ProjectManagementwithSAPR/3
TeachingMaterialfortheDepartmentof
ProductionManagement
ViennaUniversityofEconomicsand
BusinessAdministration
AndreasMild
AlfredTaudes
TOC\o"1-3"
1 Introduction
3
2 Basics&Keywords
4
3 Gettingreadyfortheworkshop
7
4 CaseStudy
13
4.1 Casedescription
13
4.2 DataforProjectRealization
14
5 Planningtheprojectstructure
15
5.1 General
15
5.2 ImplementationinSAP
17
6 Scheduling
26
6.1 General
26
6.2 Basiccalculations
29
6.3 Implementation
30
6.4 Theprojectplanningboard
41
7 Costplanning&Controlling
47
7.1 General
47
7.2 Implementation
48
8 Lookingupthecosts
61
9 CapacityPlanning
64
9.1 General
64
9.2 ImplementationinSAP
65
10 EarnedValueAnalysis
69
10.1 General
69
10.1.1 Measurementtechniques
69
10.1.2 CalculationofEarned-ValueandDeviationAnalysis
73
10.1.3 Aggregation
74
10.2 Implementation
74
11 Execution
77
11.1 Implementation
77
11.1.1 Confirmingnetworkactivities
77
11.1.2 Invoices
79
11.1.3 Material
83
12 InformationSystem
86
12.1 Implementation
86
12.1.1 Costreports
86
12.1.2 Earned-ValueAnalysis
92
13 Literature
98
Introduction
Thisscriptservesasabasisfortheworkshop"ProjectManagementwithSAPR/3".ThisworkshopispartofaseriesofSAP-relatedworkshopswhichareheldbytheDepartmentofProductionManagementoftheViennaUniversityofEconomicsandBusinessAdministration,headedbyProf.Dr.AlfredTaudes.TheworkshopwasdevelopedbyAndreasMild.
ThegoalofthisProjectManagementWorkshopisthat,afterhavingattendedit,eachstudentshouldbefamiliarwiththetheoreticalbackgroundsandbeabletoplanandcontrolaproject.Theprojectmanagerhasthetaskofensuringthattheprojectisexecutedefficiently,ontime,andwithinthebudget-whichhe/sheachievesbymakingcertainthattherequiredresourcesandfundsareavailablewhenneeded.Everystudentshouldthenbeabletoputhis/herSAPknowledgeintoaction.
Tomakethecontinuousimprovementofthisscriptpossible,pleasereportmistakesfoundorideasforfurtherdevelopmentto.
Basics&Keywords
SAPR/3isanintegratedandindustry-independentstandardsoftwarewhichcovers,integratesandconnectsallfunctionalareasinabusiness.SAPAGdefinesintegrationas"definedcommunication".AFOS(Hrsg.)SAPArbeit,Management.Braunschweig/Wiesbaden1996p.59
AlthoughR/3isdesignedforcompleteintegration,itcanalsobeusedforacoupleofbusinessareas.ComputerweltNo.13of13.3.1998,p.20
SAPistheabbreviationfor“Systeme,Anwendungen,Produkte”,theGermanwordsfor“Systems,Applications,Products”.AFOS(Hrsg.)SAPArbeit,Management.Braunschweig/Wiesbaden1996p.59
Informationaboutthecompanycanbefoundat:.
Projectsaretaskswithspecialcharacteristics.Attributesofaprojectarethefollowingissues:
complexity,non-repetitivity,highrisk
detailedgoalstobeachieved
timerestrictions
highcostandcapitalexpenditure
qualityrequirements
oftenstrategicsignificance
Tobeabletoplan,monitor,control,andcarryoutaprojectasawhole,theprojectgoalsmustbepreciselydescribedandtheactivitiestobeperformedhavetobestructured.
Aprojectcanbedescribedasfollows:
accordingtohowitisorganized,i.e.byexplainingtheprojectstructure,
accordingtotheprocessesinvolved.
Aprojectstartsoutasastatementofworkwhichiseitherawrittendescriptionoftheobjectivestobeachievedandthedesiredroughschedulelikestartandenddates.Inthedescriptiononecouldincludealsoperformancemetricsandbudgetconstraints.
Aprojectisfurthersubdividedintomeaningfulpieces,referredtoastasks.Taskstakeusuallylessthanafewmonths.Thetaskcanbefurthersubdividedintosubtasks.
Aworkpackagecanbedefinedas“agroupofactivitiescombinedtobeassignabletoasingleorganizationalunit.”ChaseR./AquilanoN./JacobsR.ProductionandOperationsManagement:ManufacturingandServices,p.48
Theprojecttasks,subtasks,andworkpackagesarebroughtintoahierarchybydefiningaworkbreakdownstructure.
Theindividualelementsrepresentactivitieswithintheworkbreakdownstructureandarecalledworkbreakdownstructureelements(WBSelements).
WBSelementscanbe:
tasks
partialtaskswhicharesubdividedfurther
workpackages
WBScanbestructuredaccordingto
object
function
phase
Whichkindofstructuringisuseddependsonthefocusoftheproject.Objectsorientationisoftenused,ifthemainpartoftheprojectisaphysicalobjectlikeapowerplant.Functionalorganisationispreferred,ifmanydifferentpartsofanorganisationormanyorganisationsareinvolved.
Inpractice,allthreekindsofstructuringareusedwithinoneWBS.
“ProjectManagementcanbedefinedasplanning,directing,andcontrollingresources(people,equipment,material)tomeetthetechnical,costandtimeconstraintsoftheproject.”ChaseR./AquilanoN./JacobsR.ProductionandOperationsManagement:ManufacturingandServices,p.48
Theprimaryreasonwhyprojectsfailisinsufficienteffortintheplanningphase.ChaseR./AquilanoN./JacobsR.ProductionandOperationsManagement:ManufacturingandServicesp.69
ProjectManagementthusisconsideredasveryimportant.
TheSAPProjectSystemenablescloseandconstantmonitoringofallaspectsofaprojectbyhavingconstantaccesstodatainallthedepartmentsinvolved.
Projectmanagementcanbesubdividedintoprojectplanning,i.e.thetaskwhichwillbeundertakenbeforetheprojectstarts,andprojectcontrollingduringtheimplementationoftheproject.Planningmustinclude:
organization–service
process–dates
costs
capacity
Therearemanypossibleprojectgoalssuchas,forexample,torealizeapositivenetpresentvalue,toachieveahighimputedinterest,tominimizecosts,tocovercosts,tomaximizegrossprofit,orsimplytofinishasearlyaspossible.However,itisimportant,thatgoalsaredefinedoperationally,thaitiswhenitispossibletomeasuretowhichextentthegoalhasbeenachieved.
Theprojectmanagerbreakstheprojectdownintoasetofactivities.Thenhealsodefinestherelationshipsamongtheseactivities.Theoutcomeisaguidelineregardingtheactivitiesthatcanbeperformedinparallelandthosethathavetobedoneinasequentialorder.Thistaskisdoneviaplanningbynetwork.
Now,thereareactivitiesthatrequirecapacitiesandresourceslikepersonnelandmaterial.Suchresourcesarelimitedandtheserequirementshavetobeconsideredinordertobeabletodevelopafeasible,soundplan.Informationfromothermodulesase.g.thematerialplanningmoduleisrequired.
Thesystemcalculatesthematerialrequirementsforeachstepoftheprojectandorganizesthatmaterialsareboughtintimetoavoiddelays.Whenpurchasingmaterial,thesystemtakesintoaccountordersizes,inventorypoliciesaswellasotherinformation.
Topreparethefinancialstatements,thevalueofworkinprogress(includingprojectwork)hastobecalculated.ThisalsorequiresinteractionofsomeR/3modules.
Thus,thesystemneedsinformationfromallbusinessareassimultaneously.Andthisisexactlywhatintegrationdoes.
TheprojectmoduleispartoftheintegratedconceptofSAPR/3providinginterfacestoothermoduleslikeAccounting,Distribution,MaterialManagementandProductionPlanningandControl.Eachareawithintheorganizationhasitsownstructureanditsownviewoftheproject,butdatahastobeenteredonlyonce.
Gettingreadyfortheworkshop
Thischapterprovidesinformationonthefirstuseofthesystem.
LoggingonR/3
Loggingoff
SAPR/3isaclient/serverapplication.Therefore,youhavetocanceltheconnectionwiththeserverbytellingitthatyouwanttologoff.
CreateSession
Oftenitisusefultoopenmorescreens.Youcandothisbycreatinganewsession,likeanewdocumentinawordprocessor.
SAPHelp
Ifyouwanttogetsomebasicinformationaboutaspecificfield,focusthisfieldwithyourmouseandpress<F1>.Thedialogboxindicateswhatthefieldisfor.Sometimesevendependenciesareexplained.
Matchcodes
Matchcodesareusefulforfindingdata,becauseitisdifficulttoknow/remembertheidentificationnumberofalinepositionsuchasamaterial.
Example:
Youwanttoeditthematerialmasterofamaterial.Youdon’tknowthenumber,butyouknowthatthematerialdescriptionstartswithsomethinglike“PM_”
IfyoupressF4yougetasearch-maskwhereyouareabletosearchwithwildcards
AfterhavingpressedEnteryougetalistwiththesearchresults.
Thenyoucanselectonematerial,youcansortorcancel.
TransactionCodes
Thefollowingscreenwillbeoftenusedduringtheworkshop.Thus,wecanuseTransactionCodesforfasteraccess.
ThenselectStructureplanning–ChangeProject.
Now,wewantto“bookmark”thisscreen.
So,welookupthetransactioncode.
Thestatusdialogboxopens:
Hereweseealotofinformationconcerningimportantrelevanttechnicaldetails.
Whereveryoufindyourselfinthesystem,youcangettothisscreenbyenteringCJ20intheTransactionscreen.
Letusrefinethisalittlebit.Ifyouhaveseveraltransactioncodes,youmaygetconfused.Keyintheappropriatetransactioncodeandthecommenteditprojectstructure.
Then,ifyouopenthecomboboxofthetransactioncodesafterhavingenteredmorecodes,youwillfindtheappropriateone.
TheStandardToolbar
Inmanyscreensyouwillfindthestandardtoolbar.
Savebutton
Whenyoupressthesavebutton,thesystemalsovalidatesyourinput.Iftherewasanerror,youhavetocorrecttheerrorfirst,beforeyoucanproceed.
Backbutton
Ifyouclickthebackbuttonyoureturntothepreviousscreenwithoutsavingyourdata.
Help
Enterbutton
Whenyouhavefinishedenteringinformationonascreen,youpresstheEnterbuttonwhichperformsthesamefunctionaspressingtheEnterkey.
Exitbutton
Pressit,ifyouwanttoleavethecurrentapplicationtogobacktothepreviousmenue.
Cancelbutton
Clickonthisbuttontoexitthecurrenttaskwithoutsaving.TheCancelbuttonperformsthesamefunctionasCancelintheEditmenu.
Printbutton
Pagingkeys
Find/Findnextbutton
Clickonthisbutton,ifyouwanttoperformasearchfordatarequiredinthescreenyouarecurrentlyworkingin.
CaseStudy
Casedescription
ThiscasewasdevelopedinordertodemonstratetheprojectsystemofSAPR/3.Allpricesanddataarepurefictionandheldverysimple.
Theobjectoftheprojectisthespecificationandinstallationofanelevator.
Physically,theElevatorconsistsof
acabine
anengine
mechanicalparts
acontrolunit
Inthecourseoftheproject,thesepartsmustbeconstructed,procuredandassembled.
Attheend,anexternalinspectionoftheentiresystemisprescribed.
Theprojectmustbefinishedby30.6.2023.
Thecompanyconsistsoftwoworkcenters:
Development(PROJ-RD)
Installation(PROJ-INS)
SpecificationactivitiesareperformedbytheDevelopmentdepartment.Procurementactivitieswillbedoneoutsidetheprojectorganisation,andneithercostnorcapacityconsiderationsareplannedwithinaprojectforprocurement.InstallationisdonebytheInstallationdepartment.
Inparticular,theactivitiesareasfollows:
Activity
Duration
Work
Work-center
Specificationofthecabine
10
20
Development
Specificationoftheengine
10
10
Development
Specificationofmechanicalparts
20
10
Development
Specificationofthecontrolunit
2
10
Development
Procurementofthecabine
20
Procurementoftheengine
50
Procurementofmechanicalparts
10
Procurementofthecontrolunit
10
InstallationI
15
100
Installation
InstallationII
20
100
Installation
ExternalInspection
1
external,80.000
Specificationactivitiescanbeperformedinaconsecutiveorderonly.Specificationstartswiththecabine.Aftercompletion,thespecificationoftheenginecanbedone.Then,themechanicalpartscanbedesigned.Thelastactivityisthedesignofthecontrolunit.
Afterthecompletionofeachspecificationactivity,theprocurementofthespecificitemcanbeeffected.
AftertheprocurementofallpartstheInstallationcanstartandmustbedoneintwoconsecutivesteps(I+II).
Thefinalactivityoftheprojectisexternalinspection.
A10%planningreserveonthebaisisofplannedcostisrequired.NoactualcostshouldbepostedtothisWBSelement.
Correspondingmaterialsassignedtothepurchasingactivities
ParametersfürEarned-ValueAnalysis
AllspecificationactivitiesandInstallationIIusethe20-80Methodforperformancemeasurement.Procurementactivitiesuse0–100method.
InstallationIhas3milestones,viz.Preparationfinished(20%),Installationfinished(80%),Qualitychecked(100%).
DataforProjectRealization
Activity
Start
End
Work
Specificationofthecabine
20
Specificationoftheengine
30
Specificationofmechanicalparts
20
Specificationofthecontrolunit
Procurementofthecabine
Procurementoftheengine
Procurementofmechanicalparts
Procurementofthecontrolunit
InstallationI
InstallationII
ExternalInspection
Externalinspectionhadtobepaidinadvanceat3.2.2023(100000ATS).
Allmaterialwastakenfromstockatgiventime.
Planningtheprojectstructure
General
Eachprojectstartswiththedefinitionandclassificationofthestructuresrequiredforprocessingandtheincorporationoftheseintotheexistingenterprisestructure.
TheProjectSystemhasnoorganizationalstructuresofitsown;ithastobeincorporatedintotheexistingstructurebymakingassignmentstotheorganizationalunitsinAccountingandLogistics.SAPOnlineDocumentationIDESRelease4.0B
Afterthat,theprojectisbrokendownintomeaningfulpiecesinahierarchyreachingfromtaskstothelowestlevel,theworkpackages.
DatastructureinSAP
Asmentionedabove,theprojectmustbeincorporatedintotheexistingstructurebyassigningorganizationalunitsinAccountingandLogistics.
Source:SAPOnlineDocumentationIDESRelease4.0B
Thischartprovidesanoverviewofwhatcanbeassignedtoaprojectanditscomponents.WewilldefinetheSAPvocabularylateron.
Thework-breakdown-structure(WBS)definesthehierarchyofthetaskswithinaprojectanddividestheprojectintousefulsteps.
TocontrolcostsassignedtoWBSelements,operativeindicatorsareused.
ThefollowingoperativeindicatorscanbeassignedtoaWBSelement:
Planning
WBSelementsforwhichcostscanbeplanned
Accountassignment
WBSelementstowhichcostscanbeassigned
Billing
WBSelementstowhichrevenuescanbeposted
ImplementationinSAP
Inthissectionwecreateanewproject.Wethenwillhavealookatthecontrolparameters.Afterthatweentertheworkbreakdownstructure.Finally,thestatusconceptofSAPR/3willbeexplained.
Createnewproject
Thus,wegettotheinitialscreen:
Weenterourprojectdefinition,adescriptionofourprojectandselectthestandardprofileforprojects.
Inourcase,weonlysetafinishdate.WhenpressingEnter,awarningmessagethatthisdateisnotaworkingdaymightoccur.OnecanpassthewarningbypressingEnter
Wethensaveourworkandgettheconfirmationthattheprojecthasbeencreated.
Note:Itiswisetosaveyourworkfromtimetotime.Wewillnotmentionthesaveprocedureintherestofthemanuscript!
Tocontinue,wehavetochoosetochangeourproject.
Makesurethatthecheckboxwithactivitiesisalwayschecked.Clickexecutetoproceed.
Nowhehavecreatedanewproject.AlthoughwehavenotkeyedinanydataexcepttheProjectProfileNumber,manyparametershavealreadybeenassignedtoournewproject.
Generalcontrolparameters
Clickheretoviewtheglobalparameters.Thissectionshouldprovideyouwithabasicinsightintowhichparametersareset.IfyoufeelthattheresultscalculatedbyR/3arenotlogical,youshouldhaveanideawheretostartsearchingtherelevantcustomizingdetails.
TheprojectprofilespecifiesgeneraldatalikeControllingarea,Plant,Factorycalendar,Planningmethodetc.Whencreatingtheproject,theprofileischoosen.
Thenetworkprofilespecifiesgeneraldatalikesettingsforthegraphicalrepresentation,activityparameters,likethecurrencydefaultofexternallyprocessedactivities.
IntheWBSschedulingprofileitemsliketheschedulingtype(forward,backward)arespecified.
Thebudgetprofilespecifiesitemslikebudgetingcurrency,thevalidtimehorizonforbudgetingbackin-tothepastorintothefuture
Theplanningprofilespecifies,e.g.,costingvariantandtimehorizon.
Planningparameters
Inthegeneralparametersection,manyparametersaresetasdiscussedabove.Naturally,onecanoverrideapartoftheminthecurrentproject.However,wearenotchanginganyparameters.
Hereyoucanspecifyifyouwanttousetop-Down,bottomup,oropenplanning.
Herewespecifywhatthesystemshoulddoifschedulingdeterminesdateswhicharenotwithinthebasicdates.Incase,thescheduleddatesshouldbetakenoverasnewdates.
Animportantparameteristheschedulingtype.Hereyouspecify,ifyouwanttouseforward,backwardorotherschedulingtypes.
Startenteringthedatagiveninthescreenshotbelow.Ifyouarefinished,pressEnter.
Then,yourscreenshouldlooklikethis:
Levelingup/downWBSElements
Thereisamistake.WBSElementELV_000-300shouldhavelevel2.
SelecttheWBSElementtolevelingitdown.
InsertingWBSElements/activities
WehaveforgottentoenterenterActivity203,ProcurementofthemechanicalpartsandActivity204,Procurementofthecabine.
SelecttherowabovewhichyouwanttoinsertarowandadditbymenueorsimplybypressingF6.Proceedwiththesecondrowinthesameway.Donotforgetthattheseactivitiesdonothavealevel.
Afterthesechangesyourscreenshouldlooklikethis:
The“hidden-quick-menue”
Ifyoupresstherightmousebutton,yougetalistofusefulcommands.Allthesecommandscanalsobeaccessedviamenuesandbuttons.However,youarefasterwhenyouusetheright-mouse-quick-menue.
UserStatusandBusinessAdministrationProcedures
Astatusdocumentsthecurrentstateofprocessingofanobject.Dependingonwhichbusinesstransactionisperformedforanobject,suchasaWBSelement,aninternalorder,oranetwork,thestatusofthatobjectchanges.Thestatusofanobject,inturn,influenceswhichbusinesstransactionscanbecarriedoutforanobject.
Therearetwotypesofstatuses:
Theuserstatusandthesystemstatus.
Asystemstatusissetbythesystemwhichtellsusthataparticularfunctionhasbeencarriedoutforanobject.Ausercannotdelete,change,orotherwiseamendthesystemstatusinanyway.
Auserstatusisastatuswhichcanbesetbytheuserinadditiontothecurrentsystemstatus.Inthisworkshop,wewillskiptheuserstatusandfocusonlyonthesystemstatus.
Now,thesystemstatusoftheprojectisCREATED.
Ifyouwanttocheckthisbyyourself,pressCRTL+F9fromtheprojectstructurechangingscreenandclicktoBusinessTransactions.Nowwegetalistofwhichbusinessproceduresarecurrentlyallowedandwhicharecurrentlydisabled.
Anumberofbusinesstransactionsarecurrentlydisallowed.Inordertoallowforenteringactualdata(e.g.viaIncominginvoices),wemustchangetheuserstatus.
Forthispurpose,wearegoingtoreleasethewholeproject.Selectallrowsandreleasetheproject.
Yougetthemessagethatthestatuswaschanged.
Confirmit.
Now,checkifwearecurrentlyallowedtoreportcosts.SelectthehighestWBSElementandthenpressCRTL+F9
ClicktoBusinessTransactionstoseewhathaschanged.
NotethatnowwearenolongerallowedtodeleteWBS-Elements.
PressEnterandleavethestatusscreenbygoingback.
Beforereleasingtheprojectwehadalreadyselectedallactivities.Thuswehavereleasedthewholeproject.NotethatwewouldhavebeenabletoselectonlyafewactivitiesorWBSelements.Therefore,itispossiblethatdifferentWBSelementsanddifferentactivitiescanhaveadifferentstatus.Infact,inpracticethisisthecasewithlarge-scaleprojects.
OperativeStructures
GetintothescreenchangestructureplanningbyusingTransactioncode“CJ20”andselectWBSbasicdata.
Checktheboxes“PE”and“Acct”totoallowforplannedcostsandforactualcosts.Notethatispossibleandsometimesusefultoallowforplannedcostonanaggregatelevel,butnotforactualcost.
Scheduling
General
Intop-downplanning,westartatthehighestleveloftheworkbreakdownstructure(WBS),andallthesubordinateWBSelementmustfallwithinthetimeframeoftheparticularhigherWBSelements.Incontrast,inbottomupplanning,westartatthesubordinatelevelsandaggregatetheplantothetop.Planningwithouthierarchicaldependenciesisreferredtoasopenplanning.However,severalconstraintshavetobeconsidered.Forexample,wecouldspecifythatthemanufacturingprocessmustendbeforetheannualplantshutdown.Apowerfultoolinprojectmanagementisplanningbynetwork.
Asapreliminarysteptogetaroughideaaboutthetimestructureofaproject,GANTTChartsareused.Thissimplymeansthatthedurationofeachactivityisdrawnagainsttime.Theproblemisthatfunctionalrelationshipsamongsequentialactivitiesarenotcapturedformallyandchangesrequireanewdrawing.Inanetworkthereisusuallyareasonforaspecificsequenceofactivities.Forexample,theremaybetechnicaldependenciesbetweenindividualactivities.
Exampleofanetwork.Source:SAPDocumentationCD
Inordertoconsidertheserelationships,severalalgorithmsforplanningproblemshavebeendevelopedandarereferredtoinanumbrelladefinitionasplanningbynetwork.
Theessentialcomponentsofanetworkare:
Activities
Relationships
Activitiescanbeseenas"componentsofaprocess"withthefollowingcharacteristics:
Theytakeacertainperiodsoftime
Theyhaveadefinedstartandadefinedend
Theyareprocessedwithoutinterruption
Resourcesareneededtoexecutethem
Theyinvolvecosts
DifferentkindsofnetworktypeshaveemergedinthefieldofOperationsResearch.Startingwithdeterministicdurationsandstructure,networkswithstochasticdurations(likePERT)andevenstochasticstructure(likeGERT)offerpowerfultimeplanningtechniques.However,practitionersarescepticalabouttheresults,andlarge,complicatedprojectstructuresrequiretoolswhicharerathereasytohandle.Therefore,wewillonlydiscussMetraPotentialMethod(MPM)whichisusedinthePSmodulaswell.MPMmethodusesdeterministicdurationsandstructures.Asaconsequence,neitherprobabiltiesof,e.g.,aspecificdurationoftheprojectcanbecalculatednorcanbecapturedaprojectstructurewhichhasstochasticelements.Thiswouldbethecase,e.g.,ifwewishedtomodelasituationatestcouldbepassedwithacertainprobability.ThiswouldleadtoalooponaMPMstructurewhichisforbidden.
Anetworkdoesnotonlygraphicallydisplaytherelationshipsamongvariousactivities,itprovidesalsoinformationonthecriticalpath.Thecriticalpathindicateswhichactivitiesarethemostcriticaltobeperformedintimetoavoiddelayingthewholeproject.Higgins,James:TheManagementChallengep.232
PlanningbynetworkisbasedontheTheoryofGraphs.Heinrich,Lutz:Systemplanungp.206
MPMusesnodestorepresentactivitiesandarrowsfortheirrelationshipsasthisiseasiertofollow.OnemustknowthatSAPsupportsseveraltypesofrelationshipsandnotonlythestandardrelationship.Thefollowingrelationshipsaresupported:
Finish-Start
Theprecedingactivitymustfinishbeforethefollowingactivitymaystart.
Start-Start
Oneactivitycannotstartuntiltheotheronehasstarted.
Finish-Finish
Oneactivitycannotbefinisheduntiltheotheroneisfinished.
Start-Finish
Oneactivitycannotbefinisheduntiltheotheronehasstarted
Forsomeactivities,theearliestpossiblestartandthelatestpossiblestartdiffers.Thedifferencebetweentheearliestpossiblestartandthelatestpossiblestartiscalledslacktime.Aslacktimegreaterthanzeromeansthatthedurationoftheactivitycanbelongerthanplannedwithoutdelayingthecompletiondateofthewholeproject.Thesequencesofactivitieshavingaslacktimeofzeroarecalledthecriticalpath.Inthiscontextcriticalmeansthat,ifthedurationofoneoftheseactivitiesislongerthanexpected,thecompletiondateofthewholeprojectisdelayedbyatleastthatperiodoftime.Onemustalsorealizethattherecanbeseveralcriticalpaths.Moreover,thecriticalpathscanchangeduringtheprojectasaresultofunexpecteddelaysofcertainactivities.
ThechangeofthecriticalpathduetoexcessiveconsumptionoftheslacktimeisreferredtoasParkinsonPhenomena.Schierenbeck,Henner.EinführungindieAllgemeineBetriebswirtschaftslehre,p.165
Theslacktimeforanactivitycannotbeusedwithoutaffectingtheslacktimeforotheractivities.Asaruleofthumb,thetotalslacktimecanbeusedonlyoncewithinanon-criticalpathwithoutchangingtheparticularpathintoacriticalone.Thus,theMPM(MetraPotentialMethod)methodsplitstheslacktimeintofourdifferentparts.Schierenbeck,Henner.EinführungindieAllgemeineBetriebswirtschaftslehre,p.159ff
Thetotalslacktimeiscalculatedasthedifferencebetweentheearliestpossiblestartandearliestpossibleend.Thisisequaltothedifferencebetweenthelatestpossiblestartandthelatestpossibleend.
Thefreeslacktimeattheendiscalculatedassumingthatallpredecessorshavebegunattheearliestpossibledate.Thus,thefreeslacktimeattheendcalculates,providedtheassumptionholds,thetimetheactivitycanb
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 罕见病药物研发中的伦理考量与患者招募策略
- 补齐民生短板 2026年河南省现代农业产业园可行性研究报告
- 智能感知赋能智慧水务:解决漏损检测痛点并提升资源效率
- 智能橱柜控制系统赋能智慧养老:重构适老化家居成本结构
- 2026年北京市光伏电站可行性研究报告
- 高端月子中心运营管理标准化手册
- 智能开合帘电机赋能智慧建筑:BIM系统下的能耗优化策略
- 2027年山西艺术职业学院单招职业技能考试题库含答案详解【培优】
- 2026年湖北省荆门市高职单招职业技能考试题库含完整答案详解(夺冠系列)
- 2026年洛阳瀍河职业学院高职单招职业技能考试题库加答案详解
- 屋面排水管施工要点方案
- 地下室工程有限空间作业专项施工方案
- 2026年湖南湘江新区发展集团有限公司校园招聘笔试模拟试题及答案解析
- DB31∕T 1662-2025 养老机构消毒卫生要求
- (正式版)DB50∕T 1920-2025 《制氢加氢一体站建设技术规范》
- 【课件】《安全生产违法行为行政处罚办法》逐章逐条解读
- 短视频广告的时长效果研究
- 2025ESC临床共识声明:心理健康和心血管疾病课件
- 警网融合培训课件
- 周勇线性代数课件
- 违禁物品X射线图像与识别课件
评论
0/150
提交评论