1、5.1 现场布置5.1 Site Layout 5.1.1项目组织机构图 Project Organization Chart 5.1.2组织机构说明 Introduction of Organization根据本工程的特点,本着“精干、高效”的原则组建南苏丹Magwi-Lobone公路项目部,项目经理为项目的第一责任人。In accordance with features of the project and under the principle of “high capability and efficiency”, establish the Southern Sudan Magwi
2、-Lobone Highway Project Department, and the project manager is the primary person in charge of the project. 项目部下设:The Project department comprises: 决策层:项目经理、项目副经理、总工程师;Decision-making level: Project Manager, Deputy Project Manager, General Project Engineer; 管理层:施工部、技术部、合同部、财务部、QHSE部、机物部、行政部;Manageme
3、nt level: Construction Dept., Technology Dept., Contract Dept., Financial Dept., QHSE Dept., Mechanical Materials Dept., Administration Dept.; 工区作业层:根据本工程特点,按照工区管理作业队及班组的形式。设置4个工区,即土方一工区、土方二工区、路面工区、综合工区。 Work area operation level: in accordance with features of the project and as per work areas form
4、 to manage operation teams and groups, set up 4 work areas, namely Earthwork area I, Earthwork area II, Road pavement area, Complex processing area. 5.1.3主要管理层的主要工作内容及职责 Main Work Content and Duties of Main Management Levelu 施工部:负责施工现场的调度及生产组织等。负责测量队的归口管理及协调工作。u Construction Dept.: be responsible fo
5、r scheduling of construction site and organization of production, etc. In charge of the centralized management and coordination work of Survey Team. 测量队:负责本项目测量控制网建立、地形地貌测绘,施工现场测控、结算测量以及竣工测量等工作。Survey Team: be responsible for the establishment of surveying control network and geographic and geomorph
6、ic surveying and mapping of the project, construction site survey and control, settlement survey and final survey, etc. u 技术部:负责工程的施工方案和施工技术措施的编写,施工图纸的设计,进度的编制及进度更新等工作。u Technology Dept.: be responsible for the compilation of construction scheme and construction technical measure of the project, des
7、ign of construction drawings, compilation of schedule and schedule update, etc.u QHSE部:负责工程质量控制管理,各工序施工终检、验收,竣工资料整编等。负责施工安全管理、爆破安全、交通安全管理、施工人员健康、消防、保卫、施工区环境保护等。负责实验室的归口管理及协调工作。u QHSE Dept.: be responsible for the projects quality control management, final inspection and acceptance of construction of
8、 all processes, reorganize completion data, etc. In charge of construction safety management, blasting safety, traffic safety management, health of construction personnel, fire control, security, construction area environmental protection, etc. In charge of the centralized management and coordinatio
9、n work of Laboratory. u 实验室:负责本项目原材料检测、土工试验、混凝土现场实验、沥青混凝土实验任务以及外送委托实验任务等内容等。u Laboratory: be responsible for material test, soil test, concrete field experiment, asphalt concrete experiment task and outside entrusted experiment task and other content of the project, etc. u 合同部:负责合同管理、工程结算、资金流控制、预算编制
10、等。u Contract Dept.: be responsible for contract management, project settlement, fund flow control, budgeting, etc. u 财务部:负责成本管理、成本控制、内部经营及负责项目部的内、外财务运作及管理等。u Financial Dept.: be responsible for cost management, cost control, internal operation and in charge of internal and external financial operati
11、on and management of the Project Department, etc. u 机物部:负责设备、物资、施工材料、设备配件供应及物供合同的管理,项目部仓储系统的管理,施工设备运行及修理的管理。u Mechanical Materials Dept.: be responsible for supply of equipment, material, construction material, equipment accessories and management of material supply contract, management of the Proje
12、ct Departments storage system, and management of the operation and repair of construction equipment. u 行政部:负责文件收发、档案管理,内部行政事务,对外协调;负责后勤服务;负责项目的人力资源招聘及管理等。u Administration Dept.: be responsible for receiving and sending files, archives management, internal administrative affairs and external coordina
13、tion; in charge of logistics service; in charge of the human resource recruitment and management of the project, etc. u 一工区:包括2个路基作业队,1个结构物作业队和1个排水作业队。负责0+000-40+000段的清表、土石方开挖回填、排水沟、涵洞、桥梁的施工管理。u Work area I: includes 2 subgrade construction teams, 1 structure construction team and 1 drains construct
14、ion team. Be responsible for surface cleaning, earth-rock excavation and backfill, and construction management of drain, culvert and bridge from 0+000 to 40+000 section. u 二工区:包括2个路基作业队,1个结构物作业队和1个排水作业队。负责40+000-811+000段的清表、土石方开挖回填、排水沟、涵洞和桥梁的施工管理。u Work area II: includes 2 subgrade construction team
15、s, 1 structure construction team and 1 drains construction team. Be responsible for surface cleaning, earth-rock excavation and backfill, and construction management of drain, culvert and bridge from 40+000 to 811+000 section.u 路面工区:包括2个路面作业队。负责本标段的选定层、底基层和面层的生产等管理工作。u Road pavement area: includes 2
16、 pavement construction teams. Be responsible for production and other management work of selected layer, subbase layer and surface layer of this section. u 综合工区:负责所有机械设备的维修、保养以及本项目的辅助工程施工等管理工作。u Complex processing area: be responsible for repair and maintenance of all mechanical equipment, construct
17、ion of the projects ancillary works and other management work.5.1.4主要作业层的主要工作内容及职责 Main Work Content and Duties of Main Operation Levelu 路基作业队:负责本标段的清表、土石方开挖回填等施工任务。u Subgrade construction team: be responsible for surface cleaning, earth-rock excavation and backfill and other construction tasks of t
18、his section. u 排水作业队:负责本标段的排水设施和浆砌片石护坡修建等施工任务。u Drains construction team: be responsible for construction of drainage facilities and mortar rubble masonry pavement and other construction tasks of this section. u 结构物作业队:负责本标段的管涵、箱涵和桥梁修建等施工任务。u Structure construction team: be responsible for construct
19、ion of pipe culvert, box culvert and bridge and other construction tasks of this section.u 路面作业队:负责本标段选定层、底基层和面层等施工任务。u Pavement construction team: be responsible for construction tasks of selected layer, subbase layer and surface layer of this section. u 机械修理厂:负责本标段所有车辆和设备的维修保养等工作。u Machine repair
20、plant: be responsible for repair and maintenance of all vehicles and equipment and other tasks of this section. u 综合加工厂:负责混凝土骨料、路面碎石料等块石材料的开采、运输及加工;以及钢筋加工、模板维修等。u Complex processing plant: be responsible for exploitation, transportation and processing of concrete aggregate, pavement metalling and ot
21、her stone materials; and processing of reinforced steel, template repair, etc. 5.1.5营地布置 Camp Layout 为方便施工管理,计划在线路起点Magwi处设置项目主营地,主营地旁边设置工程师营地,在K30+600处设置一处副营地。主营地包括办公室、宿舍和医务室,副营地包括部分办公室和宿舍。在营地附近打井取水,并检测是否适合饮用。营地设置位置详见5.1-2。To facilitate the construction management, plan to set up the projects main
22、camp on Magwi which is the starting point of the route, set up the engineer camp beside the main camp, and set up a sub-camp on K30+600 position. The main camp includes office, dormitory and dispensary and the sub-camp includes some offices and dormitories. Dig a well beside camps to get water, and
23、test whether the water is drinkable. Camps set location can be seen in 5.1-2. 5.1.6临时设施设置 Setup of Temporary Facilities5.1.6.1施工用电、用水.1 Power and Water Supply for Construction 项目办公驻地和施工现场均配备柴油发电机。Both the project site office and construction site are equipped with diesel generator. 道路沿线有部分地表水源(小溪),可
24、打井取用地下水,但均需进行检验以满足施工或饮用水要求。There are some surface water sources (brooks) along the road, it is practicable to dig a well to take use of groundwater, but the groundwater shall be tested to meet the requirements of construction or drinking water. 5.1.6.2施工通讯.2 Construction Communication 施工通讯主要以Magwi移动通讯电话为主;无信号的施工区内用对讲机联络,距离较远时设对讲机中转基站。网络通讯安装卫星接收装置,以保证施工指挥协调及对外联络需要。Construction communication mainly relies on Magwi m
温馨提示
- 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
- 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
- 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
- 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
- 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
- 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
- 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
最新文档
- 2026年内部控制实务培训课件保险公司
- 2026年家庭医生在居民健康档案动态管理中的作用
- 2026年硫酸生产尾气脱硫设施运行维护
- 2026年超声治疗设备支付标准探讨
- 2025甘肃省天水市中考生物真题(原卷版)
- 2025黑龙江省绥化市中考英语真题(解析版)
- 2026年情绪智力在管理沟通中的识别与运用
- 2026年基于数字孪生的公共卫生应急响应系统
- 2026年烘焙坊节日限定产品预售与社群接龙
- 自由曲线在微电子封装设计
- GB/T 47432-2026合规管理体系有效性评价
- 2026重庆南州城市管理服务有限公司招聘生产人员招聘15人考试模拟试题及答案解析
- 蛋糕加工技术-慕斯蛋糕制作工艺
- 医疗器械借用合同范例
- 雨棚整体吊装施工方案
- 2025年高中自主招生模拟考试数学试卷试题(含答案详解)
- 2024-2034年全球及中国智能运动器材和设备(SSDE)行业市场发展分析及前景趋势与投资发展研究报告
- ISO28000:2022供应链安全管理体系
- 人教版六年级数学下册全册分层作业设计含答案
- CCS船舶建造检验流程课件
- 超声波UTⅠ级考试题库
评论
0/150
提交评论