版权说明:本文档由用户提供并上传,收益归属内容提供方,若内容存在侵权,请进行举报或认领
文档简介
1、1,Chapter 27,项目进度安排 吴迪 齐齐哈尔大学计控学院,讨论,软件进展安排的重要性? 项目进度的步骤是什么?,3,27.1 基本概念,为什么软件延期交付? an unrealistic deadline established by someone outside the software development group changing customer requirements that are not reflected in schedule changes; an honest underestimate of the amount of effort and/or
2、the number of resources that will be required to do the job; predictable and/or unpredictable risks that were not considered when the project commenced;,technical difficulties that could not have been foreseen in advance; human difficulties that could not have been foreseen in advance; miscommunicat
3、ion among project staff that results in delays; a failure by project management to recognize that the project is falling behind schedule and a lack of action to correct the problem;,讨论和作业,“不合理的”项目结束期限是软件行业存在的显示情况。当你遇到这种情况该如何处理?,6,27.2Scheduling Principles,compartmentalizationdefine distinct tasks in
4、terdependencyindicate task interrelationship effort validationbe sure resources are available defined responsibilitiespeople must be assigned defined outcomeseach task must have an output defined milestonesreview for quality,7,Effort and Delivery Time,8,工作量分配,“front end” activities customer communic
5、ation analysis design review and modification construction activities coding or code generation testing and installation unit, integration white-box, black box regression,9,27.3 定义任务集,determine type of project assess the degree of rigor required identify adaptation criteria select appropriate softwa
6、re engineering tasks,10,Task Set Refinement,1.1 Concept scoping determines the overall scope of the project.,Task definition: Task 1.1 Concept Scoping 1.1.1Identify need, benefits and potential customers; 1.1.2Define desired output/control and input events that drive the application; Begin Task 1.1.
7、2 1.1.2.1FTR: Review written description of need FTR indicates that a formal technical review (Chapter 26) is to be conducted. 1.1.2.2Derive a list of customer visible outputs/inputs 1.1.2.3FTR: Review outputs/inputs with customer and revise as required; endtask Task 1.1.2 1.1.3Define the functional
8、ity/behavior for each major function; Begin Task 1.1.3 1.1.3.1FTR: Review output and input data objects derived in task 1.1.2; 1.1.3.2Derive a model of functions/behaviors; 1.1.3.3FTR: Review functions/behaviors with customer and revise as required; endtask Task 1.1.3 1.1.4Isolate those elements of
9、the technology to be implemented in software; 1.1.5Research availability of existing software; 1.1.6Define technical feasibility; 1.1.7Make quick estimate of size; 1.1.8Create a Scope Definition; endTask definition: Task 1.1,is refined to,11,Define a Task Network,12,27.5.1Timeline Charts,13,Use Auto
10、mated Tools toDerive a Timeline Chart,问题,甘特图画出后,如何跟踪进度?,15,27.5.2进度跟踪,conduct periodic project status meetings in which each team member reports progress and problems. evaluate the results of all reviews conducted throughout the software engineering process. determine whether formal project mileston
11、es have been accomplished by the scheduled date.,compare actual start-date to planned start-date for each project task listed in the resource table. meet informally with practitioners to obtain their subjective assessment of progress to date and problems on the horizon. use earned value analysis (Se
12、ction 27.6) to assess progress quantitatively.,17,Progress on an OO Project-I,Technical milestone: OO analysis completed All classes and the class hierarchy have been defined and reviewed. Class attributes and operations associated with a class have been defined and reviewed. Class relationships (Ch
13、apter 8) have been established and reviewed. A behavioral model (Chapter 8) has been created and reviewed. Reusable classes have been noted. Technical milestone: OO design completed The set of subsystems (Chapter 9) has been defined and reviewed. Classes are allocated to subsystems and reviewed. Tas
14、k allocation has been established and reviewed. Responsibilities and collaborations (Chapter 9) have been identified. Attributes and operations have been designed and reviewed. The communication model has been created and reviewed.,18,Progress on an OO Project-II,Technical milestone: OO programming
15、completed Each new class has been implemented in code from the design model. Extracted classes (from a reuse library) have been implemented. Prototype or increment has been built. Technical milestone: OO testing The correctness and completeness of OO analysis and design models has been reviewed. A c
16、lass-responsibility-collaboration network (Chapter 6) has been developed and reviewed. Test cases are designed and class-level tests (Chapter 19) have been conducted for each class. Test cases are designed and cluster testing (Chapter 19) is completed and the classes are integrated. System level tes
17、ts have been completed.,19,27.6 Earned Value Analysis (EVA),Earned value is a measure of progress enables us to assess the “percent of completeness” of a project using quantitative analysis rather than rely on a gut feeling “provides accurate and reliable readings of performance from as early as 15
18、percent into the project.” Fle98,20,Computing Earned Value-I,The budgeted cost of work scheduled (BCWS) is determined for each work task represented in the schedule. BCWSi is the effort planned for work task i. To determine progress at a given point along the project schedule, the value of BCWS is t
19、he sum of the BCWSi values for all work tasks that should have been completed by that point in time on the project schedule.,The BCWS values for all work tasks are summed to derive the budget at completion, BAC. Hence, BAC = (BCWSk) for all tasks k,22,Computing Earned Value-II,Next, the value for bu
20、dgeted cost of work performed (BCWP) is computed. The value for BCWP is the sum of the BCWS values for all work tasks that have actually been completed by a point in time on the project schedule. “the distinction between the BCWS and the BCWP is that the former represents the budget of the activities that were planned to be completed and the latter represents the budget of the activities that actually were completed.” Wil99,Given values for BCWS, BAC, and BCWP, important progress indicators can be computed: Schedule performance index, SPI = BCWP/BCWS Schedule va
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 小学科学五年级上册《妙用滑轮》教学设计
- 初中英语七年级下册Unit 5 Animal friends Grammar模块教学设计
- 小学科学三年级下册《制作指南针》教学设计:磁性认知与工程实践的深度融合
- 小学三年级道德与法治《走近科学家》第二课时“他们离我们并不遥远”教学设计
- 综合岗 2026往年真题试卷及参考答案
- 出纳岗事业单位面试易错题题库及参考答案
- 出纳岗事业单位面试考点训练题库及参考答案
- 室内吊顶面层拼接打磨检测施工
- 外墙保温板排版施工工艺
- 实验室安全考试试卷试题库及答案
- 2026年国家公务员考试《申论》真题(行政执法卷)及参考答案记忆版
- 肿瘤免疫治疗相关不良反应管理专家共识(2026版)
- 2026年人工智能(AI)训练师专业知识考试题库附答案(完整版)
- T/CPCA 022-2026铝基刚性印制电路板通用规范
- 高中二年级生物神经调节的分层教学设计
- 车间反应釜超压爆炸应急预案演练脚本
- 2026四川省自然资源投资集团招聘30人笔试历年典型考点题库附带答案详解
- CSCO恶性血液病诊疗指南(2026版)
- 专题01 语言文字运用(真题汇编)(2021~2025)五年高考真题模拟语文专题(附答案)
- 渭南市大荔善达精神专科医院招聘笔试真题2025
- 2026年4月自考00258保险法试题
评论
0/150
提交评论