Chapter6:
ProjectTimeManagementChapter6:
ProjectTimeManagementImportanceofProjectSchedulesPlanningScheduleManagementDefiningActivitiesSequencing
ActivityEstimatingActivityResourceEstimating
ActivityDurationDevelopingtheScheduleControllingtheScheduleUsingSoftwaretoAssistinTimeManagement3ImportanceofProjectSchedulesManagersoftencitedeliveringprojectsontimeasoneoftheirbiggestchallenges.Perhapspartofthereasonscheduleproblemsaresocommonisthattimeiseasilyandsimplymeasured.Scheduleissuesarethemainreasonforconflictsonprojects,especiallyduringthesecondhalfofprojects.Timehastheleastamountofflexibility;itpassesnomatterwhathappensonaproject.4OnedimensionoftheMeyers-BriggsTypeIndicatorfocusesonpeoples’attitudestowardstructureanddeadlineSomepeopleprefertofollowschedulesandmeetdeadlineswhileothersdonot(Jvs.P)DifferenceculturesandevenentirecountrieshavedifferentattitudesaboutschedulesIndividualWorkStylesandCulturalDifferencesCauseScheduleConflicts5ProjectTimeManagementProcessesPlanningschedulemanagement:determiningthepolicies,procedures,anddocumentationthatwillbeusedforplanning,executing,andcontrollingtheprojectscheduleActivitydefinition:
Identifyingthespecificactivitiesthattheprojectteammembersandstakeholdersmustperformtoproducetheprojectdeliverables.Activitysequencing:Identifyinganddocumentingtherelationshipsbetweenprojectactivities.Activityresourceestimating:
Estimatinghowmanyresources
aprojectteamshouldusetoperformprojectactivities.Activitydurationestimating:
Estimatingthenumberofworkperiodsthatareneededtocompleteindividualactivities.Scheduledevelopment:
Analyzingactivitysequences,activityresourceestimates,andactivitydurationestimatestocreatetheprojectschedule.Schedulecontrol:Controllingandmanagingchangestotheprojectschedule.6ProjecttimemanagementsummaryChapter6:
ProjectTimeManagementImportanceofProjectSchedulesPlanningScheduleManagementDefiningActivitiesSequencing
ActivityEstimatingActivityResourceEstimating
ActivityDurationDevelopingtheScheduleControllingtheScheduleUsingSoftwaretoAssistinTimeManagement8PlanningScheduleManagementTheprojectteamusesexpertjudgment,analyticaltechniques,andmeetingstodeveloptheschedulemanagementplanAschedulemanagementplanincludes:ProjectschedulemodeldevelopmentTheschedulingmethodologyLevelofaccuracyandunitsofmeasureControlthresholdsRulesofperformancemeasurementReportingformatsProcessdescriptionsChapter6:
ProjectTimeManagementImportanceofProjectSchedulesPlanningScheduleManagementDefiningActivitiesSequencing
ActivityEstimatingActivityResourceEstimating
ActivityDurationDevelopingtheScheduleControllingtheScheduleUsingSoftwaretoAssistinTimeManagement10ActivityDefinitionAnactivityortaskisanelementofworknormallyfoundontheWBSthathasanexpectedduration,acost,andresourcerequirements.ActivitydefinitioninvolvesdevelopingamoredetailedWBSandsupportingexplanationstounderstandalltheworktobedone,soyoucandeveloprealisticcostanddurationestimates.Thegoaloftheactivitydefinitionprocessistoensurethattheprojectteamhadcompleteunderstandingofalltheworktheymustdo,ifmisunderstandingtheactivities,requestedchangesmayberequired.11ActivityListsandAttributesAnactivitylistisatabulationofactivitiestobeincludedonaprojectschedule.Thelistshouldinclude:TheactivitynameAnactivityidentifierornumberAbriefdescriptionoftheactivityActivityattributesprovidemoreinformationabouteachactivity,suchaspredecessors,successors,logicalrelationships,leadsandlags,resourcerequirements,constraints,imposeddates,andassumptionsrelatedtotheactivity.12MilestonesAmilestoneisasignificanteventthatnormallyhasnoduration.Milestonesareusefultoolsforsettingschedulegoalsandmonitoringprogress.Milestonesshouldbe:SpecificMeasurableAssignableRealisticTime-framedChapter6:
ProjectTimeManagementImportanceofProjectSchedulesPlanningScheduleManagementDefiningActivitiesSequencingActivityEstimatingActivityResourceEstimating
ActivityDurationDevelopingtheScheduleControllingtheScheduleUsingSoftwaretoAssistinTimeManagement14Sequencing
ActivityInvolvesreviewingactivitiesanddeterminingdependencies.Adependencyorrelationshiprelatestothesequencingofprojectactivitiesortasks. Youmustdeterminedependenciesinordertousecriticalpathanalysis.15ThreeTypesofDependenciesMandatorydependencies:Inherentinthenatureoftheworkbeingperformedonaproject;sometimesreferredtoashardlogic.Discretionarydependencies:
Definedbytheprojectteam;sometimesreferredtoassoftlogicandshouldbeusedwithcarebecausetheymaylimitlaterschedulingoptions.Externaldependencies:Involverelationshipsbetweenprojectandnon-projectactivities.16TaskDependencyTypes17NetworkDiagramsAnetworkdiagramisaschematicdisplayofthelogicalrelationshipsamong,orsequencingof,projectactivities.Chapter6:
ProjectTimeManagementImportanceofProjectSchedulesPlanningScheduleManagementDefiningActivitiesSequencingActivityEstimatingActivityResourceEstimating
ActivityDurationDevelopingtheScheduleControllingtheScheduleUsingSoftwaretoAssistinTimeManagement19EstimatingActivityResourceBeforeestimatingactivitydurations,youmusthaveagoodideaofthequantityandtypeofresourcesthatwillbeassignedtoeachactivity.Considerimportantissuesinestimatingresources:Howdifficultwillitbetodospecificactivitiesonthisproject?Isthereanythinguniqueintheproject'sscopestatementthatwillaffectresources?Whatistheorganization'shistoryindoingsimilaractivities?Doestheorganizationhavepeople,equipment,andmaterialsthatarecapableandavailableforperformingthework?Arethereanyorganizationalpoliciesthatmightaffecttheavailabilityofresources?Doestheorganizationneedtoacquiremoreresourcestoaccomplishthework?Woulditmakesensetooutsourcesomeofthework?Chapter6:
ProjectTimeManagementImportanceofProjectSchedulesPlanningScheduleManagementDefiningActivitiesSequencingActivityEstimatingActivityResourceEstimatingActivityDurationDevelopingtheScheduleControllingtheScheduleUsingSoftwaretoAssistinTimeManagement21EstimatingActivityDurationDurationincludestheactualamountoftimeworkedonanactivityplustheelapsedtime.Effortisthenumberofworkdaysorworkhoursrequiredtocompleteatask.Effortdoesnotnormallyequalduration.Peopledoingtheworkshouldhelpcreateestimates,andanexpertshouldreviewthem.Oneofthemostimportantconsiderationsinmakingactivitydurationestimatesistheavailabilityofresources.Chapter6:
ProjectTimeManagementImportanceofProjectSchedulesPlanningScheduleManagementDefiningActivitiesSequencingActivityEstimatingActivityResourceEstimatingActivityDurationDevelopingtheScheduleControllingtheScheduleUsingSoftwaretoAssistinTimeManagement23DevelopingtheScheduleUsesresultsoftheothertimemanagementprocessestodeterminethestartandenddatesoftheproject.Ultimategoalofscheduledevelopmentistocreatearealisticprojectschedulethatprovidesabasisformonitoringprojectprogressforthetimedimensionoftheproject.Importanttoolsandtechniquesinclude:GanttchartsTrackingGanttChartMilestonesCriticalpathanalysisCriticalchainschedulingPERTanalysis24GanttChartProvidingastandardformatfordisplayingprojectscheduleinformationbylistingprojectactivitiesandtheircorrespondingstartandfinishdatesinacalendarformat.25SampleTrackingGanttChart26CriticalPathMethod(CPM)CPMisanetworkdiagrammingtechniqueusedtopredicttotalprojectduration.Acriticalpathforaprojectistheseriesofactivitiesthatdeterminestheearliesttimebywhichtheprojectcanbecompleted.Thecriticalpathisthelongestpaththroughthenetworkdiagramandhastheleastamountof
slackorfloat.Slackorfloatis
theamountoftimeanactivitycanbedelayedwithoutdelayingasucceedingactivityortheprojectfinishdate.27DeterminingtheCriticalPathforProjectX28UsingCriticalPathAnalysistoMakeScheduleTrade-offsFreeslackorfreefloat
Totalslackortotalfloat
Aforwardpassdeterminestheearlystartandfinishdates.Abackwardpassdeterminesthelatestartandfinishdates.29FreeandTotalFloatorSlackforProjectX30UsingtheCriticalPathtoShortenaProjectScheduleThreemaintechniquesforshorteningschedules:Shorteningthedurationofcriticalactivitiesortasksbyaddingmoreresourcesorchangingtheirscope.Crashing
activitiesbyobtainingthegreatestamountofschedulecompressionfortheleastincrementalcost.Fasttrackingactivitiesbydoingtheminparalleloroverlappingthem.Crashingandfasttrackingoftencausemoreproblems,resultinginlongerschedules.31ProgramEvaluationandReviewTechnique(PERT)PERTisanetworkanalysistechniqueusedtoestimateprojectdurationwhenthereisahighdegreeofuncertaintyabouttheindividualactivitydurationestimates.PERTusesprobabilistictimeestimates:Durationestimatesbasedonusingoptimistic,mostlikely,andpessimisticestimatesofactivitydurations,orathree-pointestimate.PERTweightedaverage=
optimistictime+4Xmostlikelytime+pessimistictime 6Chapter6:
ProjectTimeManagementImportanceofProjectSchedulesPlanningScheduleManagementDefiningActivitiesSequencingActivityEstimatingActivityResourceEstimatingActivityDurationDevelopingtheScheduleControllingtheScheduleUsingSoftwaretoAssistinTimeManagement33ControllingtheScheduleGoalsaretoknowthestatusoftheschedule,influencefactorsthatcauseschedulechanges,determinethattheschedulehaschanged,andmanagechangeswhentheyoccur.Toolsandtechniquesinclude:ProgressreportsAschedulechangecontrolsystemAschedulingtooland/orprojectmanagementsoftware,suchasProject2007orsimilarsoftwareSchedulecomparisonbarcharts,suchastheTrackingGanttchartVarianceanalysis,suchasanalyzingfloatorslackWhat-ifscenarioanalysis,whichcanbedonemanuallyorwiththeaidofsoftwareAdjustingleadsandlagsSchedulecompression,suchascrashingandfast-tracki
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2026事业单位工勤技能-江苏-江苏水工闸门运行工一级(高级技师)历年参考题库含答案详解3套试卷
- 2026事业单位工勤技能-江苏-江苏土建施工人员四级(中级工)历年参考题库含答案详解3套试卷
- 2026事业单位工勤技能-新疆-新疆无损探伤工五级(初级工)历年参考题库含答案详解3套试卷
- 2026事业单位工勤技能-新疆-新疆保安员二级(技师)历年参考题库含答案详解3套试卷
- 2026事业单位工勤技能-天津-天津工勤技能(公共科目)历年参考题库含答案详解3套试卷
- 肠镜检查健康指导总结
- 加压调蓄供水设施设备改造及庭院供水管道改造项目可行性研究报告模板-备案审批
- 2026年秋季开学初三学长寄语动员大会课件
- 2026年秋季开学大学一年级新生军训摄影展览活动课件
- 云南省迪庆藏族自治州香格里拉县2025-2026学年十校联考最后数学试题含解析
- 2027届高三语文一轮复习:高中文言文挖空训练
- 2026年安徽省池州市公安辅警招聘知识考试题(含答案)
- 2026年节能、高效脱水设备行业十年转型趋势报告
- 异位妊娠测试题及答案
- 煤气加压站安全管理与操作规范培训
- 2026年电气工程专业《中级职称》考试(含答案)(题库)
- 徐工25吨吊车使用说明书
- 气管切开术后并发症预防
- (2026版)《国家发展改革委企业技术中心认定管理办法》学习与解读课件
- 晶体缺陷调控方法-洞察与解读
- 单位采购付款管理制度
评论
0/150
提交评论