天津碱厂搬迁改造工程热电站项目#1标,,,,,,,,,,,,,,
电气专业施工质量检验项目,,,,,,,,,,,,,,
工程编号,,,工程项目名称,性质,质检机构验评范围,,,,,监检方式,,,,质量验评及签证表编号(DL/T)
单位工程,分部工程,分项工程,,,施工单位,,,监理单位,建设单位,待检点H,签证点R,见证点W,旁站点S,
,,,,,班组,工地,质检部,,,,,,,
1,,,发电机电气与引出线安装,,,√,√,√,√,,√,,,5161.1-表4.0.3
,1,,发电机电气与出线设备安装,,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,发电机本体检查,主要,√,√,√,√,√,,,√,,5161.7-表1.0.1
,,2,发电机附件安装,主要,√,√,√,√,,,,√,,5161.7-表1.0.2
,,3,励磁设备检查安装,,√,√,√,√,,,,,,5161.7-表2.1.25161.3-表1.0.1
,,4,互感器检查安装,,√,√,,,,,,,,5161.3-表3.0.1
,,5,箱、柜(盘)安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表2.0.15161.8-表4.0.25161.8-表6.0.2
,,6,电阻器安装,,√,√,,,,,,,,
,,7,交(直)流励磁母线安装,主要,√,√,√,√,,,,,,5161.4-表3.0.2
,2,,发电机引出线安装,,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,铁构架制作安装,,√,√,,,,,,,,5161.4-表1.0.25161.4-表1.0.3
,,2,封闭母线安装,主要,√,√,√,√,,,,√,,5161.4-表5.0.2
,,3,电压互感器、避雷器安装,,√,√,√,√,,,,,,5161.3-表3.0.15161.2-表6.0.2
,,4,隔离开关安装,,√,√,,,,,,,,5161.2-表5.0.1
,,5,负荷开关安装,主要,√,√,√,√,,,,,,5161.2-表5.0.2
,10,,发电机启动试运,主要,,√,√,√,√,√,√,,,5161.7-表3.0.7
2,,,主变压器系统设备安装,,,√,√,√,√,,√,,,5161.1-表4.0.3
,1,,主变压器安装,,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,主变压器本体安装,,√,√,√,√,,,,,,5161.3-表1.0.3-1
,,2,主变压器检查,主要,√,√,√,√,√,,,,,5161.3-表1.0.3-2
,,3,主变压器附件安装,,√,√,√,√,,,√,√,,5161.3-表1.0.3-3
,,4,主变压器注油及密封试验,主要,√,√,√,√,,,,,√,5161.3-表1.0.3-4
,,5,主变压器整体检查,主要,√,√,√,√,,,,,,5161.3-表1.0.3-5
,2,,主变压器系统附属设备安装,,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,中性点隔离开关安装,,√,√,√,√,,,,,,5161.2-表5.0.1
,,2,避雷器安装,,√,√,√,√,,,,,,5161.2-表6.0.2
,,3,控制柜及端子箱检查安装,,√,√,,,,,,,,5161.8-表4.0.2
,,4,软母线安装,,√,√,√,√,,,,,,5161.4-表7.0.2
,10,,主变压器带电试运,主要,,√,√,√,√,√,√,,,5161.3-表4.0.9
3,,,×××kV配电装置安装,,,√,√,√,√,,√,,,5161.1-表4.0.3
,1,,网控室设备安装,,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,控制及保护屏台安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表5.0.2
,,2,直流屏及充电设备安装,,√,√,,,,,,,,5161.13-表2.0.2
,,3,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,,4,蓄电池安装,,√,√,√,√,,,,√,,5161.9-表1.0.25161.9-表2.0.2
,,5,充放电及容量测定,主要,√,√,√,√,,,√,,√,5161.9-表3.0.35161.9-表3.0.4
,2,,主母线及旁路母线安装,,,√,√,√,√,√,,,,5161.1-表4.0.2
,,1,绝缘子串安装,,√,√,,,,,√,,,5161.4-表2.0.2
,,2,软母线安装,,√,√,√,√,√,,,,,5161.4-表7.0.2
,,3,支柱绝缘子安装,,√,√,,,,,,,,5161.4-表2.0.3
,,4,管型母线安装,主要,√,√,√,√,,,,,,5161.4-表6.0.2
,,5,隔离开关安装,,√,√,√,√,,,,,,5161.2-表5.0.1
,3,,电压互感器,,,,,,,,,,,
,,6,低压侧共箱封闭母线安装,☆,√,√,√,√,,,,√,,5161.4-表1.0.25161.4-表4.0.2
,,7,变压器整体检查,☆,√,√,√,√,,,,,,5161.3-表1.0.3-5
,10.1,,厂用高压工作变压器带电试运,☆,,√,√,√,√,√,√,,,5161.3-表4.0.9
,3,,厂用高压备用变压器安装,,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,变压器本体安装,,√,√,,,,,,√,,5161.3-表1.0.3-1
,,2,变压器检查,☆,√,√,√,√,√,,,,,5161.3-表1.0.3-2
,,3,变压器附件安装,,√,√,,,,,,,,5161.3-表1.0.3-3
,,4,变压器注油及密封试验,☆,√,√,√,√,,,,,,5161.3-表1.0.3-4
,,5,控制及端子箱安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表4.0.2
,,6,低压侧共箱封闭母线安装,☆,√,√,√,√,,,,√,,5161.4-表1.0.25161.4-表4.0.2
,,7,软母线安装,☆,√,√,√,√,,,,,,5161.4-表7.0.2
,,8,变压器整体检查,☆,√,√,√,√,,,,,,5161.3-表1.0.3-5
,,9,隔离开关等电气设备安装,☆,√,√,,,,,,,,5161.4-表7.0.2
,10.2,,厂用高压备用变压器带电试运,☆,,√,√,√,√,√,√,,,5161.3-表4.0.9
5,,,主厂房厂用电系统设备安装,,,√,√,√,√,,√,,,5161.1-表4.0.3
,1,,厂用高压工作配电装置安装(I段),,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,盘柜基础安装,,√,√,,,,,,,,5161.8-表1.0.2
,,2,配电盘安装,,√,√,,,,,,,,5161.8-表2.0.15161.8-表2.0.2
,,3,母线安装,☆,√,√,√,√,,,,,,5161.4-表3.0.2
,,4,断路器检查,☆,√,√,√,√,,,,,√,5161.2-表3.0.25161.2-表4.0.2
,,5,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,2,,厂用高压工作配电装置安装(II段),,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,盘柜基础安装,,√,√,,,,,,,,5161.8-表1.0.2
,,2,配电盘安装,,√,√,,,,,,,,5161.8-表2.0.15161.8-表2.0.2
,,3,母线安装,☆,√,√,√,√,,,,,,5161.4-表3.0.2
,,4,断路器检查,☆,√,√,√,√,,,,,√,5161.2-表3.0.25161.2-表4.0.2
,,5,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,3,,厂用高压备用配电装置安装,,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,盘柜基础安装,,√,√,,,,,,,,5161.8-表1.0.2
,,2,配电盘安装,,√,√,,,,,,,,5161.8-表2.0.15161.8-表2.0.2
,,3,母线安装,☆,√,√,√,√,,,,,,5161.4-表3.0.2
,,4,断路器检查,☆,√,√,√,√,,,,,√,5161.2-表3.0.25161.2-表4.0.2
,,5,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,4,,厂用低压公用配电装置安装(A段),,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,盘柜基础安装,,√,√,,,,,,,,5161.8-表1.0.2
,,2,干式变压器安装,☆,√,√,√,√,,,,√,,5161.3-表1.0.15161.3-表1.0.2
,,3,配电盘安装,,√,√,,,,,,,,5161.8-表2.0.15161.8-表2.0.2
,,4,空气开关检查,☆,√,√,√,√,,,,,√,5161.2-表3.0.25161.2-表4.0.2
,,5,母线安装,☆,√,√,√,√,,,,,,5161.4-表3.0.2
,,6,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,5,,厂用低压公用配电装置安装(B段),,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,盘柜基础安装,,√,√,,,,,,,,5161.8-表1.0.2
,,2,干式变压器安装,☆,√,√,√,√,,,,√,,5161.3-表1.0.15161.3-表1.0.2
,,3,配电盘安装,,√,√,,,,,,,,5161.8-表2.0.15161.8-表2.0.2
,,4,空气开关检查,☆,√,√,√,√,,,,,√,5161.2-表3.0.25161.2-表4.0.2
,,5,母线安装,☆,√,√,√,√,,,,,,5161.4-表3.0.2
,,6,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,6,,厂用低压工作配电装置安装(I段),,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,盘柜基础安装,,√,√,,,,,,,,5161.8-表1.0.2
,,2,干式变压器安装,☆,√,√,√,√,,,,√,,5161.3-表1.0.15161.3-表1.0.2
,,3,配电盘安装,,√,√,,,,,,,,5161.8-表2.0.15161.8-表2.0.2
,,4,空气开关检查,☆,√,√,√,√,,,,,√,5161.2-表3.0.25161.2-表4.0.2
,,5,母线安装,☆,√,√,√,√,,,,,,5161.4-表3.0.2
,,6,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,7,,厂用低压工作配电装置安装(II段),,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,盘柜基础安装,,√,√,,,,,,,,5161.8-表1.0.2
,,2,干式变压器安装,☆,√,√,√,√,,,,√,,5161.3-表1.0.15161.3-表1.0.2
,,3,配电盘安装,,√,√,,,,,,,,5161.8-表2.0.15161.8-表2.0.2
,,4,空气开关检查,☆,√,√,√,√,,,,,√,5161.2-表3.0.25161.2-表4.0.2
,,5,母线安装,☆,√,√,√,√,,,,,,5161.4-表3.0.2
,,6,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,8,,厂用低压备用段配电装置安装,,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,盘柜基础安装,,√,√,,,,,,,,5161.8-表1.0.2
,,2,干式变压器安装,☆,√,√,√,√,,,,√,,5161.3-表1.0.15161.3-表1.0.2
,,3,配电盘安装,,√,√,,,,,,,,5161.8-表2.0.15161.8-表2.0.2
,,4,空气开关检查,☆,√,√,√,√,,,,,√,5161.2-表3.0.25161.2-表4.0.2
,,5,母线安装,☆,√,√,√,√,,,,,,5161.4-表3.0.2
,,6,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,9,,汽机间电气设备安装,,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,MCC(电动机控制中心)盘安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表3.0.35161.12-表1.0.25161.4-表3.0.2
,,2,就地动力控制设备安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表4.0.2
,,3,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,,4,电动机检查,☆,√,√,√,√,,,,√,,5161.7-表2.2.2
,,5,电动机带电试运,☆,√,√,√,√,√,√,√,,,5161.7-表3.0.115161.7-表3.0.13
,10,,锅炉间电气设备安装,,,√,√,√,√,,√,,,5161.1-表4.0.3
,,1,MCC(电动机控制中心)盘安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表3.0.35161.12-表1.0.25161.4-表3.0.2
,,2,就地动力控制设备安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表4.0.2
,,3,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,,4,电动机检查,☆,√,√,√,√,,,,√,,5161.7-表2.2.2
,,5,电梯电气设备安装,☆,√,√,√,√,√,,,,,5161.11-表1.0.2
,,6,电动机带电试运,☆,√,√,√,√,√,√,√,,,5161.7-表3.0.115161.7-表3.0.13
,11,,集控楼电气设备安装,,,√,√,√,√,,√,,,5161.1-表4.0.3
,,1,MCC(电动机控制中心)盘安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表3.0.35161.12-表1.0.25161.4-表3.0.2
,,2,就地动力控制设备安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表4.0.2
,,3,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,,4,电动机检查,☆,√,√,√,√,,,,√,,5161.7-表2.2.2
,,5,电梯电气设备安装,☆,√,√,√,√,√,,,,,5161.11-表1.0.2
,,6,电动机带电试运,☆,√,√,√,√,√,√,√,,,5161.7-表3.0.115161.7-表3.0.13
,10,,厂用电系统设备带电试运,☆,,√,√,√,√,√,√,,,5161.1-表5.0.5-25161.1-表5.0.5-3
6,,,事故保安电源设备安装,,,√,√,√,√,,,√,,5161.1-表4.0.3
,,1,控制屏安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表5.0.2
,,2,不停电电源装置安装,,√,√,√,√,,,,,,5161.8-表1.0.25161.13-表2.0.2
,,3,配电盘安装,,√,√,√,√,,,,,,5161.8-表2.0.15161.8-表2.0.25161.8-表3.0.3
,,4,母线安装,☆,√,√,√,√,,,,,,5161.4-表3.0.2
,,5,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,10,,事故保安电源带电试运,☆,,√,√,√,√,,√,,√,5161.1-表5.0.5-3
7,,,输煤系统电气设备安装,,,√,√,√,√,,√,,,5161.1-表4.0.3
,1,,输煤系统控制设备安装,,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,输煤控制室控制及保护屏安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表5.0.2
,,2,输煤控制室二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,2,,高压配电装置安装,☆,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,基础型钢安装,,√,√,,,,,,,,5161.8-表1.0.2
,,2,配电盘安装,,√,√,,,,,,,,5161.8-表2.0.15161.8-表2.0.2
,,3,母线安装,☆,√,√,√,√,,,,,,5161.4-表3.0.2
,,4,断路器检查,☆,√,√,√,√,,,,,√,5161.2-表3.0.25161.2-表4.0.2
,,5,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,3,,低压配电装置安装(A段),,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,变压器安装,☆,√,√,√,√,,,,√,,5161.3-表1.0.15161.3-表1.0.2
,,2,配电盘安装,,√,√,,,,,,,,5161.8-表2.0.15161.8-表2.0.2
,,3,母线安装,☆,√,√,√,√,,,,,,5161.4-表3.0.2
,,4,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,4,,低压配电装置安装(B段),,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,变压器安装,☆,√,√,√,√,,,,√,,5161.3-表1.0.15161.3-表1.0.2
,,2,配电盘安装,,√,√,,,,,,,,5161.8-表2.0.15161.8-表2.0.2
,,3,母线安装,☆,√,√,√,√,,,,,,5161.4-表3.0.2
,,4,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,5,,低压备用配电装置安装,,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,变压器安装,☆,√,√,√,√,,,,√,,5161.3-表1.0.15161.3-表1.0.2
,,2,配电盘安装,,√,√,,,,,,,,5161.8-表2.0.15161.8-表2.0.2
,,3,母线安装,☆,√,√,√,√,,,,,,5161.4-表3.0.2
,,4,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,6,,输煤系统电动机带电试运,☆,,√,√,√,√,√,√,,,5161.7-表3.0.115161.7-表3.0.13
,10,,输煤系统配电装置带电试运,☆,,√,√,√,√,√,√,,,5161.1-表5.0.5-25161.1-表5.0.5-3
8,,,除尘除灰系统电气设备安装,,,√,√,√,√,,√,,,5161.1-表4.0.3
,1,,除尘除灰系统控制设备安装,,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,除尘除灰系统控制及保护屏安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表5.0.2
,,2,除尘除灰系统二次回路检查接线,,√,√,,,,,,,,5161.8-表7.0.2
,2,,除尘除灰系统高压电气设备安装,,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,基础型钢安装,,√,√,,,,,,,,5161.8-表1.0.2
,,2,整流变安装,☆,√,√,√,√,,,,,,5161.3-表1.0.2
,,3,配电盘安装,,√,√,,,,,,,,5161.8-表1.0.2
,,4,母线安装,,√,√,√,√,,,,,,5161.4-表3.0.2
,,5,断路器检查,☆,√,√,√,√,,,,,,5161.2-表3.0.25161.2-表4.0.2
,,6,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,3,,除尘系统低压电气设备安装,,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,变压器安装,☆,√,√,√,√,,,,√,,5161.3-表1.0.15161.3-表1.0.2
,,2,MCC(电动机控制中心)盘安装,,√,√,,,,,,√,,5161.8-表1.0.25161.8-表3.0.35161.12-表1.0.25161.4-表3.0.2
,,3,控制柜安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表5.0.2
,,4,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,4,,除灰系统电气设备安装,,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,变压器安装,☆,√,√,√,√,,,,√,,5161.3-表1.0.15161.3-表1.0.2
,,2,MCC(电动机控制中心)盘安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表3.0.35161.12-表1.0.25161.4-表3.0.2
,,3,电动机检查,☆,√,√,√,√,,,,,,5161.7-表2.2.2
,,4,就地动力控制设备安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表4.0.25161.12-表5.0.25161.12-表2.0.2
,,5,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,5,,除尘除灰系统电动机带电试运,☆,,√,√,√,√,√,√,,,5161.7-表3.0.115161.7-表3.0.13
,10,,除尘除灰系统配电装置带电试运,☆,,√,√,√,√,√,√,,,5161.1-表5.0.5-25161.1-表5.0.5-3
9,,,附属生产系统电气设备安装,,,√,√,√,√,,,,,5161.1-表4.0.3
,1,,燃油泵房电气设备安装,,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,MCC(电动机控制中心)盘安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表3.0.35161.12-表1.0.25161.4-表3.0.2
,,2,控制盘安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表5.0.25161.12-表5.0.2
,,3,就地电气设备安装,,√,√,,,,,,,,5161.15-表3.0.2
,,4,电动机检查,☆,√,√,√,√,,,,,,5161.7-表2.2.2
,,5,就地电气设备接地,☆,√,√,√,√,,,,,,5161.15-表4.0.2
,,6,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,10.1,,燃油泵房电气设备带电试运,☆,,√,√,√,√,√,√,,,5161.1-表5.0.5-3
,2,,空压机站电气设备安装,,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,MCC(电动机控制中心)盘安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表3.0.35161.12-表1.0.25161.4-表3.0.2
,,2,控制盘安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表5.0.25161.12-表5.0.2
,,3,电动机检查,☆,√,√,√,√,,,,,,5161.7-表2.2.2
,,4,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,10.2,,空压站电气设备带电试运,☆,,√,√,√,√,√,√,,,5161.1-表5.0.5-3
,3,,油处理站电气设备安装,,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,MCC(电动机控制中心)盘安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表3.0.35161.12-表1.0.25161.4-表3.0.2
,,2,控制盘安装,,√,√,,,,,,,,5161.8-表1.0.25161.8-表5.0.25161.12-表5.0.2
,,3,就地电气设备安装,,√,√,,,,,,,,5161.15-表3.0.2
,,4,电动机检查,☆,√,√,√,√,,,,,,5161.7-表2.2.2
,,5,就地电气设备接地,☆,√,√,√,√,,,,,,5161.15-表4.0.2
,,6,二次回路检查及接线,,√,√,,,,,,,,5161.8-表7.0.2
,10.3,,油处理站电气设备带电试运,,,√,√,√,√,√,√,,,5161.1-表5.0.5-3
10,,,全厂起重机电气设备安装,,,√,√,√,√,,√,,,5161.1-表4.0.3
,1,,汽机间起重机电气设备安装,,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,主、副滑线安装,,√,√,,,,,,√,,5161.14-表1.0.25161.14-表1.0.45161.14-表1.0.65161.14-表3.0.2
,,2,电动机检查,☆,√,√,√,√,,,,,,5161.7-表3.0.9
,,3,控制设备安装及接线,,√,√,,,,,,,,5161.12-表1.0.25161.12-表3.0.25161.12-表5.0.25161.14-表2.0.2
,2,,锅炉间起重机电气设备安装,,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,软电缆安装,,√,√,,,,,,,,5161.14-表1.0.5
,,2,滑线安装,,√,√,,,,,,,,5161.14-表3.0.2
,3,,辅助车间起重机电气设备安装,,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,滑线安装,,√,√,,,,,,,,5161.14-表1.0.25161.14-表1.0.45161.14-表1.0.65161.14-表3.0.2
,,2,软电缆安装,,√,√,,,,,,,,5161.14-表1.0.4
,10,,起重机电气设备带电试运,☆,,√,√,√,√,√,√,,,5161.14-表4.0.2
11,,,设备及构筑物照明安装,,,√,√,√,√,,√,,,5161.1-表4.0.3
,1,,锅炉本体照明安装,,,√,√,√,√,,√,,,5161.1-表4.0.2
,,1,电源及控制设备安装,,√,√,,,,,,,,5161.17-表1.0.25161.17-表3.0.2
,,2,管路敷设,,√,√,√,√,,,,,,5161.16-表1.0.2
,,3,管内配线及接线,,√,√,,,,,,,,5161.16-表2.0.2
,,4,照明灯具安装,,√,√,√,√,,,,,,5161.17-表2.0.2
,2,,回路通电检查,☆,√,√,√,√,√,,,,√,5161.17-表4.0.2
,,1,电源及控制设备安装,,√,√,,,,,,,,5161.17-表1.0.25161.17-表3.0.2
,,2,管路敷设,,√,√,√,√,,,,,,5161.16-表1.0.2
,,3,管内配线及接线,,√,√,,,,,,,,5161.16-表2.0.2
,,4,照明灯具安装,,√,√,√,√,,,,,,5161.17-表2.0.2
12,,,全厂电缆线路施工,,,√,√,√,√,,,√,,5161.1-表4.0.3
,1,,电缆管配制及敷设,,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,主厂房电缆管配制及敷设,,√,√,,,,,,,,5161.5-表1.0.2
,,2,开关站及网控室电缆管配制及敷设,,√,√,,,,,,,,5161.5-表1.0.2
,,3,输煤系统电缆管配制及敷设,,√,√,,,,,,,,5161.5-表1.0.2
,,4,电除尘系统电缆管配制及敷设,,√,√,,,,,,,,5161.5-表1.0.2
,,5,除灰系统电缆管配制及敷设,,√,√,,,,,,,,5161.5-表1.0.2
,,6,其他附属车间电缆管配制及敷设,,√,√,,,,,,,,5161.5-表1.0.2
,2,,电缆架安装,,,√,√,√,√,,,√,,5161.1-表4.0.2
,,1,主厂房电缆架安装,,√,√,,,,,,,,5161.5-表1.0.3
,,2,开关站及网控室电缆架安装,,√,√,,,,,,,,5161.5-表1.0.3
,,3,输煤系统电缆架安装,,√,√,,,,,,,,5161.5-表1.0.3
,,4,除灰系统电缆架安装,,√,√,,,,,,,,5161.5-表1.0.3
,,5,其他附属车间电缆架安装,,√,√,,,,,,,,5161.5-表1.0.3
,3,,电缆敷设,,,√,√,√,√,,,,,5161.1-表4.0.2
,,1,发电机变压器组系统电缆敷设,,√,√,,,,,,,,5161.5-表2.0.2
,,2,主厂房厂用电系统电缆敷设,,√,√,,,,,,,,5161.5-表2.0.2
,,3,全厂直流系统电缆敷设,,√,√,,,,,,,,5161.5-表2.0.2
,,4,事故保安电源系统电缆敷设,,√,√,,,,,,,,5161.5-表2.0.2
,,5,照明及检修电源系统电缆敷设,,√,√,,,,,,,,5161.5-表2.0.25161.5-表2.0.4
,,6,开关站及网控室电缆敷设,,√,√,,,,,,,,5161.5-表2.0.2
,,7,输煤系统电缆敷设,,√,√,,,,,,,,5161.5-表2.0.2
,,8,除灰系统电缆敷设,,√,√,,,,,,,,5161.5-表2.0.2
,,9,其他附属车间电缆敷设,,√,√,,,,,,,,5161.5-表2.0.2
,4,,电力电缆终端制作及安装,,,√,√,√,√,,,,√,5161.1-表4.0.2
,,1,发电机变压器组系统电力电缆终端制作及安装,,√,√,,,,,,,,5161.5-表3.0.2
,,2,主厂房厂用电系统电力电缆终端制作及安装,,√,√,,,,,,,,5161.5-表3.0.2
,,3,全厂直流系统电力电缆终端制作及安装,,√,√,,,,,,,,5161.5-表3.0.2
,,4,事故保安系统电力电缆终端制作及安装,,√,√,,,,,,,,5161.5-表3.0.2
,,5,照明及检修电源系统电力电缆终端制作及安装,,√,√,,,,,,,,5161.5-表3.0.
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2026年江西省南昌市幼儿园教师招聘笔试备考题库及答案解析
- 2026年伊春市伊春区幼儿园教师招聘笔试备考试题及答案解析
- 合作学习在初中生物学习效率方面的实践研究
- 华北平原杨树人工林土壤呼吸及其组分对水热条件与光合作用的响应
- 2026年安庆市迎江区街道办人员招聘笔试备考试题及答案解析
- 2025-2030年海南清补凉店企业制定与实施新质生产力战略分析研究报告
- 2026年河南省南阳市幼儿园教师招聘笔试备考试题及答案解析
- 2026年广东省湛江市幼儿园教师招聘笔试备考试题及答案解析
- 2026年农业营销金融科技合作协议
- 2026年法律改造碳核查协议
- 现浇钢筋混凝土排水沟施工方案
- 家校同心 决胜高考2026届高三考前一月冲刺家长会
- 人工智能AI创业计划书
- 国家电网有限公司输变电工程通 用设计(330~750kV输电线路绝缘子金具串通 用设计分册)2024版
- 志愿服务孵化基地评估标准与流程
- 2025年电解铝项目可行性研究报告
- 高中语文文言文阅读典籍分类专训:散文类 先秦诸子散文(全国甲卷、乙卷适用)
- 学生心理健康一生一策档案模板
- 《青春梦想责任担当》班会课件
- 中国历史最经典的七个人才智慧案例
- 动力柜施工方案
评论
0/150
提交评论