样板墙施工由监理单位和总包单位指定某一基面处理完成的楼层作为样板层交与外保温单位进行样板层施工挤塑板的粘贴应从细部节(如飘窗阳台挑檐及阴阳角部位开始向中间进行施工时要求在建筑物外墙所有阴阳角部位沿全高挂通线控制其顺直度(注:保温施工时控制阴阳角的顺直度而非垂直度,并要求事先用墨斗弹好底边水平线及100mm控制线,以确保水平铺贴,在区段内的铺贴应由下向上进行。5.7.3大面积施工5。7.1样板墙粘贴完毕经监理(建设)单位验收合格后方可进行大面积粘贴挤塑板施工。大面积保温板的施工顺序为自下而上,从角部开始粘贴,粘贴时要保证粘贴的质量尤其是要保证打灰的质量,要严格按照点框粘接要求施工。5。7。2胶粉聚苯颗粒保温砂浆施工在聚苯板粘贴施工的同时应按图纸要求穿插施工造型梁顶部、侧面,空调板顶部、飘窗板顶部、非采暖与采暖空间隔墙等部位的胶粉聚苯颗粒保温砂浆施工。5.8施工要点5。8.1粘贴聚苯板前应对墙体做粘贴试验,试测按下述方法进行:用外保温系统胶粘剂粘贴聚苯板,5分钟后取下,并重新贴回原位,若仍能用手揉动即为合格,否则表明基层过干或吸水性过高。eq\o\ac(○,1)对于基层墙体过干的应喷水润湿。施工过程中不可过量喷水,不得向墙面泼水.eq\o\ac(○,2)对于潮湿或吸水性过高影响粘结强度和施工的基层必要时可涂刷界面剂或抹专用砂浆。5。8。2粘贴聚苯板的板缝应挤紧,相邻板应齐平,施工时控制板间缝隙不得大于1.6板间高差不得大于1.0mm当板间缝隙大于1.6m时须用挤塑板条将缝塞满,板条不得用砂浆或胶结剂粘结;板间平整度高差大于1.0mm的部位应在施工面层前用木锉、粗砂纸或砂轮打磨平整.5。8。3用抹子在每块挤塑板周边涂50mm宽专用聚合物粘结砂浆,要求从边缘向中间逐渐加厚最厚处达10m并应在挤塑板的下侧留设50mm宽的槽口,以利于贴板时将封闭在板与墙体间的空气溢出.然后再在挤塑板中间部位均匀布置8个粘接点,每点直径不小于140mm,胶厚10mm,中心间距200mm,如图3所示。当采用非标准尺寸的聚苯板时,板面中间部位涂抹的胶粘剂一般为4~6个点.采用点框粘法胶粘剂的涂抹面积与聚苯板面积之比不得小于40%。5.8.4胶粘剂应涂抹在聚苯板上,而不是涂抹在基层墙体上,聚苯板涂胶后应及时粘贴,粘贴时应轻柔滑动就位,不得局部用力按压,造成板面受力不均而变形。聚苯板对头拼缝应挤紧,并与相邻板面齐平,胶粘剂的压实厚度宜控制在3~5mm,粘贴好后应立即刮除板缝和板侧面残留的胶粘剂。5。8。5聚苯板的施工应有勒脚部位开始(距室外散水上表面20mm),自下而上,沿水平方向铺贴,竖缝应逐行错缝1/2板长,板件高差不得大于1.0mm,否则应打磨平整后方可粘贴下一层。5。8.6对于门窗口内壁粘贴聚苯板的部位,其厚度应视门窗框与洞口间隙大小而定,一般不宜小于20mm。5。9特殊部位施工5.9。1防火隔离带的设置施工eq\o\ac(○,1)为了提高防火功能,粘贴聚苯板体系中应采取防火隔离措施.即每三层楼做一道通长连续(包括山墙)的防火隔离带,防火隔离带的高度为窗上口至上一层楼板标高处。防火隔离带分别设置在三(六、九、十二、十五、十八、二十一、二十四)层窗顶至上一层的楼板处,高度为500mm.防火隔离带的示意图如图4所示.eq\o\ac(○,2)防火隔离带部位可采用岩棉板或胶粉聚苯颗粒.5.9.2洞口加强网格布设置施工在门窗洞口等位置预先粘贴板边翻包网格布将不小于250mm宽的网格布中的100mm宽用专用粘结砂浆牢固粘贴在基面上(粘结砂浆厚度不得超过2,甩出150㎜后期粘贴挤塑板时再将网格布翻包过来.并沿门窗洞口四角450方向增贴300㎜×400㎜的附加耐碱网布。(如图5)5。9.3在保温工程施工过程中对装饰线条的施工应严格要求。对装饰线条部位应加强处理,处理方法如图7。图5洞口网格布加强图图6防火隔离带示意图5。9。4在聚苯板粘贴施工的同时应按图纸要求对女儿墙顶部、飘窗板顶部、窗台等有排水要求的部位进行找破,坡度不小于2%.5。10锚固件安装挤塑板粘结牢固后应在24h后开始安装固定件锚固件锚入基层墙体深度为50m(有抹灰层时5.11抹面层施工5。11.1涂料饰面时抹面胶浆压入耐碱网布eq\o\ac(○,1)将2~3厚抹面胶浆均匀抹在保温层表面上(面积应略大于一块网格布的范围),立即将裁好的耐碱网布用铁抹子压入抹面胶浆内,(玻纤网弯曲面应朝向墙面)待胶浆干硬至可碰触时,再抹上第二道抹面胶浆,直至全部覆盖玻纤网(不得露网),使玻纤网处于两道胶浆的中间位置,抹面胶浆总厚度为3~5㎜。eq\o\ac(○,2)洞口加强网的施工应同上一起施工,加强网的放置详图如图1。eq\o\ac(○,3)首层应铺贴双层耐碱网布,第一层耐碱网布对接,第二层搭接(第二层网格布采用加强型),两层耐碱网布之间抹面胶浆应饱满。eq\o\ac(○,4)在首层墙面阳角处设2m高的专用金属护角,护角应夹在两层耐碱网布之间。其余楼层阳角处两侧耐碱网布双向绕角相互搭接,各侧搭接宽度不小于200㎜。5.12质量控制5.12。1主要控制项目eq\o\ac(○,1)本系统所使用的所有材料质量和技术性能均应满足有关国家标准,行业标准及本规程的要求,应检查出厂合格证或进行复检。eq\o\ac(○,2)保温层的厚度及构造做法应符合建筑节能设计要求,保温层厚度应均匀,不允许有超规程的正负偏差。eq\o\ac(○,3)保温层与基层墙体以及各构造层之间必须粘结牢固,无脱层,空鼓,裂缝.5.12。2一般控制项目eq\o\ac(○,1)表面平整,洁净,接茬平整,无明显抹纹,无露网现象,线角应顺直,清晰,面层无起皮,爆灰等现象。eq\o\ac(○,2)底层外墙阳角需作护角,基余各层阴角,阳角以及门窗洞口四角等部位均需用网格布加强.eq\o\ac(○,3)墙面埋设暗线,管道后,墙面用网格布和抗裂浆加强,表面抹灰平整。eq\o\ac(○,4)分格缝宽度与深度均匀一致,平整光滑,棱角整齐,顺直,滴水线(槽)流水坡向正确,且顺直。6人力资源管理6.1现场配备项目经理一名,施工队长一名,技术主管一名,技术员6名,质检员1名,并对质检员、技术员明确分工,落实楼号,责任到人。并建立质量管理体系,本着预案在先,样板开路,过程控制,一次成优的原则进行施工。6。2在施工前应对班组做到先交底后施工,先培训后上岗的原则。7安全生产保证措施7。1建立安全管理制度7.1.1建立,健全各级部门的安全生产责任制,责任落实到人。eq\o\ac(○,1)新进工人必须进行公司、项目和班组的三级教育。eq\o\ac(○,2)工人变换工种,须进行新工种的安全技术教育。eq\o\ac(○,3)工人应掌握本工种操作技能,熟悉本工种安全操作规程.7.1.2安全检查eq\o\ac(○,1))必须建立定期安全检查制度,有时间、有要求、明确重点部位、危险岗位.eq\o\ac(○,2))安全检查有记录,对查出的隐患应及时整改,做到定人、定时间、定措施。eq\o\ac(○,3)班组"三上岗,一讲评"活动班组在班前须进行上岗交底,上岗检查,上岗记录的"三上岗"和每周一次的"一讲评”安全活动。对班组的安全活动,要有考核措施。eq\o\ac(○,4)检查安全帽、安全带、安全绳的正确佩戴使用情况,对发现有违规操作的工人要及时的说服教育,如发现有多次说服教育不听的应及时清场处理。7。1.
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 血糖检测护理查房
- 肺部感染的护理措施
- 2026主治医师(中级)-中医骨伤科学(中级)328历年题库含答案详解
- 2026临床医学期末复习-皮肤性病学(本临床教改)历年题库含答案详解
- 2026临床“三基”-医学临床三基(放射学)历年题库含答案详解
- 2026中级数控铣工(官方)-判断题参考试题库历年考点答案详解
- 2026中级会计-中级会计实务(官方)-第七章资产减值参考试题库历年考点答案详解
- 2026中国人身保险从业人员资格考试(A9寿险公司人力资源管理)历年参考题库含答案详解
- 2026中医催乳师-理论知识考试历年参考题库含答案详解
- 2026上海市公务员考试(行政职业能力测验)历年参考题库含答案详解
- 第2课 俄国的改革 课件
- 眼科疾病诊疗技术新进展与挑战
- 高校实验室建设项目投标文件
- 创伤性心搏骤停心肺复苏救治专家共识(2025版)完整版 + 损伤控制操作路径
- 2026北京市市政工程设计研究总院有限公司校园招聘笔试历年参考题库
- T∕AOPA 0086-2025 T∕CMSA 0058-2025 低空飞行器起降场地气象监测系统建设要求
- 标准预防知识培训课件
- GA/T 2342-2025车辆管理所场地设置规范
- 《规模化公猪站常温精液生产全过程质控技术规范》征求意见稿
- GB/T 6109.17-2025漆包圆绕组线第17部分:180级自粘性直焊聚酯亚胺漆包铜圆线
- 2025年中级消防题库试卷及答案
评论
0/150
提交评论