年4月19日深圳大学施工组织设计文档仅供参考目录1.编制总说明1.1编制依据············································31.2工程概况············································51.2.1总体说明··········································51.2.2基础工程概况·····································61.2.3主体工程概况······································61.2.4施工进度要求······································61.2.5施工条件··········································62.施工部署2.1施工方案与流程······································72.2施工管理组织机构及责任明细··························72.3施工总进度计划······································92.4施工准备············································92.4.1技术准备·····························.···········102.4.2材料准备·········································102.4.3施工机械布置·····································122.4.4施工平面布置说明·································132.4.5施工机械进场计划·································142.5用水用电安排·······································162.6劳动力安排计划·····································172.7质量保证措施·······································172.8建筑成品及半成品保护措施···························182.9安全管理措施·······································182.10雨季及高温天气施工技术措施························202.11消防保卫及现场材料管理措施························212.12施工现场卫生管理措施······························223.分项工程施工方案3.1放线测量···········································243.2土方工程···········································253.3基础工程···········································263.4脚手架工程·········································263.5模板工程···········································273.6钢筋工程···········································273.7混凝土工程·········································293.8预应力混凝土工程···································323.9地下室防水工程·····································323.10砌体工程··········································333.11屋面防水工程······································353.12装饰装修工程······································364.冬季施工4.1冬施部署···········································434.2冬施准备···········································434.3主要施工措施·······································444.4雨期施工方案·····································475工程交付后服务竣工后的服务与保修···································481.编制总说明1.1编制依据(1)基本依据:1、国土规划局、消防局和人防办等政府职能部门就本工程的相关批文。2、工程施工招标文件、招标答疑纪要及设计单位提供的相关图纸。3、地质勘测报告:深圳市勘察测绘院提供的本工程详细勘察报告书。4、抗震设防以及风荷载、雪荷载参数:抗震设防类别:丙类抗震设防烈度:7度抗震等级:三级设计地震分组:第一组设计基本地震加速度:0.10g建筑场地类别:Ⅱ类基本风压:0.75KPa地面粗糙度:C类(2)主要设计规范、规程以及技术规定:(除下述外尚应按国家、部委及地方制定的设计和施工现行标准、规范和规程执行)1.<房屋建筑制图统一标准> GB/T50001-2.<建筑结构制图标准>GB/T50105-3.<建筑结构荷载规范>GB50009-4.<混凝土结构设计规范>GB50010-5.<建筑抗震设计规范>GB50011-6.<建筑地基基础设计规范>GB50007-7.<建筑地基处理技术规范>JGJ79-8.<地下工程防水技术规范>GB50108-9.<混凝土结构工程施工质量验收规范>GB50204-10.<建筑地基基础工程施工质量验收规范>GB50202-11.<建筑基桩检测技术规范>JGJ106-12.<钢筋机械连接通用技术规程>JGJ107-13.<钢筋焊接及验收规程>JGJ18-14.<冷轧带肋钢筋混凝土结构技术规程>JGJ95-15.<建筑地基基础设计规范>DBJ15-31-16.<建筑桩基技术规范>JGJ94-9417.<预应力混凝土管桩基础技术规程(广东省标准)>DBJ/T15-22-9818.<广东省建筑地基基础设计规范>DBJ15-31-19.<高层建筑混凝土结构技术规程>JGJ3-20.<砌体工程施工质量验收规范>B502203-21.<屋面工程质量验收规范>B50207-)22.<建筑地面工程施工质量验收规范>(GB50209-)23.<建筑装饰装修工程质量验收规范>(GB50210-)24.<建筑给水排水及采暖工程施工质量验收规>(GB20242-)25.<建筑工程项目管理规范>(GB/T50326-)26.<多孔砖砌体结构技术规范>(JGJ137-)(J129-)27.<钢筋焊接接头试验方法标准>(GJ/T27-)(J140-)28.<工程测量规范>(GB50026-93)29.<钢筋焊接及验收规范>(JGJ18-96)30.<建筑工程质量评定标准>(GBJ302-88)31.<钢结构工程施工质量验收规范>(GB50205-)32.<钢筋焊接接头试验方法标准>(JGJ/T27-)33.<建筑电气工程施工质量验收规范>(GB50303-)34.<建筑给水排水及采暖工程施工质量验收规范>(CJJ/T29-98)35.<给水排水管道工程施工及验收规范>(GB50268-97)36.<工业金属管道施工及验收规范>(GB50235-97)37.<建设项目管理规范>(GB50326-)38.<建筑施工安全检查标准>(JGJ59-99)(3)采用的图集:1、03G101-1混凝土结构施工图<平面整体表示法制图规则和构造详图>(现浇混凝土框架、剪力墙、框架-剪力墙、框支剪力墙结构)2、03G101-2混凝土结构施工图平面整体表示方法制图规则和构造详图(现浇混凝土板式楼梯)
3、04G101-4混凝土结构施工图平面整体表示方法制图规则和构造详图(现浇混凝土楼面与屋面板)
4、06G101-6混凝土结构施工图平面整体表示方法制图规则和构造详图(独立基础、条形基础、桩基承台)(4)、设计采用可变荷载数值单位:KPa(KN/m2)部位一层楼面办公室阳台、走廊屋面消防楼梯荷载10.0(施工堆载)2.02.53.0(覆土另计)3.5楼面、地面均布活荷载(可变荷载)标准值,未注明者按GB50009-取值。屋顶花园填料厚度不大于300mm,容重不大于10KN/m3。屋顶花园填料厚度不大于800mm,容重不大于16KN/m3。公共卫生间总恒载不大于8.0KN/m2。1.2工程概况1.2.1总体说明深圳大学土木工程实验室是深圳市财政专项投资的实验办公综合楼建设项目,位于深圳大学南校区,与现有校园以白石路相隔,详见建筑总平面图Z-01和Z-02。本工程设计标高±0.000相当于绝对标高+6.450m。本工程建筑总面积13682m2。建筑总高度20.6m。地上五层,地下一层,该项目办公楼部分五层分A、B两个区,南座为A区,北座为B区,实验大厅部分一层为C区。结构类型为钢筋混凝土框架结构。北面与已建成的深圳大学研究生楼相邻,东边和南边分别与高新南九路和学府路相邻,周围环境比较开阔,有利于施工活动的展开和空间安排。该项目施工图由机械工业部深圳设计研究院设计。土建工程施工组织设计主要内容有:工程概况,施工组织管理,施工部署和施工方案,施工进度计划安排,劳动力及机具投入情况,质量、安全、文明施工保证措施,钢筋工程、模板工程、混凝土工程、脚手架工程、砌体工程、装饰工程、门窗工程、屋面防水工程等施工方法。对于未纳入总承包合同范围的诸如消防系统、弱电工程、外电工程、外水工程、煤气工程、白蚁防治工程等施工方法不做详细叙述。1.2.2基础工程概况本工程采用静压式高强预应力混凝土管桩(PHC),桩身混凝土强度等级为C80,管桩直径为Ф400mm,桩型为AB型,壁厚为95,桩尖构造按广东省标准<预应力混凝土管桩技术规程>(DBJ/T15-22-98)附录B中的十字形桩尖。桩端持力层为强风化花岗岩层,终压力取值暂定为2200kN,终压时满载连续复压次数不少于3次。除注明外,单桩竖向抗压承载力特征值暂定为:1200kN。有效桩长小于24米的桩要求桩尖进入强风化岩层不小于1米,送桩深度不应超过2米。有效桩长大于于24米的桩,以桩长及终压力为控制指标.桩承台混凝土为C30,垫层混凝土为C15,钢筋为HPB235级、HRB335级和HRB400。桩承台的钢筋保护层厚度为50mm。1.2.3主体工程概况主体结构为钢筋混凝土框架结构,实验大厅中设有无粘结后张预应力反力墙和强力地板。底板、顶板及侧墙设有后浇带。建筑结构安全等级为二级,地基基础设计等级为丙级,建筑物耐火等级为二级,上部结构框架抗震等级为二级,地下一层在上部结构之下和上部结构之外的抗震等级均为二级。抗震设防烈度为7度。1.2.4施工进度要求计划开工时间为1月4日。合同工期为20个月。1.2.5施工条件施工前场地已平整,施工临时用水水源采用市政管网给水,接水点位于现场西北角;施工临时用电由业主提供高压电源,经过500kVA电力变压器降压,采用三相五线制系统供电,设临时供电配电室,低压配电室内设一台低压配电柜。
2.施工部署2.1施工方案与流程本工程按照”先地下,后地上;先结构,后围护;先土建,后安装”的施工程序的原则,重视专业工程的搭接与配合,注意土建工程施工中设备及安装工程要求的预埋与预留,实现平面分段、立面分层、同步流水的施工程序,以达到各部分、各工种、各专业在时间上和空间上紧密配合、复式推进的目的。地下室工程面积不大,因此不考虑分段施工,一次性施工完毕。±0.000以上工程,按设计的施工缝位置及使用功能区域整体性要求将整栋建筑划分成3个施工段组织大流水作业,每个施工段内各工种之间组织小流水作业。流水施工段具体如下:第一施工段:A区第二施工段:B区第三施工段:C区总体施工流程如下:测量放线→压桩→基坑挖土→承台→基础支模→基础扎筋→基础工程浇注混凝土→地下室底板支模→地下室底板扎筋→地下室底板浇注混凝土→地下室竖向构件(墙、柱)支模→地下室竖向构件扎筋→地下室竖向构件浇注混凝土→地下室顶板支模→地下室顶板扎筋→地下室顶板浇注混凝土→首层竖向构件(墙、柱)支模→首层竖向构件扎筋→首层竖向构件浇注混凝土→回填土方→二层楼板支模→首层楼板扎筋→二层楼板浇注混凝土→二层竖向构件(墙、柱)支模→二层竖向构件扎筋→二层竖向构件浇注混凝土→按二层同样顺序直至结构封顶。结构完成至四层开始插入砌体施工,由下而上进行,与此同时陆续进入室内湿装修。砌体全体完成时由上而下进行外墙装饰。2.2施工管理组织机构及责任明细(1)本工程由公司法人代表授权委托项目经理代表公司全面履行合同直接对工程负责。项目经理部另设项目副经理和技术负责人,下设工程组、质量安全组、设备组、材料组、计财组、后勤组,分别履行项目部的有关工作,详细分工如下:1、项目经理:对工程进行全面负责,代表公司履行合同,督促检查各项职能组的工作。2、土建技术负责人:负责土建工程的技术工作,审查土建工程各作业技术方案,和外界进行技术联系。3、安装技术负责人:负责安装工程的技术工作,审查安装工程各专业技术方案,和外界进行技术联系。4、安全负责人:全面负责本工程的安全、防火工作。执行国家、省、市等有关安全、消防的法律法规。负责对工人进行安全教育。5、工程组:负责工程的具体技术工作,编制、执行各工序作业方案,收集有关技术资料。负责施工材料的统计,根据网络要求,提前作出材料详细供应计划及完成工作量计划,每月上报项目经理审批,进行成本核算。6、质量安全组:负责工程的质量、安全监督,检查、填写各项检查记录。7、设备组:负责本工程设备的订货和安装。负责施工机械设备的进场、安装和维护。8、材料组:负责工程的材料采购工作,根据经营组提供清单提前组织施工材料。9、计财组:负责本工程资金收支和工资的发放工作。10、后勤组:负责对外收发各种资料及文件、日常接待等工作。
(2)项目部领导班子工作职责职务姓名主要工作职责项目经理1、对整个工程的施工活动负全面责任,有权对项目部的所有事项进行裁决。代表项目部进行对外经济活动和签订合同。2、是整个项目的施工安全、工程质量、现场文明、施工进度、资金使用的第一责任人。3、负责处理与协调同业主、监理单位、设计单位、各承包商及其供货商的关系。4、负责项目部资金管理,在确保施工质量、施工安全、施工进度的前提下,努力降低成本,提高企业综合效益。5、贯彻执行国家法规的企业管理制度,处理违章、违纪事件,优化施工环境。6、负责内部承包管理,实施人力资源的优化组合,对人员和工资实行动态管理。项目总工程师1、在项目经理的授权下,对项目工程技术进行全面管理。2、贯彻执行国家有关技术规程、施工规范、工艺标准,负责项目组织设计的审批。3、组织项目工程中的重大技术问题处理和施工现场的综合管理和考评。4、对调试小组进行管理和培训,主持设备通电试验、系统运行等测试工作。工段负责人1、在项目经理的授权下,对主管的现场施工进行全面管理。2、主管生产调度、施工技术、工程质量、施工安全工作,对工程的质量、施工进度、施工安全负直接责任。3、负责协调各施工作业工段的施工活动,及时处理实施承包过程中的各种矛盾和问题。2.3施工总进度计划见施工进度横道图(附件1)2.4施工准备2.4.1技术准备(1)对工程的特殊部分,施工难点的施工方法,现场专门进行技术交底,制定出切实可行的施工方案及特殊作业指导书,逐级进行技术交底指导施工。技术交底的主要对象是项目部管理人员、施工作业层的管理人员、作业层的班组长和操作工人。技术交底的主要内容:工程任务、施工图要点、质量标准、操作规程、施工方法、施工技术措施、施工进度、工作配合和安全施工技术等。(2)根据业主提供的点位坐标、高程资料及设计图纸,进行现场地形地貌的复测,中间交接。尽早组织施工控制网的布设,完成测量控制点和控制网络。2.4.2材料准备(1)及时统计材料、构配件数量、规格、型号,提出加工定货的需用计划。(2)混凝土,本工程采用商品混凝土,应按施工计划与混凝土搅拌站签订供货合同。供货日期,数量,等级,配合比,塌落度均要明确规定。混凝土强度等级:A区,地下室基础、地梁、底板混凝土强度等级均为C30,抗渗等级S6。本工程所属范围内要考虑地下水对混凝土的腐蚀性,临水构件混凝土设计抗渗等级S6。与地下室外墙相连的框架柱混凝土强度等级与地下室外墙相同。地下室顶板混凝土强度等级均为C30。地下室顶梁混凝土强度等级均为C30。地面各层楼板均为C30,框架梁各层均为C30,框架柱各层均为C30。B区,地梁为C30,垫层为C15,楼板各层均为C30,框架梁各层均为C30,框架柱各层均为C30。C区,地下室基础、地梁、底板混凝土强度等级均为C30,抗渗等级S6。本工程所属范围内要考虑地下水对混凝土的腐蚀性,临水构件混凝土设计抗渗等级S6。与地下室外墙相连的框架柱混凝土强度等级与地下室外墙相同。试验台座C35,垫层为C15,框架梁均为C35,框架柱均为C30,预制板为C30,屋面板为C30,楼板各层均为C30桩身为C80,承台为C30,垫层为C15水箱为C30,楼梯均为C25。(3)钢筋开工前应按工程概算数据储备足够的预制桩施工所需钢筋。开工后,按进度提前采购各种钢筋,并安排进场,同时进行必要的质检工作。序号材料名称必做项目取样数量及要求备注1钢筋原材拉伸实验、弯曲实验同类别、同型号同批小于等于60t为一验收批总数30%2钢筋接头抗拉强度同施工条件、同批、同等级、同形式接头,小于等于500个为一批取一组总数30%(4)砌块、砂、水泥完成主体结构第三层时,马上开始采购,并安排进场,同时进行必要的质检工作。填充砌块及砂浆(砌块容重单位:KN/m3)位置地下室隔墙外墙内隔墙砌块材料加气混凝土砌块(200厚)加气混凝土砌块(200厚)加气混凝土砌块(200厚、120厚等)砌块强度等级MU5.0MU5.0MU5.0砂浆强度等级、砂浆材料M5M5M5混合砂浆混合砂浆混合砂浆砌块允许容重≤8KN/m3≤8KN/m3≤8KN/m3序号材料名称必做项目取样数量及要求备注1水泥安定性、抗拉、抗折强度同类别、同品牌、同等级、同批小于等于500t取一组总数30%2混凝土砌块稠度、抗压强度每200m3总数30%3砌筑砂浆稠度、抗压强度同等级、同原材、每楼层或250m3总数30%2.4.3施工机械布置施工机械:序号机械设备名称规格型号数量额定功率(KW)生产能力备注1塔式起重机50m\35m255.5+3550m+35m2静压桩机YZY-1002653挖掘机神钢32021121.5m34自卸车FV313151220T5施工电梯34012人6高速井架37.57砼输送泵JJ525027560m3/h9平板振动器ZB30081.010插入式振动器ZN50302.211钢筋切断机GQ4025.512钢筋弯曲机GW402313钢筋调直机JM11214钢筋对焊机UN1-100103215电焊机BX3-50056.316套丝机TQ-32117砂浆搅拌机J4-375417.518圆盘锯MJ1043319压路机YZ16-201台7512t20装载机ZL501台154.53m321空压机V-3/8-11122风镐GJ742.4.4施工总平面布置说明:本工程楼高22.4m,距北面7层研究生教学楼43m,用地南侧为绿地,西侧距基础实验室B(二期7层)17m,中间由校园道路分隔,东侧为校园道路。场地近似直角梯形,北面边长约为149m,东面边长约为193m,南面边长约为78m,南面边长约为180m,主体结构位于场地中部偏西处。(1)办公室设于现场南侧,为8间活动板房组成,面积约160平方米,设监理办公室、项目部办公室等12间。(2)厕所设于现场东南,建筑面积约40平方米。(3)大门和场内临时道路现场开设两个大门。入口设在学府路一侧,出口设在高新南九道,并有洗车槽,避免物资、车辆进入现场后需要倒车出现场。现场围墙及大门完全按照深圳市建筑工程文明施工管理实施细则要求设置。施工现场主门悬挂施工五牌,施工五牌标明工地项目名称、建设单位、设计单位、施工单位、监理单位、开竣工日期等内容。施工现场临时道路及临建地面全部硬化。施工道路路面为150mm厚C20砼,临建地面为80mmC10砼。确保现场的文明施工程度,砼地面有一定坡度朝向排水沟,排水沟沿现场内三边及办公楼四周布设,最后排入下水井。(4)材料库房、加工间、临时堆场计划以场地东面作为堆土区,南面作为生活区,与钢筋区以临时道路分隔,西面作为木工模板区,西北角为配电房,北面为砂浆站以及堆砂场、水泥库。所有材料供应库房均在塔吊工作范围内,而且按照加工生产工艺排列,以提高生产效率。(5)施工现场临时设施计划表如下:序号名称面积㎡用途1办公及会议室160多用职能部门办公、会议召开2宿舍90工人住宿3食堂60现场所在人员就餐4厕所30现场施工期间临时厕所5木工房30材料加工6门卫室20门卫值班7模板堆放场60模板临时存放8周转材料场60周转材料临时存放9钢筋加工场30钢筋加工10砂石堆放场40砂石堆放11砌体堆场20砌体堆放12工具房40小型机器13砂浆搅拌站30搅拌砂浆14配电室15提供电源具体位置详见施工现场平面布置图2.4.5施工机械进场计划序号机械设备名称数量进场时间出场时间备注1塔式起重机2完成二层楼板混凝土浇筑后屋面工程,外墙装饰工程完成后2静压桩机2第一根预制桩能够压桩前一天桩基工程完成后3挖掘机2桩基工程完成后回填土方完成后4自卸车15桩基工程完成后回填土方完成后5施工电梯3完成二层楼板混凝土浇筑砌体工程完成后6高速井架3桩基工程完成后屋面工程,外墙装饰工程完成后7砼输送泵2承台扎筋完成后屋面混凝土浇筑完成后9平板振动器8承台扎筋完成后屋面混凝土浇筑完成后10插入式振动器30承台扎筋完成后屋面混凝土浇筑完成后11钢筋切断机2开工之日屋面钢筋工程完成后12钢筋弯曲机2开工之日屋面钢筋工程完成后13钢筋调直机1开工之日屋面钢筋工程完成后14钢筋对焊机10开工之日屋面钢筋工程完成后15电焊机5开工之日屋面钢筋工程完成后16套丝机2开工之日屋面钢筋工程完成后17砂浆搅拌机4完成主体结构第三层时砌体工程完工后18圆盘锯3土方开挖完成后装饰工程完成后19压路机1台地下室顶板封顶后土方回填完成后20装载机1台开工之日砌体工程完成后21空压机1桩基工程完成后承台支模完成后22风镐4桩基工程完成后承台支模完成后2.5用水用电安排(1)施工临时用水:本工程供水总管根据建设规范工程施工用水量Q1,现场生活用水量Q2,均小于消防用水量Q3,满足消防用水后,即可满足施工生产生活用水要求。而消防用水量为12L/S,查表得经济流速为2.5-3.0m/s,取其下限。则配水管径为:D=(4×12×1000/3.14×2.5)0.5=78mm现场管网按枝状分布主干给水管采用Φ100管径的管道,次管采用φ50mm管道,支管采用φ25mm镀锌水管。临时消火栓除在施工平面图所示外,还分设于各层电梯间内,并应保证消火栓的充实水柱能到达工程内任何部位。栓口出水方向宜与墙壁成90°角,离地面1.2m。(2)施工临时用电:根据现场勘察情况,本工程具有下述几点:1、暂设临时性,施工现场临时用电工程专为现场建筑施工使用,随着建筑工程的进度至工程竣工,该临时供电系统将予拆除。2、露天性,建筑施工一般是露天作业,因此为提供电力的临时用电工程,基本上属于露天用电设备工程。3、建筑物位置,自然条件不选择性。临时用电工程的位置和自然条件由建筑工程施工位置和自然条件决定,按实际位置进行选择。4、选择和确定各供电线路的走向,敷设要求及施工用电设备的安装位置应根据施工现场条件及用电设备情况编制。总配电箱分三个回路配电,实行三级配电制,即总配电箱、分配电箱、末端开关箱配备有相应的漏电器。三个回路走向布置的规格型号。现场各配电箱按设计要求,统一由生产家定制。所有导线必须采用绝缘良好的电线各种规格的电线进入现场,均要有出产检查合格证,严禁使用不合格的产品,现场固定线路采用穿PC管防护埋地敷设移动式线路的电缆要采取临时架空防护措施,不允许拖地乱拉,乱挂在钢筋上,钢管脚手架上及压在钢管,钢筋等重物下面。5、各种电箱统一标明编号,便于使用和维修;所有箱的进出线整齐,穿管敷设。分级设置的各级电源引入县配电箱要尽量靠近负荷中心位置。各机具实行”一机一闸一漏保”制,开关箱距机具位置的距离不大于3米,以便于操作热源随时切断电源。施工现场所有照明,必须装设漏电开关,并设专用电源供电,以保证施工照明不因动作故障而停电。2.6劳动力安排计划工种人数工种人数木工50钢筋工50砼工25架子工12机工10电工5电焊工8普工30总人数190(含水电配合23人)2.7质量保证措施认真组织工长,质检员,熟悉图纸,学习质量验评标准和工艺标准。严格把好原材料成品、半成品质量关,搞好材料试验工作,凡无合格证或经试验不合格的产品,严禁进场使用。技术人员要做好关键部位,主要项目技术方案,技术交底工作,并认真执行隐检签证工作。结构施工中所有预留洞,预埋件在石全浇筑前应严格按图纸检查,不得遗漏。各民工队施工单位相应配备技术、质量、安全、现场管理等负责人,在项目经理部的统一领导下,认真细致的开展工作。试验人员要随工程进度不漏项,及时全面地提供完整准确的试验资料,各项资料齐全,保存完好。施工中做好该工程试件的见证取样和送检工作。技术交底要作到简单明了,突出重点,切实可行。翻样工作要走在施工前做好,翻样人员应加强工作责任心,做到不漏不错。生产施工组织中,技术上要尽量考虑提高周转材料使用率,协调组织流水段的施工,减少施工费用。2.8建筑成品及半成品保护措施在存放,吊运过程中对成型钢筋均应加以保护,以防变形,绑扎的梁板筋严禁踩踏,注意砼施工过程中保护其正确的位置。使用的竹编板、钢模、大模表面、逐层进行调整修理,刷油,而且注意竹编板边缘的涂漆保护,施工中砼吊斗严防与模板的碰撞,拆模时模板要轻拿轻放。加强原材料成品和半成品的保护工作,木材、构配件等运输过程中应加以覆盖和保护,到现场后应逐件验收,入库存放,码放应严格执行公司要求,不超高、超重,倾料放置。各楼层地面砼浇筑完成后,养护达到1.2MPa以上,方可上人施工,砼表面也应加以覆盖,以防碰、磕、破坏。2.9安全管理措施建立、健全项目安全管理体系,加强全员安全教育,提高安全意识。施工人员特别是专业人员要严格遵守国家颁布的<建筑安装安全技术规程>。架子工、机工、电焊工等特殊工种在施工前应接受专业技术教育培训,工长在施工前,做好本工程技术交底工作,各专业工种应持证上岗。新工人入场必须进行安全教育,坚决制止违章指挥和违章作业。落实安全生产责任制。施工现场所有施工人员,严禁不戴安全帽进入现场,严禁高空作业不带安全带,严禁在施工区域内追逐打闹,酒后上岗。严禁现场吸烟、穿拖鞋、赤背、穿短裤。各种大型机械设备安装,拆立运输必须按方案实施,禁止擅自拆改安全防护设施和安全防护装置。施工现场的出入口明显部位地段,要有安全标志牌,标语和宣传通知,随时提醒施工人员注意安全。强化现场的安全检查,坚持跟踪管理,现场发现问题及时解决。各种架子在搭设拆除时应有安全技术方案或交底,搭设时经安全生产部门验收方可使用,拆除时必须经生产安全部门批准后方可拆除。高层结构,首层设封闭水平安全网,沿楼一周,主体结构每四层外挑3m的水平安全网。电梯井、管道井,应用架子、安全网封闭,大模板外挂架,护身栏、操作平台外表面全部外罩立网和水平网。安全网采用总公司指定阻燃型产品。大模板安装拆除操作中,要严格按照规程作业,随时注意塔吊大勾的运行方向和模板运输方向,尽量避开运行线路下方和大臂下方作业,认真听信号指挥。注意脚下部位的障碍物,要求多工种配合协调一致,轻吊轻放。机械设备进场后由技术、生产、机械及有关部门组织正确安装调试及验收,要经常性保养,保持施工机械完好状态。对机械设备使用贯彻管用结合,人机固定的原则,每台机械必须有专人负责管理使用,严格执行三定(定人、定机、定制度)制度。操作人员必须经过培训持证上岗,熟悉所操作机械情况,做到”四懂三会”即懂原理、懂构造、懂性能、懂用途,会操作、会维修保养、会排除故障。对大型机械特别是塔吊、垂直提升机械,外用电梯等设备各种限位装置必须灵敏、齐全可靠。每台塔吊至少要有两名持证上岗的信号指挥员,非信号不得指挥塔吊。信号应清晰准确,各工种应配合一致,协调工作。严禁超负荷起吊,斜吊或斜拉挂钩,五级以上大风或下大雨严禁作业,超吊重物大臂下和物料超吊运行方向下方,尽量减少人员作业和活动。机械设备进场后由技术、生产、机械及有关部门组织正确安装调试及验收,要经常性保养,保持施工机械完好状态。对机械设备使用贯彻管用结合,人机固定的原则,每台机械必须有专人负责管理使用,严格执行三定(定人、定机、定制度)制度。操作人员必须经过培训持证上岗,熟悉所操作机械情况,做到”四懂三会”即懂原理、懂构造、懂性能、懂用途,会操作、会维修保养、会排除故障。对大型机械特别是塔吊、垂直提升机械,外用电梯等设备各种限位装置必须灵敏、齐全可靠。每台塔吊至少要有两名持证上岗的信号指挥员,非信号不得指挥塔吊。信号应清晰准确,各工种应配合一致,协调工作。严禁超负荷起吊,斜吊或斜拉挂钩,五级以上大风或下大雨严禁作业,超吊重物大臂下和物料超吊运行方向下方,尽量减少人员作业和活动。当遇五级以上风力时,施工塔吊应停止作业。模板施工也应尽量避开大风天气,保证施工的安全。健全用电管理制度,严禁无证人员从事电气作业,电工必须持证上岗。做好漏电保护湿作业及现场移动照明均采用安全电压,值班电工要了解和掌握全部电气设备状况及用电线路走向,晚间施工设立足够照明。电工正确穿带防护用品,严禁酒后操作,禁止带电作业,严格按现场临时用电施工组织设计进行电气设施,设备的安装,敷设和验收。所有用电设施外壳必须接零,高大金属架体必须安装避雷装置,非专业人员不得随意动用机电设备,电闸箱要设防护上锁,机电设备设有效防雷、防雨,保护措施。所有电闸箱都必须采用专用配电箱,须有编号系统图,闸具应标明用途,配电箱标明负责人。严禁使用不合格的电气材料和电气设备。凡进入本工程施工的各专业用电单位,都必须服从项目经理部统一管理和要求,按其提出的要求安装各种配电箱(柜),配电线路、计费装置、各种开关和电气保护装置,由总承包单位提供电源接驳点,做到安全用电。凡不按要求进行安装接线,不符合安全要求,存在安全隐患,危及自身及她人安全的用电行为将视为违章用电,对违章用电的单位项目经理部有权令其整改,直至停电整改,合格后方能继续用电。2.10雨天及高温天气施工主要措施雨天及高温天气施工措施的检查监督由项目工程部负责。做好现场排水系统,及时将地面雨水排至城市排水系统。地下室施工时,设排水沟及集水井,备水泵及时排除积水和上层渗水,把地下水位控制在垫层表面下30cm。现场机电设备要做好防雨、防漏电以及防雷措施。雨天施工措施时,混凝土搅拌要注意现场落度的测量。控制测量现场砂石含水率,随时调整,保证按施工规范要求施工。浇筑完成后,要注意墙体顶板砼的表面覆盖,防止砼表面被雨水侵蚀。同时夏季高温要保证每天二次以上的浇水养护,保证砼表面温润,养护要昼夜连续。同时生产施工管理部门应协调现场操作工序,尽量避开高温大雨天的作业,保证施工质量及人身安全。现场各种周转材料,施工用材应保证码放位置,垫高位置。表面应涂刷隔离层防锈漆或加以覆盖,注意有效保证,严防雨淋损坏,现场应相应设置排水设施,抽水用设备应充分,使用状况良好。塔吊、井架、电梯等大型设备要作好接地装置,遇大风、大雨尽量停止砼浇筑作业。高温天气施工梁板混凝土时,宜采用低水化热水泥,以防混凝土出现温度裂缝2.11消防保卫及现场材料管理措施(1)消防保卫管理措施现场设警卫室,配备四名护场巡逻警卫力量,并做好值班记录。建立健全现场治安、保卫安全组织机构,并设立现场义务消防队。本工程设临时消火栓4座,水管直径φ100,水流速度不低于10—15L/S,消火柱设醒目标志,并在5m范围内不准堆放其它材料,垂直方向采用φ75消防立管,多级水泵加压,每二层设出水龙头二个。施工现场严禁吸烟,任何人未经批准不得私自动用明火,使用明火要有用火证。电气焊工持证上岗,有用火审批手续,有防火灭火设施和看火员。工地的易燃易爆及剧毒物品,严格领退手续,油漆、汽油、煤油、稀料等分开存放,储存易燃物品的仓库与宿舍之间防火距离应满足30m。生活区的厨房、锅炉与宿舍间的距离不小于15m,其周围修建排水明沟。天棚的高度在2.5m以上,门向外开。生活区、库区等重点部位严禁烟火,木工房(棚)内禁止吸烟及明火作业。施工现场、生活区等设置四套灭火器材及消防设施,专人保护,定期维修保养,保持灵敏有效,严禁私自挪用消防器材设施。宿舍区,照明电线应有良好绝缘,严禁使用电炉,大灯泡,严禁私接电线,接灯。火炉与床铺安全距离1.5m,不准使用汽油,煤油引火。不准在床前,火炉边堆放可燃物。不准卧床吸烟。施工现场严禁酗酒滋事、打架斗殴、聚众赌博、盗窃公物、财物等。外埠包工队及外来务工人员,须进行认真审核登记,注册后办理暂住手续。(2)现场材料管理措施施工现场按施工平面布置图码放材料,责任明确,有责任区,责任人,设明显标牌。各种材料分规格码放,场地必须坚实平整,码放不超高,一条线,一头齐。周围设排水沟,周转材料不挪用,及时码放维修,砖成丁成行,砂子散料成堆,界限不混乱随用随清,不留底。木材堆放面积不要过大,堆与堆应保持一定距离,木工棚应设在指定地点,及时清理。水泥库具备有效的防雨、防火、防潮措施。散落灰及时清运,码放离墙10厘米楼层施工中,堆放机具,砖块等物品,不得超过200kg/m2,工人操作活完料净脚下清。现场设立施工垃圾分拣站废金属分拣站,及时分拣、清运、回收、利用、标牌明显。2.12施工现场卫生管理措施施工现场、生活区地面平整,无积水、车辆不带泥砂进出现场。办公室内清洁整齐,窗明地净,施工现场有专人清扫,垃圾定点存放。生活垃圾及施工垃圾分开,不准倒泼污水、粪便,以免污染环境。施工现场严禁随地大小便,生活区现场厕所设纱门窗,及冲洗设备,设专人清扫、冲洗、保洁,定期喷洒灭蝇、灭蛹药物。按要求搞好食堂宿舍的卫生管理,防止食物中毒,保证饮用水卫生,宿舍内要设施完备,内务整洁,窗明地净地现场保持整洁、无积水,道路要经常洒水湿润,防止尘土扬起。设专人清扫工地,严禁抛洒细颗粒材料。施工现场废水,泥浆等必须经过沉淀后方可排放,搅拌站,生活区设立污水沉淀池。对生产噪音,振动施工机械应采取有效控制措施,减少施工扰民,作业时间应控制在早6点至晚22点。施工现场垃圾采用容器吊运,随时分拣清运,生活垃圾及时清理,倒运在指定地点,并及时外运至垃圾场。施工现场存放油料,无论库内、库外必须采取防渗漏措施,并用防水砂浆抹面。现场不得焚烧产生有毒、有害烟尘和恶性气体物质,搅拌机安装除尘装置。茶炉、火灶要使用消烟除尘型,控制烟尘黑度。
3.分项工程施工方案3.1放线测量建筑物的定位放线及标高测量依据建施总平面图,放线基点经业主确定,采用全站仪对工程进行施工放线测量,施工测量用控制测量法:横向以1轴、12轴,纵向以A轴、R轴为控制轴线,以A轴为基线放线,以A轴与1轴的交点为角点作矩形,使矩形的测量闭合误差均必须小于规范允许值。本工程相对标高±0.000m,用水平仪将本工程控制水准点测出并作好固定标记。(1)所需仪器序号仪器名称数量用途1GTS-701全站仪1测设控制2J2级经纬仪2轴线投测3DS3水准仪2标高传递4无线对讲机3通讯联终550m钢尺2轴线量测6铅直仪1竖向投点(2)观测要求及测站观测限差水准观测的视线长度、前后视距差、视线高度按下表要求进行等级视线长度前后视距差前后视距累积差视线高度二等0.50.53.0m0.3m水准测量的测站观测限差不超过下表的各项规定。等级基辅分划读数差(mm)基辅分划所测高差之差(mm)上下丝读数平均值与中丝读数的差(mm)二等0.50.73.0观测数据处理采用电算、记录器采用PC1500或E500电子手簿、记录载体为随机纸带。(3)对周围永久性管道的观测,对于周围永久性管线设施的安全问题,根据现场具体管网情况,埋点进行观测,并做详细记录。3.2土方工程(1)土方开挖1、基坑支护在桩施工完后(基坑支护桩见专项方案)才能进行土方开挖。2、土方开挖顺序:土方大面积开挖至底板、承台及地梁砼垫层高高200㎜处人工开挖至底板、承台及地梁砼垫层底标高处排水沟及集水井开挖施工垫层及砌砖模。3、土方开挖前的准备工作a)开挖前清理干净施工区域内障碍物;b)修筑施工场内的机械运行的道路;c)作好设备的试运转,对进行挖土的机械和车辆及各种辅助设备进行维修检查、试运转;d)做好土方工程的放线工作,明确开挖范围及开挖深度。4、土方开挖施工方法a)土方开挖应采用分层开挖,先进行自然地面至-4.0m的土方开挖,一次开挖深度不大于2m,然后进行-4.0m以下的土方开挖,最后进行坑中坑的土方开挖。b)土方开挖用挖掘机进行挖土,汽车运土的方式,每层开挖的深度不大于2m,开挖的同时进行边坡的整理和边坡面的施工,开挖至基坑底,挖土机装运。c)土方开挖,应遵照专业支护设计方案要求进行施工。d)机械挖土应严格控制挖土标高,测量人应跟班作业,预留人工清土厚度不小于200mm,严禁超深超挖.f)在基坑开挖确定中粗砂层的详细情况后,必须通知设计单位,以确定地基处理方案.g)基坑开挖后要进行地基土载荷试验,试验数量四个(由设计确定),压板面积为0.5m2,最大加载量为180KN,试验操作步骤及数据整理应符合≪建筑与地基基础设计规范≫h)基坑土方开挖后,应分块通知监理、勘察、设计有关人员会同审底验收基坑后方可进行下一道工序.i)基坑土方开挖后,应抓紧时间进行验底,缩短基坑底面地基土暴露时间。j)完成验底、载荷试验后应立即向监理、勘探、设计、业主方报验,验底合格后立即进行垫层砼的浇筑,以保护基坑底面土不受雨水浸泡。k)按照支护设计方案要求:坡顶2m范围内不能堆载,坡顶2m范围外地面荷载应小于20MPa。5、边坡的开挖采用挖土机开挖和人工修整相结合的方式,先按照设计要求放出开挖坡顶和坡底线并用白灰线标示清楚,挖土机进行开挖,余土用人工进行清理,并人工对坡面进行夯实。(2)土方回填基础工程隐蔽检查完毕之后方可进行回填土,分层夯实,以保证回填土的质量。3.3基础工程(1)基础施工阶段平面排水基础施工过程中,采用临时明沟形式有组织地导入临时集水井,经过临时集水井经沉淀后排入市政下水道。临时明沟可顺轴线利用带基位置设置,遇基础绕开,其深度不小于200。临时积水井深度在1.5m左右,以利每天清理沉积泥砂。排水系统每天派1人进行维护清理,以保证排水畅通,防止地表水流入基础内影响其作业。(2)砼承台施工1、测量放线2、浇注垫层3、支模4、绑扎钢筋5、浇注混凝土3.4脚手架工程(1)脚手架所用直径48x3.5钢管、扣件、螺栓、铁件、脚手板等主要材料及其它辅助材料,必须经质检部门认定合格后放可使用。(2)脚手架应严格按有关技术操作规程及方案要求进行搭设,经检查合格并挂牌后方可投入使用,加强班前检查,发现问题应立即停止使用。(3)脚手架应有足够的强度、刚度和稳定性。脚手架在搭设、使用前,其稳定性可用手摇杆件等方法进行检查,强度、刚度可用加载试验进行检验。(4)脚手架与墙应有可靠的连接点,竖向间距不大于4m,水平间距不大于4.5m,每面脚手架两端及中间间距不大于15~20m,应设剪刀撑。(5)脚手架操作层应设置栏杆及踢脚板,离地面高度超过4m,应设置安全网封闭。3.5模板工程(1)施工要求1、模板及其支承结构的材料、质量符合规范和设计要求。2、模板的内侧面要平整,接缝严密。3、模板安装后,仔细检查各部位构件尺寸是否牢固,在浇捣混凝土过程中要有专人护模,发现变形、松动现象及时整修和加固。4、固定在模板上的预埋件和预留洞均不遗漏,安装牢固,位置准确。(2)注意事项1、模板及支承架应严格按施工方案进行安装,应保证其有足够的强度、刚度和稳定性。2、拼缝密度一般不应大于2mm,当达不到要求时可在缝内刮填油灰。拼装不到位处,不得随意塞入木块或者水泥纸等堵塞,必须用小模板或长木方按几何尺寸补上方可。3、所有门窗洞口其下边过长,必须在中部留有混凝土浇捣口,以防中部混凝土不密实和混凝土出现蜂窝等现象。4、在捣制混凝土过程中,应派责任心心很强的木工看模,由于泵送混凝土侧压力很大,应随时观察模板几何尺寸,及时进行检查、校正。5、模板及支撑架拆除时,不得从高处向下扔,应有人递接,应有足够的安全操作,防止撬模时,模板掉下伤人,应防止拆支承架时,杆件倒下伤人。拆除的模板、钢管、扣件、螺杆等应归类码放整齐,且应及时清理表面杂物,模板面涂刷隔离剂,螺栓、脚手扣件擦油保护。3.6钢筋工程(1)施工要求1、施工员和操作人员必须重复熟悉图纸和规范,切实掌握设计意图,按照图纸规定的品种、形状和尺寸进行钢筋的配料、加工和绑扎。钢筋加工成型严格按<钢筋混凝土结构施工及验收规范>(GBJ50204-92)和设计要求执行。2、钢筋绑扎必须做好准备工作,钢筋的编号和位置要清楚,钢筋穿插的先后顺序要明确,摆钢筋前先在模板上划好线,梁与梁、梁与柱之间要相交的钢筋重叠往往造成局部超厚,要采取控制措施,一般来说次梁钢筋应穿插在主梁内,如果主次梁高度相同,次梁箍筋应适当减小。在转角处,板的负弯矩钢筋交叉重叠,板往往超厚,因此主梁箍筋有时也要适当减小。当梁上、下主筋超过一排时,两排钢筋之间应垫Φ25@1000以保证两排钢筋之间的距离,垫筋长度为梁宽减30。绑扎形式复杂的部位时,应先研究逐根钢筋的穿插就位顺序,减少绑扎困难,避免返工,加快进度。钢筋绑扎采用18-22号铅丝,所需铅丝规格根据钢筋直径而定,并符合有关规定。3、钢筋扎好后,必须垫好保护层垫块,板的两层之间用撑凳固定,以保证钢筋在模板中的位置正确和固定牢固防止产生变形,撑凳间距应小于或等于1000。4、钢筋的接头位置、搭接长度、同一断面的接头数量应符合规范要求,柱钢筋Φ16(包括Φ16)以上采用电渣压力焊,梁主筋采用闪光对焊接头和电弧焊接头。钢筋连接应符合<钢筋焊接及验收规程>(JGJ18-96)的有关规定。基础底板钢筋、框架柱、墙内暗柱、墙体竖向钢筋其接头位置应避开最大受力部位。梁、板的底部钢筋应避免在跨中连接,上部钢筋应避免在跨中连接。地下室的基础底板钢筋接头位置:上部钢筋应避免在跨中连接,底部钢筋应避免在支座处连接。(2)注意事项1、钢筋原材料应按不同规格,分批、分开堆放,每堆应挂牌注明规格、试验结果情况,必须有明确的试验合格证,方可下料制作。钢筋工程绑扎前应先熟悉施工图及规范,核对钢筋配料表和料牌。核对半成品钢筋的品种、直径、形状、尺寸和数量,如有错漏,应立即纠正增补。钢筋需按计划进行加工,并要及时做好清料工作,以免成品钢筋混乱。2、钢筋机械要有熟悉操作技术规程的熟练工人操作,对于对焊、电弧焊、电渣压力焊的操作人员必须经过专门培训,持证上岗,先焊试件,试件合格后再批量施焊。3、钢筋焊接应有稳定电流,按正确的焊接方法操作,避免钢筋接头处出现过烧。雨天露天施焊应有防雨措施,以防接头淬火,所有接头应进行外观检查,在外观检查合格的基础上,按有关规定作现场抽样检验。4、严禁将试验不合格的钢材使用于工程,钢筋出现锈迹、泥污等应清除干净后使用,所有钢筋的代换必须符合设计规范要求,同时征得设计方同意后方可进行。5、楼面钢筋绑扎时,应在伸出楼面的剪力墙柱钢筋绑扎3~5道横筋,以保证墙筋不偏位,板罩筋绑扎时,罩脚应朝下,并设撑脚,施工人员应在铺设于板筋上的脚手板上行走。6、浇注混凝土时,应派专人看护钢筋,对于混凝土下料振捣确有困难处,可临时松动表面钢筋,但应及时复位。7、对于安装专业,预埋的管道、铁件和预留洞等不得随意扰动钢筋,凡预埋时必须切断钢筋时应得到技术部门允许后再作加强处理。3.7混凝土工程(1)施工要求1、混凝土的配合比、原材料的计量、搅拌、养护和施工缝处理必须符合施工规范规定。混凝土强度的试块取样、制作、养护和试验要求要符合<混凝土强度检验评定标准>(GBJ107—8(7)的规定。2、混凝土自吊斗口下落的自由倾落高度不得超过2m,如超过2m时必须采用串筒措施。混凝土浇筑时应分段分层连续进行,每层浇捣高度应根据结构特点、钢筋疏密决定,分层厚度一般为振捣器作用长度的1.25倍,最大不超过30cm。3、使用插入式振捣器应快插慢拔,插点要均匀排列,逐点移动,顺序进行,不得遗漏,做到均匀振实。移动间距不大于振捣半径的1.5倍(一般为30~40cm)。振捣上一层时应插入下层5cm,以消除两层之间的接缝。表面振动器(或称平板振动器)的移动间距,要能保证振动器的平板覆盖已振实部分边缘。4、浇混凝土应连续进行,如必须间歇,其间歇时间应尽量缩短,并应在前层混凝土凝结强,将次层混凝土浇筑完毕。间歇的最长时间应按所用水泥品种及混凝土凝结条件确定,如超过2h,应按施工缝处理。5、浇筑混凝土应经常观察模板、钢筋、预留孔洞、预埋件和插筋等有无移动、变形或堵塞情况,发现问题应立即停止浇筑,并应在浇筑的混凝土凝结前修正完好。6、底板混凝土的浇筑。为了保证底板混凝土的整体性,在施工缝连接处不出现薄弱点,施工缝处采用两层钢网封堵,一层网片为细钢丝网,另一层为钢板网,利用钢筋进行加固,即可保证混凝土之间的有效连接,还可视为模板使用。施工缝断面作成齿形,同时设置加强钢筋和钢板止水带,确保该断面处的有效结合。混凝土配合比由混凝土搅拌站负责调整,按现行的<普通砼配合比设计技术规定>予以执行,砼的强度应符合国家现行<砼强度检验评定标准>的有关规定。根据施工季节和气候条件,以及所使用的原材料,经过计算和试配确定各种材料的用量,包括其它外掺剂的用量,如粉煤灰、减水剂、缓凝剂,同时确保砼的可泵送性,砼的塌落度控制在14~16cm之间。(2)注意事项1、本工程在现场不设置砼搅拌站,商品混凝土由专业砼搅拌站负责提供,并保证该工程砼的供应。在施工基础底板时,为了有效的控制砼的有害裂缝的产生,降低水泥水化热,充分利用砼的后期强度,拟优先选用低水化热的矿渣硅酸盐水泥。在施工立面墙、柱及顶板、梁的砼,优先选用P525以上的普通硅酸盐水泥和早强型硅酸盐水泥。在浇筑前要做好充分的准备工作,如制定施工方案,机具准备,保证水电的供应,要掌握天气季节的变化情况,检查模板、钢筋、预留洞等的预检和隐蔽项目。检查安全设施、劳动力配备是否妥当,能否满足浇筑速度的要求。2、在满足泵送的前提下,楼面混凝土应尽量采用低坍落度混凝土。楼梯中间歇台、梯梁一起浇捣时,可先浇至歇台或梯梁面,待混凝土接近初凝时,接着浇上部墙,楼梯踏步混凝土坍落度宜采用10~20mm。在浇筑工序中,应控制砼的均匀性和密实性,砼拌和物运到浇筑地点后,应立即浇筑入模。浇筑过程中,应经常观察模板、支架、钢筋、预埋件和预留洞的情况,当发现有变形、移位时,应立即停止浇筑,并立即采取措施在已浇筑的砼凝结前修整完好。每层柱子砼应一次浇筑完毕,施工缝应设在主梁下边,待绑扎楼板梁钢筋时,在柱子与楼板梁交接处绑一圈钢丝网,以防不同标号砼互相流入,钢丝网宽度为主梁底边到楼板上口,或不绑钢丝网,在楼板梁与柱筋交接处,围着柱子插一圈钢筋头,同样能够起到阻挡不同标号砼互相流入,插筋的长度同上边提到的钢丝网一样。在浇筑柱子与楼板梁相交处时,绝对不允许低标号、普通砼流入高标号、抗渗砼中。梁板砼应同时浇筑。施工缝位置,宜沿次梁方向浇筑楼板砼,施工缝应留置在次梁跨中间的1/3范围内。施工缝的表面应与梁轴线或板面垂直,不得留斜槎,施工缝宜用木板或钢丝挡牢。进行施工缝施工前,安排人员将施工缝处砼清理干净并将表面凿毛。为保证施工缝的接缝质量,按设计要求在砼中掺FS复合型微膨胀剂,其掺量为12%,在浇筑成型后,可获得0.5-1.2N/mm的自应力,补偿后施工缝的收缩。3、振捣混凝土时,振动器距模板不宜大于1/2的作用振动半径,不能碰撞模板、钢筋及所有预埋件。4、须派责任心很强的人作专职混凝土养护工作,每层养护水不能任其向四处流淌,应适当引流集中排出,当平均气温超过300C或低于50C时,新浇混凝土外露表面覆盖一层塑料薄膜,再盖一层麻袋(或草袋),对直接受阳光照射的侧混凝土面或迎风面,需悬挂草包,隔热保温。浇筑温度不宜超过355、混凝土拆模后发现有蜂窝、麻面等不良现象,千万不能私自修补覆盖,必须通知技术部门,根据具体情况作出修补方案后,派责任心强的人员修补。(3)人员组织1、混凝土的浇筑必须各方面协调统一方可顺利施工。现场设总调度长一名,混凝土浇筑前由总调先进行各方面协调、联络和布置。应在劳动力的配备上充分考虑搅拌、运输、浇筑、换班各个环节因素的影响。2、人员安排如下:①管理层:负责前后方的协调工作1人负责解决砼施工过程中的技术问题1人负责砼供应及外联工作1人负责现场砼浇筑指挥工作1人②操作层(按一大班配)振动操作组(包括下料、平仓、振捣):2组每组6人砼表面压光组:2组每组6人泵管安拆组:1组每组5人养护组:1组每组3人钢筋组:1组每组4人木工组:1组每组3人其它:1组每组5人3.8预应力混凝土工程(1)试验台座顶板和反力墙采用后张无粘结预应力钢筋混凝土结构。依据<无粘结预应力混凝土结构技术规程>(JGJ/T92-93)设计。后张无粘结低松弛预应力钢绞线为,=1860N/mm2,=1320N/mm2。(2)混凝土达到抗压强度设计值的%80以上后,方可进行预应力筋的张拉。张拉方法可采用一次张拉,张拉控制应力为0-->1.03(0.7X1860)=1341N/mm2。也可采用二次张拉,即0-->0.7X1860=1302N/mm2,0-->0.7X1860=1302N/mm2。(3)张拉端的多余钢筋,应予切除,预应力孔道应用C35细石混凝土灌注,表面抹平压光。3.9地下水防水工程(1)施工要求1、首先应清理基层,使起平整、光滑,表面干燥,无砂眼、孔洞,穿墙管应按规定安装牢固,收头圆滑,在基层表面涂刷处理剂。2、涂抹防水层混合料应随配随用,配好的涂料宜在2h内用完。3、阴阳角、管根、水落口等部位先做附加层,采用聚胺脂涂膜。4、涂膜应厚薄均匀、封闭严密,无开裂孔洞、脱落、收头不严密等缺陷,涂膜总厚度不小于1.5mm。涂抹防水层必须固化均匀,形成一个连续整体防水层,不允许有渗漏现象。5、卷材与卷材之间,基层与卷材之间的接缝应粘结牢固,不允许有皱折、孔洞、脱层或滑动现象。6、卷材施工完毕,经监理、甲、乙方共同验收合格并作好防水施工的技术资料和施工过程中的隐闭验收记录后,立即在上面粘贴聚乙烯泡沫塑料保护层。粘贴时要求泡沫塑料片拼缝严密,以防回填土时损伤防水层。(2)注意事项1、基层不干燥时,不得进行防水层的施工,以免卷材粘结不牢或产生起鼓、开裂现象。2、操作人员要严格保护已做好的防水层。3、施工时,不允许涂膜材料污染已贴布面。4、施工材料和辅助材料多属易燃品,存放材料的仓库及施工现场必须严禁烟火。5、所有防水工程均应按<深圳建筑防水构造图集A。B>(SJ-A、SJ-B)相关规定设防和施工,凡防水材料均应采用非焦油型;凡防水卷材宜采用冷粘贴工艺施工。地下室防水等级为二级。地下主体结构侧墙、底板和室外部分的顶板采用抗渗自防水混凝土再附加防水层,并在迎水面加做3㎜厚自粘橡胶卷材柔性防水层。附加防水层必须设保护层。所有穿外墙的管道必须预埋防水穿墙管道。外墙防水按广东省标<建筑防水工程技术规范>的施工要求,门窗洞口处防水按有关规定执行,安装在外墙的构配件、孔洞、管道、螺栓等均应预埋,预埋件位于砌块墙体时,在埋件四周嵌以聚合物水泥砂浆,凸窗顶板面需做水泥浆找坡(1%坡度),并在其上做聚合物水泥基防水涂抹(3)材料准备1、基层胶粘剂,聚氨脂底胶、胶粘剂,基础粘接剂CX-401胶,卷材接缝粘结剂等。聚氨酯防水涂膜甲、乙料,固化剂,二乙胺,颜料,石膏粉。2、防水材料必须有产品质量认证书,卷材出厂合格证,材质证明书,质量检测报告。材料进场后要按要求抽样检验,合格后,并报监理认可方可施工。3、基层胶粘剂、卷材胶粘剂进场后要分类专设仓库存放,存放地点要标识并设置消防器材。3.10砌体工程(1)砌体工程的脚手架板选择的要求砌体脚架选用折叠式里脚手架,其步高要求:一步高1.0m,二步高1.60m,脚手板为木枋。砌体脚手架要求安全稳定,转运灵活方便。(2)砌体工程的组砌方法及要求1、将砌筑墙部位的楼地面,剔除底面的凝结灰浆并清扫干。施工前一天应将砌筑墙接触面浇水润湿。砌筑前先用水平仪抄一次水平标高,并做好水平标记,以此来控制和调整墙体的高度,如高差过大的地方,则应用细石砼垫平后,再砌砖。同时应按实地尺寸和砌块规格尺寸进行排列摆块,不够整块的可采用页岩砖砌筑,最下一层砌块的灰缝大于20mm时,应用豆石混凝土找平铺筑,上下十字错缝,内外搭砌,其错缝搭接长度不应小于砌块长度的1/4。墙顶与楼板或梁底加一层斜砌页岩砖,斜砌砖应在砌体砂浆凝固后,用页岩实心砖斜砌抵紧。2、砌块的下列部位应砌实心页岩砖:每层隔墙的底部三线砖;外墙勒脚部分;不够整砖而符合普砖模数处;墙中预留孔洞口、预埋件和管道周围。门窗洞口两侧一砖范围内。3、留槎应留踏步式,如留踏步式有困难时,可留阳直槎,但必须竖向每隔400~500mm。4、砌筑砂浆的强度等级按设计要求,稠度控制在5~7cm,灰缝的厚度为15mm,但不应大于20mm,也不应小于10mm,水平灰缝的饱满度应不低于80%,竖向灰缝砂浆的饱满度应不低于60%。5、砌体水平度经过结构施工中+1.000m线用挂线来控制,如果长墙几个人使一根通线,中间应设几个支线点,小线要拉紧,每层砖都要穿线看平,使水平缝均匀一致,平直通顺。(3)施工及质量标准施工标准按GB50203—98<砌体工程施工及验收规范>,质量标准按GB50300—<建筑工程施工质量验收评定统一标准>执行。首先,砌块入场时就应检查,检查出厂合格证和试验报告,以保证其品种、标号符合设计要求。其次检查砌体的砂浆密实饱满程度。砌体水平灰缝的砂浆饱满度不小于80%,接槎处灰浆密实。观察和用尺丈量检查,组砌正确,上下错缝正确、无通缝,预留洞、预埋件位置正确。验收时还应提供施工记录、隐蔽记录及质量检查记录。当提供的文件、记录及外观检查结果符合有关规范标准和技术条件规定时则进行砌体工程验收。砌块砌体的容许误差表项次项目允许偏差(mm)检查方法1轴线位置偏移10用经纬仪或拉线和尺量2垂直度≤10m10用经纬仪或吊线和丈量3表面平整(直)度8用2m靠尺楔形塞尺4底缝高差(5m内)10用拉线和尺量5高度(每层)10用吊线和尺量6长度(填充墙全长)15用拉线和尺量7平面位置15用经纬仪或拉线和尺量(4)施工技术措施:1、测量分公司测量人员放出轴线,砌筑施工人员根据图纸、依据轴线弹好墙体边线及门窗洞口位置。2、砌筑前应根据砌块皮数制作皮数杆,并在墙体转角处及交接处树立,皮数杆间距不得超过15M。3、墙体砌筑时应单面挂线,随着砌体的增高要随时用靠尺校正平整度、垂直度。4、砌筑时必须遵守”反砌”原则,即砌块底面向上砌筑,上下皮应错缝搭砌。5、水平灰缝应平直、砂浆饱满,按净面积计算砂浆的饱满度不应底于90%,竖向灰缝应采用加浆方法,使其砂浆饱满。严禁用水冲浆灌缝,不得出现瞎缝、透明缝,其砂浆饱满度不宜低于80%。6、墙体转角处即交接处应同时砌筑,如不能做到,应留马牙槎。7、每天砌筑高度小于1.8M。8、在砌筑砂浆终凝前后时间内,应将灰缝刮平。3.11屋面防水工程屋面防水等级为二级,防水耐用年限为,二道防水设防。柔性防水层采用1.5㎜厚合成高分子卷材防水,四周卷到种植土层面(或300mm高),另设一道40厚C25配筋细石混凝土刚性防水层。3.12装饰装修工程(1)天棚、内、外墙抹水泥(混合)砂浆面施工1、施工准备①在抹灰前应作好防渗漏措施,同时检查暗设的管线、预埋件是否符合要求,预留孔洞位置是否正确。②消除作业面的施工障碍,保证连续作业,并应选择合适的房间作样板间。③结构及基层经质量检查已符合验收条件,门、窗框已安装固定,所需材料、工具、机具均已备齐后方可插入抹灰。2、工艺流程及操作①基层表面处理—→做护角—→抹底层砂浆—→抹中层砂浆—→抹面层—→质量检查②根据墙面垂直度情况打巴,巴子应在距墙面顶角两边15-20cm处做道巴子,然后吊线做下巴子,然后上下拉线做中间巴子,巴子间距一般以1.2-1.5m为宜,待巴子砂浆吸水后根据巴子出柱子。③抹底层砂浆完成24小时后,抹中层砂浆前应对底层砂浆墙面进行处理,待中层砂浆抹完后应适当进行养护,以满足水泥硬化过程避免空壳。④页岩砖、加气砼砌块砌块基层在抹底层灰前应先将表面松散颗粒清扫干净,对立缝和缺楞、掉角及不饱满的水平缝先刷108胶泥浆,然后用砂浆堵抹密实,48小时调制好108胶水泥浆,用羊毛滚子对基层表面滚涂一道形成拉毛状,以利底层砂浆与基层的粘结。⑤对砼基层抹灰前,应先用钢丝刷或清理液清除隔离剂、浮浆,然后刷108胶水泥浆一道后再抹底层砂浆。⑥待湿作业基本完成后,即可插入表面腻子刮面,第一道腻子刮完后,应对墙面阴阳角进行检查,如有不符合要求处应用砂浆进行填补处理,然后方可进行二道腻子。3、质量要求①室内中级抹灰应满足平整度<4mm,垂直度<5mm,并不得有空壳。②阴阳角顺直、表面无裂纹。(2)内墙、天棚面刷乳胶漆(喷涂料)施工1、作业条件①涂面有关抹灰工种的作业全部完成。②墙面应干燥。③冬施期间室内温度应保持+50④做好样板并经业主、监理鉴定合格。2、操作工艺①基层清理:混凝土表面的浮砂、灰尘、疙瘩要清除干净,粘附着的隔离剂应用碱水(火碱:水=1:10)清刷墙面,然后用清水冲刷干净。抹灰墙面的灰尘,疙瘩等物也应清扫干净,除掉油污。②喷、刷乳胶水:混凝土墙面在刮腻子之前先喷(刷)一道乳胶水,以增强腻子与基层表面的粘结性,应喷刷均匀一致,不得有遗漏处。乳胶水重量配合比为清水:乳液=5:1。③填补缝隙,局部刮腻子:用石膏腻子将缝隙及坑洼不平处找平,操作时要抹竖起,填实填平,并把多余的浮腻子收净,石膏腻子干燥后,打砂纸磨平,并把浮尘扫净。如发现还有坑洼不平处,还能够再找一遍石膏腻子。石膏腻子配合比为石膏粉:乳液:纤维素水溶液=100:4.5:60,其中纤维素水溶液浓度为3.5%。④中级喷浆可满刮一道大白腻子。操作时要往返刮平,注意上下左右接搓,两刮板间要刮净,不能留有净腻子。每道腻子干燥后应磨一遍砂纸,要磨平磨光,要慢磨慢打,线角分明,磨完后应将浮尘扫净。如涂刷带颜色的浆,则腻子中要掺入适量的颜料。腻子配合比为乳液:滑石粉(或大白粉):20%纤维素=1:5:3.5(重量比)。⑤喷刷第一道浆:喷刷浆前用排笔把门窗周围刷出约20cm宽,然后再大面积喷刷浆。开始喷刷浆顺序应按先上后下顺序进行,喷头距墙面20-30cm,移动速度要平稳,喷刷均匀一致。eq\o\ac(○,6)复补腻子:第一遍浆干燥后,麻点、坑洼处用腻子找平刮净:腻子干燥后用细砂纸轻磨并把浮尘扫净,达到表面光滑平整。eq\o\ac(○,7)喷刷第二道浆:用料与方法同第一道浆。第二道浆干燥后,用细砂纸将浮粉轻轻磨掉并清扫干净。(3)质量通病防治措施1)粗糙:产生原因是基层处理不彻底,打磨不平,刮腻子时没有收干净、留有浮腻子,干燥后没有打磨平和扫净,大白粉细度不够。2)开裂:原墙面缺陷较大未认真处理,腻子刮的过厚、没有分层刮,底层腻子未干燥又刮上一层腻子,使底层腻子不干燥造成收缩开裂。3)脱皮:墙面喷浆太厚,浆内胶量太重,浆与基层附着力不好,均可造成脱皮现象。防治方法是掌握好浆的稠度,基层认真处理干净,为了增加附着力在喷浆前先将墙面喷一道胶水。4)反碱、咬色、墙面潮湿,底浆胶少,前一道浆没有干燥就喷下一道浆。5)流坠:墙面潮湿,浆内胶量大、不易干燥,喷浆过厚等。因此墙面应干燥,前一道浆干燥后再喷后一道浆,认真处理基层,不留有疙瘩,喷浆时均匀移动,使喷出的浆均匀一致。6)墙面颜色不一致、透底;基层表面太光滑不易粘住浆液,或基础有油污等没有清理干净,喷刷浆时,浆膜难以覆盖。因此基础必须处理干净;喷刷色浆时每次调配的浆料应满足所需数量,避免再次调配时颜色不一致;喷刷浆时,喷头距墙20-30cm为宜,移动速度要均匀,不漏喷,这样墙面颜色就一致了。4.12.3面砖墙裙施工(1)施工准备工作①嵌贴釉面砖前应对基层、暗埋管道、预留孔洞、卫生器具安设准确位置进行检查,符合要求后方可进行。②对入场釉面砖的规格、颜色一致以及其它指标进行开箱抽检,进行适当的分类选配。③应待地面垫层做完后,工作面障碍已清除,然后才开始工作。(2)施工工艺操作①釉面砖嵌贴基层抹灰应严格按二道成活,对砌体基层处理应同内墙抹灰相同,抹好后应进行1-2天养护后才能嵌贴。②在基层完成后应按高级抹灰标准进行检查,特别是阴阳角应保证方正。③在嵌贴前应按设计要求进行试排砖,一般应从阴角或门窗立边开始,阳角处必须贴整砖,同时在阴角处严禁用窄条,如出现窄条则采取用2-3块砖平均切割调整。④嵌贴采取先贴两端控制竖向位砖由下而上逐排挂线嵌贴,嵌贴前釉面砖必须在清水中浸泡2-3小时,取出待表面凉干后备用。⑤理缝、擦缝:应认真在嵌贴后及时刮理干净多余的浮浆,待砂浆凝固后,用长毛刷蘸粥状水泥浆涂满缝子,并用棉纱将其灰浆擦匀,最后将表面灰浆擦净。(3)质量要求①嵌贴必须牢固,严禁空鼓、歪斜、缺楞、掉角、裂纹等缺陷。②表面平整、洁净、色调一致,平整度允许误差<2mm,垂直度<2mm,阳角方正<2mm,接缝高低<0.5mm。4.12.4水泥砂浆楼面施工4.12.4.1施工准备工作在施工前应做好以下几项工作:a.检查砂和水泥的质量是否合格,应进行抽样检验,合格者方可使用。河砂含泥量不能超过规定,水泥应选用普通硅酸盐水泥,标号不低于32.5MPa,不得使用过期水泥和含有油污及矿物质的水。b.准备2m长硬木尺枋数根,木水平尺一只和阴角器铁滚筒等工具。c.检查楼地面基层是否符合质量要求,有无排水坡度,排水方向是否正确。d.确定施工配合比,取水泥:砂=1:2其水的使用量不能过大,应在实际中确定,坍落度应控制在6~8cm以内。4.12.4.2作业条件a.楼地面工程应在屋面断水后或上一层楼板已灌好板缝后,不被后续工程损坏和沾污的条件下进行。b.楼地面工程施工前,应安装好门框,上、下水管道,并将管口洞口、地漏等堵好。③基、垫层的质量已检查合格并办理好交接手续,楼梯、过道和室内楼地面层标高已确定好并作好标志。4.12.4.3施工工艺①清理基层—→弹出水平线、打巴做标志—→刷水泥浆结合层—→铺抹水泥砂浆—→第一遍压实收光—→第二遍压实收光—→第三遍压实收光—→抹踢脚板面层—→养护
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2026安徽宿州职业技术学院招聘36人备考题库有完整答案详解
- 2026四川德阳城市轨道交通职业学院春季学期招聘140人备考题库及答案详解(典优)
- 银行厅堂项目管理制度
- 饭店员工工资管理制度
- 高中教职工请假制度
- 请假制度感悟心得简短
- 学校卫生管理制度健全
- 小吃店薪酬绩效制度内容
- 蔬果园生产车间管理制度
- 早期影像学特征与诊断策略优化-洞察与解读
- 主播合作协议解除协议书
- 旅游产业股权合作协议书
- 养老院入住合同协议书
- DB32/ 4440-2022城镇污水处理厂污染物排放标准
- 文第19课《井冈翠竹》教学设计+2024-2025学年统编版语文七年级下册
- 车库使用协议合同
- 耐磨钢的应用现状及行业发展分析
- 《不在网络中迷失》课件
- 2024新人教版七年级上册英语单词字帖(衡水体)
- 2024-2025年上海中考英语真题及答案解析
- 新医改下医院药学转型与发展
评论
0/150
提交评论