PAGEPAGE16恩阳·首座2#、3#楼砖砌体工程专项施工方案编制人:审核人:编制单位:中齐齐齐建设工工程有有限公司司编制时间:二二二○一七年三三月月八日目录一、编制依据及及及说明························································33编制说明·····························································3编制依据·······························································33二、工程简介································································331、参建单位·······························································32、工程概概况·····························································333、各部位材料料料要求······················································4三、施工准备································································55材料准备·······························································55机具准备·······························································55人力准备·······························································55技术准备·······························································66四、施工工艺··································································6工艺流程·······························································66施工工艺·······························································66五、施工要点··································································71、墙肢部位11100砖施工方方法··············································72、墙底部、丁丁字字墙和转角角角墙的砌砌筑方方法································883、梁下口砌体体体的接触部部位位砌筑方方法·····································994、墙体拉结筋筋筋的设置······················································995、有防水功能能能要求的房房间间砌筑方方法·····································1126、构造柱的设设设置··························································1137、女儿墙砌筑筑筑大样图······················································115六、质量控制措措措施··························································1171、材料控制···································································1772、砌体灰缝控控控制····························································1773、砌体的平整整整度和垂直直度度控制···········································1884、砂浆饱满度度度的控制······················································1185、砖砌体一般般般尺寸允许许偏偏差值···········································1886、砖砌体的砂砂砂浆饱满及及检检验方法········································1197、成品保护··································································198、砂浆组批原原原则及取样样要要求···········································200七、现场安全文文文明施工工注意意事项·······································2201、安全施工···································································2002、文明施工···································································200编制依据及说明明明一、编制说明本方案主要针对对对恩阳·首座2#、3#楼项目砌砌体体工程质质量、进进度编制制。二、编制依据1、建筑工程施施施工图纸及及建建筑、结结构施施工总说说明及及施工合合同。2、工程图纸会会会审纪要及及技技术核定定单。3、《混凝土结结结构轻质填填充充墙构造造图集集》(西南15G77001-33)4、《砌体工程程程施工质量量验验收规范范》GB5002203--200025、《建筑工程程程施工质量量验验收统一一标准准》GB5003300--200136、《墙体材料料料应用统一一技技术规范范》GB55005744-2201007、《混凝土结结结构后锚技技术术规程》JGJ1145--20013第二章工程简简简介(一)参建单位位位建设单位:巴中中中静州置置业有有限责任任公司司;设计单位:深圳圳圳市物业业国际际建筑设设计有有限公司司;监理单位:中科科科标禾工工程项项目管理理有限限公司;;施工单位:中齐齐齐建设工工程有有限公司司;(二)工程概况况况3#楼建筑面积积::约3120022.011㎡,总总高度93米、层数数为为地上31层,地下2层,建筑工工程程安全等等级为为二级。抗抗震震设防烈烈度为为六度。耐耐火火等级为为一级级,建筑筑耐久久年限为50年。屋面面防防水等级级为I级;地下下::设备房房一级级,其它它部位位二级。本本工工程结构构采用用钢筋混混凝土土剪力墙墙结构构,基础础采用用防水板板、独独立基础础型式式。2#楼建筑面积积::163333.117㎡㎡,总高高度15.115米、层数数为为地上3层,地下1层,建筑工工程程安全等等级为为二级。抗抗震震设防烈烈度为为6度一组。耐耐耐火等级级为二二级,建建筑耐耐久年限限为50年。屋面面防防水等级级为Ⅱ级,一道道防防水设防防;本本工程结结构采采用框架架结构构,基础础采用用防水板板、独独立基础础型式式。(三)各部位材材材料要求求1、2#楼墙体体工程、墙墙体体技术要要求(1)、外围护护墙墙、卫生间间间采用200厚页岩多多孔孔砖,用M5水泥砂浆浆砌砌筑;电电梯隔隔墙(非非钢筋筋混凝土土墙处处)、设设备间间、水电电管井井墙体为为页岩岩实心砖砖,其其他墙体体采用用100、200厚页岩空空心心砖,其其余地地上部分分的内内隔墙为100、200厚页岩空空心心砖,用M5混合砂浆浆砌砌筑;地地下部部分内隔隔墙采采用200厚页岩多多孔孔砖砌体体,用用M5水泥砂浆浆砌砌筑。(2)、预留洞洞的的封堵:砌砌砌筑墙留留洞待待管道设设备安安装完毕毕后,用C25细石混凝凝土填实。(3)、无窗台台板板的外墙在在在窗台处处浇筑筑C25混凝土100厚(内配纵向2C6钢筋C6拉钩@200)两端伸伸入入墙内不不小于于250。(5)、门窗洞洞口口四周采用用用页岩实实心砖砖砌筑。2、3#楼墙体体工程、墙墙体体技术要要求(1)本工程主主要要墙体材料料料的选用用:地下:地下室部部部分详见见地下下车库施施工图图(后期期设计计出图),无无地下室部分分±0.00以下墙体均均采用页岩实实心砖。地上:外墙、分分分户墙、厨厨房房、卫生生间、电电梯井道道隔墙墙采用页页岩多多孔砖,其其他他墙体为为页岩岩空心砖砖砌体体。(2)填充墙材材料料:a、外隔墙、卫卫卫生间、厨厨房房隔墙采采用强强度等级MU10页岩多孔孔砖砖其余内内隔墙墙采用强强度等等级MU5页岩空心心砖砖。b、砌筑砂浆:::±0.00000以下用M5水泥砂浆浆,±0.00000以上用M5混合砂浆浆。c、无窗台板的的的外墙在窗窗台台处浇筑100厚、同墙墙宽宽的C25钢筋混凝凝土土压顶(配筋:纵向2C6、拉钩C6@22000),两端伸伸入入墙内不不小于于250。d、与填充砌体体体连接的GZ在砌体砌砌筑筑完成后后浇筑筑混凝土土,接接缝处砌砌体留留马牙磋磋。e、梁、板下部部部有构造柱柱时时,在与与构造造柱对应应位置置的梁、板板下下部预埋埋钢筋筋,数量量和直直径同构构造柱柱纵筋。构构造造柱平面面布置置图(详详附图图)。第三章施施施工准备一、材料准备材料要求:砌体体体所用砖砖体材材料其龄龄期应应超过28天,进场场后后按品种种、规规格分别别堆放放整齐。材材料料尺寸误误差在在规范允允许范范围以内内,误误差较大大的不不允许采采用。砖砖砌体砌砌筑前前应提前前浇水水湿润。各各种种砖的品种种、规规格、强强度必必须符合合设计计要求,有有出出厂合格格证、进进场试验验报告告。二、机具准备应配备砂浆搅拌拌拌机、磅磅秤、手手推车、垂垂直直运输设设备、卷卷尺、检检测尺尺、水平平尺、托托线板、线线坠坠、瓦刀刀、白白线、灰灰桶、扫扫帚等。三、人力准备泥工班组必须根根根据进度度要求求组织好好劳动动力,应应配备备技术水水平较较高的技技术工工人,普普工应应与技工工配置置适当。一一个个班组技技术工工人不少少于15人,对各各班班组每日日完成成工作量量进行行控制,在在保保证施工工进度度的前提提下必必须确保保工程程质量。四、技术准备1、砌体施工前前前,项目部部应应对砌体体施工工图进行行仔细细审阅,形形成成技术交交底并并逐层交交底下下去。对对于图图纸上的的疑问问应提前前与甲甲方、监监理、设设计院进进行沟沟通。2、对具有施工工工难点的部部位位,施工工人员员要认真真向技技术负责责人、甲甲方、设设计院院进行询询问,以以确定具具体做做法。禁禁止擅擅自采用用违反反操作规规程、方方案及技技术交交底要求求的施施工方法法。第四章施工工工工艺工艺流程施工准备→放线线线→砖预排模模数数→砌体砌筑筑→梁底斜砖砖补补砌→浇筑构造造柱柱施工工艺1、在砌筑前应应应先进行场场地地清理,并并浇浇适量水水进行行湿润。在在拌拌制砂浆浆的时时候,为为了增增加砂浆浆的和和易性,可可在在拌制过过程中中掺入适适量外外加剂。2、在材料准备备备完毕后预预先先用干砖砖进行行预排模模数。砌砌块砌筑筑时,应应采用“三一”砌筑方法法,即即“一块砖、一一一铲灰、一一揉揉压”。3、砌块垂直、水水水平灰缝缝厚度度严格照照规范范要求,砂砂浆浆饱满度度应超超过80%。4、填充墙采用用用错缝搭砌砌,在在砌体砌砌筑200墙每500MMM高时设置2A6.5拉结筋一一道道(第一一道拉拉结筋为430mmm高),100墙每500MMM高时设置2A6.5拉结筋一一道道。拉结结筋锚锚入砖墙700MMM,端部设90°弯钩。5、砌体砌筑至至梁梁底或板底底底时,应应留200mm高的空隙隙,等等砌体收收缩稳稳定后(一一般般为7天)再用用实实心砖斜斜砌挤挤紧,并并用砂砂浆填实实。6、在墙体墙长长长大于5M及室外约约束束支座处处均应应设置构构造柱柱。在遇遇到构构造柱的的位置置时,应应砌筑筑成马牙牙槎形形状,并并清理理干净槎槎内砂砂浆,等等砌体体收缩稳稳定后后再支模模浇筑筑混凝土土。构构造柱砼砼应采采用插入入式振振捣,但但应避避免振动动棒与与砌体接接触。构构造柱钢钢筋均均采用主主体结结构时预预留和和植筋技技术,设置4C12主筋,箍箍筋为C6.55@2000,上部锚入入梁底部,形形成一个整整体。7、砌筑时每层层层砖均应拉拉水水平线,随随砌砌筑高度度而上上升,以以控制制灰缝的的水平平度。8、墙体各种预预预留洞、预预埋埋件等,应应按按设计要要求留留置,避避免事事后剔凿凿。第五章施工要要要点一、墙肢部位砌砌砌100砖垛施工工方方法由于个别设置在在在门洞口口处的的砖垛较较小,在在今后房房屋使使用过程程中,经经常开关关门对对砖垛的的稳定定性是一一个考考验。根根据这这一个特特点,我我们采用用页岩岩砖砌筑筑,由由于砖垛垛不能能错缝搭搭砌,所所以每隔500mmm高在墙肢肢上上植2C6..5拉结筋。在在在砌筑时时要保保证砂浆浆的强强度,特特别是是砖砌体体在与与砼接触触部位位灰缝的的饱满满度(如如下图图)。二、墙底部、丁丁丁字墙和和转角角墙的砌砌筑方方法墙底部应砌烧结结结普通砖砖其高高度不宜宜小于于180mmm。丁字字墙和墙墙体转转角的交交接处处若特殊殊情况况没有设设置构构造柱时时应交交错搭砌砌,如如错缝长长度不不能满足1/3砖,且不不小小于150mmm时,竖向向每400mmm应设置2Φ6拉结钢筋筋,每每边伸入入墙内内不小于10000mmm并设180°弯钩。三、梁下口砌体体体的接触触部位位的砌筑筑方法法由于砂浆的收缩缩缩性,如如果一一次性砌砌筑至至梁底,以以后后砖砌体体与梁梁下口会会形成成一条水水平裂裂缝。所所以我我们要求求在填填充墙砌砌筑至至梁底的的时候候,应留留一定定的空隙隙,待待填充墙墙砌筑筑完后至至少应应间隔7天,再用用页页岩实心心砖斜斜砌挤紧紧,在在补砌时时,要要求砂浆浆一定定要饱满(详下图)。四、墙体拉结筋筋筋的设置置1、施工工艺:::定位钻钻孔清孔钢筋除锈植筋胶配配料植筋固化保护检查验收收2、施工要求砌体主要作填充充充、隔断断作用用,因此此在拉拉结筋设设置多多数是一一边锚锚入砼内内,一一边锚入入砌体体内。在在没有有预埋拉拉结筋筋的情况况下,我们采用用植植筋技术术。采采用电钻钻在砼砼中每隔500mmm间距的位位置置钻2个孔,并用小型型空空压机把把孔内内的灰尘尘吹干干净,植筋筋材材料为圆圆钢,按按要做规规格预预先进行行下料料,并按按要求求留搭接接,按按50%钢筋错错位位搭接,注注胶胶后立即即种植植筋钢筋筋,将将钢筋按按顺时时针的方方向缓缓慢旋进进孔内内,确保保植入入深度,留留有有足够的的时间间粘合剂剂固化化。做完完每到到工序,必必须须经甲方方及监监理检查查验收收合格后后才能能进行下下道工工序施工工。3、质量要求⑴钻孔质量①主控项目(1)钻孔孔径径符符合设计要要要求及有有关规规定。(2)钻孔内应应清清理干净,无无粉尘;植筋筋胶产品要求求孔道干燥的的要保持孔道道干燥。②一般项目(1)钻孔位置置应应符合设计计计(构造造)要要求和砌砌块模模数。(2)钻孔深度度允允许偏差为为为(+200mmm,0mm),水水平度允允许偏偏差为5mmmm,位置允允许许偏差为为5mmm。⑵拉结筋“植筋筋筋法”施工质量量①主控项目(1)植筋胶质质量量应符合要要要求。拉拉结筋筋无锈蚀蚀,表表面无杂杂质。(2)钻孔内植植筋筋胶应饱满满满,固化化良好好,拉结结筋要要锚牢锚锚实。②一般项目(1)拉结筋的的位位置、尺寸寸寸、弯钩钩、间间距应符符合设设计或构构造要要求。(2)拉结筋施施工工质量应符符符合设计计或规规范要求求。3.抗拔试验植筋4888小时后即即可可达到强强度要要求,请请有资资质的检检测单单位对植植筋情情况进行行现场场抗拔抽抽检,抗抗拔力要要求在在钢筋的的设计计强度以以上为为植筋锚锚固合合格。植植筋抽抽检数量量按每每组/30000根。按每每一一个部位位,每每种规格格均分分别抽检检。4、成品保护⑴加强成品保护护护交底教育育。⑵结构表面拉结结结筋位置定定位位弹线后后和钻钻孔、清清孔完完成后要要严禁禁人为污污染。⑶加工好的拉结结结筋要架起起存存放,上上方要要有挡雨雨设施施,存放放地要要通风防防潮良良好,防防止锈锈蚀。⑷配胶搅拌时要要要均匀搅拌拌,防防止胶液液从容容器中溅溅出,造造成结构构成品品污染。⑸注胶时要控制制制好胶液的的注注入量,防防止止注入过过多,致致使植入入拉结结筋时挤挤出的的胶液过过多,污污染结构构表面面。⑹拉结筋在植筋筋筋完成后,植植筋胶固化前前防止扰动和和人为碰撞。⑺填充墙砌体施施施工前,拉拉结结筋不得得进行行任意弯弯折、拆拆卸。五、有防水功能能能要求的的房间间砌筑方方法1、卫生间、厨厨房房等用水房房房间四周周的非非钢筋混混凝土土墙体在在墙根根处浇筑200高C20混凝土止止水水导墙,厚厚度度同墙厚厚。(详详下图)2、砌筑时灰缝缝缝砂浆饱满满,避避免形成成假缝缝影响防防水质质量。六、构造柱的设设设置1、构造柱的设设设置按设计计图图纸进行行布置置,填充充墙长长度>5m时在墙中中部部设置构构造柱柱,构造造柱间间距不大大于20倍墙厚且且不不大于4m。构造柱柱的的位置的的砌体体应砌筑筑成马马牙槎状状,并并清理干干净槎槎内的砂砂浆及及其他杂杂物。留留槎的部部位采采用页岩岩砖砌砌筑,构构造柱柱钢筋采采用植植筋预留留钢筋筋技术。(如如图一)图一构造柱大样图2、过梁、腰带带带的设置(1)门、窗洞洞过过梁,当跨跨跨度<2.11m时按西南15G77001-3,过梁按按荷荷载等级1级选用,过过过梁宽度度同墙墙厚。(2)填充墙高高度度>4m时,半层层高高处或门门窗上上口设通通长过过梁,梁截截面面为墙厚×100mm,配筋46@200圈梁钢筋筋锚锚入两端端柱内内。填充墙墙高高度>6m时,沿墙高高每2m设置现浇浇腰腰带(详下图)。七、女儿墙砌筑筑筑大样图图(一)2#楼女女女儿墙大大样图图(二)3#楼女女女儿墙大大样图图第六章质量控控控制措施施材料控制1、现场采用原原原材料必须须是是满足28天后的产产品品,进场场后抽抽样送检检,合合格后方方可用用于施工工。2、拌制砌筑砂砂砂浆:现场场采采用砂浆浆搅拌拌机拌合合砂浆浆,严格格按照照配合比比配制制。3、砂浆配合比比比用重量比比,计计量精度度为::水泥±2%、砂及掺掺合合料±5%。4、体砌筑244小小时后浇水水水养护保保证砂砂浆强度度。二、砌体灰缝控控控制砌体必须做到横横横平竖直直、砂砂浆饱满满、接接槎合理理、灰灰缝一致致。页页岩空心心砖灰灰缝厚度度控制制在8~122mmm左右,所所有有墙体水水平灰灰缝平直直度控控制在8mm以内。在砌体施工时,每每皮砖均拉水水平线,随砌砌筑高度上升升控制灰缝的的水平直度。另另外在砌体上上弹出500mm或1000mmm线,砌筑时时随时用卷尺尺控制灰缝的的厚度,并用用广线检查灰灰缝的平直度度。三、砌体的平整整整度和垂垂直度度的控制制砌体的垂直度应应应随时用用吊线线锤复核核,当当墙体砌砌筑到到一定高高度时时应用2m托线板复复核核墙面垂垂直度度。墙体体表面面平整度度用靠靠尺随时时检查查,随砌砌随复复核。砌砌体垂垂直度控控制在在5mm以内,表表面面平整度度控制制在8mm以内。四、砂浆饱满度度度的控制制空心砖:水平灰灰灰缝饱满满度达达到80%以上,垂垂垂直灰缝缝填满满砂浆,不不得得有透明明,暗暗缝,假假缝等等。五、砖砌体一般般般尺寸允允许偏偏差应符符合下下表规定定:序号项目允许偏差(mmmm)检验方法1轴线位移10用尺检查2垂直度小于或等于3mmm5用2m托线板或或吊线线、尺检检查大于3m103门窗洞口高、宽宽宽(后塞塞口)±5用尺检查4外墙上下窗口偏偏偏移20用经纬仪或吊线线线检查六、砖砌体的砂砂砂浆饱满满度及及检验方方法应应符合下下表灰缝饱满度及要求检验方法水平灰缝≥80﹪用百格网检查砖砖砖底面砂砂浆的的粘结痕痕迹面面积垂直灰缝填满砂浆,不得得得有透明明缝、瞎瞎缝、假假缝第七、成品保护护护:1.预埋的拉结结筋筋应加强保保保护。2.手推车或平平板板车运输砖砖砖砌体时时,每每次装载载高度度应与车车身高高度一致致,应应平稳行行使,防防止碰撞撞墙体体,严禁禁用力力倒砖,破破坏坏砖棱角角。3.砌体材料料料运输、装装卸卸过程中中严禁禁抛掷和和倾倒倒。进场场后,要要按品种种、规规格分别别堆放放整齐,堆堆放放高度不不能超超过2m。4、砌体在墙上上上支撑

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论