1、PERMIT TO WORK MANAGEMENT工作许可证管理ISSUE REVISSUE OR REVISION DESCRIPTIONORIGIN BYDATECHKD BYDATEAPP d BYDATER00ORIGINALCONTENTS 目录1 PURPOSE ANDSCOPE 目的和 范围2 TERMINOLOGY / DEFINITIONS 术语与定义3 RESPONSIBILITIES 职责4 PROCEDURE 程序5 ATTACHMENTS 附件1. PURPOSE AND SCOPE目的和范围1.1 The aim of this procedure is to pr
2、ovide guidance on the site Permit to Worksystem.本程序的目的在于就现场作业的许可证制度提出指导性意见。1.2 The site handles a large diversity of work, so the potential for serious accidents is high. To prevent them it is vital that there should be safe systems of work. They will often be applied and enforced by means of a form
3、al Permit to Work system.施工现场充满了高强度的作业,因此发生重大事故的可能性也比较高。为了防 患于未然,必须制定一套安全作业系统。其中用得比较多的是一种正式制度是 作业许可证制度。1.3 All Critical Operations will be under the control of a Permit to Work systemoperated by the Site.Specific training will be given to all employees on thePTW system .All permit requests must be m
4、ade at least 24 hours prior to work commencing.所有关键作业行为均必须处于现场作业许可证制度的控制之下。全体员工均必 须接受有关作业许可证制度的具体培训。各种作业许可证都必须在作业开始之 前至少提前二十四小时提出申请。1.4 Routine Operationswill not be covered by Permit to Work.常规作业不需要办理作业许可证。2. TERMINOLOGY / DEFINITIONS术语 /定义PTW - Permit to Work作业许可证Critical Operations- Critical oper
5、ations include hot works in vicinity of thearea that have inflammable material storage, enter into vessels/equipment or any confine space work, temporary electrical work electrical work, excavations deep than 300mm; use of radioactive, spray painting and grit blasting ,use of cartridge tools ,use of
6、 man baskets, erection or removal of flooring and handrails on open steelwork, diving operations and explosive material,;pressure testing, lifting operations over 50 tons and multi-crane lifting work and any other operations which might be identified during the progress of the project that need to b
7、e covered under the Permit to Work system.关键作业 -关键作业包括在材料存放有可燃性材料的区域附近进行的高温(动火 )作业、进入容器、设备和密闭空间作业、临时性电气作业、超过 0.3 米的开掘作 业、放射性、喷漆和喷砂作业、使用冲击工具、使用载人吊舱,载开放式钢架 上架设或移除地板和栏杆、潜水作业和易爆炸材料的使用、压力测试作业、使 用多台 (含两台 )吊机起吊或超过五十吨以上的起吊作业以及项目进行过程中识 别出来的其它适用作业许可证制度的各类作业。Routi ne Operati ons Operati ons in areas solely des
8、ig nated for operati ons willnot require Permit to Work even though critical operations are carried out.For example a workshop or grit blasting area where hot work is considered“normal operation ” will not require Permit to Work. However these activities must be covered under other SSPs or special p
9、rocedure for the area.Anyother work that is not covered under the area 's procedure will require a Permit to Work.常规作业 -这是指那些在专属区域进行的、但不需要取得作业许可证就可以施 工的作业(即使是关键作业)。例如在喷钢砂处理区域,高温作业是“常规操 作”,所以就不必申请作业许可证。但是,在这些区域进行作业时,必须接受 其它现场安全规定或适用该区域的特殊程序的控制。超出区域程序范围的任何 作业,必须申请并获得作业许可证方可实施。3. RESPONSIBILITIES职责
10、3.1 The Safety Manager is responsible for ensuring that this procedure is implemented. He is also responsible for the checking of the effectiveness of the Permit to Work system by carrying out random audits at the work site.安全经理负责该程序的实施。其另一个任务是通过现场的随机审核,负责检查 并评估作业许可证制度的落实情况。3.2 The Safety engineer i
11、s responsible for ensuring that this procedure is adhered to at all times.安全工程师负责该程序在日常工作中的全面贯彻实施。3.3 The safety engineer is responsible for approving the Permit to Work operatedon his project/area is clearly understood and adhered to by all contractors under their control.安全工程师负责本项目 /本区域作业许可证的批准和实施
12、,确保其负责管理的全 体承包商正确理解并严格遵守相关的条例和制度。3.4 The duties of the safety engineer are:安全工程师的职责是:3.4.0 To be the co-coordinator of all permit work at the facility, including those permits which are suspended, but where the work is not complete 充当本区域所有与作业许可证制度有关事宜的协调员, 包括那些许可暂时收 回,但工作尚未完成的作业的后续处理事宜。3.4.1 To keep
13、 the Construction Managerinformed of any potentially hazardoussituations arising from permit work, advise theConstruction Manager ofany activities that need to be bought under the control of the PTW system and to ensure all staff involved have an overview of significant ongoing work 为了保证施工经理及时掌握由于作业
14、而引起的各种潜在危险情况, 应该加强 与施工经理的沟通,及时提醒其开展作业许可制度规定的各种行动,确保所 有的相关员工从总体上了解正在进行的各项重要作业。3.4.2 To operate the permit issue point to reflect the current state of work 及时解决作业许可证制度在当前执行过程中出现的各种问题。3.4.3 To provide a quality check on the completion of permits 在许可证的任务完成以后,负责检查作业许可证的完成情况。3.4.4 To be the focal point fo
15、r PTW at the location, and generate a sense of ownership in those individuals who work with the system. 担当本区域作业许可证制度的推行重任,培养有关员工的主人翁意识3.4.5 Monitor all aspects of the PTW procedure. 监督实施作业许可证制度的各方面工作。3.4.6 Identify any changes required to the PTW procedure to allow for continuous improvement.适时地对作业许
16、可证制度作出修改,以实现持续改善的目的3.4.7 Liaise with the electrical Competent person to allow for correct isolations.加强与电气专业人员的联系,对电气设施采取正确的隔离措施。3.4.8 Carry out audits of all PTW ongoing work operations. 对各种现行的作业许可证制度实施情况进行审核。4. PROCEDURE程序4.1 General 概述A Permit to Work system is a formal written system used to con
17、trol certain types of work, which are identified as potentially hazardous.Essentialfeatures of a Permit to Work system are:作业许可证制度是一种对某些类型的作业进行控制的正式书面制度。 这类作业 一般是指那些具有潜在危险的活动。作业许可证制度的基本特征为:a. Clear identification of who may authorize particular jobs, 明确地规定谁有权批准某些特殊的作业,b. Training and instruction in
18、the issue and use of permits. 就作业许可证的颁发和使用进行必要的培训和指导。c. Monitoring and auditing to ensure that the system works as intended. 对作业许可证的使用进行监督和审核,确保制度的实施满足预期的目标 .d. A Permit to work system is applied to protect personnel and plant. It consists of an organized and predefined HSE procedure forming a clear
19、 record of all foreseeable hazards that have been considered in advance. Correct operation of the system ensures that: 为了保护装置和人员安全,采用工作许可制度。提前考虑制定出的有 条理的 HSE 程序清楚记录了所有的危害预测。正确执行制度能够确 保:-Only one authority issues permits to allow personnel to work.只有一个人有权发出工作许可证-Only authorized supervisors shall requ
20、est and receive permits.只有经授权的主管人提出申请和接受工作许可-All personnel are aware of safety measures required to be taken所有人员清楚所要采取的安全措施-The area affected by the work is clearly defined明确工作涉及区域- The period of time during which the work may take place is clearly defined.明确工作可能进行的时间段-The correct protective clothin
21、g and equipment is provided and used提供和使用正确的防护服和设备-Appropriate management are aware of the work in progress管理层知道工作正在进行中4.2 Permit Display 许可证上的显示内容4.2.0 Copies of a Permit to Work should be clearly displayed: 应该在下列场合清楚地显示作业许可证的内容:a) At the work site. 在作业场所。b) In the permit co-ordination room, with a
22、dditional copies at the worksite. 在许可证办公室,留有作业现场许可证的副本。4.3 Permit Suspension 许可暂时中止4.3.1 If for any reason work controlled by a permit has to be suspended then the permit will immediately be returned to the Superintendent who will acknowledge the fact and co-ordinate the return of all permits to the
23、 Permit Office.如果由于各种原因,原来受许可证控制的某项作业不得不暂时停止 , 则应该 将许可证立即返还所在部门的主管,再由主管向许可证办公室通报真相,并 将各种许可证退还给许可证办公室。4.3.2 Example of reasons for suspension are: 许可证暂时收回执行的理由举例如下:a) Site general alarm. 现场出现一般的报警。b) Operational reasons. 操作原因。c) Conflict of work activities. 作业发生冲突。d) Expiry of period for which permit
24、 is valid.作业许可证有效期到期。e) Change in work site conditions. 作业现场的情况发生变化4.3.3 After suspension it will be necessary, once permission has been given to recommence work, to have the permit re-validated before the work can restart. 在许可证暂时收回以后,一旦允许重新开始作业,则在重新开始作业之前, 必须对原颁发的许可证重新核准。4.4 Cross Reference 交叉确认4.4
25、.1 It is important to make sure that one activity under a Permit to Work does not create danger for another ongoing activity.在根据作业许可证进行某项作业时, 必须确保不对其它正在进行中的工作构 成威胁。这一点是非常重要的。4.4.2 The safety engineer should be aware of potential interaction and should check when a permit is prepared whether it impin
26、ges on one already issued.安全工程师应该清楚地意识到各种作业之间可能存在的关联关系, 在准备签 发许可证时,应该仔细确认它是否与此前颁发的许可作业之间存在着冲突。4.5 Permit Revalidation 许可证的重新核准4.5.1 When a permit is authorized by safety engineer , it will have a time expiry placed on it. This may vary form a few hours to a full shift or even several days, depending
27、 upon the nature of the work being undertaken and the frequency at which the activity is repeated. 安全工程师在签发许可证时,应该注明许可证的有效时间。有效期有可能是 几个小时,也有可能是整个班次甚至是几天,具体要由作业的性质以及作业 重复的频率决定。4.5.2 If, at the end of this time period, the work being controlled by the permit is not complete the permit may be revalidat
28、ed by the responsible person, who shall ensure, together with the safety engineer, that the original conditions required by the permit are still being met.如果在有效期到期时,许可证规定的作业没有如期完成,则应该由相关的负 责人对许可证进行重新核准。负责核准的人员在核准之前,必须与安全工程 师一起,确认许可证原对应的作业条件是否已经发生变化。4.6 Hand Back 退还4.6.1 Prior to the permit being sig
29、ned off and handed back the following must be met:在注销并交还许可证之前,必须满足下列条件:a) Has the work been completed; this should be confirmed by the permit holder.指定的作业是否已经完成?许可证持有者必须对此予以确认。b) Has the site/area been left in a safe condition?作业完成以后有关现场或区域是否安全情况良好?c) Has the person in control of operations acknowle
30、dged the return of the permit?有关的作业负责人是否知道许可证已经退还?4.7 Responsibilities under Permit to Work System 作业许可证制度所规定的责 任4.7.1 Duties are placed on various persons with regard to the operation of aPermit to Work system.In general these are as follows:在执行作业许可证制度过程中, 不同的人承担着不同的责任。 总的分工如下:a) The Contractor - w
31、ho must ensure that all persons within his employment have a clear understanding of how the PTW system operates. In the case of Contractors this is normally undertaken in conjunction with the Superintendent, 承包商 - 负责保证他所雇佣的所有员工都能正确地理解作业许可证制度 的运行方式。对承包商而言,他可能更多的是与现场主管合作执行这一 制度。b) Each project should
32、issue and co-ordinate the permits and identify those activities for which a permit is required.每个项目 -负责专门管理颁发和协调许可证事宜,并明确哪些作业需要 申请许可证。c) The safety engineer, - who is responsible for accepting the permit for a particular activity and must ensure that the conditions of the permit are maintained throu
33、ghout its period of validity.安全工程师 - 负责接受并处理特殊作业的许可证申请,并确保在许可证 有效期内,作业现场的作业条件不发生根本性的变化。d) The employee - who must understand and adhere to the conditions and requirements stipulated on the permit and not undertake any activities, which cannot be understood or are not covered by the permit.员工-必须;理解并遵
34、守相关许可证上规定的作业条件和作业要求,不 从事任何不理解的或超出许可证许可范围的作业。4.8 Training Required 培训要求4.8.1 Training on Permit to Work systems is necessary for all persons who may be involved. This should include managers, supervisors, safety engineers of site HSE , approver of Permit and contractors. 对于所有涉及的人员,都必须进行有关作业许可证制度方面的培训
35、。这些人 员包括各级经理、主管、安全工程师、许可证批准人和承包商。4.8.2 Responsible people and personnel responsible for carrying out any isolation should be formally assessed before appointment. 在指定各级负责人和负责实施隔离的人员前,要进行正式的评估。4.8.3 Before formal appointment by the Construction Manager responsible people should be assessed on: 在施工经理进
36、行正式任命之前,应该对将要 被任命的负责人员进行以下方面的评估:a) Work experience. 工作经验b) Familiarization. 熟悉程度c) Training 培训d) Result of a written test 书面测试的结果 .4.8.4 Training should be covering the legal requirements, official guidance and company guidance. 培训内容包括法律要求、官方的指导材料和公司的指导材料。4.9 Type of Permit 许可证的类型4.9.1 Permit to Work Certificates required will generally cover the following areas:一般情况下,在下列场合作业需要事先申请作业许可证。a) Hot Work, i.e. welding, flame cutting, grinding. 高温作业,例如,焊接、火焰切割和磨削等。b) Entry into vessels, equipment or any confined spaces 进入容器、设备或任何限制空间c) Temporar
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 九年级历史上册 第五单元 第12课 西欧走出中古时代说课稿 华东师大版
- 2025年中国高纯环己烷行业市场分析及投资价值评估前景预测报告
- 14.我的收藏卡教学设计-2025-2026学年小学美术二年级下册人美版(常锐伦、欧京海)
- 医疗意外险知识培训内容课件
- 江苏省扬州市高中地理 第一单元 探索海洋奥秘 1.2 海水性质与海水运动说课稿 鲁教版选修2
- 一年级道德与法治下册 第一单元 我和春天在一起 4《让疾病走开》说课稿 鄂教版
- 2024-2025学年高中数学 第1章 三角函数 6 6.1 余弦函数的图像 6.2 余弦函数的性质(教师用书)说课稿 北师大版必修4
- 汽车维护的分类和内容说课稿-2025-2026学年中职专业课-汽车保养与维护-汽车运用与维修-交通运输大类
- 第3节 信息的处理说课稿初中信息技术粤教清华版七年级下册-粤教清华版
- 第一节 生物群落与其无机环境形成生态系统教学设计高中生物沪教版2019选择性必修2 生物与环境-沪教版2019
- 物流配送调度管理系统设计方案
- 35kV线路工程电杆安装施工方案
- 2025年度环评文件技术复核服务方案投标文件(技术方案)
- 新生儿硬肿症个案护理
- 2025至2030中国生物医药行业发展趋势分析与未来投资战略咨询研究报告
- 城市智能感知系统-洞察及研究
- 艺考机构学校合作协议书
- 肺结核患儿的护理
- 冬季风力发电机组安装施工安全技术措施
- DB1331∕T 034-2022 建筑与市政工程无障碍设计图集
- 2025年江苏省苏州市中考数学模拟试卷(十三)(含答案)
评论
0/150
提交评论