1、Content 目录1 CONTENT 目录12 GENERAL 工程概况23 SPECIALITY 工程特点24 CODE 执行标准35 PIPING INSTALLATION 管道施工56 MATERIAL TEST 材料检验77 PIPE INSTALLATION 管道敷设128 PIPE SWEEPING AND CLEAN 管道的吹扫与清洗129 WATER PRESSURE TEST 管道的水压试验1410 PIPE TRENCH BACKFILLING 管沟回填1411 FINISH PRODUCT PROTECTION 成品保护1412 LABOR AND MACHINE PL

2、AN 人力及机具计划1513 CIVIL AND SAFETY WORK PLAN 文明施工及安全计划1614 QUALITY STANDARD 质量标准17 Underground Piping Installation Plan地下管道施工方案1 General 工程概况SANDISK CVIP FACTORY PROJECT underground piping installation locate at the number 555 of jiangchuan road ,minhang District Shanghai City . This plan applies for t

3、he interior underground piping and exterior underground piping . The interior underground piping include: Industrial , domestic water supply , industrial waste water drainage , domestic sewage drainage, storm water drainage; main piping material is PVC-U drain pipe , Galy , pipe . The exterior under

4、ground piping include industrial , domestic water supply system , industrial waste water drainage , storm water drainage , domestic sewage drainage system , totally 2500m ; water supply pipe is graphite iron pipe , storm water , domestic sewage is PVC-U pipe , industrial waste water is UPVC pipe .晟碟

5、半导体(上海)有限公司新建厂房工程地下管网工程,位于上海市闵行区江川路555号,本方案适用于室内底板下管网及室外地下管网两部分。室内底板下管道包括:生产、生活给水管网、生产废水管、生活污水、雨水排水管网,主要管材为PVC-U排水管、镀锌钢管;室外部分为地下生产、生活给水管网,雨水、生活污水、工业废水管网,总长约为2500m ; 给水管采用离心球墨铸铁管, 雨水、生活污水采用加筋PVC-U排水管 , 工业废水采用UPVC管2 . Speciality 工程特点This is new expansion project , pay attention to safety .本工程为新建项目 ,施工

6、时要注意安全 . 3 . Code 执行标准 a . SHANGHAI ELECTRONIC ENGINEERING DE SIGN & RESEARCH INSTTTUTE COV. LTD design上海电子工程设计研究院有限公司 设计图纸 b . GB50242-2002 Code for Quality Acceptance of Water Supply & Drainage and . heating construction . GB50242-2002 建筑给排水及采暖施工质量验收规范 c . GBJ141-90 Code for Water Supply & Drainag

7、e Building Construction and acceptance GBJ141-90 给水排水构筑物施工及验收规范 c . GB50268-97 Code for Water Supply & Drainage Piping Construction and Acceptance GB50268-97 给水排水管道工程施工及验收规范 e . GB50303-2002 Code for Quality Acceptance of Building Electricity Engineering Construction GB50303-2002 建筑电气工程施工质量验收规范4Pipi

8、ng installation 管道施工(1) Layout 测量放线Proceed the survey and orientation according to the design drawing and bench mark , when it conflict with design drawing , settled down by M+W coordination . Recheck the first survey point supplied by M+W to confirm , obtain the excavation permit from M+W prior to

9、commencement .根据图纸对施工坐标点进行测量定位,当与设计图纸不符时,协同M+W 公司共同解决。对M+W 提供的第一个测量点应反复核实,确定其正确性,开挖前报M+W 确认许可后,方可开始施工(2) Excavation of pipe trench 管沟开挖 The excavation of pipe trench will be by backhoe mainly and assist with labors 管道开挖,采用机械开挖为主,人工开挖为辅。 During backhoe excavation , take reverse excavation measure 机械开

10、挖过程中,采用反铲进行开挖,开挖采用倒挖法进行管沟开挖。 For the pipe trench excavation , install support system or not considering the earth condition , still when the depth exceeds 1.4m must have slope . The excavated earth stocking at least 1.4m far away from the pipe trench to avoid earth collapse . 管沟开挖时,应根据土质进行考虑放坡与是否打支撑

11、,但管沟深度超过1.4m必须放坡施工,管沟开挖的土,必须堆放于距离管沟不小于1.4m,以免造成管沟塌方。 During pipe trench excavating , monitoring the elevation at any time , the backhoe excavating to a little higher level of designed level . 管沟开挖时,标高控制应采用随开挖,随测量,机械开挖到设计要求标高左右 If underground water immerged than drained by open trench , the open tren

12、ch should 100mm lower than pipe trench bottom and slope to water collection pit . Set one water collection pit every 30m , pump out the water in time to ensure no water standing in pipe trench and assign watching man to check the crack and water permeate condition . Take appropriate measures to avoi

13、d dangerous. 管沟开挖时,如有地下水采用明沟排水,明沟应比管沟底低100mm并坡向集水坑,在每30m设一个集水坑,利用潜水泵抽水保证管沟内无水,并专人检查沟边是否有裂纹及渗水情况,如有应采取措施以防止发生危险确保施工安全. During pipe trench excavation , set obvious signs to avoid incident 管沟开挖过程中,应设置标志防止人员发生意外。 Assist by labor to dig 100mm and level the bottom , pave sand cushion 利用人工随机清底,挖土下挖100mm ,

14、并做沙垫层基础。(3) Work face width 工作面宽度 The excavate width of pipe trench bottom shall be calculate by the under formula: 管道沟槽底部的开挖宽度,以下式计算: B=D1+2b1 B:excavate width (mm) of pipe trench bottom ; D1:the exterior width mm of piping structure; b1work face width of pipe side. B=D1+2b1 其中:B:管道沟槽底部的开挖宽度(mm);D1

15、:管道结构的外缘宽度(mm);b1管道一侧的工作宽度 Work face width of pipe side 管道一侧的工作面宽度b1(mm) Exterior width mm of piping structure管道结构的外缘宽度D1Work face width of pipe side管道一侧的工作面宽度b1Non-metal piping 非金属管道Metal piping 金属管道D=10003002005 . Material test 材料报验 Water supply pipe use ductile iron pipe , socket connect by rubbe

16、r ring; 给水管采用给水用球墨铸铁管,橡胶圈承插连接; Building of the Factory 1and the cub 1 drainage water pipe use PVC-U water supply pipe , adhesive connection: Building of the Factory 1and the cub 1 drainage pipe use HDPE pipe inlet , socket connect by rubber ring , building of the CUB 1 to cool down pool drainage use

17、 Hot Dip Galv . Steel pipe , anti-corrosion by two cloth and three layers asphalt. 生产1和动力1建筑内划片废水管采用PVC-U给水管,粘接;生产1和动力1建筑室外划片排水管采用HDPE双壁波纹管,橡胶圈承插连接; CUB1建筑到降温池采用热镀锌钢管,做两布三油防腐。 Exterior storm water , sewage drainage use U-PVC pipe , socket connect by rubber ring; 室外雨水、生活污水管道采用U-PVC加筋承插式排水管,橡胶圈连接; Che

18、ck the type , standard , material and quantity and apparent view of all pipe , pipe fittings , valve etc . according to design prior to installation , the check content as follows: 所有管道、管件、阀门等材料在安装前按设计要求核对其规格、型号、材质及数量并进行外观检查,检查内容如下: Check whether there is damage , crack of graphite iron pipe , the p

19、ipe opening size in the allowed scope , the bitumen coating finished , the inner lined cement loosed , the rubber ring complete and smooth . 检查球墨铸铁管有无损坏、裂缝,管口尺寸是否在允许范围,外涂沥青漆是否完成,内衬水泥是否脱落;橡胶圈应形体完整、表面光滑; Apparent view of Reinforce PVC-U , HDPE , PVC-U drainage pipe prior to installation , the inner wa

20、ll of pipe , pipe fittings should be smooth , level without bubbles , crack , delamination or distinct mark , depressed condition .The pipe can not with different direction bending , its straight deviation shall less than 1% . The pipe end should be level and vertical to gridline 加筋PVC-U管,HDPE管,PVC-

21、U排水管在安装前要进行外观检查,管材与管件内外壁应光滑、平整无气泡裂口、裂纹、脱皮和严重的冷斑及明显的痕蚊、凹陷,管材轴向不得有异向弯曲,其直线度偏差应小于1%,管材端口必须平整,并垂直与轴线。 Steel pipe surface should with no crack , shrinkage hole , slag , delamination etc . defects , the corrosion not exceed the minus deviation of wall thickness , the steel pipe and wail thickness in the d

22、eviation allowance . 钢管表面应无裂纹、缩孔、夹渣、重皮等缺陷,锈浊不超过壁厚负偏差,钢管及壁厚在允许的偏差范围内。 Valves must accompany with ex-factory qualified certificate , check the apparent check prior to installation . The valve seal face should be perfect , and some need water test. 阀门等在出厂前必须有合格证明,安装前要进行外观检查,阀门密封面完好无损,部分阀门须做水压试验; The we

23、ld material (electrode , welding wire ) , air chemical constitution , mechanical property should match with the mother material and comply with the welding craftsmanship . 管道焊接采用的焊材(焊条、焊丝)及气体的化学成分、机械性能须与母材匹配并兼顾满足焊接工艺的要求。6 . Pipe installation 管道敷设6.1 Install Sequence 施工顺序(1) Interior piping 室内管道 :Fac

24、tory 1 (production building 1) (生产厂房1):Trench excavation -Cushion concrete - Rebar - Lay Pipe - Pipe Test - Pour concrete沟槽开挖垫层混凝土钢筋绑扎下管管道试验浇注混凝土Other buildings 其他建筑:Trench excavation - Sand cushion - Lay pipe - First backfilling - Pipe Test - Trench backfilling管沟开挖垫层沙下管第一次回填管道试验管沟回填(2) Exterior pip

25、ing 室外管道The exterior piping install sequence shall according to bury depth , deeper prior to shallow principle .室外管道施工顺序应按管道埋设深度,先深后浅原则 。Drainage piping 排水管道 :Trench excavation - sand cushion - Lay pipe - First backfilling - Pipe test - Trench backfilling - Flush管沟开挖沙垫层下管第一次回填管道试验管沟回填冲洗Water supply

26、piping 给水管道 :Trench excavation - Concrete cover - Lay pipe - First backfilling - Pressure , refined test - Trench backfilling -Flush管沟开挖垫块下管第一次回填压力、严密性试验管沟回填冲洗6.2 Install key 安装要点:6.2.1 Install key of graphite iron pipe , exterior drain pipe 球墨铸铁管、室外排水管道安装要点(1) Install sequence 安装程序 :Lay pipe - Clea

27、n pipe opening - Clean rubber ring , install rubber ring -Install machine equipment - Paint lubricant on socket surface and rubber ring - Push pipe into socket - Check下管清理管口清理胶圈、上胶圈安装机具设备在插口外表面和胶圈上刷润滑剂顶推管子使之插入承口检查(2) Preparation prior to installation 安装前准备Remove the stir and dust at pipe opening .将管

28、口的毛刺和杂物清除干净;Check the match condition and work condition of tools 。检查安装机具是否配套齐全,工作状态是否良好(3) Install key 安装要点 :Lay pipe : according to the technical requirement lay the the pipe to the trench bottom , according to the signs if there is on pipe body .下管 应按下管技术要求将管子下到沟底,如管体有向上放的标志,应按标志摆放管子;Clean pipe o

29、pening : remove the debris at socket and clean up , for the adhesive articles may cause water leakage .清理管口 将承口内的所有杂物予以清除,并擦干净,因为任何附着物都可能造成接口漏水;Clean rubber ring , install rubber ring :Clean up the adhesive articles on rubber ring ; bend the rubber as heart shape or flower shape (big diameter),then

30、insert in socket channel and a circle pressure by hand to ensure the rubber ring in position , pushed into channel uniformly.清理胶圈、上胶圈 将胶圈上的粘结物清查干净;把胶圈弯成心型或花型(大口径)装入承口槽内,并用手沿整个胶圈按压一遍,确保胶圈各个部分不翘不扭,均匀一致的卡在槽内;Machines and Tools : Use jin chain hoist or wire grip put the machines and tools in position ,

31、take care of pollution to the cleaned pipe .安装机具设备 可采用手拉葫芦或紧线器,将准备好的机具设备安装到位,安装时注意不要将已清理的管子部位再次污染;Paint the lubricate agent on socket surface and rubber ring : the lubricate agent is supplied by manufacturer , or use soap water pave on the inner side of rubber ring uniformly . Tack care of the broke

32、n area when paint the lubricate agent to the socket top .在插口外表面和胶圈上刷润滑剂 润滑剂用厂方提供的,也可用肥皂水,将润滑剂均匀的刷在承口内已安装好的橡胶圈内表面,在插口外表面刷润滑剂时应注意刷至插口端部的破口处;Push the pipe into socket.顶推管子使之插入承口。(4) Install method 安装方法:Use sling chain (jin chain hoist) or wire grip : tie the steel rope on the fixed pipe , pull it into

33、pipe socket and well lay the back beam , connect and adjust the steel rope and sling chain right against , pull the sling chain to the socket .吊链(手拉葫芦)或紧线器拉入法 在已安装稳固的管子上拴住钢丝绳,在待拉入管子承口处放好后背横梁,用钢丝绳和吊链连好绷紧对正,拉动吊链,即将插口拉入承口中。6.2.2 Install valve 阀门安装 Prior to valve installation , check whether the valve t

34、ype , size comply with design requirement . The installed valve and valve sign (arrow) shall same as inner media 安装阀门前,应仔细核对阀门型号、规格是否符合设计要求,安装的阀门其阀体表示的箭头应与介质的流向一致。 The valve pole of horizontal piping normally be installed on the upper half-radius , the valve pole can not be installed under side . 水平

35、管道上的阀门其阀杆一般应安装在上半周范围内,不许阀杆向下安装。 The flange or thread connect valve shall be installed at valve closed condition . 法兰和螺纹连接的阀门应在关闭状态下安装。6.2.3 Install key point of inner drain piping 室内排水管安装要点(1) Install sequence 安装程序 Preparation - Prefabrication - Install main pipe - Install riser pipe - Install branc

36、h pipe - Fix the clips - Water close test - Water test 安装准备预制加工干管安装立管安装支管安装卡件固定闭水试验通水试验(2) Install key 安装要点:Prefabrication : According to design requirement and combine the site actual condition , measure the pipe size for pipe cut . The cut section should be smoot and neat , remove the stir by mill

37、ing cutter or drawknife , mill 15angle on exterior edge . Take insert test for socket prior to adhere , normally 3/4 of socket depth . If the trail insert qualified , remove the water and dust by cotton cloth . If there is oil stain need to be cleaned by acet . Pave adhesive agent by brush , socket

38、first then faucet , then vertical insert in by a sudden push , a little rotate to average the adhesive agent , the adhere needs about 30s to 1 min . Remove the overflowed adhesive agent immediately . Pay attention to the Pre-reserved mouth direction for multi-mouth connection .预制加工:根据图纸要求并结合实际情况,量好管

39、道尺寸,进行断管。断口要平齐,用铣刀或刮刀除掉断口内外飞刺,外棱铣出15角。粘接前应对承插口先插入试验,不得全部插入,一般为承口的3/4深度。试插合格后,用棉布将承插口粘接部位的水分、灰尘擦拭干净。如有油污需要丙酮除掉。用毛刷涂抹粘接剂,先涂抹承口后涂抹插口,随即用力垂直插入,插入粘接时将插口稍做转动,以利粘接剂分布均匀,约30s至1min 即可粘接牢固。粘牢后立即将溢出的粘接剂擦拭干净。多口粘连时应注意预留口方向。Install main pipe : for the buried pipe ,dig trench according to coordinate , elevation ,

40、slope direction , slope and backfill with compaction . If take support or hang pipe installation , make support or hang shelf first according to coordinate , elevation , slope direction . When the construction conditions ready , move the processed pipe section to the place according to No . for inst

41、allation . All pipe sections adhesion must comply with craft sequence . When they were connected , the pipe should be straight and with average sloping , all pre-reserved openings are correct . Take close water test when the main pipe installed , it is qualified if no water level fall down . 干管安装:埋入

42、地下时,按设计坐标、标高、坡向、坡度开挖槽沟并夯实。采用托吊管安装时应按照设计坐标、标高、坡向做好托、吊架。施工条件具备时,将预制加工好的管段,按编号运至安装部位进行安装。各管段粘连时也必须按粘接工艺依次进行。全部粘连后,管道要直,坡度均匀,各预留口位置准确。干管安装完后应做闭水试验,水位不下降为合格。Install branch pipe : move the prefabricated branch pipe to site place according to No . Clean the stain and water for every connect part . Suspend

43、the branch pipe and pave the adhesive agent gradually then sudden push into pre-reserved pipe opening . Adjust the slope according to pipe length .支管安装:将预制好的支管按编号运至现场。清除各粘接部位的污物及水分。将支管水平初步吊起,涂抹粘接剂,用力推入预留管口。根据管段长度调整好坡度。Take close water test when the drain pipe installed , for the conceal pipe install

44、ation must comply with work sequence.排水管道安装后,按规定要求必须进行闭水试验.凡属隐蔽暗装管道必须按分项工序进行.The adhesive agent easy for volatilize , close the cap after use immediately . For the adhesive work in winter , the set time is 23min . The adhesive place shall be well draught , far away from open fire .粘接剂易挥发,使用后应随时封盖。冬季

45、施工进行粘接时,凝固时间为23min 。 粘接场所应通风良好,远离明火。7 . Pipe sweeping and clean 管道的吹扫与清洗 The pressure pipe suitable for wash by water , such as , industrial & domestic water supply .压力管道宜采用水冲洗。如:生产生活给水管道。8. Water pressure test 管道的水压试验 When piping installation finished , take water pressure test or close water test

46、according to design .管道安装完成后,按图纸要对管道进行水压强度或闭水试验。8 . 1 Test pressure 压力管道试验压力Fire pipe : 1.4Mpa Industrial & domestic water supply pipe : 1.0Mpa .消防水管道: 1.4Mpa 生产生活给水管道: 1.0MpaTest method : The test pressure fall down in 10min shall not more than 0.05Mpa , then fall down to work pressure for strictne

47、ss check , the water permeable quantity shall in the following scope :试验方法:试验压力10分钟内压力不降不应大于0.05Mpa,然后降至工作压力进行严密性检查,管道严密性试验允许渗水量符合下表规定:Inner pipe diameter管道内径(mm)Allowable water permeable允许渗水量(L/(min.km)1000.71501.052001.40Water pressure test pipe length shall not longer than 1.0KM.管道水压试验的长度不大于1.0KM

48、8 . 2 Close water test 闭水试验(1) When the manhole built and ups to design strength , take close water test in sections . Fill in water and keep 1-2 day and night .在检查井砌筑后并达到设计强度后,分段进行闭水试验,管道试验段灌满水后浸泡1-2昼夜进行.(2) Take apparent check to the connection and pipe body prior to close water test , the time no

49、t less than 30 min . it is qualified if no water leakage and serious water leakage , the test should as the close water test sequence .闭水试验时对接口和管身进行外观检测,时间不少于30分钟,以无漏水和无严重漏水为合格,且应按闭水法试验进行。(3) The designed water inlet set at 2 m more on the basis of pipe top inner wall .试验段上游设计水头不超过管顶内壁时实验段水头应以实验段上游管

50、顶内壁加2m计。(4) Close water test conditions闭水试验条件:The apparent check of pipe and manhole has accepted , no earth at pipe connection , no standing water in pipe trench , no water permeableness , except the inlet and outlet water pipe , the pipe should be sealed without water permeableness . 管道及检查井外观质量已验收

51、合格,管道接口处未回填土,且沟槽内无积水,全部预留孔应封堵不得渗水,除预留进出水管外,应封堵坚固不得渗水。 Reference : SHANGHAI ELECTRONIC ENGINEERING DE SIGN & RESEARCH INSTTTUTE COV. LTD design上海电子工程设计研究院有限公司 设计图纸 GB50242-2002 Code for Quality Acceptance of Water supply & Drainage and Heating Construction . GB50242-2002 建筑给排水及采暖施工质量验收规范 GB50268-97 C

52、ode for Water Supply & Drainage Piping Construction and Acceptance . GB50268-97 给水排水管道工程施工及验收规范9 . Pipe trench backfilling 管沟回填 When the backfilling 300mm higher than the pipe top , start labor compact to avoid pipe damage , then by 300mm layers upside , also can be backfilled and compacted by machi

53、ne . The trench backfill compacting factor shall comply with regulation requirement 93% . 在管顶回填到300mm厚方可进行人工夯实,以免破坏管道,然后每层300mm进行分层回填,可采用机械回填与夯实。管道回填夯实系数根据规范要求需达到93%方为合格。 管沟回填分两步进行:第一步为试水前回填,将各个接口露出;第二步为试水合格后进行的全部恢复回填。 其他回填时采用原土回填,但土中不得有砖块、污土、垃圾、土块颗粒不应大于15mm 。10 . Finish product protection 成品保护 When

54、 the pipe installation finished , seal all pipe openings to prevent debris block the pipe . 管道安装完成后,应将所有管口封闭严密,防止杂物进入,造成管道堵塞。11 . Labor and machine plan 人力及机具计划 Labor plan 人力计划 Machine plan 主要机具计划 No.序号 Machine机械名称Type型号Qty.数量Unit单位1Pedrail excavator 履带式挖掘机2台2Truck 汽车1台3Compactor 打夯机4台4Universal sur

55、vey instrument 全站仪 1台5Water leveler 水准仪3台6Submerged pump 潜水泵7Electro pressure test pump 电动试压泵25MP2台8Jin chain hoist 手拉葫芦5T2个9Auto threader 自动套丝机1台10Welding machine 焊机2台12 . Civil and safety work plan 文明施工与安全计划(1) Safety goad .安全管理控制目标(2)“Zero”accident is our companys working goal always . 施工“零”事故永远是

56、我公司的工作目标。(3) his plan is to regulate the site safety management , ensure labors life ,ensure the smooth usage of equipment .为规范施工现场的安全管理,保证施工员工的生命安全,保障施工设备的正常使用,特制定本规定。(4) Obtain approval prior to commencement , the general construction proposal , special work technical plan and measures must including safety measures .项目开工前,承包商编制的施工组织设计,专业技术方案及措施必须包含安全措施的具体要求,经业主批准后方可施工。(5) The labors working on

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

最新文档

评论

0/150

提交评论