目录
1编制说明...........................................................12
1.1编制目的.....................................................12
1.2编制依据.....................................................12
1.3技术标准和要求...............................................12
2工程概况...........................................................14
2.1工程概述.....................................................14
2.2自然条件......................................................15
2.3其他情况说明.................................................15
3施工总体部署及准备工作.............................................16
3.1施工总平面图布置.............................................16
3.1.1施工总平面布置图.......................................16
3.2施工准备工作计划..............................................16
3.2.1前期施工准备...........................................17
3.2.2施工准备内容...........................................18
3.2.3现场交接准备...........................................18
3.2.4施工技术准备...........................................18
3.2.5主要机械设备准备.......................................20
3.2.6劳动力准备.............................................21
3.2.7主要物资准备...........................................21
4施工项目管理目标及组织架构.........................................22
4.1质量目标.....................................................22
4.2安全文明施工目标.............................................22
4.3环境保护目标.................................................22
4.4投资控制目标.................................................22
4.5团结协作目标.................................................22
4.6服务目标.....................................................23
4.7项目管理机构设置.............................................23
4.8主要岗位人员职责、授权范围...................................23
4.9施工组织机构高效运作保障措施.................................33
4.10项目组织管理机构图...........................................34
5工程施工方案与技术措施............................................36
5.1施工测量.....................................................36
5.1.1施工测量的原则.........................................36
5.1.2施工测量准备...........................................36
5.1.3测量控制网的布设.......................................37
5.1.4施工测量...............................................38
5.1.5施工中的测量放线.......................................39
5.2防水施工.....................................................40
5.2.1防水卷材...............................................40
5.2.2聚氨酯防水涂料.........................................43
5.3基础工程.....................................................47
5.3.1截桩头.................................................47
5.3.2质量标准...............................................47
5.3.3土方回填................................................48
5.4模板工程.....................................................49
5.4.1施工目标和原则.........................................49
5.4.2模板体系的选择.........................................49
5.4.3模板的安装与支撑固定....................................50
5.4.4模板施工................................................50
5.4.5模板安装质量控制........................................55
5.4.6模板拆除................................................58
5.4.7模板工程质量通病防治措施................................60
5.5钢筋工程......................................................60
5.5.1钢筋的采购与检验........................................60
5.5.2钢筋的制作..............................................61
5.5.3钢筋的连接..............................................63
5.5.4钢筋的绑扎..............................................65
5.5.5钢筋工程质量检验........................................67
5.6混凝土工程...................................................68
5.6.1混凝土强度等级.........................................68
5.6.2混凝土施工实施目标.....................................68
5.6.3混凝土施工特点分析.....................................68
5.6.4混凝土施工前的准备.....................................68
5.6.5商品混凝土的质量控制...................................71
5.6.6混凝土材料的选择.......................................72
5.6.7现场混凝土施工.........................................75
5.6.8混凝土施工技术措施.....................................76
5.6.9成品保护...............................................78
5.7砌体工程.....................................................78
5.7.1施工准备...............................................78
5.7.2加气混凝土砌块墙体施工.................................80
5.7.3加气混凝土砌块拉结钢筋与框架柱墙的锚固工艺.............83
5.8脚手架工程....................................................86
5.8.1材料与设备计划.........................................86
5.8.2技术参数...............................................88
5.8.3工艺流程...............................................88
5.8.4施工方法...............................................89
5.8.5架体安装...............................................94
5.8.6检查验收..............................................100
5.8.7施工安全保障措施......................................103
5.8.8监测监控..............................................115
5.9屋面工程.....................................................117
5.9.1施工操作要点..........................................117
5.9.2细部做法..............................................121
5.9.3成品保护措施及安全注意事项............................124
5.10电气安装工程................................................125
5.11给排水工程..................................................135
5.11.1工艺流程..............................................135
5.11.2预留预埋..............................................136
5.11.3给排水工程主要施工方法................................136
5.12楼地面工程................................................138
5.12.1施工准备..............................................138
5.12.2施工工艺..............................................138
5.12.3质量标准及注意事项....................................143
5.12.4质量保证..............................................144
5.12.5成品保护.............................................145
5.12.6安全保证.............................................146
5.12.7文明施工.............................................147
5.13装饰装修工程..............................................147
5.13.1施工顺序.............................................147
5.13.2施工准备.............................................148
5.13.3主要项目施工方法.....................................148
5.13.4质量标准.............................................162
5.13.5不合格品控制及纠正措施...............................162
5.13.6安全管理措施.........................................163
6工程质量技术保证措施.............................................165
6.1质量保证体系................................................165
6.1.1质量管理文件..........................................165
6.1.2质量组织体系图........................................165
6.1.3质量职责..............................................166
6.1.4质量保证程序..........................................167
6.1.5质量过程执行程序......................................167
6.1.6质量信息反馈体系.......................................167
6.2质量保证管理制度.............................................168
6.2.1工程项目质量负责制度...................................168
6.2.2技术交底制度...........................................168
6.2.3材料进场检验制度.......................................169
6.2.4样板引路制度...........................................169
6.2.5施工挂牌制度...........................................169
6.2.6过程三检制度...........................................169
6.2.7质量一票否决制度.......................................169
6.2.8成品保护制度...........................................169
6.2.9计量管理制度...........................................170
6.2.10质量文件记录制度......................................170
6.2.11竣工服务承诺制度......................................170
6.2.12培训上岗制度.........................................170
6.2.13工程质量事故报告及调查制度...........................170
6.2.14工程回访服务制度.....................................171
6.3质量保证措施................................................171
6.3.1采购物资质量保证......................................171
6.3.2技术保证..............................................171
6.3.3合同保证..............................................172
6.3.4试验保证..............................................172
6.3.5施工质量过程控制......................................172
6.4成品保护措施................................................178
6.4.1成品保护组织机构......................................178
6.4.2成品保护的实施措施....................................179
6.5质量薄弱环节及预防措施......................................181
7安全文明施工保证措施.............................................185
7.1安全施工保障措施............................................185
7.2安全生产管理目标............................................185
7.3安全生产管理方针和原则......................................185
7.4安全生产管理体系............................................186
7.4.1安全管理机构...........................................186
7.4.2安全保证管理体系.......................................186
7.4.3安全保障组织机构.......................................187
7.4.4安全保障管理程序.......................................188
7.4.5安全保障检查程序.......................................189
7.4.6安全生产管理职责.......................................189
7.5安全管理制度................................................191
7.5.1安全教育培训制度.......................................191
7.5.2安全交底制度...........................................191
7.5.3班组班前安全活动制度...................................191
7.5.4安全检查制度...........................................192
7.5.5安全隐患整改责任制度...................................192
7.5.6安全用电制度...........................................193
7.6安全技术措施................................................193
7.6.1工地大门..............................................193
7.6.2安全通道..............................................194
7.6.3加工车间棚............................................194
7.6.4三宝”的使用..........................................195
7.6.5“四口”、“五临边”的安全防护措施.....................197
7.6.6脚手架的使用和安全防护................................199
7.6.7基坑内作业安全防护措施................................200
7.6.8高空作业安全防护......................................200
7.6.9施工机具安全防护......................................201
7.6.10现场施工用电安全防护措施.............................202
7.6.11消防安全防护措施......................................202
7.7安全薄弱环节的预测及防治措施...............................203
7.8文明施工管理体系............................................209
7.9施工作业区文明施工管理......................................210
7.9.1现场围墙...............................................210
7.9.2封闭管理...............................................210
7.9.3施工现场...............................................210
7.9.4材料堆放...............................................211
7.9.5现场管理...............................................211
7.10办公生活区文明施工管理....................................212
7.10.1临建搭设.............................................212
7.10.2现场办公室...........................................212
7.10.3生活区.................................................213
7.10.4食堂.................................................213
7.10.5厕所...................................................213
7.10.6六牌三图.............................................214
7.10.7办公生活区管理.......................................214
7.10.8文明施工检查措施.....................................214
7.11现场文明及环保施工管理体系................................215
7.12降低环境污染技术措施......................................215
7.12.1施工排放污水控制措施..................................215
7.12.2扬尘控制措施..........................................216
7.12.3固体废弃物污染控制措施................................217
7.12.4噪声污染控制措施......................................217
7.12.5大气污染控制措施......................................218
7.12.6光污染控制措施........................................219
7.12.7资源回收再利用措施....................................219
7.12.8施工环境绿化措施......................................219
7.13减少扰民技术措施...........................................219
7.13.1现场管理措施..........................................219
7.13.2降低现场噪音的控制措施................................220
7.13.3防止灯光干扰.....................................221
7.13.4加强对外宣传工作,争取周围居民的谅解与支持.......221
7.13.5建立项目与周围居民的协调互助关系......................222
7.14安全生产事故应急救援预案...................................222
7.14.1现场危险性较大分部分项工程及施工现场易发生重大事故部位222
7.14.2应急准备和响应组织准备...............................223
7.14.3施工现场的应急处理设备和设施管理.....................224
7.14.4潜在危险源的应急准备和响应(事故)事件...............227
8工程进度计划与工期保证措施.......................................249
8.1施工总进度计划...............................................249
8.2工期保证措施.................................................250
8.2.1前期准备..............................................250
8.2.2确保工期的组织措施....................................250
8.2.3确保工期的技术措施....................................250
8.2.4确保工期的管理措施....................................252
8.2.5确保工期的经济措施....................................253
8.2.6其他方面措施..........................................253
9主要机械设备、材料选用及进场计划.................................255
9.1资源配备计划................................................255
9.1.1分批、分期所用的主要材料、构配件计划..................255
9.1.2主要周转材料..........................................255
9.1.3工程用主要材料........................................256
9.2拟投入的主要施工机械设备及进场计划.........................257
9.2.1主要机械设备的进场计划................................257
9.2.2主要机械设备的布置....................................258
9.2.3设备的维护............................................258
10劳动力资源配置计划............................................259
10.1项目经理部管理人员计划.....................................259
10.2劳务队伍劳动力计划.........................................259
10.3劳务分包情况...............................................259
10.3.1拟派往本工程劳务队伍及劳务分包情况...................259
10.3.2劳动力保障措施.......................................259
10.4劳动力计划表..............................................260
11季节施工措施..................................................261
11.1雨季施工措施...............................................261
11.2夏季高温施工措施...........................................261
12大体积混凝土施工措施..........................................263
12.1.1大体积混凝土裂缝的防治技术............................263
12.1.2浇筑施工要点..........................................263
12.1.3温度监控措施..........................................264
13工程交付、回访和维修服务......................................267
13.1工程交付..................................................267
13.1.1保修期限承诺........................................267
13.1.2定期回访制度.........................................267
13.1.3保修责任.............................................267
13.1.4保修措施.............................................267
13.1.5保修记录.............................................268
14附表部分......................................................269
14.2附表一:开、竣工计划......................................270
14.3附表二:施工总平面图......................................270
1编制说明
我司在认真查看施工图纸和仔细勘察现场的基础上,经过充分的研究和论证,
以严谨的态度编写本工程施工组织设计。
L1编制目的
本施工组织设计体现了我司对本工程施工的总体部署与原则性做法,我司将依
据本文件及其他有关文件确定的原则和方法,严格遵循我司质量、职业健康与安全
和环境管理体系文件和技术管理标准,编制详细的重要分部分项工程《施工方案》。
经审批的《施工组织设计》和《施工方案》将是指导和规范工程施工的重要技术文
件之一,以确保优质、高速、安全、文明地完成本工程的建设任务。
1.2编制依据
1、XX启源建筑设计有限公司提供的施工图纸;
2、对现场和周边的踏勘情况;
3、国家行业及地方现行的相关法规、规范、规程及验评标准;
4、xx省及佛山市有关现场安全、文明施工的各种规定;
5、招标文件、设计单位指定的各类标准、规范、规程;
1.3技术标准和要求
根据设计施工图纸和技术文件要求,本工程项目的材料、设备、施工达到以下
现行中华人民共和国及省、市、行业的有关法规、规范的要求,如下述标准及规范
要求有出入则以较严格者为准。
《工程测量规范》(GB50026-2007)
《建筑地基基础工程施工质量验收规范》(GB50202-2002)
《钢筋焊接接头试验方法标准》(JGJ/T27-2001)
《钢筋焊接及验收规范》(JGJ18-2003)
《钢筋机械连接通用技术规程》(JGJ107-2003)
《混凝土外加剂应用技术规范》(GB50119-2003)
《混凝土泵送施工技术规程》(JGJ/T10-2011)
《砌体工程施工质量验收规范》(GB50203-2002)
《建筑装饰装修工程施工质量验收规范》(GB50210-2001)
《屋面工程质量验收规范》(GB50207-2002
《建筑地面工程施工质量验收规范》(GB50209-2002)
《建筑给水排水及采暖工程施工质量验收规范》(GB50242-2002)
《建筑电气安装工程施工质量验收规范》(GB50303-2002)
《建筑工程施工质量验收统一标准》(GB50300-2001)
《建筑工程施工现场供用电安全规范》(GB50194-93)
《施工现场临时用电安全技术规程》(JGJ46-2005)
《建筑机械使用安全技术规程》(JGJ33-2001)
《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2011)
《建筑施工高处作业安全技术规范》(JGJ80-91)
《建筑施工安全检查评分标准》(JGJ59-99)
《建筑变形测量规范》(JGJ8-2007)
《建筑施工手册》(第四版)
《建筑工程施工质量评价标准》(GB/T50375-2006)
《建设工程文件归档整理规范》(GB/T50328-2001)
以上规范如有变化,以最新发布的为准。
2工程概况
2.1工程概述
-工程概况
序号项目内容
1工程名称梅沙实验学校A标段
2工程地址
3建设单位
4设计单位XX省启源建筑设计有限公司
5监理单位XX粤能监理有限公司
6勘察单位XX永基建筑基础股份有限公司
7施工单位
一、建筑设计概况:
小学宿舍楼
建筑面积15123.76m2建筑特点
教学楼16233.4m2
建筑用途住宅/教学地下层高度/
地下层数/地上标准层高度3.6m
地上层数6F/7F室内外高差/
非标准层高度2.95m建筑总高26.60m
±0标高绝对高程20.100m建筑防火等级一级
檐口高度26.2m地下室防水等级/
楼梯结构形式板式楼梯地下室用途/
二、结构设计概况:
项目内容
基础形式预应力管桩基础
结构形式
结构形式框支剪力墙结构
混凝土
C20、C25、C30、C35、C40、C45、C50、
强度等级
抗震等级二级工程设防烈度7度
钢筋等级三级使用位置主楼/泳池
2.2自然条件
本工程建设地点位于南海区佛山科技学院以西,道路交通方便,施工机械设备及
材料均可方便到位施工;现场三通一平工作已完成,施工用水及用电按照施工需要
已有建设单位提供到位并可满足施工;工程所在地每年4月份至9月份为主汛期,
较多雷雨天气,对施工进度、质量及安全均可能造成一定影响;工程所在地年平均
气温为21.9C,冬季最低气温大于5C,夏季最高气温可达30c以上,故可不考虑
冬季施工,但夏季高温作业应允以考虑。
2.3其他情况说明
3施工总体部署及准备工作
3.1施工总平面图布置
3.1.1施工总平面布置图
按照“合理布置,有利施工”原则,同时考虑到现场条件及设计特征要求,布置
现场,具体平面布置见施工平面布置图。
3.2施工准备工作计划
主要把握原则为:按顺序分段分块流水展开,主体结构为主线,安装工程随后
跟进,流水作业施工,纵横穿插,衔接紧凑,组织严密,空间占满,时间不断的立
体交叉施工。
施工程序主要原则:
以结构为主线,按施工总平面布置图中的分块顺序流水施工,相应机械设备如
塔吊、输送泵、汽车吊等适时进场,其它分部分项工程如楼梯、砌体、预留预埋适
时插入。
主体结构按照每一楼层每个单元为一个施工分段,施工顺序为自下而上逐层施
工。在墙、柱根部留设水平施工缝,梁柱节点按设计规范要求处理。
插图3-2-1主体结构施工流程图
3.2.1前期施工准备
1、进场后积极配合建设单位、监理工程师做好与前期土方施工单位的交接,办
理好与规划部门现场测量控制点交验手续。
2、作好前期技术准备工作,包括图纸会审准备,施工组织设计和施工方案编制、
详细的实施施工进度计划编制,按照各专业结构预留预埋深化设计,及混凝土配合
比优化设计等前期技术准备工作。
3、按照确定的总平面布置设计图进行现场平面布置的调整和完善工作。
4、按经审批的施工方案完成塔吊基础施工和塔吊安装。
5、做好项目各种资源的调配工作,管理人员、各种机械设备、周转架料、劳动
力按计划分批进场。
6、配合建设单位完成开工前各项质量、安全、文明施工、环保、交通、消防等
法定监督手续,与建管、质监、环保、交通、公安、街道办事处、居委会等地方政
府部门及周围居民取得联系和沟通,作好外部的协调工作;建立与地方政府管理部
门和建设单位、监理、设计院间的联络机制,保证沟通渠道畅通。
3.2.2施工准备内容
1、配合业主完成政府部门相关手续的办理、备案及取证;
2、施工现场规划;
3、人员、机械、物资调配;
4、施工技术准备;
5、施工计划准备:包括劳动力计划、主要设备物资计划、方案编制计划等;
6、临时设施施工准备。
3.2.3现场交接准备
平整现场场地,清除现场障碍物。根据工程施工总平面布置设计,修建临时生
产及生活设施,敷设现场供水、供电等管线。
根据现场施工总平面布置图,在施工场地内设置临时性排水系统,使场地内雨
水、施工及生活污水有组织地排入市政排水系统。
按照企业形象设计实施标准、施工总平面布置和本施工组织设计关于文明施工
与环境保护的要求,对现场进行CI策划和设计,在进场后一个月内完成CI相关标
识等的实施。
配合业主办理施工许可证等法定手续,并与质量安全监督部门、交通、市政、
电力、自来水、电讯、城管、公安部门建立联系,办理必要的登记和监督手续,为
工程的顺利开工创造良好的外部环境。
3.2.4施工技术准备
(1)施工图纸会审
项目部组织有关专业人员认真学习和熟悉图纸,及时将设计和图纸疑问以书面
形式提交监理转业主、设计单位处理,协助业主组织好图纸会审工作。
(2)施工组织设计编制
编制本工程进场实施的施工组织设计,经内部审批后报监理、业主审批。并根
据本工程特点,我们将在施工进展过程中,编制单项施工方案,作为工程施工生产
的指导性文件。各分部分项工程的施工方案的编制计划如下表5.3T如示。
插表3-2-1专项技术方案编制计划
序号分项工程施工方案名称完成时间
1施工组织设计进场后三周
2塔吊安装专项施工方案施工前一周
3临时施工用电施工方案施工前一周
4钢筋工程施工方案施工前一周
5模板工程施工方案施工前一周
6混凝土工程施工方案施工前一周
7脚手架工程施工方案施工前一周
8砌体工程施工方案施工前一周
9屋面工程施工方案施工前一周
10重大安全事故应急处理预案施工前一周
11重大危险源控制专项施工方案施工前一周
12质量通病防治专项施工方案施工前一周
13其它甲方、监理要求的施工方案施工前
(3)进行技术交底
工程开工前由项目技术负责人组织施工人员、质安人员、班组长进行交底,针
对施工的关键部位、施工难点、质量和安全要求、操作要点及注意事项等进行全面
的交底,各个班组长接受交底后组织操作工人认真学习,并要求落实到各个施工环
节之上,对参与重点工程项目施工的人员进行培训,使其充分掌握施工重点,为搞
好施工质量打好基础。
(4)测量控制网建立
根据业主给定的基准点,建立适合本工程的测量控制网,包括控制基线、轴线
和水平基准点,做好定位轴线的控制测量和校核。控制网要避开建筑物、机械操作
及运输线路,并有保护标志,其中重要的控制坐标要做成相对永久性的坐标点。
(5)试验工作准备
按照设计及规范要求,编制试验工作计划,包括混凝土强度试验及抗渗试验、
钢筋原材料与接头试验、防水材料试验、钢筋原材与接头连接试验、混凝土结构实
体检验等试验与检验计划,提前进行混凝土、砂浆配合比设计申请与试验,并完成
现场试验室必需的试验工具的准备。
(6)施工技术交底
进场后,组织施工人员学习和熟悉施工图纸,严格按照企业标准,精心准备和
组织“三级”技术交底,即项目技术负责人一一管理层一一作业班组一一操作工人。
交底的内容包括主要设计内容和各项技术要求,施工组织设计主要内容,工程质量、
安全、工期和文明施工等要求,施工程序和各专业工序间的配合关系等。
3.2.5主要机械设备准备
主体结构施工阶段拟采用3台塔吊进行场内机具、大宗材料的水平运输和垂直
运输。
主体结构施工人货电梯进场,具体数量按照使用木模的楼栋每单元1台,使用
铝模楼栋每栋1台安排,共计2台。
详细的主要施工机械、设备的投入计划如下表:
序号设备型号数量来源
1塔吊TC6016(55米)2租赁
2挖掘机PC200-86租赁
3人货电梯SCD200/200V3租赁
4地泵HBT90.20.180S4租赁
3.2.6劳动力准备
根据本工程的特点,我们将通过招标确定具备相应资质、业绩优秀、作风过硬、
服务意识强、人员素质高的劳务分包单位,签订分包施工合同。施工人员进场后,
按照有关规定组织入场教育,对特殊工种作业人员持证上岗进行严格审查。
3.2.7主要物资准备
根据设计图纸和实际情况编制不同施工阶段的主要材料的需用计划,根据总体
需用计划编制每月、周需用计划,由我公司物资部组织采购进场。材料的进场,将
严格按照设计、规范要求、企业标准和业主及监理单位要求进行原材料的检验和试
验,确保质量。
4施工项目管理目标及组织架构
我司将按照投标承诺以及质量管理体系、环境管理体系、职业健康安全管理体
系对本工程施工进行全过程控制,并对工程实施目标管理。
4.1质量目标
(1)争创佛山市“佛山市优良样板工程”;
(2)每次集团或区域检查在84分以上,保证一次性通过联合验收;
(3)确保交楼后维修关闭率维持在90%以上。
4.2安全文明施工目标
(1)确保取得“佛山市房屋市政工程安全文明施工示范工地”;
(2)争创“xx省安全文明施工示范工地”
(3)杜绝重大安全事故,争取工伤事故死亡率为零,一般事故发生V1.5%。。
4.3环境保护目标
遵守地方政府及相关管理部门的各项有关规章制度,做好施工噪音、污水排放、
粉尘排放等方面的控制措施,做好既有基础设施的保护工作,做好现场出入口附近
的保洁工作,最大限度地减少施工对周边业主日常工作、生活的干扰。
4.4投资才空制目标
积极协助业主进行投资控制,提出合理化建议,科学地编制施工方案和作业计
划,以帮助业主达到投资与效益的最佳结合点。
4.5团结协作目标
急业主之所急,想业主之所想,提高服务意识,协调好与业主、设计、监理、
各专业分包单位以及政府部门的关系,密切配合,营造一种精诚协作、积极高效、
和谐健康的工作氛围,以实现本工程各项目标。
4.6服务目标
服务目标:建造业主满意工程。
信守合同、密切配合、认真协调与各方关系,接受业主和监理的控制与监督,
做好“三项服务”:
(1)施工前服务:开工前积极配合协助业主进行现场规划布置、施工组织设计
的编制、施工资源的准备等。对设计、设备、材料等提供合理化的建议。
(2)施工中服务:满足业主方对工程进度、质量、安全、文明施工等方面的要
求,服从业主的调度与管理,并积极协助业主方对现场进行管理。
(3)施工后服务:按照国家标准和招标文件要求在我司承诺保修期内及时进行
工程回访及维修。根据工程特点和必要性,编制使用说明书,与竣工资料一起提交
业主,以方便业主的使用与管理。
4.7项目管理机构设置
为确保本工程各项管理目标和服务目标的实现,本着结构合理、精干高效的原
则,我司将设立梅沙实验学校工程项目经理部,项目经理部为直线型组织机构,以
便充分利用企业资源,下设“五部一室”。选派综合素质高、具有丰富的同类工程施
工经验的各个专业人员组成项目班子。实行项目经理负责制,履行施工管理的权力
和义务,负责工程的计划、组织、指挥、协调和控制,代表法人全面履约。
4.8主要岗位人员职责'授权范围
4.2.1、项目经理
1、项目经理是公司法人在项目上的授权人,对项目的质量、进度、安全、文明
施工、资金、信息化、CI覆盖和成本控制全面负责;
2、认真执行国家、地方政府和上级有关方针、政策及公司、集团公司的各项规
章制度;
3、根据公司授权代表项目部负责对集团、公司内部以及项目围墙外的大小事务
统一进行归口管理;
4、主持或参与项目整体策划、施工组织设计、项目质量计划的编制工作,积极
推广建筑业十项新技术;
5、负责编制项目部所需劳务、材料、设备等资源需求计划(招标计划),参与
项目材料的询价和招标工作,参与项目劳务队伍的选择和劳务合同的谈判工作;
6、代表项目部和公司一同签订与劳务队(班组)、材料供应商等有关经济合同、
安全合同(含各种协议);
7、负责组织、完善项目管理各项规章制度并督促贯彻执行;
8、认真履行与业主的各项合同条款;
9、建立项目成本核算制度。代表项目
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 青岛旅游元宇宙项目可行性研究报告
- 钢水增氮技术项目可行性研究报告
- 防汛知识培训粮库课件
- 智慧城管数某省市管理系统建设方案
- 人教版(2024)八年级上册Unit 2 Home Sweet Home Section A (1a-pronunciation)课件(内嵌视频)
- 行业标准合作协议
- 金融证券行业发展前景预测
- 人力资源代理合同6篇
- 合同范本之牛羊肉销售合同7篇
- HR数据分析应用-洞察及研究
- 湖南文艺出版社小学四年级上册全册音乐教案
- 乡村振兴文旅融合发展项目可行性研究报告
- 专科护理建设体系构建与实施路径
- 直销团队文化课件
- 旅游景区管理协议书
- 如何提高采购效率培训课件
- 《飞行控制系统》课件
- 环境保护工程质量保证措施
- 2025外研版英语八年级上册多元化教学计划
- 新团员培训第一课:青年你为什么要入团
- 公司6s管理制度
评论
0/150
提交评论